New York State Department of Transportation. NY Route 347 Route 111 to Mount Pleasant Road Design-Build Project Request for Qualifications Informational Meeting September 5, 2012. NY Route 347 – Design Build Agenda. Introductions and Opening Remarks Project Overview - PowerPoint PPT Presentation
Citation preview
NEW YORK STATE DEPARTMENT OF TRANSPORTATION
NY Route 347
Route 111 to Mount Pleasant Road
Design-Build Project
Request for Qualifications
Informational Meeting
September 5, 2012
1
NY Route 347 – Design BuildAgenda
Introductions and Opening Remarks Project Overview Quality Control & Quality Assurance Procurement Questions and Answers
2
Peter RussellAttn: NY Route 347
Office of Contracts ManagementNew York State Department of
Transportation50 Wolf Road, 6th Floor
Albany, New York 12232Peter.Russell@dot.ny.gov
NY Route 347 – Design BuildRules of Contact
3
NY Route 347 – Design BuildAgenda
Introductions and Opening Remarks Project Overview
General Location Goals General Scope of Work
NY Route 347 Vision Plan Quality Control & Quality Assurance Procurement Questions and Answers
4
NY Route 347 – Design Build General Location
5
Bike
Path
NY Route 347 – Design Build General Location
Start
End
6
NY Route 347 – Design Build Goals
Improve safety and mobility along the Route 347 Corridor;
Efficient and Effective Project Delivery; and
Implementation of the NY 347 Vision Plan.
7
NY Route 347 – Design Build Goals Continued…
Improve safety and mobility along the Route 347 Corridor by: Providing additional roadway lanes and
improving traffic flow; Implementing Intelligent Transportation
System (ITS) technology (use of INFORM); Improving access to public transportation; Providing enhancement to infrastructure for
use by pedestrians; and Creating a shared-use path for bicyclists and
pedestrians.
8
NY Route 347 – Design Build Goals Continued…
Efficient and Effective Project Delivery by: Ensure coordination with other construction
projects Minimize disruption to existing traffic Minimizing temporary construction impacts to
adjacent residents and businesses Keep adjacent residents and business informed Address general project related questions from public Forward project concept questions to NYSDOT Forward questions from elected & public officials and
the media to NYSDOT Deliver Project Safely, On Schedule, On Budget,
and Environmentally Compliant.
9
Implementation of the NY 347 Vision Plan by: Implement the principles of traffic calming
measures; Improving pedestrian and bicycle connectivity
along the roadway and to bus transit; Minimize the removal of existing vegetation and
provide extensive new plantings; Planting native vegetation to support wildlife; and Treating road runoff to improve water quality
NY Route 347 – Design Build Goals Continued…
10
NY Route 347 – Design Build General Scope of Work
Widening of NY Route 347 with additional travel lanes and shared-use path for pedestrians and bicyclists;
Pedestrian facility design and installation; Bus turnouts and enhanced bus stop design and
installation; Extensive landscape design and installation
potentially including, but not limited to: vegetated screening, planted raised median, street trees, vegetated drainage features;
Sound wall design and installation; and Installation of street and pedestrian lighting.
