A Layman's Guide to Dams & Spillway (2011) - Presentation (44)

Preview:

Citation preview

A LAYMAN’S GUIDE TO DAMS &

SPILLWAYS

by

Bram Knoop & Bruce Cole

Australian Engineering Heritage 2011

INTRODUCTION

Dams generally attract public attention:-

• When they are in the planning stage,

• During droughts, - water restrictions,

• During major floods, - inundation.

• And when they receive a Bronze Plaque.

Australian Engineering Heritage 2011

Wivenhoe Dam Brisbane River

QLD

Australian Engineering Heritage 2011

Upper Reservoir Waterworks Reserve

Australian Engineering Heritage 2011

H = 18m

Lc= 204m

Vef= 0.135Mm3

Vs= 0.300Mm3

<< Spillway &

Bypass

OUTLINE

• Public Expectations

• Functions of Dams & Essential Features

• Spillway Requirements & Types

• ANCOLD Register of Large Dams & Types of Dams

• Examples of types of dams, Earthfill Embankments, etc.

• This will include spillways, and Outlet Works

• Dam Upgrades,

Australian Engineering Heritage 2011

PUBLIC EXPECTATIONS

Typical questions included:

• Why can’t dams control large floods?

• Why do we have a ‘100 year flood’ 34 years

after the previous 100 year flood in 1974?

• Why can’t flood waters be diverted to the dry

inland Murray-Darling Basin?

Engineering Heritage Conference 2011

FUNCTIONS OF DAMS

Mainly to store water for later use in:

– Irrigation farming– (#) ~70%

– Industrial use ~20%

– Domestic consumption <10%

– Flood protection

– Navigation

– Environmental flows

– Waste storages – tailings dams

– Recreational activities # - % storage capacity of all dams in Australia

Australian Engineering Heritage 2011

ESSENTIAL FEATURES

Extensive studies are required to establish the feasibility of a major dam project.

This includes hydrological, engineering and economic evaluations.

• Dam Sites – normally on-stream, but can be or off-stream,

• Foundations – need to be stable and water tight,

• Structural Stability – requires appropriate safety factors,

• Spillway Facilities – can be un-controlled, or controlled,

• Outlet Works – gates, valves to suit specific requirements.

All parts need to be optimised to for an economic dam project.

Australian Engineering Heritage 2011

SPILLWAY REQUIREMENTS

• To release excess water from the reservoir.

• Capacity: initially based on existing flood data, or experience.

• Now Based: on probable maximum precipitation (PMP),

• PMP estimates: depend geographic and atmospheric conditions,

• And on probable maximum flood (PMF) estimates, this is the notional

“upper limit” for a specific catchment area.

• The annual exceedance probability (AEP) for a PMF event may vary

from 1/10E7 for small catchments to 1/10E4 for large catchments.

There are different types of spillways some of which will be pointed out.

Australian Engineering Heritage 2011

TYPES OF SPILLWAYS

• Uncontrolled Spillways – Free flow over a spillway crest.

• Controlled Spillways – Flow regulated by gates.

• Earthfill and Rockfill Embankments: normally have

Spillways adjacent to the dam embankment.

• Concrete Dams: can have Spillway Crests that are part of the

dam structure; or they can have a Spillway adjacent to the dam.

Australian Engineering Heritage 2011

ANCOLD REGISTER OF LARGE DAMS

Types of Dams No. Examples Ht m

Earthfill Embankment 260 Eucumbene 116

Rockfill Embankment 145 Dartmouth 180

Concrete Gravity 108 Warragamba 142

Concrete Arch 40 Gordon 140

Concrete Buttress 5 Meadowbank 43

Multiple Arch Buttress 3 Julius 38

561

Australian Engineering Heritage 2011

EARTHFILL EMBANKMENT DAMS

EUCUMBENE DAM

H = 116m

Lc = 579m

Vef = 6.75Mm3

Spillway >>>

Qs = 475m3/s

Vs = 4,800Mm3

This is the largest

Dam of its type.

SMHA Photo

Australian Engineering Heritage 2011

ROCKFILL EMBANKMENT DAMS

Australian Engineering Heritage 2011

BLOWERING DAM

H = 112m

Lc = 808m

Vrf = 8.6Mm3

Qs =2350m3/s

Vs = 1,600Mm3

< Power Stn.

<< Tail Race

ROCKFILL EMBANKMENT DAMS

Blowering Dam Cross Section SMHA Diagram

Australian Engineering Heritage 2011

CONCRETE FACED ROCKFILL DAMS

Australian Engineering Heritage 2011

REECE DAM

Pieman River P. D.

