Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden Dr. to Simmons Loop Project Numbers: 69647000 – PLAT ( US 41 to US 301), 69656000 – PD&E Quick Facts Location: Gibsonton/Riverview Length: 1.25 miles, from Covington Garden Dr. to Simmons Loop Category: Planning Schedule Project Development & Environmental Study complete late 2019 (FDOT & County) Preliminary Design and Land Acquisition begins Early 2019 (County –transfer to FDOT) DesignBuild Procurement begins Early 2020 (FDOT) Construction start begins late 2021 DesignBuild Construction complete Late 2024 (FDOT) Overview Widen Big Bend Road from a 4lane divided road, from Covington Garden Drive to Simmons Loop to 6lanes including enhanced pedestrian, bicycle and bus facilities. Improvements to I75 interchange to be designed and constructed by Florida Department of Transportation (FDOT) Reconstruction of bridge on Old Big Bend Road. Reconstruction of bridge on Big Bend Road Signal improvements at Covington Gardens and Simmons Loop. Enhance pedestrian safety features, including wide sidewalks and enhanced crosswalks and signals. Improve stormwater drainage. Benefits Better accommodate growth and traffic volume Increase the overall mobility along Big Bend and I75, while maximizing safety along the corridor Project Funding Total: $62.55 FDOT: $8 million Federal: $1.5 million County: $53.05 million Hillsborough County has applied for a Build Grant in the amount of $25 million. Hillsborough County is also pursuing additional funding from FDOT to offset local County funds October 2018 Note: The information on this fact sheet is subject to periodic updates. Questions? Manny Santos, E. I. Public Works Project Manager (813) 6355400

Capital Improvement Program Projectmediaassets.abcactionnews.com/document/2018/Big Bend Fact...Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Capital Improvement Program Projectmediaassets.abcactionnews.com/document/2018/Big Bend Fact...Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden

 

Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden Dr. to Simmons  Loop Project Numbers: 69647000 – PLAT ( US 41 to US 301), 69656000 – PD&E 

 

Quick Facts • Location: Gibsonton/Riverview • Length: 1.25 miles, from Covington Garden 

Dr. to Simmons Loop 

• Category: Planning 

 Schedule • Project Development & Environmental Study 

complete late 2019 (FDOT & County) 

• Preliminary Design and Land Acquisition begins Early 2019 (County –transfer to FDOT) 

• Design‐Build Procurement begins Early 2020 

(FDOT) 

• Construction start begins late 2021 • Design‐Build Construction complete Late 2024 

(FDOT) 

 Overview • Widen Big Bend Road from a 4‐lane divided road, from Covington Garden Drive to Simmons Loop to 6‐lanes including enhanced pedestrian, bicycle and bus facilities. 

• Improvements to I‐75 interchange to be designed and constructed by Florida Department of Transportation (FDOT) 

• Reconstruction of bridge on Old Big Bend Road. 

• Reconstruction of bridge on Big Bend Road • Signal improvements at Covington Gardens and Simmons Loop. 

• Enhance pedestrian safety features, including wide sidewalks and enhanced crosswalks and signals. 

• Improve stormwater drainage. 

Benefits• Better accommodate growth and traffic 

volume 

• Increase the overall mobility along Big Bend and I‐75, while maximizing safety along the corridor 

 Project Funding • Total: $62.55  FDOT: $8 million 

Federal: $1.5 million 

County: $53.05 million 

  Hillsborough County has applied for a Build Grant in the amount of $25 million.            

 

Hillsborough County is also pursuing additional funding from FDOT to offset local County funds 

 

     October 2018 Note: The information on this fact sheet is subject to periodic updates. 

Questions? Manny Santos, E. I. 

Public Works Project Manager (813) 635‐5400 

  

Page 2: Capital Improvement Program Projectmediaassets.abcactionnews.com/document/2018/Big Bend Fact...Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden

 

Capital Improvement Program Project Fact Sheet Big Bend Road Widening – US 41 to Covington Gardens Drive and                                                       Simmons Loop to US Hwy 301 Project Number: 69647000 – PD&E & Design (US 41 to Covington Gardens) Project Number: 691149000 – PD&E (Simmons Loop to US Hwy 301) 

 

 Quick Facts • Location: Gibsonton/Riverview • Length: 1.75 mile, from US 41 to Covington 

Gardens Drive and Simmons Loop to US 301 

• Category: Planning 

 Schedule • Project Development & Environmental Study 

Begins mid 2019 

• Preliminary Design and Land Acquisition begins Early 2021 

• Construction begins Late 2023 

 Overview • Widen Big Bend Road from a 4‐lane divided road, from US 41 to Covington Garden Drive to 6‐lanes including enhanced pedestrian, bicycle and bus facilities. 

• Enhance pedestrian safety features, including wide sidewalks and enhanced crosswalks and signals. 

• Improve stormwater drainage. 

Benefits • Better accommodate growth and traffic 

volume 

• Increase the overall mobility along Big Bend, while maximizing safety along the corridor 

 Project Funding  Total: $ 20.3 million 

 

Cost Estimate • Total: $20.3 million 

PD&E: $1.5 million 

Land Acquisition: $4.0 million 

Design:  $2.5 million 

Construction: $12.3 million  

 

                October 2018 Note: The information on this fact sheet is subject to periodic updates. 

 

 

 

 

Questions? Manny Santos, E. I. 

Public Works Project Manager (813) 635‐5400 

 

Page 3: Capital Improvement Program Projectmediaassets.abcactionnews.com/document/2018/Big Bend Fact...Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden
Page 4: Capital Improvement Program Projectmediaassets.abcactionnews.com/document/2018/Big Bend Fact...Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden

BIG BEND ROAD 

PROJECT SCHEDULE