23 JunePFRC

JUNE 23, 2016

NEW ELEMENTARY SCHOOL AT THOMAS JEFFERSON MIDDLE SCHOOL

PFRC Meeting

1

23 JunePFRC

Project Parameters1. New Elementary School for the Henry Community 2. Support Strategic Plan Goal #4 – Provide Optimal      

Learning Environments3. Address capacity by providing 725 seats4. Open by start of school 20195. Multi‐story building in northwest corner of site6. Structured parking 7. Project cost $59 million 

2

23 JunePFRC

Concept DesignSiting and Massing:

general building location, shape, size, and height

General site layout and circulation: frontage bus loop/service accesspick-up and drop-off

Structured parking:rough target on number of parking spotsplay area above parking

Items for consensus 3

23 JunePFRC

June 15, 2016

NEW ELEMENTARY SCHOOL AT THOMAS JEFFERSON MIDDLE SCHOOL

Massing and Site Update

4

23 JunePFRC Comparison between 4.2 and 4.3

Scheme 4.2a: “Biscuit”

• 1st floor exterior footprint: 27,828 gsf• Gym on third floor• Building slightly cantilevers out as it goes up• 4 stories• Linear feet of exterior skin: 3,341 linear feet• Energy Use Intensity (EUI): 18 kBTU/sf/yr• Annual energy cost: $50,201• Roof space suitable for solar panels: 26,700 sf• Post energy production EUI: 4

Scheme 4.3a: “Lobster”

• 1st floor exterior footprint: 38,723 gsf• Gym on ground floor• Building significantly steps back as it goes up• Part 3 story, part 4 story• Linear feet of exterior skin: 3,769 linear feet• Energy Use Intensity (EUI): 18 kBTU/sf/yr• Annual energy cost: $50,652• Roof space suitable for solar panels: 53,760 sf • Post energy production EUI: -2.5

5

23 JunePFRC 4.2a “Biscuit” 4.3a “Lobster”6

23 JunePFRC 4.2a “Biscuit” 4.3a “Lobster”

Northern-most extent of facades of 4 story building massing in “Biscuit”

Northern-most extent of facade of 4 story building massing in “Lobster”

80’ further south

7

23 JunePFRC Scheme 4.3b8

23 JunePFRC Scheme 4.3b 225 garage spots, 50 feet between garage and MS9

23 JunePFRC Scheme 4.3b10

23 JunePFRC Scheme 4.3b11

23 JunePFRC Scheme 4.3b12

23 JunePFRC Scheme 4.3b13

23 JunePFRC Scheme 4.3b14

23 JunePFRC Scheme 4.3b15

23 JunePFRC Scheme 4.3b: 1st floor16

23 JunePFRC Scheme 4.3b17

23 JunePFRC Scheme 4.3b18

23 JunePFRC Scheme 4.3b19

23 JunePFRC Scheme 4.3b20

23 JunePFRC Scheme 4.3b21

23 JunePFRC Scheme 4.3b22

23 JunePFRC Scheme 4.3b: 1st floor23

23 JunePFRC Scheme 4.3b24

23 JunePFRC

Concept DesignSiting and Massing:

general building location, shape, size, and height

General site layout and circulation: frontage on South Old Glebebus loop/service access on north side of sitecombined pick-up and drop-off within parking garage

Structured parking:single level parking structure with maximum amount of parkingplay area above parking

Items for consensus 25

23 JunePFRC 26

23 JunePFRC

Discussion

New ES on Thomas Jefferson Site27

23 JunePFRC

NEXT STEPS

July 1 Concept Design to school board (information)

July 20 Concept Design to school board (action)

28

23 JunePFRC

ADJORN

For further information please contact:

APS Project ManagerSteve Stricker571-220-0048steven.stricker@apsva.us

Web links:APS Project Website PFRC Project WebsiteSubmit Public Comment and Sign up for Email Distribution

County Project ManagerMarco Rivero703-228-3572mrivero@arlingtonva.us

29