11
NY Route 347 – Design Build Typical Cross Section
12
NY Route 347 – Design Build General Scope of Work Continued…
Installation and integration of the INFORM system;
Traffic signals; Signing & pavement markings; Work Zone Traffic Control; Drainage and Utilities
13
NY Route 347 – Design Build General Scope of Work Continued…
Relocation and/or preservation of existing utilities Inventory of existing utilities provided to DB Team DB Team responsible for holding utility
coordination meetings DB Team to provide supporting documents for
utility design, including: plans, Special Note of Utility Coordination & Table of Conflicts
Special Note of Utility Coordination must include work description, proposed locations and time frames
Table of Conflicts to include existing & proposed locations
14
NY Route 347 – Design Build General Scope of Work Continued…
Relocation and/or preservation of existing utilities (continued) Supporting documents are required for Utility &
Municipal Agreements to be completed by RUE DB Team must include the cost to relocate
Suffolk County Water Authority facilities in their bid. The cost shall include all permits from the Suffolk County Dept of Health and all service connections
LIPA to provide a cost estimate for their work to the RUE, once all supporting documents are provided by the DB Team. The RUE will complete the Agreement
15
NY Route 347 – Design Build “The Threads that Weave”
Concepts in the Vision Plan include: Sustainability Smart Growth Context Sensitive Solutions Environmental Stewardship Walkability Livability GreenLITES
16
NY Route 347 – Design Build GreenLITES – Evergreen Certification
The New York State Department of Transportation (NYSDOT) is committed to improving the quality of our transportation infrastructure through the use of best practices that minimize impacts to the environment.
NYSDOT implemented “GreenLITES” (Leadership In Transportation and Environmental Sustainability), a project rating program recognizing four levels of successfully attaining these goals in our projects.
Route 347 will continue to implement as many of these best practices as possible achieving the
highest level of certification… …Evergreen.
17
NY Route 347 – Design Build Making Route 347 More “Bicycle & Pedestrian Friendly” & Multimodal
Improving Bicycle & Pedestrian Facilities Constructing a Shared-Use Path Adding Sidewalks Reducing Crossing Distances Extending Crossing Times at Crosswalks Creating “Greenway Stops” along the proposed shared-use path Enhancing Visibility & Motorist Cues at High Pedestrian Areas ie. Senior “Activity Centers”, Schools, etc
Improving Connections to Places of Interest, Community Centers, & Transit Identifying Destinations Improving Access to Community Centers & Parks Enhancing Bus Stops
18
NY Route 347 – Design Build “Enhancing the Plan”
Recognizing Opportunities for Improving & Expanding Non-Motorized Transportation
Alternatives Improving & Expanding Access to Mass Transit &
Connections Conserving Energy Improving & Preserving Quality of Life, Aesthetics, & the
Environment Stimulating the Economy
Developing a Corridor Theme “ Parks to Ports Greenway ”
Identifying & Highlighting Environmental Assets Greenway Stops, Interpretive Signs, Info. Kiosks
Utilizing Traffic Calming Features Narrowing Lane Widths Narrowing Shoulders Visually Narrowing by Adding Vertical Elements ie. Street
Trees, Decorative Street Lighting, and Aesthetically Enhanced Raised Planted Medians
Constructing a Buffer between Multi-Use Path and Shoulder Reducing the Posted Speed
19
NY Route 347 – Design Build Typical Plan
20
NY Route 347 – Design Build Proposed Sound Walls or Vegetated Screening
Sound Wall Design Objective to Provide Noise Abatement;
Must Maintain Proposed Wall’s : Location, Top Elevation, Length;
Must Integrate Sound Absorptive Material on Select Walls;
Must Provide a Through-Access Panel on at least one Wall
Design to Meet Conceptual Aesthetic Design Criteria
Vegetated Screening Design Objective to Provide Visual Screening to
the Road May use a combination of preservation
of existing vegetation, new planting and durable fence materials;
Design to Meet Conceptual Aesthetic Design Criteria
NY Route 347 – Design Build Proposed Greenway Stop
22
NY Route 347 – Design Build Implementing the NY Route 347 Vision Plan
23
NY Route 347 – Design Build Implementing the NY Route 347 Vision Plan
24
NY Route 347 – Design BuildAgenda
Introductions and Opening Remarks Project Overview Quality Control & Quality Assurance Procurement Questions and Answers
25
NY Route 347 – Design Build Quality Control (QC)
QC is Design-Builder’s Responsibility Design-Builder shall appoint a QC Manager responsible
for developing QC Plan for both Design and Construction
Design QC shall be by the Designer in accordance with the QC Plan
Construction Inspection shall be by an Independent Engineering Firm (Hired by the Design-Builder)
Materials Testing shall be by an Independent Testing Firm or Laboratory (Hired by the Design-Builder)
The Independent Testing Firm shall report to the Construction Inspection Firm who shall report to the Department
Offsite Plant Quality Control will be performed by the Department
26
NY Route 347 – Design Build Quality Assurance (QA)
QA is Department’s Responsibility The Department may perform QA on any
of the Design-Builder’s activities The Department may utilize an
independent Consultant to perform QA of the Design-Builder’s Designs
The Construction QA will be department staff.
