Understand what risk is and the importance of good project risk management
Discuss the elements involved in risk management planning
List common sources of risks on information technology projects
Describe the risk identification process and tools and techniques to help identify project risks
Discuss the qualitative risk analysis process and explain how to calculate risk factors, use probability/impact matrixes, the Top Ten Risk Item Tracking technique, and expert judgment to rank risks
2
Explain the quantify risk analysis process and how to use decision trees and simulation to quantitative risks
Provide examples of using different risk response planning strategies such as risk avoidance, acceptance, transference, and mitigation
Discuss what is involved in risk monitoring and control
Describe how software can assist in project risk management
Explain the results of good project risk management
3
Project risk management is the art and science of identifying, assigning, and responding to risk throughout the life of a project and in the best interests of meeting project objectives
Risk management is often overlooked on projects, but it can help improve project success by helping select good projects, determining project scope, and developing realistic estimates
A study by Ibbs and Kwak show how risk management is neglected, especially on IT projects
KPMG study found that 55 percent of runaway projects did no risk management at all
, 4
5
A dictionary definition of risk is “the possibility of loss or injury”
Project risk involves understanding potential problems that might occur on the project and how they might impede project success
Risk management is like a form of insurance; it is an investment
6
Risk utility or risk tolerance is the amount of satisfaction or pleasure received from a potential payoff Utility rises at a decreasing rate for a
person who is risk-averse Those who are risk-seeking have a
higher tolerance for risk and their satisfaction increases when more payoff is at stake
The risk-neutral approach achieves a balance between risk and payoff
, 7
8
The goal of project risk management is to minimize potential risks while maximizing potential opportunities. Major processes include Risk management planning: deciding how to approach and plan
the risk management activities for the project Risk identification: determining which risks are likely to affect a
project and documenting their characteristics Qualitative risk analysis: characterizing and analyzing risks and
prioritizing their effects on project objectives Quantitative risk analysis: measuring the probability and
consequences of risks Risk response planning: taking steps to enhance opportunities
and reduce threats to meeting project objectives Risk monitoring and control: monitoring known risks, identifying
new risks, reducing risks, and evaluating the effectiveness of risk reduction
9
The main output of risk management planning is a risk management plan
The project team should review project documents and understand the organization’s and the sponsor’s approach to risk
The level of detail will vary with the needs of the project
10
What questions should be addressed in a Risk Management Plan
11
Contingency plans are predefined actions that the project team will take if an identified risk event occurs
Fallback plans are developed for risks that have a high impact on meeting project objectives
Contingency reserves or allowances are provisions held by the project sponsor that can be used to mitigate cost or schedule risk if changes in scope or quality occur
12
Several studies show that IT projects share some common sources of risk
The Standish Group developed an IT success potential scoring sheet based on potential risks
McFarlan developed a risk questionnaire to help assess risk
Other broad categories of risk help identify potential risks
13
14
Success Criterion Points
User Involvement 19
Executive Management support 16
Clear Statement of Requirements 15
Proper Planning 11
Realistic Expectations 10
Smaller Project Milestones 9
Competent Staff 8
Ownership 6
Clear Visions and Objectives 3
Hard-Working, Focused Staff 3
Total 100
15
1. What is the project estimate in calendar (elapsed) time?
( ) 12 months or less Low = 1 point
( ) 13 months to 24 months Medium = 2 points
( ) Over 24 months High = 3 points
2. What is the estimated number of person days for the system?
( ) 12 to 375 Low = 1 point
( ) 375 to 1875 Medium = 2 points
( ) 1875 to 3750 Medium = 3 points
( ) Over 3750 High = 4 points
3. Number of departments involved (excluding IT)
( ) One Low = 1 point
( ) Two Medium = 2 points
( ) Three or more High = 3 points
4. Is additional hardware required for the project?
( ) None Low = 0 points
( ) Central processor type change Low = 1 point
( ) Peripheral/storage device changes Low = 1
( ) Terminals Med = 2
( ) Change of platform, for example High = 3
PCs replacing mainframes
Market risk: Will the new product be useful to the organization or marketable to others? Will users accept and use the product or service?
Financial risk: Can the organization afford to undertake the project? Is this project the best way to use the company’s financial resources?
Technology risk: Is the project technically feasible? Could the technology be obsolete before a useful product can be produced?
16
17
Many information technology projects fail because of technology risk. One project manager learned an important lesson on a large IT project: focus on business needs first, not technology. David Anderson, a project manager for Kaman Sciences Corp., shared his experience from a project failure in an article for CIO Enterprise Magazine. After spending two years and several hundred thousand dollars on a project to provide new client/server-based financial and human resources information systems for their company, Anderson and his team finally admitted they had a failure on their hands. Anderson revealed that he had been too enamored of the use of cutting-edge technology and had taken a high-risk approach on the project. He "ramrodded through" what the project team was going to do and then admitted that he was wrong. The company finally decided to switch to a more stable technology to meet the business needs of the company.
