View
11
Download
0
Category
Preview:
Citation preview
April 1, 2020 File No.: 301539.00025/14797
Matthew Ghikas Direct +1 604 631 3191
Facsimile +1 604 632 3191 mghikas@fasken.com
By Electronic Filing British Columbia Utilities Commission Suite 410, 900 Howe Street Vancouver, BC V6Z 2N3 Attention: Patrick Wruck, Commission Secretary
Dear Sirs/Mesdames:
Re: British Columbia Hydro and Power Authority (“BC Hydro”) F2020 to F2021 Revenue Requirements Application ~ Project No. 1598990
We enclose for filing BC Hydro’s Final Submission in the above-noted proceeding.
Yours truly,
FASKEN MARTINEAU DuMOULIN LLP [Original signed by] Matthew Ghikas Personal Law Corporation
MTG/lh Enclosure
301539.00025/94161307.1
BRITISH COLUMBIA UTILITIES COMMISSION
IN THE MATTER OF THE UTILITIES COMMISSION ACT,
R.S.B.C. 1996, CHAPTER 473
and
BRITISH COLUMBIA HYDRO AND POWER AUTHORITY
FISCAL 2020 TO FISCAL 2021 REVENUE REQUIREMENTS APPLICATION
Final Submission of BC Hydro
April 1, 2020 FASKEN MARTINEAU DuMOULIN LLP Matthew Ghikas, Christopher Bystrom and Tariq Ahmed
TABLE OF CONTENTS PART ONE: INTRODUCTION AND OVERVIEW ................................................................................ 1
A. INTRODUCTION .................................................................................................................... 1
B. SUBMISSION OVERVIEW AND KEY POINTS .......................................................................... 2
301539.00025/94161307.1
PART TWO: LEGAL FRAMEWORK AND THE PROPER SCOPE OF THE PROCEEDING ....................... 5
PART THREE: PROVIDING SAFE, RELIABLE AND COST EFFECTIVE SERVICE IN AN INCREASINGLY COMPLEX ENVIRONMENT............................................................................................................... 7
A. BC HYDRO HAS DEMONSTRATED ITS ATTENTION TO CONTAINING CONTROLLABLE COSTS ............................................................................................................................................. 7
B. THE DEMANDS ON BC HYDRO ARE INCREASING AS WORK BECOMES MORE COMPLEX ... 8
C. ADDITIONAL INVESTMENT WILL BE NECESSARY AFTER THE TEST PERIOD ....................... 12
PART FOUR: LOAD AND REVENUE FORECASTS ............................................................................ 13
A. INTRODUCTION .................................................................................................................. 13
B. SNAPSHOT OF THE OCTOBER 2018 LOAD FORECAST UNDERLYING THE EVIDENTIARY UPDATE .............................................................................................................................. 14
C. THE LOAD FORECAST METHODOLOGY HAS PERFORMED WELL IN RECENT YEARS .......... 15
D. THE TEST PERIOD LOAD FORECAST IS BASED ON AN IMPROVED METHODOLOGY .......... 16
(a) Improvements to the Methodology Respond to BCUC Commentary ........................ 16
(b) BC Hydro Has Incorporated Audit Recommendations on Methodology and Governance ................................................................................................................. 17
(c) BC Hydro Has Made Sector-Specific Methodology Improvements for All Four Sectors 20
E. THE CONFIDENCE INTERVAL AROUND THE MID FORECAST CAPTURES A VARIETY OF UNCERTAINTIES ................................................................................................................. 25
F. THE JUNE 2019 20-YEAR LOAD FORECAST UPDATE IMPACTS THE YEARS AFTER THE TEST PERIOD ............................................................................................................................... 27
G. THE OCTOBER 2018 LOAD FORECAST ALREADY ASSUMED FORESTRY SUB-SECTOR DECLINE .............................................................................................................................. 28
H. THE LOAD FORECAST INCLUDES THE PORTION OF THE CLEANBC “UPSIDE” POTENTIAL THAT CAN REASONABLY BE ASSESSED AT THIS TIME ........................................................ 29
(a) The June 2019 Load Forecast Reflects Some, but Not All, of the CleanBC Initiatives 30
(b) BC Hydro Continues to Work to Build Load and Remove Barriers to Electrification . 31
I. REGULATORY ACCOUNTS TRUE-UP ANY VARIANCES FROM THE LOAD FORECAST .......... 33
J. REVENUE FORECAST IS INDUSTRY STANDARD AND CONSISTENT WITH PAST PRACTICE . 34
K. CONCLUSION AND REQUESTED FINDINGS ........................................................................ 34
PART FIVE: FORECAST COST OF ENERGY ..................................................................................... 35
A. INTRODUCTION .................................................................................................................. 35
B. FORECAST INCREASE IN THE COST OF ENERGY DRIVEN BY EXISTING EPAS, FOR WHICH COST RECOVERY IS DIRECTED ............................................................................................ 36
301539.00025/94161307.1
(a) The Vast Majority of Total IPP Purchase Cost Increases Are Related to Existing EPAs 37
(b) A Small Portion of the Total IPP Purchase Cost Relates to EPA Renewals, which Includes Directed Biomass Purchases, and New EPAs ............................................... 38
C. BC HYDRO IS TAKING AVAILABLE STEPS TO MITIGATE IPP ENERGY COSTS ...................... 40
D. FORECAST COST OF ENERGY REFLECTS HOW BC HYDRO OPERATES THE SYSTEM ........... 41
(a) BC Hydro’s Operating Horizon Objective (Meeting Load First While Maximizing Value Within a Range of Outcomes) Is in the Best Interests of Ratepayers ........................ 42
(b) In 2018, BC Hydro Managed Through Significant Events While Maximizing Value for Ratepayers .................................................................................................................. 46
(c) Energy Study Methodology Produces a Sound Price Signal that Enables BC Hydro to Achieve its Operating Objective ................................................................................. 50
(d) The Lower Cost of Energy Forecast in the Evidentiary Update Reflects Shift from Run-of-River IPP Power to Lower Cost Market Purchases Due to Low Water Conditions ................................................................................................................... 53
E. BC HYDRO IS GETTING THE MOST OUT OF ITS HERITAGE ASSETS .................................... 54
(a) Operating Horizon: Prioritizing Operating Specific Heritage Assets Over Existing EPAs Would Be Detrimental to Ratepayers ........................................................................ 55
(b) Planning Horizon: Capital Planning Maximizes the Long-Term Benefits from Heritage Assets .......................................................................................................................... 55
F. VARIANCE ACCOUNTS ENSURE CUSTOMERS PAY ACTUAL COST OF ENERGY .................. 56
G. CONCLUSION AND REQUESTED FINDINGS ........................................................................ 57
PART SIX: OPERATING COSTS ....................................................................................................... 58
A. INTRODUCTION .................................................................................................................. 58
B. OPERATING COSTS SNAPSHOT: COST PRESSURES WITH OFFSETTING TEST PERIOD SAVINGS ............................................................................................................................. 59
C. BC HYDRO ADDRESSED THE BCUC’S RECOMMENDATIONS AND COMMENTS ON OPERATING COSTS ............................................................................................................. 60
D. BC HYDRO’S ROBUST BUDGETING AND GOVERNANCE PROCESSES DRIVE COST CONTAINMENT EFFORTS ................................................................................................... 62
(a) BC Hydro’s Budgeting Approach Assessed More than Just Incremental Requirements and Imposed Limits on Funding .................................................................................. 62
(b) The Advantages of BC Hydro’s Budgeting Approach Over Zero-based Budgeting Include $24 Million Lower Budgeted Operating Costs ............................................... 63
(c) BC Hydro’s Governance Process Includes Vacancy Management, Performance Metrics and Regular Reporting ................................................................................... 64
301539.00025/94161307.1
E. BC HYDRO ABSORBED CONTROLLABLE COST PRESSURES WITHIN EXISTING BUDGETS, WITH INCREASES GENERALLY ATTRIBUTABLE TO UNCONTROLLABLE COSTS .................. 66
(a) Non-Controllable Storm Restoration Costs Are a Significant Driver of Operating Costs Increases ..................................................................................................................... 67
(b) The Employer Health Tax and Rising Cost of Health Care Contribute to Standard Labour Rate Increases................................................................................................. 68
(c) Salary Increases Are Needed to Keep Pace With the Market After Years of Restraint 69
(d) Changes in the Discount Rate Increased BC Hydro’s Pension Costs .......................... 72
F. BC HYDRO HAS USED A NUMBER OF MEANS TO CONTROL COSTS AND ABSORB NEW UNCONTROLLABLE OPERATING COST PRESSURES ............................................................ 73
(a) Replacing Contractors with Internal FTEs (Workforce Optimization) Has Decreased Total Costs by $18.5 Million Annually ........................................................................ 74
(b) Accenture Repatriation Provides $8.2 Million of Annual Savings During the Test Period .......................................................................................................................... 78
(c) BC Hydro Has Reflected Vacancy Factor Savings in the Revenue Requirements ...... 80
(d) BC Hydro Has Eliminated the Unallocated Funds Budget .......................................... 81
(e) Eliminating a Property Lease is Expected to Generate Additional $1.2 Million in Savings ........................................................................................................................ 83
(f) BC Hydro Has Reduced the Communications Budget by an Additional $1.2 Million. 83
(g) Expansion of Paperless Billing Expected to Generate Additional $1 Million in Savings 83
(h) Work Smart Program Creates Capacity to Manage Workload and Avoids Costs ...... 84
(i) “Making it Easier to Get Work Done” Initiative Offsets Increased Complexity of Work 89
G. FTE NUMBERS REFLECT WORK ON SITE C AND COST-EFFECTIVE INSOURCING ................ 89
(a) FTE’s Have Remained Relatively Flat Since Fiscal 2012 Except For Capital Projects .. 90
(b) Site C Project is the Only Organizational Need Driving Net New Positions in the Test Period .......................................................................................................................... 91
(c) BC Hydro Uses Overtime Only When it Makes Financial Sense ................................. 93
H. BC HYDRO IS OPTIMIZING POWER SYSTEM MAINTENANCE ............................................. 94
(a) BC Hydro Uses Industry-Leading Maintenance Practices........................................... 95
(b) BC Hydro Benchmarks Very Well on Maintenance Costs........................................... 96
(c) The Increases Planned in the Test Period Provide for Only Limited New Activity ..... 99
(d) Vegetation Management is a Priority and Will Need Additional Investment After this Test Period ................................................................................................................ 100
301539.00025/94161307.1
I. BRATTLE REPORT AND INDICATIVE COMPARISON SUPPORTS THE REASONABLENESS OF BC HYDRO’S OPERATING COSTS ...................................................................................... 102
(a) BC Hydro Benchmarks Favourably Against U.S. Peer Group on Operating Costs (Brattle Report) ......................................................................................................... 103
(b) BC Hydro Compares Well in Indicative Canadian Utility Comparison ...................... 105
(c) Value of Continuing to Prepare Uniform System of Accounts Must Be Weighted Against Other Priorities and Costs ............................................................................ 105
J. CONCLUSION AND REQUESTED FINDINGS ...................................................................... 107
PART SEVEN: CAPITAL EXPENDITURES AND ADDITIONS ........................................................... 108
A. INTRODUCTION ................................................................................................................ 108
B. BC HYDRO’S EVIDENCE SUPPORTING CAPITAL FORECASTS IS SUBSTANTIAL AND ACCORDS WITH APPROVED CAPITAL FILING GUIDELINES ............................................... 109
C. BC HYDRO HAS A ROBUST CAPITAL PLANNING PROCESS ............................................... 110
(a) The Top-Down and Bottom-Up Approach Permits Balancing Affordability, System Performance and Risk ............................................................................................... 111
(b) Affordability is Reflected Throughout the Capital Planning Process........................ 114
(c) BC Hydro Has Improved the Governance Framework for Ex-Plan Projects ............. 114
(d) New Value-Based Assessment Approach Represents the Evolution of BC Hydro’s Capital Prioritization Process .................................................................................... 116
D. BC HYDRO HAS REDUCED THE CAPITAL FORECAST TO BALANCE AFFORDABILITY, SYSTEM PERFORMANCE AND RISK ................................................................................................ 117
(a) Strong System Performance and Slower Demand Growth Created Opportunity for Moderating Capital Spending ................................................................................... 117
(b) Asset Condition and Performance Will Be Monitored ............................................. 120
(c) Additional Reductions in Capital Spending Would Be Undesirable ......................... 121
E. BC HYDRO DELIVERS CAPITAL PROJECTS EFFICIENTLY AND EFFECTIVELY....................... 122
(a) BC Hydro’s Planning and Delivery Functions Work Together to Ensure Seamless Transition and Accountability ................................................................................... 122
(b) BC Hydro’s Delivery Processes Are Tailored to the Size and Complexity of Projects 122
(c) BC Hydro is Continuously Improving its Delivery Processes .................................... 126
(d) BC Hydro Has Rigorous Financial Approval Processes in Place for All Investments. 126
(e) BC Hydro Evaluates Power System Projects Upon Completion ............................... 127
(f) BC Hydro Has Delivered its Capital Portfolio On Budget .......................................... 128
(g) Improvements in Technology Processes Have Brought Strong Results ................... 133
301539.00025/94161307.1
F. BC HYDRO’S CAPITAL MANAGEMENT PROCESSES HAVE BEEN ENDORSED BY THIRD PARTIES ............................................................................................................................ 134
G. AMORTIZATION OF CAPITAL ADDITIONS REGULATORY ACCOUNT WILL ENSURE THAT CUSTOMERS ONLY PAY ACTUAL COSTS ........................................................................... 135
H. EXPENDITURES ON RIP RAP FOR W.A.C. BENNETT DAM WERE PRUDENT ..................... 136
I. VARIANCE OF DIRECTIVE 3 IS WARRANTED AND MIN TO LNG CANADA PROJECT IS EXEMPT ............................................................................................................................ 138
J. BC HYDRO HAS ANSWERED SPECIFIC ISSUES RAISED ...................................................... 140
(a) The PRES Project is a Prescribed Undertaking ......................................................... 140
(b) Bear Mountain Terminal to Dawson Creek Transmission Voltage Conversion and North Montney – Transmission Development Projects May Also be Prescribed Undertakings ............................................................................................................. 143
(c) Electric Vehicle Investments are Added to Rate Base per Direction No. 8 .............. 144
(d) BC Hydro is Managing Cybersecurity Risks ............................................................... 145
(e) BC Hydro is Appropriately Coordinating Projects in the Same Location and Individual Projects at the Same Location Should Not Be Combined ........................................ 150
(f) Strategic Property Purchases in Vancouver Support Substation Projects and Will Be Included in Future Substation CPCN Applications .................................................... 155
(g) Project Write-Offs Demonstrate Maturity of Capital Planning and Delivery Processes 160
(h) BC Hydro Has Explained Variances from Plan on Past Projects ............................... 160
(i) Industrial Load Interconnection: BC Hydro Has and Is Improving the Process ........ 163
K. CONCLUSION AND REQUESTED FINDINGS ...................................................................... 171
PART EIGHT: REGULATORY ACCOUNTS ..................................................................................... 172
A. INTRODUCTION ................................................................................................................ 172
B. BC HYDRO’S REGULATORY ACCOUNTS ADHERE TO ACCOUNTING STANDARDS AND BCUC GUIDELINES ...................................................................................................................... 173
C. FOCUS ON THE MERITS OF EACH ACCOUNT, NOT THE NUMBER OF ACCOUNTS ........... 175
(a) Regulatory Accounts Are Common and Numbers Vary Widely Among Utilities ..... 175
(b) BC Hydro is Proposing to Close Four Regulatory Accounts, With Up to Four More Soon to Follow .......................................................................................................... 177
D. BC HYDRO’S REGULATORY ACCOUNTS ARE BENEFICIAL TO CUSTOMERS ...................... 177
(a) Cost of Energy Variance Accounts Manage Uncontrollable Factors and Volatility .. 177
(b) Non-Current Pension Cost Regulatory Account Manages Uncontrollable Factors and Volatility .................................................................................................................... 179
301539.00025/94161307.1
(c) Real Property Sales Regulatory Account Allows Ratepayers to Receive Benefits that Would Otherwise Flow to the Shareholder .............................................................. 180
(d) DSM Regulatory Account Ensures Intergenerational Equity by Matching Costs and Benefits ..................................................................................................................... 184
(e) Remediation Regulatory Account Manages Uncontrollable and Unpredictable Costs 186
E. BC HYDRO AND GOVERNMENT HAVE ADDRESSED THE AUDITOR GENERAL’S CONCERNS ABOUT REGULATORY ACCOUNTS .................................................................................... 186
F. BC HYDRO IS MANAGING REGULATORY ACCOUNT BALANCES APPROPRIATELY ........... 187
(a) Overall Regulatory Balance Has Declined Significantly from its Peak ...................... 187
(b) Approximately 80% of the Fiscal 2024 Forecast Balance is Associated With Longer-Term Accounts .......................................................................................................... 188
(c) Appropriate BCUC-approved Recovery Mechanisms Are in Place ........................... 188
(d) Cost Control Measures Are in Place for Deferred Controllable Costs ...................... 193
G. BC HYDRO’S PROPOSED CHANGES TO REGULATORY ACCOUNTS ARE WARRANTED ..... 194
(a) Proposal to Reduce the DARR and Refund the Balance in the Cost of Energy Variance Accounts over the Test Period Promotes Intergenerational Equity and Rate Stability 194
(b) Proposal to Defer Variances Related to EPAs that are Leases Under IFRS 16 to the Non-Heritage Deferral Account Means Ratepayers Will Pay Actual Costs through Stable Rates .............................................................................................................. 195
(c) Proposal to Defer Variances Between Forecast and Actual Amounts Related to Biomass Energy Program Means BC Hydro Will Recover its Costs, as Directed ...... 198
(d) Proposal to Continue Deferring Dismantling Costs Recognizes Uncontrollable Nature and Supports Regulatory Efficiency .......................................................................... 198
H. FORECAST FOR REAL PROPERTY SALES IS REASONABLE ................................................. 200
I. CONCLUSION AND REQUESTED FINDING ........................................................................ 202
PART NINE: OTHER REVENUE REQUIREMENTS ITEMS .............................................................. 203
A. INTRODUCTION ................................................................................................................ 203