27
NY Route 347 – Design BuildAgenda
Introductions and Opening Remarks Project Overview Quality Control & Quality Assurance Procurement
Schedule Contract Information SOQ Evaluation and Selection Additional Information and Website
Questions and Answers
28
NY Route 347 – Design Build Procurement Schedule
Activity Due Date
Final RFQ Released September 12, 2012
Final Date for receipt of Proposer’s questions September 28, 2012
Issue Date for Final Addendum to the RFQ and/or answers to Proposer’s questions
October 5, 2012
SOQ Due Date October 17, 2012
Shortlisted DB Teams Announced November 1, 2012
Draft RFP Issued November 7, 2012
Draft RFP Info Meeting November 20, 2012
Final RFP to Shortlisted Firms December 5, 2012
Proposals Due January 17, 2013
Selection of Best Value February 1, 2013
Execute Contract February 28, 2013
Notice to Proceed March 1, 2013
29
NY Route 347 – Design Build Contract Information
Lump Sum Design-Build Contract Two Step Design-Build Procurement Process Project Schedule
Total Duration 28 Months +/- (under review) There will be a Payment Schedule provided in the RFP Stipend Under Consideration by NYSDOT Liquidated Damages may be imposed for missed
milestones and final completion ROW by NYSDOT Construction Related Permits (i.e., SPDES) by Design-
Builder The final RFQ will be updated to reflect that only
Greenman-Pedersen, Inc. and Stantec Consulting Services, Inc. will be disqualified
30
NY Route 347 – Design Build SPDES General Permit
D/B Team to prepare SPDES Stormwater Pollution Prevention Plan (SWPPP) consistent with NYSDEC and NYSDOT procedures;
D/B Team shall design drainage system to treat Stormwater Quality and Quantity as per NYSDEC and NYSDOT guidance documents;
D/B Team to prepare Notice of Intent (NOI) for NYSDOT signature/submission to NYSDEC.
31
NY Route 347 – Design Build SOQ Evaluation and Selection
Pass/Fail Evaluation Factors Legal; Financial; Backlog Capacity; Proposal responsiveness; and Vendor Responsibility.
Quality Evaluation Factors Organization and Key Personnel (40%) Experience of the Firms (25%) Project Understanding (20%) Past Performance (15%)
32
NY Route 347 – Design Build Additional Information
Responses to Proposer Questions will be posted on the Department Website
Final Addendum to the RFQ will be issued by Friday, October 5, 2012
Additional Reference Information to be Posted on Website: Final Design Report / Final EIS / Final Section 4(F) Evaluation Contract D261357 Design Drawings (Adjacent Contract) As-Built Drawings NY 347 Soil Borings SUE Utility Data Route 347 Revaluation 23CFR771.129 – Review & Appendixes (Including
NY 347 Vision Plan)
There will be a Buy America Clause There will be a DBE Participation Goal
33
NY Route 347 – Design Build Project Website
https://www.dot.ny.gov/main/business-center/designbuildproject1
34
Peter RussellAttn: NY Route 347
Office of Contracts ManagementNew York State Department of
Transportation50 Wolf Road, 6th Floor
Albany, New York 12232Peter.Russell@dot.ny.gov
NY Route 347 – Design Build Project Contact
35
NY Route 347 – Design Build Questions and Answers
Questions??