Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden Dr. to Simmons Loop Project Numbers: 69647000 – PLAT ( US 41 to US 301), 69656000 – PD&E
Quick Facts • Location: Gibsonton/Riverview • Length: 1.25 miles, from Covington Garden
Dr. to Simmons Loop
• Category: Planning
Schedule • Project Development & Environmental Study
complete late 2019 (FDOT & County)
• Preliminary Design and Land Acquisition begins Early 2019 (County –transfer to FDOT)
• Design‐Build Procurement begins Early 2020
(FDOT)
• Construction start begins late 2021 • Design‐Build Construction complete Late 2024
(FDOT)
Overview • Widen Big Bend Road from a 4‐lane divided road, from Covington Garden Drive to Simmons Loop to 6‐lanes including enhanced pedestrian, bicycle and bus facilities.
• Improvements to I‐75 interchange to be designed and constructed by Florida Department of Transportation (FDOT)
• Reconstruction of bridge on Old Big Bend Road.
• Reconstruction of bridge on Big Bend Road • Signal improvements at Covington Gardens and Simmons Loop.
• Enhance pedestrian safety features, including wide sidewalks and enhanced crosswalks and signals.
• Improve stormwater drainage.
Benefits• Better accommodate growth and traffic
volume
• Increase the overall mobility along Big Bend and I‐75, while maximizing safety along the corridor
Project Funding • Total: $62.55 FDOT: $8 million
Federal: $1.5 million
County: $53.05 million
Hillsborough County has applied for a Build Grant in the amount of $25 million.
Hillsborough County is also pursuing additional funding from FDOT to offset local County funds
October 2018 Note: The information on this fact sheet is subject to periodic updates.
Questions? Manny Santos, E. I.
Public Works Project Manager (813) 635‐5400
Capital Improvement Program Project Fact Sheet Big Bend Road Widening – US 41 to Covington Gardens Drive and Simmons Loop to US Hwy 301 Project Number: 69647000 – PD&E & Design (US 41 to Covington Gardens) Project Number: 691149000 – PD&E (Simmons Loop to US Hwy 301)
Quick Facts • Location: Gibsonton/Riverview • Length: 1.75 mile, from US 41 to Covington
Gardens Drive and Simmons Loop to US 301
• Category: Planning
Schedule • Project Development & Environmental Study
Begins mid 2019
• Preliminary Design and Land Acquisition begins Early 2021
• Construction begins Late 2023
Overview • Widen Big Bend Road from a 4‐lane divided road, from US 41 to Covington Garden Drive to 6‐lanes including enhanced pedestrian, bicycle and bus facilities.
• Enhance pedestrian safety features, including wide sidewalks and enhanced crosswalks and signals.
• Improve stormwater drainage.
Benefits • Better accommodate growth and traffic
volume
• Increase the overall mobility along Big Bend, while maximizing safety along the corridor
Project Funding Total: $ 20.3 million
Cost Estimate • Total: $20.3 million
PD&E: $1.5 million
Land Acquisition: $4.0 million
Design: $2.5 million
Construction: $12.3 million
October 2018 Note: The information on this fact sheet is subject to periodic updates.
Questions? Manny Santos, E. I.
Public Works Project Manager (813) 635‐5400
BIG BEND ROAD
PROJECT SCHEDULE