B. TEST PERIOD REVENUE REQUIREMENTS REFLECT APPROPRIATE DEPRECIATION RATES ......................................................................................................................................... 204
C. BC HYDRO’S FORECAST FINANCE CHARGES ARE A REASONABLE BASIS FOR SETTING RATES ............................................................................................................................... 207
(a) Hedging Strategy has Mitigated Interest Rate Risk .................................................. 207
(b) Evidentiary Update Used the Most Recent Interest Rates Available for Unhedged Debt .......................................................................................................................... 208
301539.00025/94161307.1
(c) Regulatory Accounts Are an Efficient Means of Addressing Interest Rate Changes Since the Evidentiary Update ................................................................................... 209
D. INTERGROUP’S RECOMMENDATIONS REGARDING BC HYDRO’S FUTURE RETURN ON EQUITY ARE PREMATURE ................................................................................................. 209
E. CONCLUSION AND REQUESTED FINDINGS ...................................................................... 210
PART TEN: TRANSMISSION REVENUE REQUIREMENTS ............................................................. 211
A. INTRODUCTION ................................................................................................................ 211
B. THE TRR AND OATT RATES REFLECT ESTABLISHED COST OF SERVICE METHODOLOGY AND APPROVED RATE DESIGN ................................................................................................. 211
C. RE-EXAMINING THE MERITS OF THE OATT RATE DESIGN IS UNNECESSARY ................... 213
D. CONCLUSION AND REQUESTED FINDINGS ...................................................................... 215
PART ELEVEN: DEMAND-SIDE MANAGEMENT .......................................................................... 216
A. INTRODUCTION ................................................................................................................ 216
B. MODERATION APPROACH CONTINUES TO BE A REASONABLE RESPONSE TO ENERGY SURPLUS ........................................................................................................................... 217
C. BC HYDRO’S TRADITIONAL DSM PLAN RESPONDS TO BCUC DIRECTIVES, GOVERNMENT PRIORITIES AND DSM REGULATION ................................................................................ 220
(a) BC Hydro Has Increased Residential Initiatives by Approximately 50% ................... 220
(b) BC Hydro Has a New Commercial Social Housing Initiative ..................................... 222
(c) BC Hydro Has Increased its Activities in Non-Integrated Areas ............................... 223
(d) BC Hydro Has Updated How it Presents its Codes and Standards Savings .............. 226
(e) BC Hydro Has Extended the Funding Period for Capacity Focused Initiatives ......... 227
(f) BC Hydro Has Re-categorized Energy Management Activities to Align with DSM Regulation ................................................................................................................. 228
D. DIRECTION 61 REGARDING ALLOCATION OF PORTFOLIO COSTS SHOULD BE RESCINDED ......................................................................................................................................... 228
E. TRADITIONAL DSM IS ALIGNED WITH THE UCA, CLEAN ENERGY ACT, AND DSM REGULATION .................................................................................................................... 229
(a) The UCA Constrains the BCUC’s Discretion in Relation to a DSM Expenditure Schedule .................................................................................................................... 230
(b) BC Hydro’s Traditional DSM Is in the Interest of Customers .................................... 230
(c) BC Hydro’s Traditional DSM Supports British Columbia’s Energy Objectives .......... 231
(d) Traditional DSM is Consistent with the IRP .............................................................. 232
(e) BC Hydro’s Traditional DSM is Cost-Effective as Defined by the DSM Regulation .. 232
(f) Traditional DSM Meets Adequacy Requirements Under the DSM Regulations ...... 232
301539.00025/94161307.1
(g) BC Hydro Retains Flexibility to Reallocate Costs in Response to Challenges and Opportunities ............................................................................................................ 233
F. THE EXPENDITURE SCHEDULE EXCLUDES THERMO-MECHANICAL PULP EXPENDITURES ......................................................................................................................................... 234
G. LOW CARBON ELECTRIFICATION EXPENDITURES ARE PRESCRIBED UNDERTAKINGS AND COST RECOVERY IS MANDATED ....................................................................................... 235
(a) Section 18 of the Clean Energy Act Requires Cost Recovery for Prescribed Undertakings ............................................................................................................. 235
(b) Acceptance of a Section 44.2 Expenditure Schedule is Not Required ..................... 236
(c) BC Hydro’s LCE Expenditures are Prescribed Undertakings ..................................... 237
(d) Deferral of LCE Expenditures is Required by Regulation .......................................... 240
H. BC HYDRO IS MANAGING ITS TRADITIONAL DSM AND LCE INITIATIVES EFFECTIVELY ... 240
I. CONCLUSION AND REQUESTED FINDINGS ...................................................................... 243
PART TWELVE: IMPLEMENTATION OF RATES AND CONSIDERATION OF NEW INFORMATION 245
A. INTRODUCTION ................................................................................................................ 245
B. BC HYDRO’S RATE IMPLEMENTATION PROPOSAL IS IN THE INTERESTS OF BOTH CUSTOMERS AND THE COMPANY ................................................................................... 245
C. THE BCUC SHOULD AVOID UPDATING EVIDENTIARY UPDATE INPUTS IN ISOLATION .... 248
(a) Snapshot: Directional Impact of Changing Evidentiary Update Inputs .................... 248
(b) Unfavourable Impact of Lower than Forecast Domestic Sales Revenue Should Be Considered Before Updating Five-Year Averages..................................................... 249
(c) InterGroup’s Recommendation to Update Interest Rate Forecasts While Using an Out of Date Pension Discount Rate Would Produce an Unreasonable Result ......... 251
(d) Regulatory Accounts Facilitate Ratesetting in the Context of Uncertainty due to COVID-19 Pandemic .................................................................................................. 253
D. CONCLUSION AND REQUESTED FINDING ........................................................................ 255
PART THIRTEEN: CONCLUSION AND ORDER SOUGHT ............................................................... 256
301539.00025/94161307.1
PART ONE: INTRODUCTION AND OVERVIEW
A. INTRODUCTION
1. In broad terms, BC Hydro has had two objectives for this proceeding. The first is to
provide the British Columbia Utilities Commission (the “BCUC”), interveners and customers with
an open and transparent view of its operations and cost structure and to be open to feedback
and suggestions received through this process.1 The second is to convey that BC Hydro’s
revenue requirements and requested rate changes reflect a pervasive culture of restraint and
cost containment in the face of external cost pressures and an increasingly complex operating
environment. BC Hydro respectfully submits that it has accomplished both objectives.
2. The robust evidentiary record is a product of a comprehensive Application, BC Hydro’s
considered responses to thousands of information requests, the testimony of 19 witnesses and
a number of hearing undertakings. BC Hydro and its representatives have, throughout the
process, demonstrated candour and a willingness to engage with all stakeholders.
3. BC Hydro’s evidence demonstrates the appropriateness of BC Hydro’s forecast fiscal
2020 and fiscal 2021 (the “Test Period”) revenue requirements, and the resulting rates (a 5%
decrease in the Deferral Account Rate Rider and a 6.85% rate increase in fiscal 2020, for a net
bill increase of 1.76%, followed by a 1.01% rate decrease in fiscal 2021).2 The Demand-Side
Management (“DSM”) expenditure schedule provides broad access to cost-effective DSM, while
continuing with the moderation strategy that recognizes BC Hydro already has sufficient energy
resources at this time to meet demand. As Chris O’Riley, President and Chief Executive Officer
of BC Hydro, said in his opening statement, BC Hydro has put forward a business plan that is
consistent with the objective of affordability and “I’m proud of the efforts we’ve made to
1 On February 14, 2020, BC Hydro filed Exhibit B-43, setting out actions BC Hydro is taking in response to feedback
received during the first part of the Oral Hearing for this proceeding. 2 Exhibit B-11-2 corrected the rate requests in the Evidentiary Update.
- 2 -
301539.00025/94161307.1
maintain our competitive position against a backdrop of increasing complexity in our operating
environment.”3
4. The BCUC should approve the proposed rates, and rate-related orders (as set out in
Appendix B of the Evidentiary Update, corrected by Exhibit B-11-2), as just and reasonable. It
should find that the proposed DSM expenditure schedule is in the public interest.
B. SUBMISSION OVERVIEW AND KEY POINTS
5. These Final Submissions are organized around the following key points:
● Part Two: Legal Framework and the Proper Scope of the Proceeding – With the
repeal of Direction No. 7, the BCUC now has much broader discretion regarding
BC Hydro’s rates; however, some important limits remain. The BCUC’s decision
should remain focussed on matters that truly require a determination, leaving
other matters for more pertinent future processes.
● Part Three: Providing Safe, Reliable and Cost Effective Service in an Increasingly
Complex Environment – BC Hydro’s revenue requirements reflect concerted
effort to contain costs throughout the organization in the face of external cost
pressures.
● Part Four: Load and Revenue Forecasts – BC Hydro’s Load Forecast is reasonable
for the purposes of setting rates in the Test Period, being the product of an
improved methodology and reasonable inputs.
● Part Five: Forecast Cost of Energy – Forecast increases in Cost of Energy are
primarily associated with Electricity Purchase Agreements (“EPAs”) that either
pre-date fiscal 2017 or are part of the Biomass Energy Program, for which cost
recovery is mandated. The BCUC will conduct public interest reviews of future
EPAs under section 71 of the Utilities Commission Act (the “UCA”). The Cost of
3 Tr. 5, p. 358, ll. 2-6 (O’Riley).
- 3 -
301539.00025/94161307.1
Energy Variance Accounts ensure that customers only pay the actual Cost of
Energy.
● Part Six: Operating Costs – BC Hydro absorbed controllable cost pressures within
existing budgets. Operating cost increases during the Test Period are generally
attributable to uncontrollable factors.
● Part Seven: Capital Expenditures and Additions – BC Hydro has planned forecast
capital spending in the Test Period to fund necessary investments in safety and
reliability while moderating spending in response to consistent system
performance and a reduced rate of demand growth.
● Part Eight: Regulatory Accounts – BC Hydro’s regulatory accounts are beneficial
to ratepayers and consistent with BCUC guidelines and decisions. Appropriate
recovery mechanisms are in place for the balance in those accounts that
currently require recovery.
● Part Nine: Other Revenue Requirements Items – Some significant Other
Revenue Requirement Items flow from the legislative framework and prior BCUC
orders. Other items are based on objective and consistent forecasts.
● Part Ten: Transmission Revenue Requirements – BC Hydro’s Transmission
Revenue Requirement reflects the revenue reasonably required from
transmission customers for the safety and reliability of the transmission system.
● Part Eleven: Demand-Side Management – The proposed DSM expenditure
schedule continues BC Hydro’s moderation strategy, while still enabling broad
and cost-effective DSM with increased residential expenditures in response to
previous BCUC feedback.
● Part Twelve: Implementation of Rates and Consideration of New Information –
BC Hydro’s proposal to set permanent rates for fiscal 2020 at the same level
approved on an interim basis, followed by a rate decrease of 1.01% on April 1,
- 4 -
301539.00025/94161307.1
2020, produces the best outcome for customers. BC Hydro’s regulatory accounts
are an efficient means of addressing new developments and changes from the
Cost of Energy and finance charge assumptions reflected in the Evidentiary
Update. This includes revenue-related developments due to COVID-19 that have
occurred since the hearing record closed, and will continue to unfold in the
coming months. If the BCUC is nonetheless minded to base its decision on
different information or assumptions, then it should do so holistically to ensure
that the overall result remains reasonable.
- 5 -
301539.00025/94161307.1
PART TWO: LEGAL FRAMEWORK AND THE PROPER SCOPE OF THE PROCEEDING
6. Chapter 2 of the Application details the regulatory and legal framework and its
implications for the BCUC’s determinations in this proceeding. Although the BCUC’s discretion
is much broader now, cost recovery is still mandated for certain matters:
(a) the balance of BC Hydro’s regulatory accounts as at March 31, 2019, which is
the entire balance as of the start of the Test Period (see Part Eight);4
(b) the costs incurred by BC Hydro with respect to the construction of extensions to
BC Hydro’s plant or system that came into service before April 1, 2016;5
(c) the costs incurred by BC Hydro with respect to energy supply contracts entered
into before April 1, 20166, which includes the vast majority of BC Hydro’s
forecast Independent Power Producer (“IPP”) costs in the Test Period (See Part
Five, Section B);
(d) debt servicing costs on amounts borrowed in relation to the rate smoothing
regulatory account;7
(e) the costs associated with “prescribed undertakings” under the Greenhouse Gas
Reduction (Clean Energy) Regulation (the “GGRR”), which includes the Peace
Region Electricity Supply (“PRES”) project (see Part Seven, Section J);
(f) the prescribed return on equity of $712 million for each of fiscal 2020 and fiscal
2021 (see Part Nine, Section D).8
7. InterGroup Consultants Ltd. (“InterGroup”), on behalf of AMPC, advocates that the
BCUC identify the costs of legislated policies even if the BCUC cannot direct associated changes.
4 Direction No. 8 to the BCUC, B.C. Reg. 24/2019 (“Direction No. 8”), section 4(1). 5 Direction No. 8, section 4(1). 6 Direction No. 8, section 4(1). 7 Direction No. 8, section 4(1). 8 Direction No. 8, section 3.
- 6 -
301539.00025/94161307.1
It also contends that the BCUC should consider and test the prudence and “least cost nature” of
all costs that continue to be included in the revenue requirement, including costs associated
with government directions.9 BC Hydro submits that the exercise contemplated by InterGroup
is, in effect, an attempt to second-guess legislated government policy. The BCUC, as a creature
of statute, derives its mandate from the existing legislation and must operate within that
framework.
9 Exhibit C11-11, InterGroup Evidence, Recommendations 9 and 10.
- 7 -
301539.00025/94161307.1
PART THREE: PROVIDING SAFE, RELIABLE AND COST EFFECTIVE SERVICE IN AN INCREASINGLY COMPLEX ENVIRONMENT
8. At the outset of the oral hearing, BC Hydro identified themes that run through the
evidence in this proceeding. In addition to the importance placed on transparency, the themes
centred on (1) BC Hydro’s concerted effort to contain costs, and (2) the mounting cost
pressures associated with an increasingly complex operating environment.10
A. BC HYDRO HAS DEMONSTRATED ITS ATTENTION TO CONTAINING CONTROLLABLE COSTS
9. In his Opening Statement, Mr. O’Riley emphasized that “a lot of rigour goes into our
budgeting process”.11 He elaborated that difficult decisions went into developing the Test
Period budget, and that accommodating additional work within the budget is unrealistic:
Well, as I said in the opening, we are absolutely open to feedback and open to suggestions. And if those can be brought forward, that is fantastic, and we will take them. We’re going to start right into a budgeting process very quickly for the coming—the next test period. And what Mr. Wong and I are saying is, we put a tremendous effort into ensuring we had the right budget. We are nine and a half months into the first year of the two year test period, and pretty much on track. Lots of pressures on the budget, pretty much on track. We are not expecting within the test period to come in well below the budgets. That’s not a likely expectation.
Absolutely, if we get suggestions for where we can make improvements going forward, we’ll do that. I do note that most of the suggestions that have come forward in the process have been suggestions to do additional work, and there is a long list of suggestions of studies and programs and things that we could add to the budgets. There have not been a lot of suggestions of things we could remove.
One of the things I note in my role that’s very—I meet with a lot of outside groups, including customer groups, and almost invariably I receive suggestions where BC Hydro could be more effective by spending additional money, or having another program, or investing over here, almost invariably, and I find the implicit part of my job description is actually saying no. And I’ve actually—that’s
10 Tr. 5 p. 336, l. 13 to p. 337 l. 21 (Ghikas). 11 Tr. 5, p. 358, ll. 11-19 (O’Riley).
- 8 -
301539.00025/94161307.1
slightly counter to my nature, I don’t like saying no, but I’ve had to come up with ways of doing that.12
10. Mr. O’Riley’s testimony was echoed by other members of the Executive Team and
senior management that have the day-to-day responsibility for budgets across the organization.
As David Wong, Executive Vice President of Finance, Technology, Supply Chain and Chief
Financial Officer, explained:
Well, first of all, when we put together this application we pushed hard to recreate [sic] budgets that I would say are hard to deliver on what we need to deliver on. And we are actually finding that this year.
I mean, [there] are pockets of groups within our company [that] are finding it really challenging. Just the technology as an example, in our area.
And so a lot of effort went in [to the] development of this application to find those savings, and now what we need to do is actually realize on them, which I think we are doing a really good job of. We are working hard every day to rationalize and manage our costs.13
11. The lengths to which BC Hydro has gone to assess the operations, find savings and
create capacity throughout the organization during the Test Period are discussed throughout
the remainder of this Final Submission. The attention to cost control is particularly evident in
the context of Cost of Energy, Operating Costs, Capital and DSM.
B. THE DEMANDS ON BC HYDRO ARE INCREASING AS WORK BECOMES MORE COMPLEX
12. At the same time, the demands on the company have increased: “While BC Hydro’s core
work has remained the same, the type, complexity, and volume of work BC Hydro performs has
changed and increased since the Previous Application.”14 BC Hydro has thus far attempted to
absorb additional costs associated with these demands. However, BC Hydro “expect[s] that it
will be difficult to continue to do so, depending on factors such as the pace and nature of
12 Tr. 5 p. 376 l. 1 to p. 377, l. 6 (O’Riley). 13 Tr. 5, p. 373, ll. 12-26 (Wong). 14 Exhibit B-5, BCUC IR 1.64.1.
- 9 -
301539.00025/94161307.1
changes.”15 The magnitude of the task is highlighted by the fact that BC Hydro, at the time of
the oral hearing, was tracking slightly over budget on operating costs in fiscal 2020. The
Executive Team was working to identify further cost reductions to stay on budget for the year.16
13. BC Hydro highlighted, in particular, a number of changes in the law and regulatory
requirements that are driving increased costs:
● New NERC Critical Infrastructure Protection (“CIP”) requirements: In order to
comply with Mandatory Reliability Standards (“MRS”), BC Hydro and other
utilities in North America must, among other things, abide by a series of
reliability and cyber security standards set by the North American Electric
Reliability Corporation (“NERC”). These standards impact how BC Hydro plans,
builds, and operates its system. The standards introduce new complex work.
