DongYang BIM Process - CITYWALL ENG Co., Ltd.: HOME ·  · 2014-08-25DONGYANG STRUCTURAL ENGINEERS...

Preview:

Citation preview

20 DONGYANG STRUCTURAL ENGINEERS GROUP

DongYang BIM Process

03

21 DONGYANG STRUCTURAL ENGINEERS GROUP

Analysis

Bills of Quantities

Building Management

Fabrication Details

Project Management

3D Visualization

2D Drawings

03 DongYang BIM Process

• B I M 을 통 한 업 무 기 대 효 과

22 DONGYANG STRUCTURAL ENGINEERS GROUP

SD

BIM

DD+CD

BIM

As Built

Model

2D

CAD

Revit Tekla

Micro

staion

Catia

Inventor

Advance

Steel

3D

MAX

Rhino

Sketch

up

03

관련 프로그램

DongYang BIM Process

Archi

CAD

23 DONGYANG STRUCTURAL ENGINEERS GROUP

SD

BIM

DD+CD

BIM

As Built

Model

Document

Model

Detail

Model

Structural

Analysis

Studies Structural

Model

Architecture

Design

Studies

Structural

4D

Simulation Structural

5D

Cost

Structural 4D

Simulation

Structural

5D

Cost

Building

Model

2D

Document

Curtain

wall

Panel

Systems

03

활용 프로세스

DongYang BIM Process

24 DONGYANG STRUCTURAL ENGINEERS GROUP

03 DongYang BIM Process

• C r a s h D e t e c t i o n

This is not only to find design errors by checking

interferences, but also to collaborate with each

sector and to provide possible problems by using

BIM data. It brings significant advantages in

financially and in time.

25 DONGYANG STRUCTURAL ENGINEERS GROUP

03 DongYang BIM Process

• D i g i t a l F a b r i c a t i o n

Digital Modeling and Fabrication is a process that

joins Design with the Construction / Production

through the use of 3D modeling software and

additive and subtractive manufacturing processes.

These tools allow designers to produce digital

materiality, which is something greater than an

image on screen, and actually tests the accuracy

of the software and computer lines.

26 DONGYANG STRUCTURAL ENGINEERS GROUP

03 DongYang BIM Process

• P r e - C o n s t r u c t i o n

OVERALL PROJECT EVALUATION

- Our goal is to generate sufficient thought,

insight and communication that the big picture of

the project is well understood by all project

participants. This is where we ensure a good

foundation for the project

SITE ANALYSIS

– We find the way to confirm that the site will

conform to the requirements of the project without

excessive cost or future surprises.

27 DONGYANG STRUCTURAL ENGINEERS GROUP

03 DongYang BIM Process

• S k i n S t r u c t u r e & P a n e l i n g

More complicating and enlarging façade and exterior

shape requires intricate structural system and higher costs.

However, BIM provides simpler and modularized paneling

work which suggests efficient structural system and better

constructability.

28 DONGYANG STRUCTURAL ENGINEERS GROUP

국내 BIM 프로젝트

04

29 DONGYANG STRUCTURAL ENGINEERS GROUP

Size : 4F

Gross Area : 90,000㎡

Architect : Space Group

Young In Citizen Stadium Park

First BIM Turn-Key Project in Korea 04

2 0 1 4 Dong Yang Structural Engineers Group

Revit Structure

Navis works MEP

Construction Stie

Young In Citizen Stadium Park

DONGYANG STRUCTURAL ENGINEERS GROUP

흙막이 가시설 검토 장비 반입 검토

가설 벤트 검토 크레인 검토

시공단계 BIM의 활용

DONGYANG STRUCTURAL ENGINEERS GROUP

공종간 간섭 체크(골조와 설비간의 간섭)

DONGYANG STRUCTURAL ENGINEERS GROUP

안전시설물 설치계획 및 검토

DONGYANG STRUCTURAL ENGINEERS GROUP

레미콘 타설 관리

DONGYANG STRUCTURAL ENGINEERS GROUP

파일 항타 작업 관리

2 0 1 4 Dong Yang Structural Engineers Group

4D Simulation

37 DONGYANG STRUCTURAL ENGINEERS GROUP

Seoul National University Hospital

Revit Structural

Temporary Beam

Sunken View Construction Sequence

04 BIM Project in Korea

Recommended