This is the largest CFRD

in Australia

< Spillway

<<< Power Station

H = 122m

Lc = 374m

Vr = 2.7Mm3

Qs = 4714m3/s

Vs = 641Mm3

CONCRETE FACED ROCKFILL DAMS

CFRD – Cross Section

Australian Engineering Heritage 2011

3 – Concrete Plinth

4 – D/S Face Protection

5 – Compacted Rockfill Zone

6 – Transition Zones

7 – Upstream Face Membrane

CONCRETE FACED ROCKFILL DAMS

Reece Dam

Upstream Face

<<< Slipform

<< Plinth

<< Plinth

Australian Engineering Heritage 2011

CONCRETE GRAVITY DAMS

GUTHEGA DAM

H = 34m

Lc = 139m

Vc = 44,000m3

<< Spillway

Qs = 1420m3/s

Vs = 1.8Mm3

< Spillway Apron

This was the first

Dam in the Snowy

Hydro Scheme

Australian Engineering Heritage 2011

ROLLER COMPACTED CONCRETE GRAVITY DAMS

Meander Dam

Construction

H = 50m

Lc = 186m

Vc = 85,000m3

Vs = 24Mm3

Qs = 2600m3/s

Australian Engineering Heritage 2011

ROLLER COMPACTED CONCRETE GRAVITY DAMS

MEANDER

RCC DAM

< D/S Face

RCC placing

<<< U/S Face

Australian Engineering Heritage 2011

ROLLER COMPACTED CONCRETE GRAVITY DAMS

Australian Engineering Heritage 2011

Meander Dam

Downstream face

as the dam nears

completion

This RCC Gravity

Dam has a central

stepped spillway

with a d/s impact

basin.

CONCRETE ARCH DAMS

Australian Engineering Heritage 2011

A - Gordon Dam start of Construction B - After Diversion Closure

CONCRETE ARCH DAMS

Australian Engineering Heritage 2011

GORDON DAM

<

Concrete placement

at Block C

CONCRETE ARCH DAMS

Australian Engineering Heritage 2011

GORDON DAM

This is the highest arch

dam and largest storage

in Australia

H = 140m

Lc = 198m

Vc = 154,000m3

Vs = 12,450Mm3

Qs = 175m3/s

This is via an

emergency spillway that

is made by removing

two crest parapet wall

sections.

MULTIPLE ARCH & BUTTRESS DAMS

Australian Engineering Heritage 2011

Miena Multiple Arch Dam – Tas.

Julius Dam - Qld

Oberon Buttress Dam - Qld

UNUSUAL SPILLWAYS

Geehi Dam – Glory Hole Spillway

Crotty Dam - Chute Spillway on the crest

and downstream face of a rockfill dam.

Australian Engineering Heritage 2011

OUTLET WORKS

Australian Engineering Heritage 2011

Hume Dam Outlet Valves

Typical Cone Dispersion Valve

DAM UPGRADES

• ANCOLD produced a number of Guidelines – including:

• Design of Dams for Earthquake – 1998a,

• Acceptable Flood Capacity – 2000a,

• Assessment of the Consequences of Dam Failure – 2000b,

• Guidelines on Risk Assessment – 2003.

• Older dams may have insufficient spillway capacity.

• Over the past 40 years many dams have been modified to

comply with currently accepted criteria for dam safety and

flood capacity

Australian Engineering Heritage 2011

WARRAGAMBA DAM

Warragamba Dam

in the early 1960s.

H = 137m

Lc = 351m

Vc = 1.3Mm3

Vs = 2.1Gm3

WARRAGAMBA DAM – SPILLWAY UPGRADE - 2008

Australian Engineering Heritage 2011

H = 142m

Lc = 351m

Right Bank

Fuse Plug

Spillway

INCIDENTS & FAILURES

Dam Incident:

A structural failure that generally can be fixed, usually at great expense.

Examples range from: failed gate works, major leakages, substantial

settlements, concrete cracking, etc.

Dam Failure:

A structural failure that can not be fixed and is normally followed by a

judicial inquiry.

Recent Examples:

Camara Dam (RCC Dam) – Brazil – June 2004

Malpasset Dam (Arch Dam) – France – 2nd December 1959

Australian Engineering Heritage 2011

CAMARA DAM FAILURE - BRAZIL

Australian Engineering Heritage 2011

This RCC Dam failed

on June 2004.

H = 50m

Lc = ?

Vc =?

Failure flood 17Mm3

5 Deaths

20 Vanished

250 Homes lost

800 Families

homeless

CAMARA DAM FAILURE - BRAZIL

Australian Engineering Heritage 2011

This was a first filling failure.

The left bank section of the dam

section of the dam collapsed as

shown.

DAM FAILURES

Malpasset Dam

< July 1959

And after 2-12-1959

Right & Left Banks

GORDON DAM

GORDON DAM

GORDON DAM

GORDON DAM CONSTRUCTION

Australian Engineering Heritage 2011

Left: After the

upstream coffer

dam was

breached.

Right: With the

storage level

rising.

RECENT HISTORY

• Australia experienced below average

rainfalls for most of the decade 2000-2010

• Dam storage levels dropped to low levels

• Water restrictions applied in many towns

• This changed in 2010-2011 – when …..

• The eastern states saw extensive flooding

• With property damage and loss of life.

Australian Engineering Heritage 2011

DAM PROJECT INVESTIGATIONS

Extensive Studies are required to Establish the Feasibility

of a Major Dam Project; these include:

• Catchment Surveys; geography, climate, hydrology, environment, geology,

• Water Resources; run-off, minimum, average, peak flows,

• Dam Site & Reservoir Investigations; soil, rock, stability, materials,

• Suitable Dam Design Types; embankment, concrete gravity, arch,

• Suitable Spillway Arrangements; uncontrolled, controlled,

• Appropriate Outlet Works; gates, valves,

• Economic Studies; project costs, operating costs, returns on investment,

Australian Engineering Heritage 2011

PUBLIC INTEREST

• The 2011 floods in Queensland were widely reported.

• There appeared to be a lack of understanding of the principal features of large dams and their operation.

• This applied to journalist, and members of the public.

• A Commission of Inquiry was set up to investigate the Queensland Floods.

Australian Engineering Heritage 2011

Recommended