Costs for maintaining compliance, which have been increasing, are embedded
within overall operating costs across the organization.17
➢ NERC CIP version 5 expanded cyber and physical security standards to
43 medium impact substations.18
➢ In addition, NERC CIP has had significant and growing impact on BC
Hydro’s front-line operations teams.19
Sustainment costs are expected to increase in the future as new standards come
into effect.20
15 Exhibit B-12, BCUC IR 2.214.1. 16 Tr. 5, p. 374, ll. 4-14 (Wong). 17 Exhibit B-12, BCUC IR 2.214.1. 18 Exhibit B-5, BCUC IR 1.64.1. An example of new work from these standards is that BC Hydro is now mandated to
check and evaluate security patches for more than 2,000 in scope assets on a monthly basis and must apply most of the applicable patches to operational assets within a one year time frame. In many cases, this involves evaluating complex options to determine how to apply patches without impacting reliability in aging systems.
19 Exhibit B-5, BCUC IR 1.64.1. For example, any intrusion alarm within critical physical security areas requires a response within 15 minutes and all NERC keys and authorizations must be reviewed quarterly or annually based on security level.
- 10 -
301539.00025/94161307.1
● New general cybersecurity requirements: Assets that fall outside of MRS
requirements still require cybersecurity investment. The recent audit report
from the Office of Auditor General of British Columbia included a series of
cybersecurity recommendations that are expected to result in additional
operating costs.21
● Safety regulation changes: Changes to safety regulations require new
equipment, upgrades to existing equipment, and training on new, and often
more complex, work procedures.22 The costs of achieving and maintaining
regulatory compliance are incurred within overall actual operating costs.
● Archaeological work: Increased consultation and engagement with First Nations
directly in archaeological protection has also required subject matter expert
support and Indigenous cultural monitors to both facilitate discussions as well as
ensure BC Hydro incorporates Indigenous perspectives in the work.
Amendments to the Heritage Conservation Act and additional provincial
permitting and reporting requirements (such as new requirements for permit
notification content and annual blanket permit reporting) have also necessitated
additional subject matter expert involvement in ensuring programs and projects
are fully addressing regulatory requirements.
20 Exhibit B-12, BCUC IRs 2.214.1 and 2.257.20. 21 For example, as noted in BC Hydro’s responses to BCUC IR 1.123.2.1 (Exhibit B-5) and BCUC IR 2.257.1 (Exhibit B-
12), BC Hydro expects to incur a cost of $0.3 million for a related risk assessment. This cost was not included in the Application as the need for (and cost of) the assessment was unknown at the Application currency date. BC Hydro continues to evaluate the recommendations for adoption. The audit report can be found at: https://www.bcauditor.com/sites/default/files/publications/reports/OABGC_Cybersecurity-ICS-BC-Hydro_RPT.pdf.
22 Exhibit B-5, BCUC IR 1.64.1. For example, new heat stress assessment tools and procedures have added complexity to work procedures and additional costs to acquire new tools. BC Hydro has introduced a policy that an Occupational Health and Safety Specialist must now attend every entry into a confined space (approximately 500 per year) unless otherwise authorized.
- 11 -
301539.00025/94161307.1
● Environmental regulatory requirements: New environmental requirements have
increased workload and required additional investment. For instance:23
➢ Provincial Water Sustainability Act: Amendments to this Act in 2016
resulted in increased regulatory requirements for groundwater use
and for managing activities in non-fish bearing streams. These
requirements increase regulatory compliance activities, increase
mitigation efforts to avoid impacts in streams, and increase the time
required to conduct work in transmission corridors.
➢ Species at risk: The number of terrestrial and aquatic species being
recommended for listing has increased, which has increased planning
and regulatory requirements.
➢ Invasive species: Since the Previous Application, BC Hydro has been
supporting the Government of B.C.’s invasive mussel defence
program at a cost of $1.3 million, which has been absorbed over
recent years.
14. Mr. O’Riley also emphasized increasing customer service and societal expectations that
go beyond complying with regulations:
Having served in the president’s role for two and a half years now, I am very conscious of the service expectations on BC Hydro and I feel these responsibilities keenly. Some of these are obvious in terms of the importance of reliability. On January 2nd I was in the Lumby area and able to see firsthand the tremendous efforts required to restore power to customers in the rural areas on Mable Lake Road after the snowstorm. Some of these expectations are more subtle, such as a growing expectation by customers to be kept updated during storms and outage events, and for BC Hydro to meet best practices in processes as articulated in audits. Other expectations come through the growing regulatory requirements on BC Hydro for safety, environment, reliability, as well as the higher expectations for conduct from society in general. I think societal expectations on institutions are increasing across the board, and correspondingly
23 Exhibit B-5, BCUC IR 1.64.1.
- 12 -
301539.00025/94161307.1
societal risk tolerance is decreasing. And this in itself becomes a cost pressure for a critical infrastructure provider such as BC Hydro.24
Overall, the consequence of the changes discussed above, and others, is that “it is increasingly
difficult to get front-line work done within existing resource levels and that opportunities to
find new efficiencies are quickly negated by increases to work volume or complexity.”25
C. ADDITIONAL INVESTMENT WILL BE NECESSARY AFTER THE TEST PERIOD
15. Company-wide initiatives like Work Smart and “make it easier to get work done”
(discussed in Part 6, Section F) help to avoid cost increases. However, Mr. O’Riley tempered
expectations about BC Hydro’s ability to continue absorbing cost pressures associated with
changing expectations:
So perhaps one of the things that we may have not made clear enough is the context we operate in, and there are, all over the place, new and rising expectations on BC Hydro, and I don’t think you should expect to see operating costs going down in real terms given the rising expectations. And I feel, as a management team, that we swim against that, and work really hard to absorb those expectations and requirements in the company in the context of inflation. But I think we have no business expecting real decreases in operating costs for a company like BC Hydro in the environment it operates. No business at all. And I want to be clear that that’s not something I think is reasonable or even prudent given the service expectations on the company, and the compliance expectations.26
16. Mr. O’Riley identified three areas in particular where he expects budgets will need to
increase in subsequent test periods: vegetation management, cybersecurity and employee
training to meet evolving safety and regulatory requirements.27
24 Tr. 5, p. 359, l. 9 to p. 360, l. 5 (O’Riley). 25 Exhibit B-5, BCUC IR 1.64.1. 26 Tr. 5, p. 372, l. 19 to p. 373, l. 9 (O’Riley). 27 Tr. 5, p. 359, ll. 1-8 (O’Riley).
- 13 -
301539.00025/94161307.1
PART FOUR: LOAD AND REVENUE FORECASTS
A. INTRODUCTION
17. BC Hydro’s requested rates in the Evidentiary Update reflect actual sales for the first
two months of fiscal 2020 (April and May 2019), and the October 2018 Load Forecast for the
remainder of the Test Period. BC Hydro described the October 2018 Load Forecast in Chapter 3
of the Application and Appendix O.28 The evidence discussed in this Part demonstrates that the
October 2018 Load Forecast, and the associated Revenue Forecast, are reasonable for the
purposes of setting rates in the Test Period. In particular, the evidence supports the following
findings:
● First, the load forecast methodology has performed well in recent years.
● Second, the October 2018 Load Forecast reflects improvements in BC Hydro’s
load forecast methodology, including improvements to address feedback from
the BCUC and audit recommendations.
● Third, the confidence interval around the mid forecast, represented by the high /
low forecasts, is a critical part of the context when defining the reasonableness
of using the October 2018 Load Forecast for setting Test Period rates.
● Fourth, the June 2019 Load Forecast results, on average, remained within 0.1 per
cent of the October 2018 Load Forecast for the Test Period.
● Fifth, the October 2018 Load Forecast already assumed that electricity sales to
the forestry sub-sector would decline.
● Sixth, while considerable upside potential exists with the CleanBC Plan, BC Hydro
took the reasonable approach of including only those elements of the CleanBC
Plan that were already in place or were close to being enacted. The next
Integrated Resource Plan (“IRP”) will be the appropriate venue to discuss
28 Exhibit B-1, Application, Appendix O, Electric Load Forecast Report Fiscal 2019 to Fiscal 2024 (October 2018).
- 14 -
301539.00025/94161307.1
medium and longer-term planning and load forecast implications of
electrification.
● Seventh, variances between actual and forecast cost of energy arising from
differences between forecast and actual domestic customer load are deferred to
the Cost of Energy Variance Accounts, thus keeping customers whole.
● Eighth, once the Load Forecast has been determined, the Revenue Forecast
based on it is a straightforward calculation. The methodology is unchanged from
the Previous Application.
B. SNAPSHOT OF THE OCTOBER 2018 LOAD FORECAST UNDERLYING THE EVIDENTIARY UPDATE
18. The October 2018 Load Forecast is summarized in the table below. Overall, the mid
load forecast shows demand increasing by approximately 650 GWh or 1.2% from fiscal 2019 to
fiscal 2021. Over the five year period from fiscal 2018 to fiscal 2023, average growth is 0.5%
per year.29
Electricity Sales Summary after Rates after DSM Savings
F2019 F2020 F2021 Forecast (GWh)
Forecast (GWh)
Forecast (GWh)
Residential 18,049 18,258 18,330
Commercial and Light Industrial 18,976 18,973 19,030
Large Industrial 14,003 14,702 14,243
Other 1,575 1,634 1,650
Total Domestic Sales 52,604 53,567 53,253
F2019 F2020 F2021
Low Band 51,716 52,244 51,364
Mid Load Forecast 52,604 53,567 53,253
High Band 53,507 54,907 55,189
29 Exhibit B-1, Application, pp. 3-37 and 3-38; corrected in Exhibit B-6, BCOAPO IR 1.17.1 (though with a
typographical error in the last column that has been corrected in these Submissions). Mid Load Forecast for fiscal 2019 includes six months of actuals, and six months of forecast data.
- 15 -
301539.00025/94161307.1
19. Messrs. Rich and Clendinning provided a concise explanation as to how to interpret the
mid, high and low forecasts. They explained that the mid forecast represents the sum of the
sector forecasts, which are prepared using various methodologies and modelling (A+B=C). The
low and high forecasts represent a confidence interval that is generated by Monte Carlo
analysis.
20. Mr. Rich elaborated: “…our mid-forecast is actually not a P50 forecast, it’s a
deterministic forecast. So we are aiming in an unbiased, objective way to get it right, and so
the uncertainty band is a probabilistic method of creating a confidence interval around that.”30
Section D below highlights the improvements in the methodology used to arrive at the
deterministic mid forecast. Section E outlines types of uncertainties captured in the confidence
interval.
21. Mr. Clendinning confirmed that the combination of the deterministic and probabilistic
approaches “make a robust way in order to do forecasting over the short and the longer-term
and there’s a solid basis for ratemaking.”31
C. THE LOAD FORECAST METHODOLOGY HAS PERFORMED WELL IN RECENT YEARS
22. The Load Forecast for the Previous Application was developed in May 2016 and has
performed well. Actual results for fiscal 2017, fiscal 2018, and fiscal 2019 tracked within 0.1%
to 0.5% of the forecast, which is well within a range of expectancy based on industry
benchmarks.32 Two of those years were underforecast, and the other was overforecast. Ms.
Daschuk stated that, “ …if you look at the last three years, I would actually say that we’ve done
an exceptional job in terms of forecasting.”33
23. Most of the variance in longer term outlooks is due to the large industrial sector, which
is largely based on the resources industry, which is inherently uncertain and for which it is very
30 Tr. 8B, p. 1300, ll. 14-20 (Rich). 31 Tr. 8B, p. 1300, ll. 21 to p. 1302, l. 12 (Clendinning). 32 Exhibit B-1, Application, p. 3-4. 33 Tr. 8B, p. 1304, l. 15 to p. 1305, l. 1 (Daschuk).
- 16 -
301539.00025/94161307.1
difficult accurately project future demand.34 The initial years of each forecast vintage, which
are of greatest relevance when setting rates for a single test period, tended to be reasonably
accurate.35 The next IRP is a more appropriate venue to explore long-term forecasting.
D. THE TEST PERIOD LOAD FORECAST IS BASED ON AN IMPROVED METHODOLOGY
24. Since the May 2016 Load Forecast, BC Hydro made improvements to its load forecast
methodology and governance based on feedback from the BCUC and internal audit
recommendations.36 In December 2018, the Auditor General of B.C. characterized the load
forecasting process as “robust”, concluding that, “BC Hydro has a load-forecasting capability
that compares favourably with industry standards.”37 The improved methodology, which was
incorporated into the October 2018 Load Forecast, provides a sound basis on which to set rates
in the Test Period.
(a) Improvements to the Methodology Respond to BCUC Commentary
25. Table 3-1 of the Application identified concerns raised by the BCUC in the Previous
Application and the Site C Inquiry and how BC Hydro addressed them:
34 Tr. 10, p. 1633, l. 15 to p. 1634, l. 16 (Rich). 35 Tr. 10, p. 1633, ll. 20-25 (Rich). 36 Tr. 8B, p. 1290, l. 22 to p. 1291, l. 18 (Rich). 37 Exhibit B-1, Application, p. 3-9.
- 17 -
301539.00025/94161307.1
26. BC Hydro’s short-term methodology performed favourably to FortisBC Electric’s
methodology when applied to the same input data used in the May 2016 Load Forecast.38
(b) BC Hydro Has Incorporated Audit Recommendations on Methodology and Governance
27. An August 2017 audit of BC Hydro’s load forecasting function endorsed the overall load
forecast methodology, while making some specific recommendations for improvement. As
38 Exhibit B-1, Application p. 3-36, Exhibit B-6, CEC IR 1.10.2: The purpose of this comparison was to inform a
decision with regards to whether to adopt an alternative short-term load forecast methodology. Exhibit B-13, CEC IR 2.93.2: The variance in accounts for fiscal 2019 would have been greater if the alternative forecast based on the FortisBC Electric short-term method was used. See also, Exhibit B-13, CEC IR 2.94.5.
- 18 -
301539.00025/94161307.1
discussed below, BC Hydro is implementing the audit recommendations and many are already
reflected in the October 2018 Load Forecast.39
28. The audit of BC Hydro’s forecasting function was completed by BC Hydro Audit Services,
a department that operates subject to strict rules and protocols designed to ensure
objectivity.40 BC Hydro Audit Services retained independent subject matter experts, GDS
Associates Inc. (“GDS”), to perform the assessment.41 GDS’s findings, which were incorporated
in the Audit Report, included:42
● “Overall, the load forecasting function at BC Hydro compares favorably to
industry standards and to other large electric utilities in North America. No
critical weaknesses were found.”
● “Load forecasting methodologies are consistent with best practices and load
forecast outputs are provided to users and stakeholders on a timely basis.”
● “The greatest risk of load forecasting inaccuracy falls on the industrial class and
is due to the uncertainty of future economic activity and the volatility of many
individual customer loads.”
● “Areas for improvement identified primarily relate to making adjustments to
forecast models and inputs to enhance overall forecast accuracy.”
39 Exhibit B-6, BCOAPO IR 1.14.2. 40 Exhibit B-1, Application, Appendix P, Load Forecast Internal Audit. 41 Exhibit B-5, BCUC IR 1.12.1. 42 Exhibit B-1, Application, Appendix O, Electric Load Forecast Report Fiscal 2019 to Fiscal 2024 (October 2018), p.
16.
- 19 -
301539.00025/94161307.1
BC Hydro Has Implemented Governance Recommendations
29. BC Hydro has completed all of the audit recommendations related to governance:43
Updated Elasticity Factor Was Among the Methodology Changes Flowing from Audit Recommendations
30. BC Hydro has similarly implemented changes in response to each of GDS’s
recommendations on forecast methodology.44 As described below, those changes include
updating BC Hydro’s elasticity factors.
31. As a result of the audit, BC Hydro retained DNV GL to conduct a review of price
elasticity. Based on their findings, BC Hydro has increased the electricity price elasticity value
used for all of the main customer sectors in the Load Forecast from -0.05 to -0.10. The impact
43 Exhibit B-12, BCUC IR 2.203.2. 44 Exhibit B-6, BCOAPO IR 1.14.2 summarizes the status of the audit recommendations related to forecast
methodology. See also, Exhibit B-1, Application, p. 3-5; Exhibit B-12, BCUC IR 2.203.1.
- 20 -
301539.00025/94161307.1
of changing the elasticity, all else equal, is a small net change to the total Load Forecast of
about 21 GWh in fiscal 2020 and about 37 GWh in fiscal 2021.45
32. In response to an Information Request, BC Hydro performed a sensitivity analysis using
elasticity assumptions of 0.05, -0.1 and -0.15. Changing the price elasticity assumption had
minimal impact on the overall Load Forecast.46
33. BC Hydro’s continued use of a single price elasticity for all customer sectors reflects DNV
GL’s recommendation.47 DNV GL recommended that BC Hydro continue to use the same price
elasticity estimate for all sectors, citing (a) practices at other utilities, and (b) BC Hydro’s
complementary use of a site-by-site assessment for industrial facilities, which captures the price
effect for a selection of energy intensive facilities:
In general, we find BC Hydro’s application of price elasticity to be consistent with that of many of the Canadian and U.S. utilities we reviewed. DNV GL supports the continuation of BC Hydro’s approach to load forecasting which involves building up sector specific forecasts, including site-specific large commercial and industrial forecasts, and applying a single price elasticity to account for price changes in the forecast. Given that BC Hydro employs a site by site assessment for industrial facilities which captures price effect for a selection of energy intensive facilities, such as pulp mills; and precedent elsewhere, of applying the same price elasticity across all three sectors, we recommend that BC Hydro continue to use the same price elasticity estimate for all sectors.48
(c) BC Hydro Has Made Sector-Specific Methodology Improvements for All Four Sectors
34. BC Hydro has made methodology improvements across all four sectors (Residential,
Commercial and Light Industrial, Large Industrial and Other), discussed below.