Hildebrand, Carol. “If At First You Don’t Succeed,” CIO Enterprise Magazine, April 15, 1998
Risk identification is the process of understanding what potential unsatisfactory outcomes are associated with a particular project
Several risk identification tools and techniques include Brainstorming The Delphi technique Interviewing SWOT analysis
18
What risks can you identify (as many as you can think of)
How critical are they (low – medium – high)
Prioritise your list in order of importance
Can you think of mitigating strategies to manage these risks (pick 5 of interest )
19
20
Knowledge Area Risk Conditions
Integration Inadequate planning; poor resource allocation; poor integrationmanagement; lack of post-project review
Scope Poor definition of scope or work packages; incomplete definitionof quality requirements; inadequate scope control
Time Errors in estimating time or resource availability; poor allocationand management of float; early release of competitive products
Cost Estimating errors; inadequate productivity, cost, change, orcontingency control; poor maintenance, security, purchasing, etc.
Quality Poor attitude toward quality; substandarddesign/materials/workmanship; inadequate quality assuranceprogram
Human Resources Poor conflict management; poor project organization anddefinition of responsibilities; absence of leadership
Communications Carelessness in planning or communicating; lack of consultationwith key stakeholders
Risk Ignoring risk; unclear assignment of risk; poor insurancemanagement
Procurement Unenforceable conditions or contract clauses; adversarial relations
Assess the likelihood and impact of identified risks to determine their magnitude and priority
Risk quantification tools and techniques include Probability/Impact matrixes The Top 10 Risk Item Tracking
technique Expert judgment
21
IS370 Project Management, Dr Pat Halloran 22
IS370 Project Management, Dr Pat Halloran 23
24
Top 10 Risk Item Tracking is a tool for maintaining an awareness of risk throughout the life of a project
Establish a periodic review of the top 10 project risk items
List the current ranking, previous ranking, number of times the risk appears on the list over a period of time, and a summary of progress made in resolving the risk item
25
26
Monthly Ranking
Risk Item This
Month
Last
Month
Number of Months
Risk Resolution Progress
Inadequate planning
1 2 4 Working on revising the entire project plan
Poor definition of scope
2 3 3 Holding meetings with project customer and sponsor to clarify scope
Absence of leadership
3 1 2 Just assigned a new project manager to lead the project after old one quit
Poor cost estimates
4 4 3 Revising cost estimates
Poor time estimates
5 5 3 Revising schedule estimates
Many organizations rely on the intuitive feelings and past experience of experts to help identify potential project risks
Experts can categorize risks as high, medium, or low with or without more sophisticated techniques
27
Often follows qualitative risk analysis, but both can be done together or separately
Large, complex projects involving leading edge technologies often require extensive quantitative risk analysis
Main techniques include decision tree analysis simulation
28
A decision tree is a diagramming method used to help you select the best course of action in situations in which future outcomes are uncertain
EMV is a type of decision tree where you calculate the expected monetary value of a decision based on its risk event probability and monetary value
29
30
Simulation uses a representation or model of a system to analyze the expected behavior or performance of the system
Monte Carlo analysis simulates a model’s outcome many times to provide a statistical distribution of the calculated results
To use a Monte Carlo simulation, you must have three estimates (most likely, pessimistic, and optimistic) plus an estimate of the likelihood of the estimate being between the optimistic and most likely values
31
32
A large aerospace company used Monte Carlo simulation to help quantify risks on several advanced-design engineering projects. The National Aerospace Plan (NASP) project involved many risks. The purpose of this multibillion-dollar project was to design and develop a vehicle that could fly into space using a single-stage-to-orbit approach. A single-stage-to-orbit approach meant the vehicle would have to achieve a speed of Mach 25 (25 times the speed of sound) without a rocket booster. A team of engineers and business professionals worked together in the mid-1980s to develop a software model for estimating the time and cost of developing the NASP. This model was then linked with Monte Carlo simulation software to determine the sources of cost and schedule risk for the project. The results of the simulation were then used to determine how the company would invest its internal research and development funds. Although the NASP project was terminated, the resulting research has helped develop more advanced materials and propulsion systems used on many modern aircraft.
After identifying and quantifying risks, you must decide how to respond to them
Four main strategies: Risk avoidance: eliminating a specific threat or
risk, usually by eliminating its causes Risk acceptance: accepting the consequences
should a risk occur Risk transference: shifting the consequence of a
risk and responsibility for its management to a third party
Risk mitigation: reducing the impact of a risk event by reducing the probability of its occurrence
33
34
Monitoring risks involves knowing their status
Controlling risks involves carrying out the risk management plans as risks occur
Workarounds are unplanned responses to risk events that must be done when there are no contingency plans
The main outputs of risk monitoring and control are corrective action, project change requests, and updates to other plans
35
Risk response control involves executing the risk management processes and the risk management plan to respond to risk events
Risks must be monitored based on defined milestones and decisions made regarding risks and mitigation strategies
Sometimes workarounds or unplanned responses to risk events are needed when there are no contingency plans
36
Databases can keep track of risks. Many IT departments have issue tracking databases
Spreadsheets can aid in tracking and quantifying risks
More sophisticated risk management software, such as Monte Carlo simulation tools, help in analyzing project risks
37
38
39
Unlike crisis management, good project risk management often goes unnoticed
Well-run projects appear to be almost effortless, but a lot of work goes into running a project well
Project managers should strive to make their jobs look easy to reflect the results of well-run projects