Earned Value Dashboard - Gantt chart · Earned Value PV Earned Value Dashboard PV (BCWS) EV (BCWP)...

Preview:

Citation preview

IV I II III

J A S O N D J F M A M J J

Plan

Baseline

0

1,500

3,000

4,500

6,000

7,500

9,000

10,500

12,000

13,500

15,000

16,500

18,000

19,500

21,000

22,500

24,000

25,500

27,000

28,500

30,000

BudgetActualEarned ValuePV

Earned Value Dashboard

PV(BCWS)

EV(BCWP)

ActualCost

BaselineCost

Name PercentComplete

SV CV CPI

$6,296$6,703$13,924$19,873 PROJECT SUMMARY $407.05 ($7,221) 0.48

$1,489$1,480$3,000$3,523TEST MOTOR DESIGN AND SUPPORT ($9.01) ($1,520) 0.49

$1,803$1,907$3,050$4,333ANALYSIS PLAN $103.47 ($1,143) 0.63

$1,900$1,984$2,050$4,222TEST & VERIFICATION PLAN $84.44 ($66) 0.97

$429$508$3,600$1,452DESIGN PLAN $78.78 ($3,092) 0.14

$675$825$2,224$6,343SYSTEM DESIGN ANALYSIS $149.37 ($1,399) 0.37

$0$0$0$2,555SYSTEMS ENGINEERING AND INTEGRATION $0.00 $0 0.00

Plan

Baseline