FBISD 2014 Bond Program Project Manager: Gaurav Agarwal ...€¦ · Project Manager: Gaurav Agarwal...

Preview:

Citation preview

Project Summary

DULLES HIGH SCHOOLPhase 3 - BP24

FBISD 2014 Bond ProgramProgram Manager: JacobsProject Manager: Gaurav AgarwalProject Architect: Stantec Architecture, IncGeneral Contractor:Location: 550 Dulles Avenue, Sugar Land, TX 77478

SCHEDULE SUMMARY Main Construction Scope of Work Schedule (Excludes Cameras, Keying and Civil SOW if applicable)

COSTBUDGET COMMITMENTSFinancials include Security Cameras, Keying and Civil if applicable

A D E H=D+E+F+G I=C-H JB C=A+B K=J/CF G

Description Cost To DateBudget Changes

Current Budget

OriginalBudget

% ExpendedOriginalCommitments

Approved Changes

Pending Commitments

Estimate to Complete

ProjectedCommitments

ProjectedOver/Under

$917$0$456,509$257$824$456,527 ($18) $456,509Architect & Engineering/Professional Services 0%$0 $455,428

$338,456$0$4,002,989$0$413,958$4,000,122 $2,867 $4,002,989Construction 8%$0 $3,589,031

$0$0$29,194$0$0$29,194 $0 $29,194Site Development 0%$0 $29,194

$0$0$202,900$0$1,680$202,900 $0 $202,900Administrative and Other Project Costs 0%$0 $201,220

$0$0$260,712$0$0$262,633 ($1,921) $260,712Project Contingency 0%$0 $260,712

$113,553$0$288,000$0$130,736$288,000 $0 $288,000Security Cameras 39%$0 $157,264

$452,926$0$5,240,304$257$547,198$5,239,376 $928 $5,240,304 9%Totals $0 $4,692,849

SCOPE/COMMENTS PROJECT PHOTO BUDGET /COST STATUSSCOPE: BP24: Access Control including video intercom, Security Vestibules, Teller Window/Door Upgrade, Window Film, Central Cooling, Domestic Water Equipment, Carpeting, Wall Coverings, Wall Painting and Coating, Replacement of Public Address, Metal Exterior Door, Bleachers, Boiler/Air Handler HVAC Component, Water Heater Plumbing Fixtures, Drains, Gutters, Package Roof Top Unit, Exterior Condenser, Fan Coil HVAC Component, Motor Control Center, Roof Condenser, Generator, Panelboard, Power Service, Distribution Panel, Electrical Disconnect, Switchgear, and Electrical Transformer

BP01 and BP01A: Re-key Doors, Interior Door Hardware and Security Cameras BP02: Update Existing Sidewalk

COMMENTS: Architectural services were approved by the Board of Trustees and notice to proceed was issued. This work is scheduled for the last phase of the 2014 Bond program.

As approved by Board of Trustees on 05/16/2016, $928 was transferred from the Program Contingency in relation to BP02.

DULLES HIGH SCHOOLReport Date: 10/10/2016 42

Recommended