45 Exhibit B-1, Application, p. 3-17; Exhibit B-6, AMPC IR 1.1.7. 46 Exhibit B-5, BCUC IR 1.8.1. See also, Exhibit B-6, INCE IRs 1.8.7 and 1.8.9. 47 Exhibit B-5, BCUC IR 1.8.4. 48 Exhibit B-1, Application, Appendix Q, Elasticity Study and GDP Study, p. 19.
- 21 -
301539.00025/94161307.1
Residential Sector Improvements
35. BC Hydro has made the following methodology improvements to the Residential Sector
Load Forecast:
(a) Recalibrated residential account growth relationship to housing starts by
updating BC Hydro’s approach to forecasting account growth;49
(b) Updated customer response to temperature after reviewing the relationship
between temperature and residential use per account using smart meter data;50
(c) Recalibrated the relationship between economic variables and electricity,
including disposable income and use per account, for all residential statistical
adjusted end-use (“SAE”) models;51 and
(d) Adjusted the price elasticity assumption from -0.05 to -0.10 based on a price
elasticity study conducted by the consultant, DNV GL.52
Commercial and Light Industrial Sector Improvements
36. Improvements to the Commercial sector methodology were similar to the SAE model-
related improvements from the Residential Sector Load Forecast. They include:
(a) Updated customer response to temperature;
(b) Recalibrated relationship of economic variables to electricity sales based on an
updated 10-year model calibration period; and
49 Exhibit B-1, Application, pp. 3-14 and 3-15. 50 Exhibit B-1, Application, p. 3-15. BC Hydro provided the magnitude of the impact over the Test Period in
response to Exhibit B-5, BCUC IR 1.11.2. In Exhibit B-6, INCE IR 1.8.21, BC Hydro prepared a comparison of forecasts developed with different assumptions on normal temperature. They showed that there is less than one per cent difference in the sales for each sector between the two scenarios.
51 Exhibit B-1, Application, p. 3-15. 52 Exhibit B-1, Application, pp. 3-15 to 3-17.
- 22 -
301539.00025/94161307.1
(c) Updating price elasticity from -0.05 to -0.10, consistent with the results of the
independent elasticity study discussed above.53
Large Industrial Sector Improvements
37. BC Hydro has approximately 190 large industrial customers, representing approximately
26% of total sales.54 As in prior years, BC Hydro forecasted sales to the large industrial sector
on an individual customer account basis; however, it has made a number of methodological
improvements.55
38. BC Hydro develops the Large Industrial Sector Load Forecast using information from a
variety of sources:56
● For existing customers, the key customer data is historical sales.57 BC Hydro uses
the other sources of information noted above to develop a probability weighting
representing a risk assessment of the likelihood of future sales increasing,
decreasing or remaining steady.58
● For new customers or customers requesting expanded service, the customer
specifies its anticipated demand, which BC Hydro verifies using information from
market research and industry experts. BC Hydro also assigns a probability
weighting to the forecast with regards to when and how much of the new
demand may materialize.59
39. The “bottom-up / top-down” approach, and the collaborative nature of the process,
allows for different perspectives and addresses the risk of bias in self-reported information.60
53 Exhibit B-1, Application, p. 3-20. 54 Exhibit B-1, Application, p. 3-22. 55 Exhibit B-1, Application, p. 3-23. 56 Exhibit B-1, Application, p. 3-24. 57 Exhibit B-5, BCUC IR 1.9.1. This process is described on pages 61 and 62 of Appendix O of the Application. 58 Exhibit B-1, Application, p. 3-24. 59 Exhibit B-5, BCUC IR 1.9.1. This process is described on pages 61 and 62 of Appendix O of the Application. 60 Exhibit B-5, BCUC IR 1.9.1.1. See also, Exhibit B-5, BCUC IR 1.9.2.
- 23 -
301539.00025/94161307.1
40. The improvements made to BC Hydro’s Large Industrial Sector Load Forecast
methodology include:
(a) The use of external subject matter experts to provide a comprehensive analysis
of B.C. shale gas development, which fed into the Oil and Gas subsector
forecast;61
(b) Revising price elasticities for this sector from -0.05 to -0.10 (discussed above);62
(c) Updating the methodology for forecasting sales to LNG customers to use a
probabilistic assessment approach (e.g., a 10% probability would still result in
10% of the forecast load being included), similar to that used for the long-term
forecasts other large industrial customers;63 and
(d) Changing from a probabilistic approach to a binary approach (i.e., in or out) for
the first three years of the Large Industrial Sector Load Forecast. Under a binary
approach, a customer with a less than 50% probability of taking service in a
particular year is included as zero for that year.64 BC Hydro explained: “Given
that we have good information to make the binary call, we believe forecasting
load in this manner is preferred over the test years rather than having partial
load and partial revenue projections.”65
41. BC Hydro cautioned that, on an aggregate sector total basis, the binary approach for the
Large Industrial Sector Load Forecast in the first three years of a forecast may or may not
improve load forecast accuracy over the Test Period; positive variances in one sub-sector may
offset negative variances in another. However, BC Hydro expressed that this approach
addresses why the most recent variances have occurred and will improve load forecast
61 Exhibit B-1, Application, p. 3-30; Exhibit B-12, BCUC IR 2.212.1. See also, Tr. 8B, p. 1313, ll. 21-26 (Rich). 62 Exhibit B-1, Application, p. 3-30. 63 Exhibit B-1, Application, pp. 3-27 to 3-30. 64 Exhibit B-1, Application, pp. 3-28 and 3-29. See also, Tr. 8B, p. 1309, l. 10 to p. 1311, l. 11 (Rich). 65 Exhibit B-1, Application, Appendix O, Electric Load Forecast Report Fiscal 2019 to Fiscal 2024 (October 2018), p.
20.
- 24 -
301539.00025/94161307.1
accuracy within specific segments where probability-weighted forecasts are influenced by
account-specific risk assessments.66 BC Hydro explained that, over the longer-term, a
probabilistic-based approach continues to be the best method for developing the large
industrial sector forecast on an aggregate basis.67 This methodology is preferred to other
methods as it provides greater flexibility to quantify relevant factors for the sector and
individual customer energy sales. It also provides greater detail for tracking and explaining
forecast variances.68
42. BC Hydro’s work to improve the forecasts will continue. For instance, BC Hydro is
retaining third-party experts to provide market assessments for emerging segments
(cryptocurrency and cannabis), inform the methodology development and identify trends for
future load forecasts for these segments.69
Other Sector Improvements
43. The Other sector currently represents approximately 3% of the total sales demand in
the Load Forecast. Demand in this sector comes from irrigation and street light customers,
sales to other inter-utility sales (City of New Westminster and FortisBC Electric), and firm
exports (Seattle City Light and Hyder). BC Hydro revised the price elasticities from -0.05
to -0.10 across all customers in this sector for which applying an elasticity factor is
appropriate.70 The rationale for the revision of the price elasticities from -0.05 to -0.10 is the
same as that discussed in Subsection (b) above.
66 Exhibit B-1, Application, p. 3-30; Exhibit B-13, BCOAPO IR 2.96.2. 67 Exhibit B-1, Application, p. 3-30. 68 Exhibit B-1, Application, Appendix P, Load Forecasting Internal Audit, p. 4. 69 Exhibit B-22, BCUC IR 4.320.1. 70 Exhibit B-1, Application, pp. 3-30 to 3-31. Elasticity factors are not required for Seattle City Light and FortisBC
Electric. Seattle City Light loads are established under the Skagit River Treaty. Sales to ForticBC Electric have the elasticity impact implicitly built into the methodology.
- 25 -
301539.00025/94161307.1
E. THE CONFIDENCE INTERVAL AROUND THE MID FORECAST CAPTURES A VARIETY OF UNCERTAINTIES
44. The confidence interval, represented by the high / low forecasts, is a critical part of the
context when defining the reasonableness of using the October 2018 Load Forecast for setting
Test Period rates.
45. As Mr. Rich observed,71 it is inevitable that actual results will vary from forecasts. The
challenge of producing accurate forecasts has only increased in recent years with what Mr.
Clendinning referred to as a “paradigm shift in load”. He emphasized that, in the context of this
greater uncertainty, the confidence interval takes on new importance:
The mid-forecast is obviously important, especially in the short term when we’re setting rates over a one or two-year period. No doubt accuracy is important. But I think as we get into this period, as you described it, paradigm shift in load, and a lot of increasing uncertainty of where the past can’t be used. I fall back to the confidence in our load forecast.
So, what are the high and low bands? And what are we trying to capture with those in terms of the risks that are facing us? And so, it’s an easier concept to understand what’s your percentage accuracy versus the mid-forecast. Are you high or low, and to use words like over-forecasting and under-forecasting.
But to answer your question about performance, you know, if we’re saying the high and low bands represent an 80 percent confidence interval, over a 10 year period I’d expect the electricity demand from our customers to fall outside that band, and for me that would represent good performance. And I think we’re shifting our mindset. Other utilities are as well, and I think intervenors and regulators are coming to terms with the increased uncertainty of this post-2016 political and post-2008 economic environment.
So I really look to the confidence intervals in addition to forecast accuracy. And I encourage the team to compare their performance, not just against other load forecasts, which on a one, three, and six-year basis, we are performing better than—for example our model supplier for residential is ITron. You know, performing much better than those customers.
But against other economic forecasts, how are we doing relative to the province of British Columbia or private economic institutes forecasting GDP? That’s an
71 Tr. 10, p. 1633, ll. 6-10 (Rich).
- 26 -
301539.00025/94161307.1
input to ours. So if they have difficulty in forecasting GDP, you can imagine that that gets multiplied as it goes through. And we’re in the range of—the same range that we have for the load forecast, so sub-5 percent, sub-2 percent in some cases.72
46. BC Hydro was asked about whether the Load Forecast accounts for the potential of a
recession, which had been an issue in the last revenue requirements proceeding. BC Hydro
elaborated that, although BC Hydro does not forecast any specific period of economic recession
or recovery, the modelling does consider recessionary effects73 and accounts for the possibility
of recessions.74 The use of a perturbation process for GDP based on data from a 20 year period
that included a recession (B.C.’s annual GDP growth was -2.4% in fiscal 2009) means the Monte
Carlo modelling itself contains simulations with recessions.75 Generally speaking, a mild to
moderate recessionary period (e.g., -1 to -3 percentage point real GDP change over 3 quarters)
would likely fall within the high and low forecast uncertainty band.76 Mr. Clendinning expanded
on this at the hearing:
We dug a bit deeper into our Monte Carlo simulations, and one of the things that it varies in those simulations is GDP. And so in doing the Monte Carlo simulations and producing that low-end of the band, we looked at for all the variables that were changing, how often in each of those thousands of simulations of potential future load did we see recessions? And in the 20 years of historical GDP that is included in our forecasting that we use for that model, it included the 2008 recession and so that’s an input into that Monte Carlo simulation. You should at least go that low on GDP to see negative growth.
And so what we found was of the 30,000 samples that we took, 13 percent of the time the simulation included periods of recession. So, those are actually quite deep recessions, because the model only works on a yearly basis. So a recession is defined on a per quarterly basis of negative GDP, but these were years, whole years of negative GDP. So what I will say is, I think our responses in the past have said we don’t make those predictions about exactly when a recession will happen, but we do feel confident that our Monte Carlo processes do incorporate the risks associated with recessions and other potential negative
72 Tr. 8B, p. 1297, l. 16 to p. 1299, l. 5 (Clendinning). 73 Exhibit B-1, Application, p. 3-51; Exhibit B-5, BCUC IR 1.7.2. 74 Exhibit B-6, CEC IR 1.13.3. 75 Exhibit B-5, BCUC IR 1.7.2. 76 Exhibit B-5, BCUC IR 1.7.1. See also, Exhibit B-6, CEC IR 1.13.2.
- 27 -
301539.00025/94161307.1
consequences to customer demand for load that could in aggregate really hurt us. And that is where we get that lower part of the band.77
47. BC Hydro’s modelling also accounts for weather (temperature) uncertainties and
potential climate trends. The model forecasts are based on a ten-year rolling average of
monthly heating and cooling degree days for BC Hydro’s service area, which better reflects
current trends relative to longer-term averaging periods. BC Hydro’s Monte Carlo model also
reflects uncertainty in the impact of temperature on load through a random simulation of the
heating degrees over the past ten years.78
F. THE JUNE 2019 20-YEAR LOAD FORECAST UPDATE IMPACTS THE YEARS AFTER THE TEST PERIOD
48. BC Hydro completed the June 2019 Load Forecast after it had finalized the financial
inputs for the Evidentiary Update. It did not propose any further adjustments to the
Evidentiary Update revenue forecast (beyond the subsequent correction to the financial
schedules79). BC Hydro submits that this was a reasonable approach:
(a) The Evidentiary Update already incorporated two months of actual results for
fiscal 2020.
(b) The June 2019 Load Forecast was prepared as an interim step to inform BC
Hydro’s capital planning cycle and the February 2020 Service Plan. BC Hydro
filed it in this proceeding to fulfil a commitment made at the March 15, 2019
Workshop and in response to information requests received.80 BC Hydro will
complete an updated comprehensive 20-year load forecast to inform the 2021
IRP.
77 Tr. 8B, p. 1356, l. 21 to p. 1357, l. 23 (Clendinning). 78 Exhibit B-6, CEC IR 1.14.1. 79 Exhibit B-11-2. 80 Exhibit B-15, Twenty-Year Load Forecast, p. 1; Tr. 8B, p. 1261, ll. 17-22 (Rich). In Exhibit B-12, BCUC IR 2.209.1 BC
Hydro described how and when it updates its load forecasts.
- 28 -
301539.00025/94161307.1
(c) The June 2019 Load Forecast is, on average, within 0.1 per cent of the October
2018 Load Forecast for the Test Period.
(d) Load changes constantly in response to any number of factors. It is impractical
to continually update forecasts and expect to bring the regulatory process to a
timely resolution. Variances between forecast and actual revenue would be
deferred in the normal course for future recovery from, or refund to,
ratepayers.81
G. THE OCTOBER 2018 LOAD FORECAST ALREADY ASSUMED FORESTRY SUB-SECTOR DECLINE
49. There is no doubt that the forestry sub-sector has continued to face difficulties since BC
Hydro prepared the June 2019 Load Forecast.82 Continued reliance on the October 2018 Load
Forecast nonetheless remains reasonable because it already assumed that electricity sales to
the forestry sub-sector would decline.
50. The October 2018 Load Forecast projected mid sales to decline by 1,285 GWh or 18%
from fiscal 2018 to fiscal 2024, with a decline of over 1,000 GWh between fiscal 2020 and fiscal
2024.83 Mr. Rich, who was asked to provide a current assessment, stated:
Yeah, I mean the industry has faced its structural challenges and it has been for a number of years. I would say that for a number of load forecasts, at least over the long-term we are projecting a decline as a result of those. I would say that what’s happened this past summer is what is somewhat expected, it’s just happening sooner and harder.84
81 Exhibit B-15, Twenty-Year Load Forecast, pp. 2-3 and 5. 82 Exhibit B-22, BCUC IR 4.319.1. 83 Exhibit B-1, Application, Appendix O, Electric Load Forecast Report Fiscal 2019 to Fiscal 2024 (October 2018), p.
82. 84 Tr. 8B, p. 1318, ll. 1-8 (Rich). See also, Tr. 8B, p. 1348, ll. 15-22 (Rich).
- 29 -
301539.00025/94161307.1
51. Mr. Rich later elaborated as to the reasons why the forecasted decline happened
“sooner and harder”:
Well, I think I said, when we were [here] in January, that our load forecasts for that sector do project, and have projected a decline in the sector over the long term. And they are largely structurally related. And basic example of the demand for newsprint is declining as digital media has replaced the demand for that particular product. So, the sector is expected to decline over the long term.
The recent phenomena is I would say is best described is it is happening sooner and harder than we anticipated. When we spoke to our forestry consultants as to why that happened sooner and harder than was anticipated, the example that was demonstrated or highlighted to us with regards to lumber prices, for example, which is driven by U.S. housing starts, it was in part driven by a perfect storm of a wet summer, a dump of supply if you will from Europe, because they are facing their own beetle infestation. So there are a couple things that happened at the same time, that literally cause lumber prices in the U.S. to fall overnight. And that triggered a number of closures.85
52. Despite the significant decline in forestry sub-sector, BC Hydro’s overall year-to-date
fiscal 2020 sales as of December 31, 2019 were 2.6 per cent below the forecast provided in the
Evidentiary Update.86
H. THE LOAD FORECAST INCLUDES THE PORTION OF THE CLEANBC “UPSIDE” POTENTIAL THAT CAN REASONABLY BE ASSESSED AT THIS TIME
53. Although the ongoing challenges in the forestry sub-sector have been at the forefront of
public attention, upside potential also exists from electrification. Mr. Clendinning indicated
that the CleanBC plan represents incremental load potential.87 BC Hydro’s Load Forecast
reflects an appropriate amount of this upside potential, having regard to the early state of
development of the CleanBC Plan and the available information.
85 Tr. 9, p. 1652, l. 12 to p. 1653, l. 7 (Rich). 86 Exhibit B-41, BC Hydro Undertaking No. 15. 87 Tr. 1, p. 47, ll. 12-18 (Clendinning). See also, Tr. 1 p. 50, ll. 14-19 (O’Riley).
