California Energy Commission

Energy Commission Review of Power Plants –

Southern California Reliability

2015 Integrated Energy Policy Report Workshopon Southern California Electricity Reliability

University of California, IrvineAugust 17, 2015

Roger JohnsonSiting, Transmission and Environmental Protection Division

Roger.Johnson@energy.ca.gov / (916) 654-5100

California Energy Commission

Southern California Power Plants

May 20, 2015 2

California Energy Commission

NRG PuenteMandalay Generating Station replacement of Units 1&2 with

262 MW GE Frame 7HA CTG

City of Oxnard

Information Hearing 8/27/2015

CEC Decision expected 6/2016

OTC compliance date 12/31/2020

PPA - Yes

California Energy Commission

AES AlamitosAlamitos Generating Station Replacement

640 MW air-cooled combined cycle

[400 MW LMS 100 simple cycle]

City of Long Beach

AFC supplement expected 2015

CEC Decision 2016

OTC compliance date 12/31/2020

PPA – Yes (640 MW)

California Energy Commission

NRG El SegundoEl Segundo Units 1&2 replaced on 8/2013

with 560 MW fast-start combined cycle.

City of El Segundo

El Segundo Units 3&4 Replacement

449 MW (1 fast-start air-cooled combined

cycle and 2 simple cycle peakers)

Final Staff Assessment 8/2015

CEC Decision expected late 2015

OTC compliance date 12/31/2015

PPA - No

California Energy Commission

AES Redondo BeachRedondo Beach Generating Station

Replacement

496 MW (3-on-1 air-cooled combined cycle)

City of Redondo Beach

PSA workshops 5/2015

CEC Decision 2016

OTC compliance date 12/31/2020

PPA - No

California Energy Commission

AES Huntington BeachHuntington Beach Generating Station Replacement

644 MW air-cooled combined cycle

[200 MW LMS 100 simple cycle]

City of Huntington Beach

Amendment to CEC Decision expected 9/2015

OTC compliance date 12/31/2020

PPA- Yes (644 MW)

California Energy Commission

NRG CarlsbadEncina Power Station Replacement

City of Carlsbad

Petition to Amend filed 4/23/2013 for 632 MW (6 LMS 100 simple cycle) and removal of Encina Generating Station

CEC Decision 7/2015

Storage tank demolition underway

Start of Construction TBD

OTC compliance date 12/31/2017

PPA – Yes (500 MW)

California Energy Commission

Pio Pico300 MW simple cycle project approved by CEC 9/12/2012

San Diego County (Otay Mesa)

Project construction started 2/2015

Operation expected 9/2016

California Energy Commission

Wellhead

Wellhead

98 MW (2 LM 6000)

City of Stanton

AFC expected in 2015 after CPUC approves PPA

PPA - Yes

California Energy Commission

Status of Southern California Power Plants

May 20, 2015 11

Project Capacity Development Status ScheduleOTC

Compliance Date

Puente 262 MW Info Hrng 8/2015 CEC Decision 2016 12/31/2020

El Segundo 1El Segundo 2

560 MW449 MW

Operational 8/2013FSA 8/2015

N/ACEC Decision 2015

N/A12/31/2015

Redondo 496 MW PSA wkshps 5/2015 CEC Decision 2016 12/31/2020

Alamitos 640 MW +400MW

AFC supplement expected 2015

Unknown 12/31/2020

Huntington Beach

644 MW +200MW

Amendment to CEC Decision expected 9/2015

Unknown 12/31/2020

Carlsbad 632 MW CEC Decision 7/2015 Const. start TBD 12/31/2017

Wellhead 98 MWAFC expected 2015 after PPA approved

Unknown N/A

Pio Pico 300 MW Const. started 2/2015 Operation 9/2016 N/A

Recommended