BASE RAFT SLABRAW DATA:- Total Qty: 5043 m3;- Total Duration: 45 day; : - Barbender: 30 men;- Carpenter cum concretor: 20 men;- Casting method: mobile concrete pump with trunk distributorTYPICAL CASTING UNIT: - 35m x 10m, 460 m3;- Duration: 4d;PRODUCTION RATE FROM RAW DATA:5043/45/50=2.24 m3/man.d