- 30 -
301539.00025/94161307.1
(a) The June 2019 Load Forecast Reflects Some, but Not All, of the CleanBC Initiatives
54. The June 2019 Load Forecast incorporated legislative and policy measures related to
CleanBC that were already in place or were close to being enacted, giving them a higher degree
of certainty.88 These initiatives, which represent approximately 75% of the initiatives under the
CleanBC Plan,89 include electric vehicles (based on the legislative target for electric vehicle sales
by 2024) and low carbon electrification in the oil and gas sector.90
55. There may be potential load growth from electrification in the Test Period that is not yet
reflected in the Evidentiary Update.91 Mr. Clendinning explained:
I think we do see in our traditional sectors, our traditional customer segments, you know, a moderating of growth, and so I think the forecast that we’ve put forward in the range of 0.5 to 1 percent. That said, I think as everyone in the room knows, there’s the potential for electrification as we respond to the climate crisis. There are other industries that are evolving that could provide additional growth, and so sometimes the rearview mirror is a useful way to chart your—navigate your way forward, but it comes with risks.92
56. The Government of B.C. has not yet released its plans to achieve the remaining 25% of
the 2030 goals. BC Hydro anticipates that, when fully implemented, these remaining initiatives
will introduce additional demand in the years beyond the Test Period. It is premature to
incorporate loads in the forecast before a quantitative analysis of these initiatives can be
undertaken.93 The IRP will be the appropriate venue to discuss longer-term load forecast
implications of electrification.94
88 Exhibit B-22, BCUC IR 4.325.2. Mr. Rich: “…we do have the low-carbon electrification program which predated
the public release of the CleanBC plan but it's entirely consistent with the objectives of the plan. So that's reflected in the October 2018 load forecast.” Tr. 8B, p. 1362, ll. 11-16 (Rich).
89 Exhibit B-6, CEABC IR 1.9.1. 90 Tr. 8B, p. 1362, ll. 11 to p. 1363, l. 20 (Rich and Clendinning). 91 Tr. 10, p. 1683, ll. 11-18 (Rich). 92 Tr. 8B, p. 1295, ll. 1-11 (Clendinning). 93 Exhibit B-6, BCSEA IR 1.9.1. 94 In undertaking an assessment of the impact of CleanBC in future load forecasts, BC Hydro will examine several
factors including the level of detailed planning undertaken, the funding allocated to achieve the objectives, the enactment of legislation and regulations, and the expected availability of enabling technologies. Exhibit B-12, BCUC IR 2.207.2. See also, Exhibit B-22, BCUC IR 4.325.2; Tr. 8B, p. 1365, ll. 6-16 (Clendinning).
- 31 -
301539.00025/94161307.1
57. The approach that BC Hydro is taking when recognizing the potential upside of the
CleanBC Plan is appropriate. The BC Hydro witnesses explained that the load forecasting
function is intended to be unbiased and data driven. Ms. Daschuk put it this way “…it’s not
intended to be optimistic or pessimistic, it’s intended to be our best view of what the future is
based on the information we have.”95
(b) BC Hydro Continues to Work to Build Load and Remove Barriers to Electrification
58. The fact that BC Hydro forecasts with the intent of being neither optimistic, nor
pessimistic, based on current information must be distinguished from BC Hydro’s substantial
efforts to build load.
59. As Mr. Rich put it, there is a difference between a load forecast and a sales target:
We are not going to put stuff in the load forecast that is speculative at this time. And so we have an entire other group within BC Hydro called Business Development, within Customer Service, they are also working with Key Account Management. And that’s their function. So they are looking at, to the extent that the province is developing economically, and to the extent that there is electrification potential combined with provincial policy measures and legislation linked to the province’s Clean B.C. objectives.
At some point when those projects become real they will be reflected in the load forecast.
So there is a bit of a divide between what I’ll call a sales target versus what we can reliably assume to occur in terms of future demand for electricity recognizing that there’s uncertainty in that future demand and that’s why we develop uncertainty bounds around it.96
60. There is ample evidence on the record of BC Hydro’s ongoing work to build load to
reduce greenhouse gas emissions. Mr. O’Riley responded to questions by counsel for CEABC by
stating, for instance:
But in particular there was a question about the extent to which the CleanBC plan is reflected in the load forecast and there was talk of 4,000 gigawatt hours
95 Tr. 13, p. 2430, ll. 22-25 (Daschuk). 96 Tr. 10, p. 1682, l. 25 to p. 1683, l. 10 (Rich).
- 32 -
301539.00025/94161307.1
of that and only a portion of that is in the load forecast, though we’re working on all aspects of that 4,000 gigawatt hours. And when the load becomes sufficiently probable, it will show up in the load forecast.97
Mr. O’Riley cited recent initiatives of the Better Buildings program, developing charging stations
to remove barriers to electric vehicle adoption, and the development of the Dawson
Creek/Chetwynd Area Transmission (“DCAT”) project in the Montney region.98 BC Hydro has
planned to spend $28 million on low carbon electrification over the Test Period, which are
“prescribed undertakings” under the GGRR.99
61. BC Hydro has 27 FTEs within the Key Account Management Department of the
Customer Service Key Business Unit. Key Account Managers are BC Hydro’s “sales force”. As
part of their role, Key Account Managers work directly with customers and promote
opportunities for both traditional DSM as well as low carbon electrification. Approximately 13
of these Key Account Managers are budgeted under demand-side management.100
62. The PRES Project, discussed in Part Seven of these Submissions, is another example of
how BC Hydro is investing to remove barriers to low carbon electrification. The infrastructure
must be in place in order to realize the significant potential for electrification in the oil and gas
sector. Mr. Kumar explained:
So our expectation is that the load is going to materialize, and actually the potential for load materializing is even going to be higher than what’s shown in the latest load forecast. So I think that’s the driver for PRES, and we feel confident that we have captured all the uncertainty in this load forecast in this mid-forecast that we are showing over there and there is potential, actually, to go higher than what’s shown on here depending how phase 2 review of the government goes and some of the initiatives that may come out of that.101
97 Tr. 5, p. 516, ll. 8-15 (O’Riley). 98 Tr. 5, p. 488, l.9 to p. 489, l.6; p. 515, l.1 to p. 516, l.6 (O’Riley). 99 Tr. 1, p. 71, l. 13 to p. 72, l. 22 (Hobson). The expenditures on low carbon electrification projects/programs that
are prescribed undertakings under the GGRR. are shown in the updated version of Appendix Y, provided as Attachment 1 to BC Hydro's response to Exhibit B-31, BCUC Panel IR 2.18.2.
100 Exhibit B-36, BC Hydro Undertaking No. 9. 101 Tr. 12, p. 2312, l. 23 to p. 2313, l. 18 (Kumar).
- 33 -
301539.00025/94161307.1
63. Through its capital planning process, BC Hydro is also investing in three other projects to
encourage new load growth and revenue through electrification: (1) the Bear Mountain
Terminal to Dawson Creek Transmission Voltage Conversion,102 (2) the North Montney
Transmission Development;103 and (3) the Prince George to Terrace Capacitors Project.104 Mr.
O’Riley explained: “So what we have included in our capital plan is the upfront money for those
projects, for the three projects, so we’re investing. We are investing ahead of need relatively
modest amounts but ensuring that we’re leaving open the possibility of electrifying those
customers.”105 Given the early stage of these projects and given that customers have not yet
committed to taking service,106 BC Hydro has not yet included the load from those projects in
the forecast. As stated by Ms. Daschuk:
…we mentioned earlier and Mr. O’Riley mentioned three projects that we’re doing preliminary investigation on. That would be the North Montney projects, the Bear Mountain project and the Prince George to Terrace project. We did not include any load in our forecast for those because they were—we did not make the decision to go ahead with those projects. So I think that we’ve taken also a balanced approach to say we’re not including the revenues in the estimates in the forecast but neither are we including the costs of some of the projects that we might need to do to attract those customers.107
64. The Phase Two Comprehensive Review final report, once issued, and the upcoming IRP
will inform BC Hydro’s further efforts in this regard.
I. REGULATORY ACCOUNTS TRUE-UP ANY VARIANCES FROM THE LOAD FORECAST
65. As described in Part Five below, variances between actual and forecast Cost of Energy
arising from differences between forecast and actual domestic customer load are deferred to
the Non-Heritage Deferral Account. A regulatory variance account is a fair and efficient means
of addressing emerging conditions during the regulatory process (and after it). It is
102 Exhibit B-12, BCUC IR 2.254.2. 103 Exhibit B-12, BCUC IR 2.254.2. 104 Exhibit B-12, BCUC IRs 2.247.6 and 2.247.6.1. 105 Tr. 5, p. 544, ll. 17-22 (O’Riley). 106 Tr. 8B, p. 1315, ll. 16-19 (Rich). 107 Tr. 8B, p. 1314, ll. 15-26 (Daschuk).
- 34 -
301539.00025/94161307.1
symmetrical. It provides an alternative to “data chasing”, which is problematic when (a)
interveners may tend to focus on updating factors that reduce rates, such that the overall
outcome may be unreasonable (see Part Twelve of this Submission for further discussion of
how this has occurred in the present proceeding), and (b) it impedes the timely resolution of
proceedings.
66. The Non-Heritage Deferral Account will, for similar reasons, permit the fair and efficient
management of load variances associated with the ongoing COVID-19 pandemic that has
emerged in the weeks after the closure of the evidentiary record. BC Hydro addresses COVID-
19 in Part Twelve of these Submissions.
J. REVENUE FORECAST IS INDUSTRY STANDARD AND CONSISTENT WITH PAST PRACTICE
67. The Revenue Forecast, summarized in Section 3.5 of the Application, is used to
determine the revenue shortfall and the proposed rate increases to meet BC Hydro’s forecast
revenue requirements. The forecast methodology uses load and customer projections from the
Load Forecast and applies approved fiscal 2019 tariff rates to calculate revenue. The Revenue
Forecast is a straightforward calculation, relative to the preparation of the Load Forecast, and
the method is unchanged from the Previous Application.108
K. CONCLUSION AND REQUESTED FINDINGS
68. The BCUC should find that the Load Forecast and Revenue Forecast for the Test
Period reflected in the Evidentiary Update are reasonable. The Load Forecast for years
following the Test Period will be updated in the upcoming IRP filing.
108 Exhibit B-1, Application, p. 3-52.
- 35 -
301539.00025/94161307.1
PART FIVE: FORECAST COST OF ENERGY
A. INTRODUCTION
69. In broad terms, BC Hydro’s Cost of Energy is influenced by many factors, including the
available Heritage resources, reservoir levels, pricing and delivered volumes under existing IPP
contracts, market prices, and load. The evidence discussed in this Part demonstrates that BC
Hydro’s forecast Cost of Energy, as updated in the Evidentiary Update, is reasonable for the
purpose of setting rates in the Test Period.
70. We focus on the following supporting points:
● First, the increase in the forecast Cost of Energy since the Previous Application is
primarily driven by an increase in costs related to IPPs and Long-Term
Commitments.109 The vast majority of those costs are associated with existing
EPAs, the terms of which are fixed, and for which cost recovery is mandated by
Direction No. 8.
● Second, BC Hydro is taking available steps to reduce IPP energy costs, including
exercising contractual rights under EPAs and suspending the Standing Offer
Program (“SOP”) indefinitely.
● Third, the forecast Cost of Energy for the Test Period reflects prudent system
operations.
➢ BC Hydro operates the system to meet load first, and then makes
decisions to dispatch resources and to undertake Electricity Purchases
or Surplus Sales to maximize the expected110 value of its energy
109 Costs for EPAs on the integrated system are categorized under “IPPs and Long-Term Commitments”. 110 Maximizing the value of BC Hydro’s energy supply portfolio on an “expected” basis does not mean that BC
Hydro attempts to predict what inflows will actually be at some point in the future, as described further in this Part.
- 36 -
301539.00025/94161307.1
supply portfolio within a range of outcomes. This approach brings
significant benefits for ratepayers.
➢ BC Hydro’s Energy Studies, which inform decisions made to achieve
this objective, are based on a sound methodology that has been
endorsed by independent experts as part of a recent audit.
● Fourth, BC Hydro’s approach to operating the system and capital planning both
ensure that ratepayers are getting the most out of BC Hydro’s Heritage Assets.
● Fifth, although the forecast Cost of Energy is used in determining BC Hydro’s
revenue requirements, through the use of regulatory accounts, customers
ultimately only pay the actual Cost of Energy.
71. BC Hydro is not, as part of this Application, proposing any generation projects or seeking
acceptance of any EPA. Long-term resource planning and its effect on Cost of Energy after this
Test Period will be addressed in the upcoming IRP. The next IRP will be informed by the results
of Phase Two of the Comprehensive Review as well as the CleanBC Plan.111
B. FORECAST INCREASE IN THE COST OF ENERGY DRIVEN BY EXISTING EPAS, FOR WHICH COST RECOVERY IS DIRECTED
72. The forecast increase in Cost of Energy in the Application is primarily driven by an
increase in costs related to IPPs and Long-Term Commitments. The vast majority of those costs
are associated with existing EPAs,112 the terms of which are fixed and for which cost recovery is
mandated.113
111 Exhibit B-6, CEC IR 1.1.2. 112 In the confidential response to Exhibit B-5-1, BCUC IR 1.18.3 BC Hydro provided a list of existing IPP contracts
included in the cost of energy forecast for the test period, including their respective resource type, levelized price $2019 (c/GWh), expected energy delivery (GWh), Cumulative Annual Energy (GWh/yr), and earliest expiration date.
113 Direction No. 8 and Clean Energy Act, s. 8.
- 37 -
301539.00025/94161307.1
(a) The Vast Majority of Total IPP Purchase Cost Increases Are Related to Existing EPAs
73. Figure 4-2 in the Application,114 included below, provides an indicative view of the key
drivers of changes to the Total IPP Purchase Cost forecast between the fiscal 2019 Plan values
from the Previous Application and the fiscal 2021 Plan values in this Application.115 The figure
illustrates that vast majority of total IPP cost increases relate to existing EPAs.
Costs Under Existing EPAs Increased Due to Price Escalation Clauses, Coming into Service and Volume Changes
74. The net increase in costs associated with existing EPAs reflects operational changes at
IPP facilities or other changes, as permitted under existing agreements, which impact the
forecast cost of IPP energy. These types of changes include price escalation, capacity increases,
and forecast delivery changes resulting from a partial-year forecast becoming a full-year
forecast. More than half of the forecast IPP cost increase (before savings) can be attributed to
114 Exhibit B-1, Application, p. 4-32. 115 Exhibit B-5, BCUC IR 1.17.1.
- 38 -
301539.00025/94161307.1
increased forecast deliveries from two IPP facilities, as permitted under their respective
agreements.116
Cost Recovery Is Mandated for Existing EPAs Entered into before April 1, 2016
75. Direction 8 provides that the BCUC must not disallow for any reason the costs incurred
by BC Hydro with respect EPAs entered into before April 1, 2016.117 As a result, the recovery of
the increase in IPP costs under most existing EPAs has been mandated by Government.
(b) A Small Portion of the Total IPP Purchase Cost Relates to EPA Renewals, which Includes Directed Biomass Purchases, and New EPAs
76. As illustrated in Figure 4-2 of the Application reproduced above, costs associated with
EPA renewals118 and new EPAs represent only a small portion of the total IPP purchase cost
forecast increases. The net cost increase shown as “EPA renewals” includes the costs of
expiring EPAs, the costs for hydro renewals (renewed at lower prices than the original
contracts) and the costs associated with the government-directed Biomass Energy Program
(renewed at lower costs than the original contracts but at higher volumes than compared to the
2013 IRP).119 Mr. Chow explained BC Hydro’s approach to IPP renewals:
Yes, so at this point, for the test period, there are really only a limited number of EPA renewals happening. So there are six biomass energy program contracts, that are biomass EPAs that are expiring, due to expire, and they are all covered by the biomass energy program. And then there were two small hydro projects – less than – in total they are less than 4 megawatts.
116 Exhibit B-1, Application, p. 4-32. 117 Direction No. 8, s. 4(1)(b). 118 The $1.3 million value for EPA renewals in Figure 4-2 represents the net change in cost (i.e., certain new EPAs to
replace existing expiring EPAs are forecast to increase in cost and others are forecast to decrease) from the Previous Application to the fiscal 2021 Plan of those EPAs that have been renewed since the Previous Application (as of May 2016) and those EPAs that are assumed to be renewed during the Test Period. Exhibit B-1, Application, section 4.7.1.2; Exhibit B-6, CEC IR 1.22.1. See also, Exhibit B-5, BCUC IR 1.15.1.1 and Exhibit B-16, BCUC IR 3.303.1.
119 Exhibit B-6, CEC IR 1.22.1. See also, Exhibit B-5, BCUC IR 1.15.1.1 and Exhibit B-16, BCUC IR 3.303.1.
- 39 -
301539.00025/94161307.1
So what we’ve said in our filings is that we are adopting a conservative internal approach for at least for the hydro renewals, and that would be to evaluate those at market value.120
77. It is appropriate to include these costs in the forecast Cost of Energy, for the following
reasons:
● BC Hydro has considered cost benchmarks when evaluating the cost
effectiveness of renewing hydro EPAs (which are subject to a process under
section 71 of the UCA). These benchmarks include (i) an estimate of the IPP’s
cost of service (including a rate of return), (ii) the IPP’s opportunity cost, (iii) the
impact to BC Hydro rates, and (iv) system benefits and support characteristics (if
applicable).121
● BC Hydro and the Government of B.C. worked together to develop a biomass
energy strategy to deal with biomass generating facilities with expiring EPAs.
One outcome of the biomass energy strategy is the Biomass Energy Program,
which BC Hydro is responsible for implementing. The Biomass Energy Program
applies to the seven biomass generating facilities with EPAs that are due to
expire before March 31, 2022.122 Under the Biomass Energy Program, BC Hydro
will potentially renew up to 80% of the historical aggregate deliveries for eligible
projects. As a result, up to 1,280 GWh per year will be renewed under the
program.123 Under Order in Council No. 158, the Government of B.C. has
provided a direction to the BCUC with respect to the biomass contracts and to
require the costs associated with the program to be recovered from
customers.124
120 Tr. 9, p. 1400, l. 23 to p. 1401, l. 11 (Chow). 121 Exhibit B-16, BCUC IR 3.303.3. 122 Exhibit B-6, BCSEA IR 1.11.5. 123 Exhibit B-6, BCSEA IR 1.11.7. 124 Exhibit B-6, BCSEA IRs 1.11.2 and 1.11.7. The Direction to the British Columbia Utilities Commission Respecting
the Biomass Energy Program, B.C. Reg. 71/2019, provides that the BCUC may not disallow for any reason the
- 40 -
301539.00025/94161307.1
78. BC Hydro expects that its EPA renewal approach beyond the Test Period will be revisited
as part of the process for the next IRP filing.125
C. BC HYDRO IS TAKING AVAILABLE STEPS TO MITIGATE IPP ENERGY COSTS
79. BC Hydro is managing energy costs from IPPs to the extent possible within the
parameters of its contractual obligations under EPAs.
● Exercising turn-down rights: BC Hydro enforces its rights and obligations in EPAs
to reduce cost commitments, such as exercising turn down rights when it is cost
effective to do so.126
● Terminations for cause and by agreement: BC Hydro does not have unilateral
rights to terminate its EPAs, i.e., to terminate without cause.127 In general, BC
Hydro only has a right of termination under an EPA if the counterparty triggers a
termination right, such as failing to reach commercial operation by the required
date or taking actions that constitute a material default under the specific
EPA.128 BC Hydro monitors its EPA portfolio to ensure that IPPs are in
compliance with the terms of their agreements and to consider exercising
termination rights when such rights arise. In addition, BC Hydro may exercise an
opportunity to terminate an EPA by mutual agreement, provided that it is in the
interest of customers to do so.129 Between fiscal 2015 and the filing of the
Application, BC Hydro terminated three EPAs. In addition, BC Hydro did not
renew three other expiring EPAs.130
recovery in rates of BC Hydro's costs with respect to a biomass contract for biomass facilities listed in the regulation.
125 Exhibit B-6, CEC IR 1.22.4. 126 Exhibit B-1, Application, p. 4-10. See also, Exhibit B-5, BCUC IRs 1.17.1, 1.17.2, 1.17.3 and 1.18.1. 127 Exhibit B-5, BCUC IR 1.18.1. See also, Exhibit B-5, BCUC IR 1.18.3.1. 128 Exhibit B-5, BCUC IR 1.18.1. 129 Exhibit B-5, BCUC IR 1.18.1. 130 Exhibit B-1, Application, p. 4-10.
- 41 -
301539.00025/94161307.1
80. BC Hydro has taken additional steps to proactively manage IPP costs such as pursuing
selective renewals at lower prices that are subject to BCUC acceptance of applications under
section 71 of the UCA,131 as described above.
BC Hydro Has Indefinitely Suspended the Standing Offer Program
81. The SOP was created in response to provincial policy direction. In February 2019, as
part of the Phase One Comprehensive Review, the Government of B.C. issued a regulation that
allowed BC Hydro to suspend the SOP indefinitely.132 Existing SOP EPAs, none of which expire
before fiscal 2030, will remain in place.133 Since there is no present obligation associated with
the indefinite suspension of the SOP, no costs associated with the suspension have been
included in the Test Period forecast.134 In any event, recovery of SOP EPA costs is prescribed by
section 8 of the Clean Energy Act.
D. FORECAST COST OF ENERGY REFLECTS HOW BC HYDRO OPERATES THE SYSTEM
82. BC Hydro plans its resources to meet domestic load and then, in the operating time-
frame, makes decisions to dispatch resources and to undertake Electricity Purchases or Surplus
to maximize the expected value of its energy supply portfolio within a range of outcomes. The
capability of BC Hydro’s supply resources is shown through the planning view and a forecast of
how that portfolio will actually be operated, based on expected conditions, is shown through
the operating view.135 As Mr. Clendinning explained:
And so those are the medium of what we’re doing, and to Ms. Matthews’s points, we’re looking at when and how to pr[o]cure additional resources. As we get closer in the timeframe that resource stack – if I’ll call it that – gets fixed. And
131 Exhibit B-1, Application pp. 4-8 to 4-12. 132 Exhibit B-1, Application, p. 4-9. The SOP includes the Micro-Standing Offer Program. BC Hydro will not be
executing any other SOP EPAs, with the exception of five First Nations’ clean energy projects that are part of Impact Benefit Agreements with BC Hydro and/or are mature projects that have significant First Nations involvement.
133 Exhibit B-6, CEC IR 1.6.1. 134 Exhibit B-5, BCUC IR 1.19.2.1. 135 The differences between the planning view and the operating view are described in Exhibit B-13, CEABC IR
2.28.1.
- 42 -
301539.00025/94161307.1
so how we then work with that fixed constraint on the system, that’s really where the operational view takes over and I know Ms. Matthews can get into that more detailed world in a bit.136
83. The forecast Cost of Energy for the Test Period is based on the operating view, which is
informed by outputs from BC Hydro’s Energy Studies.137 As discussed below, BC Hydro
operates the system to meet load first and then makes decisions to dispatch resources and to
undertake Electricity Purchases or Surplus Sales to maximize the expected value of its energy
supply portfolio within a range of outcomes. The Energy Studies support this objective by
developing an optimal set of reservoir and generation station operations and modelled market
transactions with Powerex, given the current forecasts of water inflow, market prices, and
weather adjusted load.138 BC Hydro has established an appropriate objective for its system
operations, as demonstrated by recent events in 2018 (fiscal 2019), and the Energy Studies are
a robust tool to help BC Hydro deliver on it.
(a) BC Hydro’s Operating Horizon Objective (Meeting Load First While Maximizing Value Within a Range of Outcomes) Is in the Best Interests of Ratepayers
84. In the operational (i.e., up to three years) time horizon, BC Hydro operates the system
to meet load first and then makes decisions to dispatch resources and to undertake Electricity
Purchases or Surplus Sales to maximize the expected value of its energy supply portfolio within
a range of outcomes. This objective is in the best interests of ratepayers.
85. Electricity Purchases or Surplus Sales are undertaken to both cost-effectively meet load
requirements and to take advantage of trade opportunities. As Ms. Matthews explained:
So BC Hydro wants to import or export from the system when we have a surplus, and we also want to import to meet our load, whereas what Powerex does is that they import for the purpose of reselling later to make trade revenue. So the purpose of what the two companies do are quite different. They are trying to [maximize] trade income, we’re trying to maximize the surplus when we have it, and sell it to Powerex to sell into the market, and then we’re also buying when
136 Tr. 8B, p. 1271, ll. 7-15 (Clendinning). 137 Tr. 9, p. 1425, ll. 3-11 (Matthews). 138 Exhibit B-1, Application, pp. 4-13 and 4-14.
- 43 -
301539.00025/94161307.1
we need it to meet our domestic needs, which could be for a number of reasons.139
86. Surplus Sales (also referred to as domestic sales) are sales to Powerex that occur
because BC Hydro has a surplus. Market Electricity Purchases are purchases from Powerex to
cost-effectively meet load. Net Purchases (Sales) from Powerex are transactions with Powerex
to generate Trade Income.140 Powerex also generates Trade Income from a wide range of
activities that are not connected to BC Hydro’s system.141 Ratepayers receive the full benefit of
Trade Income generated by Powerex’s activities and bear no downside risk under BC Hydro’s
definition of Trade Income, which has the effect of assigning any net loss in Trade Income to the
Government of B.C.142
87. While Powerex is able to use the residual capability of the BC Hydro system to generate
Trade Income, BC Hydro makes all of the decisions related to system operations and has the
ability to put constraints on Powerex’s activities. As Ms. Matthews emphasized:
So yes, Powerex imports and exports out of the system for trade, but I and my team have full ability to put constraints on what they do, and we set those constraints on what they can and can’t do, because ultimately I’m responsible for operating the system. They like to trade and sometimes there can be discussion back and forth on if they are wanting to do something and we’re saying no. Like especially when we’re coming up to a peak. Like we’re going to be conservative making sure we’re holding back.
139 Tr. 9, p. 1480, ll. 9-19 (Matthews). 140 Exhibit B-1, Application, pp. 4-6 and 4-7. Trade Income is the greater of (a) the amount that is equal to BC
Hydro’s consolidated net income, less BC Hydro’s non-consolidated net income, less the net income of BC Hydro’s subsidiaries except Powerex, less the amount that BC Hydro’s consolidated net income changes due to foreign currency translation gains and losses on intercompany balances between BC Hydro and Powerex; and (b) zero: Exhibit B-1, Application, p. 1-41.
141 Exhibit B-17, AMPC IR 3.3.2. 142 BC Hydro forecasts Powerex’s net income based on its historical five year average. The difference between
forecast Powerex net income and actual Powerex net income is deferred to the Trade Income Deferral Account. However, if Powerex’s net income is less than zero, the amount deferred to the Trade Income Deferral Account is the difference between zero and the forecast amount.
- 44 -
301539.00025/94161307.1
So like last week when we had the high winter peak, so it’s us who are setting like what are we needing to have, and if there’s leftover capability, then Powerex can use, but we decide how we use our resources.143
88. While different imports or exports to/from the BC Hydro system may occur for different
reasons, the overall objective is the same: to meet load first while maximizing the expected
value of the energy supply portfolio to ratepayers, within a range of outcomes. BC Hydro often
refers to this objective as “maximizing consolidated net revenue”, but the implicit starting point
phraseology is that domestic load is being met first.144 This is evident, for instance, in Ms.
Matthews’ response as to why she considers meeting domestic load and maximizing the
expected value for ratepayers to be complementary, rather than conflicting, objectives:
No, I don’t think they are, because the – I guess within the energy studies the first thing you have to do is meet load, and then how we’re meeting it is to then maximize the consolidated net revenue. So I don’t see that as a conflict. It’s more like meeting the load is a given as part of the modeling and it’s part of how we operate.145
89. The fact that there is uncertainty and risk around domestic requirements does not mean
the objectives themselves are inconsistent. But it does require an assessment of probabilities,
which is done as part of the Energy Studies.
90. BC Hydro maximizes the value of BC Hydro’s energy supply portfolio on an “expected”
basis. This does not mean that BC Hydro attempts to predict what inflows will actually be at
some point in the future. Rather, it means that BC Hydro makes decisions based on
probabilities. The probabilities are informed by historical ranges, and become more refined as
the year rolls forward and more information about conditions becomes known. As Ms.
Matthews explained:
143 Tr. 9, p. 1447, l. 22 to p. 1448, l. 11 (Matthews). See also, Tr. 10, p. 1746, ll. 10-16 (Matthews). 144 Ms. Matthews explained the phrase this way: “Yeah, so our objective that we operate the system to is to
maximize the consolidated operation net revenue, and I know that’s sort of our mantra that we say all the time, and what it means when I say “consolidated” is that it’s the BC Hydro domestic buying and selling – or selling our surplus and buying for our deficit and the Powerex trade”: Tr. 9, p. 1426, l. 22 to p. 1427, l. 2.
145 Tr. 10, p. 1746, ll. 10-16 (Matthews).
- 45 -
301539.00025/94161307.1
As I had asked the question, you know, earlier, if you’re going to guess at whether it rains or not in April, what you’d do is you look back at historics. So we’re not trying to use physical weather forecasting models to do it, we’re just looking at what’s the probability and we know the probability. We know it’s not right.
Like, we’re not trying to guess, that’s the point. What we’re doing is we’ve got a range of probabilities and then as we go forward we’re always adjusting as we get more information. And what we’re doing is we’re not betting that it’s going to be wet and we’re not betting it’s going to be dry, we’re just going forward economically kind of always aiming for the middle and adjusting as it goes.146
91. BC Hydro’s approach recognizes that actual conditions will be different than expected
conditions. While decisions are made to maximize value, BC Hydro manages those decisions to
maintain its ability to respond to a range of probable future conditions. As Ms. Matthews
explained:
So to answer your question about the risk, we use energy studies to give the economic picture and then we evaluate and look at – I tend to call them the tails. They are the outliers on the distribution. So we keep an eye on our tails.147
92. Adopting an unduly risk averse approach that withholds exports in anticipation of very
low probability events occurring, would produce higher rates. Ms. Matthews explained:
Now, we did in a few places talk about --- I think there were some IRs that asked about what if your objective was something different. I’m trying to find those there. But within that IR I think how we answered it was that if we had a different objective, It might address one risk versus another, but our overall value of the system would be less. So I don’t see that our objective of maximizing consolidated net revenue feeds into increasing that risk.148
93. The following section demonstrates that BC Hydro’s approach is in the best interest of
ratepayers, with reference to BC Hydro’s recent ability to maximize value for ratepayers while
managing through significant events that occurred in 2018 (fiscal 2019).
146 Tr. 9, p. 1464, ll. 2-16 (Matthews). 147 Tr. 9, p. 1455, ll. 8-12 (Matthews). 148 Tr. 10, p. 1779, ll. 2-11 (Matthews).
- 46 -
301539.00025/94161307.1
(b) In 2018, BC Hydro Managed Through Significant Events While Maximizing Value for Ratepayers
94. In the summer of 2018, BC Hydro had a forecast surplus and sold energy to take
advantage of high prices for the benefit of ratepayers. As Ms. Matthews explained:
So, in the summer of 2018, as we came through and we have a forecast of surplus, we had a threshold sale price set, and the prices were really high, so a lot of sales were made from the system, and those were allocated to domestic. Then towards the end of the summer we got to the point where we were actually on balance. And BC Hydro, we really try not to sell and then need to buy back, that really is Powerex’s job, so we removed our threshold sale price at that point. But that was towards the end of the summer. So, those sales were economic.149
95. While BC Hydro’s load and resources were approximately balanced following these
exports, three significant events then occurred, which then created a need for imports:150
• First, dry conditions in the Williston basin resulted in four consecutive months of low
inflows, with September, October and November being the third, second and fourth
lowest in 60 years.
• Second, the Enbridge pipeline explosion in October caused a high-level of gas supply
uncertainty in B.C. and the Pacific Northwest with only 80% of normal capacity expected
throughout the winter. This affected western wholesale electricity markets by creating
an increased demand for electricity to replace gas-generating units that would have
otherwise been able to run.
• Third, B.C. experienced a record-breaking cold February, which resulted in three
electricity demand records being broken that month, followed by the driest March on
record in parts of the province. These dry conditions impacted inflows into BC Hydro’s
reservoirs as well as energy supply from IPPs. Run-of-river projects were producing less
than projected because of low water levels. In addition, wind projects also delivered less
149 Tr. 9, p. 1482, ll. 4-14 (Matthews). 150 Exhibit B-17, AMPC IR 3.3.1, Attachment 1.
- 47 -
301539.00025/94161307.1
than expected. For example, in February, run-of-river and wind projects only produced
29% and 50% respectively of what they were forecast to produce.
96. In order to secure the imports required to meet load in this environment, at as
reasonable a price as possible, BC Hydro entered into the Powerex Letter Agreement to reduce
BC Hydro’s risk and secure the required imports.151 As Ms. Matthews noted:
So similarly if you look at the total numbers for the year, I think the imports and exports are total imports, or you could almost say wash, because we sold a bunch in the summer and then bought it back in the winter.152
97. Ms. Matthews summarized the results of these events, stating:
I mean, making those sales was the appropriate thing to do at that time. I think we sold them at 76, in the end we bought back at about 50. We made a gain of $26, on what we did in the most difficult year.
So we do have to be very careful and watch those [tails]. But I think the flexibility of the system, I mean we always talk in concept how important the flexibility of the system is, but last year was I think the first time where I really felt it. And you really realize how benefit [sic] that system is, and the flexibility that we have, especially when we could look forward and say, “Okay, with the pipeline and really high prices in December, we are not wanting to be buying then, and we had the ability to look forward.”
Now, coming to the February and March, that was also an event that was, I would say, outside the historical dataset of what we had. We had a six-week cold period. And it was still cold in March. Now, in March and end of February it’s not as cold as let’s say it was last week. But for that time of year, it was still extremely cold, and that six-week period was—actually coming back to the weather forecast that we had coming into that section, that seasonal forecast was actually saying it should be warmer than normal, and we ended up having like a six week very cold period.
But so that actually proved out that that was really the sort of risks that we were protecting against, and it actually happened to occur—I don’t think in the fall I
151 Exhibit B-16, BCUC IR 3.314.1. 152 Tr. 9, p. 1509, ll. 21-26 (Matthews).
- 48 -
301539.00025/94161307.1
had any idea or thought that—you know, that that sort of thing is definitely is going to happen but we had to protect against the chance that it might.153
98. Ms. Matthews explained that it was not “luck” that led to the favourable results for BC
Hydro’s customers, but rather the outcome of making operational decisions based on informed
probabilistic analysis:
So I disagree with the comment that it’s not sure if it is luck or skill. I mean, that’s what the energy studies does in terms of looking at the range of possible outcomes. I wasn’t trying to guess what the year would turn out to be, but I was being careful to make sure that we managed those tails.
And really for all probability, it might have not turned out to have that February, and we might have, you know, bought energy at—I think it was in the—I just can’t remember, 30s, 40 dollars or the total cost was, I think, $50 that we might not have needed. But that still would have been worth it and we could have still then, you know, eventually sold that back into the market at perhaps, you know, usually probably around that cost anyway.
So the whole thing on mismanagement is you’re not actually trying to guess what the year is going to be. And what I really find is that—I mean that’s why we have to look at the data. Like everybody tends to have current-itis on what is happening now. Like I mean think of last summer. May and June how dry that was. And there was fires already starting up north, and there was a lot of talk about how bad the fire season was going to be. Like I think everybody was betting on a dry summer, but we just have to look at the data and the probabilities and still protect the ends. And that’s what we did and do.
So I guess what I’m saying is like we—we always—all we can really do is look at what those probability are as the range of outcomes. We base our decisions on the economics where we are, and we watch our tails.154
99. Ms. Matthews explained that even with the benefit of hindsight, she wouldn’t have
made any changes:
THE CHAIRPERSON: So you just used the term “protecting against risks”. So I think what I’m hearing you say is that there was—I think there was three particular risks that crystalized earlier last year. One is a cold February, second is a drought and third is the Enbridge pipeline explosion. And you wouldn’t
153 Tr. 9, p. 1483, l. 12 to p. 1484, l. 20 (Matthews). 154 Tr. 9, p. 1488, l. 21 to p. 1490, l. 1 (Matthews).
- 49 -
301539.00025/94161307.1
normally even attempt to protect against the pipeline explosion, presumably, let alone all three of those risks occurring at the same time. Is that—
MS. MATTHEWS: A Yes, that’s fair to say.
THE CHAIRPERSON: That’s fair?
MS. MATTHEWS: A That’s correct.
THE CHAIRPERSON: But I think I’m hearing you say though that in spite of that it was still, in retrospect, turned out to be the right decision to make the sales in 2018 that you did because you made enough money off those sales to cover even those three unexpected events all together.
MS. MATTHEWS: A Yes.
THE CHAIRPERSON: Did I hear you say that? And I—
MS. MATTHEWS: A Yes. No, that’s correct that the—I mean, I think the sales that we made in the summer were maybe slightly less than actually what we had bought back, I’d have to check the numbers, but certainly I stand by that those sales that we made in the summer were the correct things to do and I’d do them again.
THE CHAIRPERSON: So with hindsight you would go back and do exactly the same thing anyway?
MS. MATTHEWS: A Yes.155
100. In summary, Ms. Matthews concluded:
We face every day making decisions in uncertainty. That’s actually what my job is. So that’s part of what we do all the time. If we had a perfect forecast of everything we’d all be rich probably and life would be easy.
But the other thing I would say is that I think if you really want to look at the success of fiscal ‘19 you actually just have to look at the results. We managed through the most difficult period that we’ve had and we’ve saved money for the ratepayers. And that’s something I’m actually very proud of, and so I think that’s where you actually look if you look at what was the success of that year.156
155 Tr. 9, p. 1484, l. 24 to p. 1486, l. 1 (Matthews). 156 Tr. 9, p. 1470, ll. 9-21 (Matthews).
- 50 -
301539.00025/94161307.1
(c) Energy Study Methodology Produces a Sound Price Signal that Enables BC Hydro to Achieve its Operating Objective
101. BC Hydro’s Energy Studies, which it uses to achieve its operating horizon objective
(discussed above), are based on a sound methodology that has been endorsed by independent
experts as part of a recent audit.
Energy Studies Identify Probabilities, Allowing Data-Driven Risk/Reward Decisions
102. BC Hydro outlined in the Application how an Energy Study works, and Ms. Matthews
elaborated at the hearing.157 At its core, the Energy Study provides price signals that allow BC
Hydro to decide (a) which basins to use, and (b) at what price BC Hydro should undertake
Electricity Purchases or Surplus Sales.158 As Ms. Matthews described:
When we’re actually in operations, like the shift office that I had talked about previously, what they are doing is doing a load resource balance for the next hour. So we use that term a lot and we can use it in different times, but for the energy studies what it is a load resource balance on the energy out across the operating time period.
And so what the energy studies also really do is it – it’s really looking at the probabilities. So there is the key factors that are the drivers into the energy studies are the inflows, and that’s the biggest one. Also the load. And then the market prices. So those three tend to be the big ones that change things a lot.
Also included that can have an impact is any outages or system constraints that we have in. So that’s all in the energy study.
So what they do is they model it out and they give an optimal set of where you are now versus all the things that can happen. And so we see that going out, and that gives us the price signals.159
103. Operationally, BC Hydro fills its system storage during the freshet, when inflows exceed
loads. The precise amount of refill depends on reservoir elevations at the end of winter,
157 Tr. 9, p. 1421, l. 17 to 1442, l. 4 (Matthews); Tr. 9, p. 1445 l. 11 to p. 1451, l. 25 (Matthews); Tr. 9, p. 1452, l. 22
to p. 1470, l. 21 (Matthews); Tr. 9, p. 1472, l. 23 to p. 1490, l. 1 (Matthews); Tr. 9, p. 1490, l. 13 to p. 1503, l. 10 (Matthews); Tr. 9, p. 1504, l. 17 to p. 1507, l. 12 (Matthews).
158 Tr. 8B, p. 1269, ll. 9-15 (Matthews). 159 Tr. 9, p. 1453, l. 11 to p. 1454, l. 6 (Matthews).
- 51 -
301539.00025/94161307.1
snowpack (and to a lesser extent, spring precipitation), generation from other resources (e.g.,
IPPs) and loads. While reservoir levels at the end of winter are largely dependent on load and
start-of-winter elevations, BC Hydro is able to adjust end of period storage levels through
market purchases and/or sales and thermal generation.160 Ms. Matthews explained that BC
Hydro makes use of multi-year storage, which means that in any given year BC Hydro might end
up storing into the system storage or drafting from the storage.161
104. The Energy Study models account for the trade-offs (risk/reward) between selling now
and selling later, or buying now and buying later.162 There are potential risks with decisions to
act (i.e., buy/sell), as well as decisions not to act (i.e., not buy/not sell).
● Short-term decisions that result in market purchases or surplus sales will always
result in changes in longer-term probabilities of the need to either purchase or
sell energy, or re-operate to manage system storage. Making sales in the high
priced summer period also would increase the probability of the need for
purchases in the coming fall and winter.163
● There is similarly risk associated with a decision to forego purchases or sales.
There is always a risk that foregone opportunities to sell (at a lower price) or
purchase (at a higher price) will turn out to have been economically beneficial. In
addition, inflows may come in higher than forecast such that the volume of sales
should have been higher (thus selling at a lower price), or vice versa.164
160 Exhibit B-5, BCUC IR 1.20.6. 161 Tr. 9, p. 1424, l. 22 to p. 1425, l. 15 (Matthews). 162 Exhibit B-31, BCUC Panel IR 2.6.3. In more technical terms, the Energy Study optimization trades off the
financial benefit of withdrawing energy from storage while accounting for a decrease in the amount of generation per unit of water due to operating at the lower reservoir levels. See Exhibit B-5, BCUC IR 1.20.3.
163 Exhibit B-31 BCUC Panel IR 2.6.3. 164 Exhibit B-31 BCUC Panel IR 2.6.3.
- 52 -
301539.00025/94161307.1
BC Hydro manages trade-offs in short-term and long-term risks by modelling the system over a
five-year time horizon, which takes into account the longer-term impacts of any shorter-term
benefits or costs.165
105. A key output of the Energy Studies is a forecast of the marginal value of water in BC
Hydro’s two largest reservoirs (Williston and Kinbasket).166 The forecast monthly marginal
value of water provides a price signal — a relative measure that guides the operation of these
reservoirs in the context of market and system conditions. In other words, it informs when (a)
domestic energy resources should be dispatched versus purchases made from Powerex, or (b)
when additional domestic resources should be dispatched to facilitate sales to Powerex.167
106. The Energy Studies account for a wide range of potential occurrences. The use of
weather year ensembles ensures that the variability in inflows, prices, loads, and resources due
to the impacts of weather are well represented in the models. This range captures both dry
and wet periods. It represents the historic geographic correlation in weather among the
regions included in the modeling.168 Each year, the most recent year of historic data is added to
the modeled weather sequences, so that the range adjusts over time and always includes the
most recent data. For this reason, impacts of climate change are implicitly included in the
forecast.169 Ultimately, the range of potential occurrences is sufficiently large that the average
of the resulting forecast represents an unbiased estimator of the drivers, and hence how the
system will be operated.170
165 Exhibit B-16, BCUC IR 3.309.1. See also, Exhibit B-5, BCUC IR 1.29.2.1; Exhibit B-6, AMPC 1.15.4; Exhibit B-6,
BCOAPO 2.108.1; Exhibit B-49, BC Hydro Undertaking No. 28; Exhibit B-31, BCUC Panel IR 2.5.2.1. 166 Exhibit B-1, Application, pp. 4-13 and 4-14. 167 Exhibit B-1, Application, pp. 4-13 and 4-14. 168 Exhibit B-1, Application, Appendix DD, Energy Studies Process Internal Audit. See also, Exhibit B-5, BCUC IR
1.31.1; Exhibit B-6, AMPC IR 1.15.8; Exhibit B-13, AMPC IR 2.48.7. 169 Exhibit B-6, CEC IR 1.17.1. See also Exhibit B-23, GJOSHE IR 4.2.1. 170 Exhibit B-1, Application, Appendix DD, Energy Studies Process Internal Audit. See also, Exhibit B-5, BCUC IR
1.31.1; Exhibit B-6, AMPC IR 1.15.8; Exhibit B-13, AMPC IR 2.48.7.
- 53 -
301539.00025/94161307.1
Energy Studies are Updated Monthly and Are Augmented With Additional Analysis
107. BC Hydro updates the Energy Studies monthly with new input data pertaining to
import/export transmission limits and market prices.171 BC Hydro also incorporates the most
recent actual load data, augmented by the latest approved load forecast.172 On a weekly basis,
the forecast is compared to actuals and changes to key drivers are reviewed. BC Hydro
augments the Energy Studies with a number of other models, which are used for daily and
weekly analysis to verify that the Energy Studies are working as intended.173
BC Hydro’s Energy Studies Process Endorsed by Recent Audit
108. In fiscal 2019, BC Hydro undertook an internal audit of its monthly Energy Studies
process.174 BC Hydro’s Internal Audit group retained SINTEF, an organization with expertise in
load forecasting, risk management, hydrothermal market modelling and hydropower
scheduling models.175 The internal audit concluded that:
(a) BC Hydro has a well-established Energy Studies process in place;
(b) Key models are appropriate; and
(c) The methodologies applied are in line with leading industry practices.
(d) The Lower Cost of Energy Forecast in the Evidentiary Update Reflects Shift from Run-of-River IPP Power to Lower Cost Market Purchases Due to Low Water Conditions
109. The forecast Cost of Energy in the Evidentiary Update, which is based on the June 2019
Energy Study, was materially lower than the forecast in the Application.176 In fiscal 2020, BC
171 Exhibit B-5, BCUC IR 1.20.5.1 172 Exhibit B-12, BCUC IR 2.208.1. 173 Exhibit B-5, BCUC IR 1.31.3. Ms. Matthews elaborated on the tools that BC Hydro uses for within-month
planning: Tr. 10, p. 1752, l. 19 to p. 1753, l. 23 (Matthews). 174 The internal audit report is provided as Appendix DD to the Application. 175 Tr. 10, p. 1788, l. 16 to p. 1789, l. 1 (Matthews). The working paper that SINTEF prepared for the BC Hydro
Internal Audit team for the Energy Studies Internal Audit was filed as Exhibit B-52, BC Hydro Undertaking No. 29.
176 Exhibit B-19, Evidentiary Update, p. 7. See also, Exhibit B-16, BCUC IR 3.307.1. The Cost of Energy forecast in the Application was based on BC Hydro’s October 2018 Energy Study.
- 54 -
301539.00025/94161307.1
Hydro’s total Cost of Energy is forecast to increase by $41.9 million from the fiscal 2020 Plan. In
fiscal 2021, total Cost of Energy is forecast to decrease by $185.6 million from the fiscal 2021
Plan. Overall, the updated Cost of Energy forecast in the Test Period represents a decrease of
$143.7 million compared to the forecast in the Application.177
110. The primary driver of the decreased Cost of Energy in the Evidentiary Update was lower
costs for IPPs and Long-Term Commitments.178 Dry conditions and lower water inflows
decreased planned hydroelectric generation (water rentals) and purchases from hydroelectric
IPPs and Long-Term Commitments. The decreased Cost of Energy is was also attributable to
updates to historical average deliveries to incorporate the fiscal 2019 actual deliveries for
operating projects, which resulted in a lower IPP forecast compared to the Application,179 as
well as delayed commercial operation dates.180 The decrease in hydroelectric generation and
purchases from IPPs and Long-Term Commitments result in lower planned surplus sales and
higher planned market electricity purchases.181 The forecast market price was lower than the
forecast delivered cost of IPP energy, such that the overall Cost of Energy decreased. As Ms.
Matthews explained:
So, if BC Hydro is buying from Powerex, what’s the price of those versus the price of the IPPs? And then to the extent that the market prices are lower then that will show a savings and I think that is what’s being shown in those figures there.182
E. BC HYDRO IS GETTING THE MOST OUT OF ITS HERITAGE ASSETS
111. In its Decision on the Previous Application, the BCUC questioned whether Heritage
Assets are providing optimal value to BC Hydro customers.183 The evidence, discussed below,
177 Exhibit B-19, Evidentiary Update, Appendix C, p. 1. 178 Exhibit B-19, Evidentiary Update, p. 9. 179 Exhibit B-19, Evidentiary Update, Appendix C, p. 3. 180 Exhibit B-19, Evidentiary Update, Appendix C, pp. 1-2. See also, Exhibit B-6, CEABC IRs 1.7.2 and 1.7.3. 181 Exhibit B-19, Evidentiary Update, p. 8. 182 Tr. 9, p. 1397, ll. 22-26 (Matthews). 183 Decision on the Previous Application, p. 24.
- 55 -
301539.00025/94161307.1
demonstrates that they are providing optimal value in both the operating and planning time
horizons.
(a) Operating Horizon: Prioritizing Operating Specific Heritage Assets Over Existing EPAs Would Be Detrimental to Ratepayers
112. BC Hydro’s approach of operating the system in an integrated manner is better for
ratepayers than prioritizing operating specific Heritage Assets. While Heritage Assets are
generally lower cost than IPP purchases, in the operating horizon the resource stack available to
BC Hydro is essentially fixed.184 EPAs with IPPs are take-or-pay. BC Hydro’s monthly Energy
Studies optimize the operational management of all sources of energy supply on BC Hydro’s
integrated system. Over the operating horizon, BC Hydro operates the system to meet its
objective of meeting load and otherwise maximizing net revenue for the benefit of its
ratepayers.185 The price signals that come out of the Energy Studies are used to determine
which basins to run, and in what order, or whether BC Hydro is willing to either import or
export.186 This approach means that over the operating horizon, BC Hydro will obtain energy in
the most economic manner possible, rather than prioritizing lower cost sources of energy.
(b) Planning Horizon: Capital Planning Maximizes the Long-Term Benefits from Heritage Assets
113. BC Hydro is in a multi-decade period of significant renewal of its Heritage Assets.
Investments are prioritized and staged to maintain overall system reliability and spread capital
costs to avoid sudden rate impacts. For facilities that are not a significant contributor to overall
system reliability, investments to restore generation have been deferred until such time that
there is a system need for energy and capacity; and they are of a high enough priority to be
included within BC Hydro’s 10 year Capital Plan.187
184 Tr. 9, p. 1503, l. 1 to p. 1505, l. 1 (Matthews and Clendinning). 185 Tr. 8B, p. 1268, l. 25 to p. 1269, l. 8 (Matthews). 186 Tr. 8B, p. 1269, ll. 9-15 (Matthews). 187 Exhibit B-5, BCUC IR 1.32.3.1.
- 56 -
301539.00025/94161307.1
114. Investments to renew Heritage Assets are currently proposed in the next 10 to 20 year
period. The current strategy includes the necessary preventative maintenance and capital
investments to mitigate risks related to safety, water conveyance, and the environment.188 BC
Hydro’s witnesses explained the analysis that BC Hydro undertakes in deciding whether to
cease investing in a particular asset.189
115. Cost is an important consideration informing investment decisions across different
resources (e.g., choices between IPP renewals and investments in Heritage Assets).190 The cost
of individual IPP EPA renewals depend on many factors (e.g., resource type, location, age or
condition of generation assets, energy profile, reliability) and such costs are not known until
negotiations are completed. The cost of incremental Heritage Asset capital investments to
increase energy and/or capacity output depends on the scale, location, and timing of the
project as well as whether they are conducted in concert with other necessary asset
investments.191
F. VARIANCE ACCOUNTS ENSURE CUSTOMERS PAY ACTUAL COST OF ENERGY
116. BC Hydro’s costs of energy will inevitably vary from planned amounts for a number of
reasons including weather, water inflows, timing of delivery, and market conditions. In
recognition of this fact, the BCUC has thus approved the deferral of variances between planned
and actual costs of energy to either the Heritage Deferral Account or the Non-Heritage Deferral
Account. The Non-Heritage Deferral account also captures the variances between planned and
actual domestic customer load, referred to as the Domestic Revenue Variance. These accounts
have been in place for a number of years, and continue to play an important role for both
188 Exhibit B-5, BCUC IR 1.32.3.1. 189 Tr. 11, p. 1885, l. 20 to p. 1893, l. 20 (Darby and Kumar). 190 Please refer to BC Hydro’s response to Exhibit B-5, BCUC IR 1.32.3.1 for a description of some of the other
factors that influence the investment decisions with regard to Heritage Asset upgrades or expansions. 191 Exhibit B-5, BCUC IR 1.32.3.3.
- 57 -
301539.00025/94161307.1
customers and BC Hydro. In the end, although BC Hydro’s revenue requirements are based on
a forecast Cost of Energy, customers only pay the actual costs.192
G. CONCLUSION AND REQUESTED FINDINGS
117. The BCUC should find that BC Hydro’s forecast Cost of Energy for the Test Period is
reasonable, being based on a sound methodology and appropriate assumptions. The BCUC’s
determination on the forecast, while necessary for rate setting purposes, will not impact the
actual Cost of Energy paid by customers that is “trued-up” using existing variance accounts.
192 Exhibit B-1, Application, p. 4-19.
- 58 -
301539.00025/94161307.1
PART SIX: OPERATING COSTS
A. INTRODUCTION
118. In this Part, we address the evidence demonstrating BC Hydro’s successful efforts to
contain controllable operating costs throughout the company. These efforts are a
manifestation of the culture of cost-containment highlighted by Messrs. O’Riley and Wong (the
Policy Panel), among other witnesses.193 While there will be increasing pressure to increase
operating cost budgets after this Test Period,194 BC Hydro’s efforts to date have delivered
immediate benefits for customers.
119. We focus on the following points:
● First, BC Hydro has provided detailed operating cost information and
benchmarking in response to the BCUC’s comments and recommendations.
● Second, BC Hydro’s robust top-down and bottom-up budgeting process yielded a
lower budget than would have been possible using zero-based budgeting. BC
Hydro monitors performance and makes necessary budget adjustments as
circumstances arise.
● Third, BC Hydro absorbed controllable cost pressures within existing budgets.
Operating cost increases during the Test Period are generally attributable to
uncontrollable factors.
● Fourth, BC Hydro has achieved savings, offset uncontrollable cost pressures and
absorbed additional work requirements from increased operating complexity
through: the Workforce Optimization Program; Accenture repatriation; the
consistent approach to a vacancy factor; re-purposing the unallocated funds
193 See Part Three of these Submissions. 194 See Part Three of these Submissions.
- 59 -
301539.00025/94161307.1
budget; lease consolidations; reduced spending on advertising; paperless billing;
the Work Smart Program; and, the “making it easier to get work done” initiative.
● Fifth, operating Full-Time Equivalents (“FTEs”) have been flat since 2012, and
planned increases in the Test Period are associated with work ramping-up on
Site C. FTEs added as part of the Workforce Optimization Program and
Accenture repatriation have reduced, not increased, BC Hydro’s overall costs.
● Sixth, BC Hydro has mitigated increases in Power System maintenance
expenditures in recent years, while still maintaining reliability. It has done so
despite a growing Power System asset base, aging assets, and increased
regulatory requirements.
● Seventh, BC Hydro operating expenses benchmark favourably.
B. OPERATING COSTS SNAPSHOT: COST PRESSURES WITH OFFSETTING TEST PERIOD SAVINGS
120. In the Application, base operating costs were budgeted to increase by only 1.1% in fiscal
2020 and 1.3% in fiscal 2021, which is less than forecast inflation.195 The planned increases
were largely due to uncontrollable factors, since BC Hydro absorbed controllable cost increases
within existing budgets. In the Evidentiary Update, operating costs increased relative to the
Application because the discount rate used to value BC Hydro’s pension costs (which is
uncontrollable and correlated with interest rates) had decreased; this increased BC Hydro’s
current service pension costs.196
121. The following table provides an overall snapshot of BC Hydro’s operating costs, after
incorporating the impacts of the Evidentiary Update (as corrected by Exhibit B-11-2).197
195 Exhibit B-5, BCUC IR 1.40.2. Please refer to Table 5-4 on page 5-21 and Table 5-6 on page 5-25 of Chapter 5 of
the Application for further information on these cost savings. 196 Exhibit B-19, Evidentiary Update, p. 12. 197 Exhibit B-11-2, Evidentiary Update, Appendix A, Schedule 5, Lines 1 to 9.
- 60 -
301539.00025/94161307.1
C. BC HYDRO ADDRESSED THE BCUC’S RECOMMENDATIONS AND COMMENTS ON OPERATING COSTS
122. The BCUC’s Decision on the Previous Application stated that the Panel did not have “a
high degree of comfort in BC Hydro’s starting point, being the 2016 base operating cost.”198
The BCUC also commented on the absence of benchmarking. Section 5.2 of the Application
outlines how BC Hydro has considered and responded to each of the BCUC’s comments and
recommendations.
123. Relative to the Previous Application, BC Hydro filed additional information in support of
its forecast revenue requirements, including:
● Seven chapters (Chapters 5A to 5G), consisting of hundreds of pages of evidence,
on the composition, drivers and outcomes of the overall budget of each of BC
Hydro’s Key Business Units (“KBUs”) and their Departments. The information
provided differs from the Previous Application in that it goes beyond justifying
the incremental amounts sought and provides support for the entire budgeted
amount.
● Detailed discussion of BC Hydro’s budgeting process (addressed in Section D
below).
● An explanation of various initiatives and steps that have resulted in BC Hydro’s
revenue requirements being lower than they would have otherwise been
(addressed in Section F below).
198 Decision on the Previous Application, p. 33.
Total Base Operating Costs (Fiscal 2019 - Fiscal 2021)($ million)
Reference RRA Actual Diff Plan Update Diff Plan Update DiffLine Column 1 2 3 = 2 - 1 4 5 6 = 5 - 4 7 8 9 = 8 - 7
Operating Costs by Business Group1 Integrated Planning 5.1 L8 270.1 285.9 15.8 290.8 290.8 0.0 293.0 293.0 0.02 Capital Infrastructure Project Delivery 5.2 L6 81.9 85.9 4.0 80.1 80.1 0.0 81.1 81.1 0.03 Operations 5.3 L9 216.2 215.6 (0.6) 237.3 237.3 0.0 240.1 240.1 0.04 Safety 5.4 L6 54.9 53.6 (1.3) 56.8 56.8 0.0 57.5 57.5 0.05 Finance, Technology, Supply Chain 5.5 L5 265.0 261.2 (3.8) 262.6 262.6 0.0 264.8 264.8 0.06 People, Customer, Corporate Affairs 5.6 L9 122.5 105.5 (17.0) 110.6 110.6 0.0 111.9 111.9 0.07 Other 5.7 L6 (251.6) (250.5) 1.0 (260.2) (244.3) 15.9 (260.5) (244.4) 16.18 F17-F19 RRA Compliance Filing Adjustment 10.4 0.0 (10.4) 0.0 0.0 0.0 0.0 0.0 0.09 Total Base Operating Costs 769.5 757.2 (12.2) 777.9 793.8 15.9 787.8 803.9 16.1
F2020 F2021F2019
- 61 -
301539.00025/94161307.1
124. BC Hydro also addressed benchmarking. The absence of evidence on benchmarking in
the Previous Application likely created the incorrect impression that BC Hydro does not use
benchmarking for internal purposes. While not all KBUs lend themselves to the use of
benchmarks or metrics, there are a number of KBUs that do use benchmarks and metrics to
help inform management decisions.199 In this proceeding, BC Hydro has discussed the Morneau
Shepell compensation benchmarking and the Navigant and First Quartile maintenance
benchmarking. BC Hydro also summarized in Table 5-16 of the Application a number of other
metrics that it uses.200 In addition, BC Hydro retained the Brattle Group (“Brattle”) to prepare
an independent benchmarking report of BC Hydro’s operating costs, and undertook a high-level
comparison against three Canadian electric utilities (discussed further in Section I below).201
125. Lastly, in the sections below, BC Hydro has addressed the BCUC’s remaining comments
and recommendations with regards to operating costs:
● Section E below provides evidence of the value of BC Hydro’s Total Rewards
program. Specifically, BC Hydro has been able to achieve above average
employee retention at compensation levels that are below median market rates.
● Section F below explains how BC Hydro made decisions to replace contractors
with employees under the Workforce Optimization Program, including
consideration of long-term costs.
● Section F below also sets out why ratepayers benefit from BC Hydro’s approach
to its Work Smart Program, which aims to deliver capacity hours gained rather
than labour budget or FTE reductions.
199 Exhibit B-1, Application, Chapter 5, p. 5-63. 200 Exhibit B-1, Application, Chapter 5, p. 5-64. In Exhibit B-6, CEC IR 1.37.1, BC Hydro confirmed that this is a
complete list, i.e., it was not being selective. The details of the peer group for the metrics appearing in Table 5-16 are set out in Exhibit B-5, BCUC IR 1.62.3 and other details about the results of individual benchmarking are set out in Exhibit B-5, BCUC IR 1.62.1 to 1.63.15. Further discussion of these benchmarks are provided as part of the operating costs and FTEs discussion for various KBUs in Exhibit B-1, Application, Chapters 5A through 5G.
201 Exhibit B-1, Application, Section 5.7.
- 62 -
301539.00025/94161307.1
● Section G below reviews BC Hydro’s FTE increases over time. Operating FTEs
have been flat since 2012. Recent FTE increases have been driven by capital
requirements as well as initiatives that have reduced overall costs.
126. BC Hydro submits that the materials filed, and evidence presented by the witnesses in
this proceeding should give the BCUC much greater confidence that the forecast operating
costs are reasonable and reflect an organization-wide focus on cost containment.
D. BC HYDRO’S ROBUST BUDGETING AND GOVERNANCE PROCESSES DRIVE COST CONTAINMENT EFFORTS
127. The forecast operating costs presented in this Application are the product of a
budgeting process that involves top-down and bottom-up elements. As discussed below, this
process has advantages over zero-based budgeting, and it produced a lower Test Period
budget. BC Hydro’s governance processes provide the requisite oversight of operating costs,
including vacancy management and tracking performance of KBUs against budget.202
(a) BC Hydro’s Budgeting Approach Assessed More than Just Incremental Requirements and Imposed Limits on Funding
128. BC Hydro’s budgeting approach, described in Chapter 5 of the Application, goes beyond
examination of incremental changes from the prior year. It requires Business Groups and
individual KBUs to consider, and articulate to the Executive Team, their overall responsibilities,
cost drivers, FTEs and targeted outcomes.203 Since the Previous Application, BC Hydro has
enhanced its process:
The budgeting process used for this Application is consistent with the process used in the Previous Application, with the enhanced examination and information on the overall starting base budget in addition to detail on incremental changes.
An examination of each Key Business Unit’s full operating budget was performed, which allowed for validation and confidence in the starting base
202 BC Hydro’s response to Exhibit B-5, BCUC IR 1.40.3.1 provides a list of accounts along with examples of cost
control mechanisms. 203 Exhibit B-1, Application, p. 5-14.
- 63 -
301539.00025/94161307.1
budget. This examination allowed more insight into the base budgets and a greater understanding of the drivers behind the cost pressures and savings that were identified.
The Business Groups undertook an examination of their operations to identify areas requiring additional funding while also identifying cost savings to mitigate the cost increases requested. Explanations for the cost pressures and savings were provided and reviewed by the Executive Team.204
129. The “top down” aspect of the budgeting process ultimately dictated the budget
amounts during the Test Period. BC Hydro did not fund the specific cost pressures identified by
KBUs during the “bottom-up” assessment; rather, BC Hydro determined to fund only the non-
controllable, organization-wide cost pressures, which were offset by identified cost savings.205
(b) The Advantages of BC Hydro’s Budgeting Approach Over Zero-based Budgeting Include $24 Million Lower Budgeted Operating Costs
130. In its Decision on the Previous Application, the BCUC identified zero-based budgeting as
an area for further exploration. BC Hydro submits, for the reasons discussed below, that
customers are better served by the budgeting approach that BC Hydro has employed.
131. Zero-based budgeting is a method of budgeting in which the budget is essentially re-
created “from scratch” for each new period. BC Hydro’s budgeting approach did incorporate
many of the zero-based budgeting principles, such as a detailed and transparent examination of
resources and cost drivers by each KBU. BC Hydro explained:
In the Application, we have provided supportive arguments and justifications for the total budget, not just the incremental increase. BC Hydro underwent an in-depth exercise examining its fiscal 2019 budget at a granular level to demonstrate that the current level of resources are in fact still required to achieve business objectives and that those resources are being managed responsibly. We have also identified opportunities for process and operational improvements resulting in cost savings as shown in Table 5-6 of Chapter 5 of the Application.206
204 Exhibit B-5, BCUC IR 1.34.1. 205 Exhibit B-1, Application, section 5.5.2.2;Exhibit B-5, BCUC IR 1.34.1. 206 Exhibit B-5, BCUC IR 1.34.3.
- 64 -
301539.00025/94161307.1
132. Zero-based budgeting lacks the top-down constraint on costs that might otherwise be
suggested by workload and new cost pressures. The top-town constraint was critical when
developing the Test Period budgets. BC Hydro explained that zero-based budgeting would have
produced a materially higher operating cost budget:
In addition to being very labour intensive, a formal zero-based budgeting approach can result in the determination that more resources are required to perform activities, potentially resulting in an overall recommended budget increase. Given this would not be consistent with BC Hydro’s focus on limiting base operating cost increases, this would not have been an acceptable outcome.
Business Groups identified significant cost pressures in their respective areas during the fiscal 2020 budgeting cycle. Using the top-down, bottom-up budgeting approach these costs were not funded as the approach did not allow for costs related to these items beyond the existing budget to be funded. These costs had to be accommodated within the Business Group’s existing budgets, allowing us to limit our costs increases to $8.5 million and $9.9 million in fiscal 2020 and fiscal 2021 respectively. Using a formal zero-based budgeting approach could have resulted in an additional $24 million in significantly higher base operating cost budgets.207 [Emphasis added.]
133. Mr. O’Riley reiterated this point at the hearing:
As a result of a changing operating environment, a lot of rigour goes into our budgeting process. The Commission had questions about our budgeting coming out of our last revenue requirements application and my strong view is that our top-down and bottom-up budgeting process has limited operating and capital cost increases and that a fully zero-based budgeting approach that lacks the top-down constraint would see greater cost increases.208
(c) BC Hydro’s Governance Process Includes Vacancy Management, Performance Metrics and Regular Reporting
134. BC Hydro has appropriate oversight processes in place so that it operates within its
budgets and targets. This includes a vacancy management process, performance metrics and
regular reporting.
207 Exhibit B-5, BCUC IR 1.34.3. 208 Tr. 5, p. 358, ll. 11-19 (O’Riley).
- 65 -
301539.00025/94161307.1
135. BC Hydro’s vacancy management process has two main elements. First, filling vacancies
requires the prior review and approval by an Executive Team member or Director of a KBU.
Second, any request to create a new position that is not within BC Hydro’s established FTE and
budget plans is supported by a business case and accommodated with offsetting cost
reductions or incremental cost savings.209
136. Senior and executive management establishes performance criteria in advance of each
fiscal year and results are tracked on Business Group dashboards, Business Group performance
packages, or KBU scorecards.210 BC Hydro’s response to BCUC IR 1.62.1211 provides a lengthy
(over nine pages) list of the specific measures that are included on performance measurement
dashboards for each Business Group. Each KBU has a performance measure based on its ability
to maintain actual annual expenditures at or below the annual operating plans, while
completing the related annual KBU work plans. Each Business Group “is expected to manage
within their operating budget”.212
137. Internal reporting is regular and extensive:
● The Finance KBU prepares monthly financial reporting at the KBU, Business
Group and overall BC Hydro levels to track progress against budget. The
reporting also includes forecasts for the remainder of the year, along with
expenditures from prior years for validation purposes.213 These reviews consider
corrective action options such as advancing or delaying work. They may result in
funding reallocations between Business Groups or KBUs, while keeping BC
Hydro’s overall budget the same.214
209 Exhibit B-1, Application, p. 5-15; Exhibit B-5, BCUC IR 1.42.4. 210 Exhibit B-5, BCUC IR 2.228.1. See also, Exhibit B-13, CEC IR 2.92.2, which discusses the use of BC Hydro’s Service
Plan to determine cost effectiveness. 211 Exhibit B-5. 212 Exhibit B-12, BCUC IR 2.231.5. 213 Exhibit B-5, BCUC IR 1.36.1. 214 Exhibit B-5, BCUC IRs 1.36.3 and 1.36.2.1.
- 66 -
301539.00025/94161307.1
● Quarterly financial reports published for external reporting purposes compare
actual spend to prior year amounts.215
● Periodically, multi-year comparisons are reviewed to confirm budget planning
assumptions. In addition, there may be specific cost items where multi-year
trend analysis is reviewed on a regular basis (e.g., bad debt expenditures).216
138. Similar processes and procedures apply to costs that are to be recovered in regulatory
accounts.217 As BC Hydro’s Chief Accounting Officer, Ryan Layton, explained:
And we know that if something gets in that rate, it needs to be paid down. And since we are collecting almost all of our regulatory accounts in rates already, what’s in those accounts matters a lot to us and matters a lot to every revenue requirements application that we bring forward.218
E. BC HYDRO ABSORBED CONTROLLABLE COST PRESSURES WITHIN EXISTING BUDGETS, WITH INCREASES GENERALLY ATTRIBUTABLE TO UNCONTROLLABLE COSTS
139. During the budgeting process for this Application, which occurred in conjunction with
the Phase One Comprehensive Review, BC Hydro’s Executive Team determined that all cost
pressures would be managed within the existing (i.e., fiscal 2019 forecast) operating cost
budget, with the exception of (a) storm restoration costs, which are uncontrollable, (b) the
Employer Health Tax and rising benefits costs, which are uncontrollable costs that affect the
Standard Labour Rate,219 and (c) wage increases, which also affect the Standard Labour Rate
215 Exhibit B-5, BCUC IR 1.36.1. 216 Exhibit B-5, BCUC IR 1.36.1. 217 Further information, organized by regulatory account, is provided in the response to Exhibit B-5, BCUC IR
1.40.3.1. 218 Tr. 6, p. 824, ll. 9-17 (Layton). 219 Exhibit B-1, Application, p. 5-48: Standard Labour Rates are calculated at the beginning of each budgeting cycle
and are based on forecasts of wage and salary increases, employee benefits, current service pension costs, gainsharing under our union contracts, sick days, annual vacation, and flex day entitlements; Exhibit B-12, BCUC IR 2.231.5; Exhibit B-1, Application, p. 5-1. Per Exhibit B-13, BCOAPO IR 2.112.1: Existing budgets refer to the Business Groups’ fiscal 2019 budgets. Fiscal 2019 budgets are the Business Groups’ approved net operating cost budgets adjusted for the BCUC approved expenditures relating to the Waneta two-thirds operating costs, the Customer Crisis Fund operating costs, and budget transfers between Business Groups which net to zero across BC Hydro.
- 67 -
301539.00025/94161307.1
and are an area where BC Hydro has limited flexibility in practice.220 In the Evidentiary Update,
the updated pension discount rate determined by BC Hydro’s external actuary increased
forecast operating costs. The evidence regarding these cost drivers is discussed below.
(a) Non-Controllable Storm Restoration Costs Are a Significant Driver of Operating Costs Increases
140. Increases in forecast storm restoration costs, attributable to the use of an updated five-
year average (fiscal 2014 to fiscal 2018), contribute significantly to the increase in forecast
operating costs.
141. BC Hydro uses a five-year average to forecast storm restoration costs, as required by a
previous BCUC order, Order No. G-16-09. Variances between forecast (based on an average of
the actual storm restoration costs for the five most recent normal weather years) and actual
storm restoration costs are deferred to the Storm Restoration Costs Regulatory Account, in
accordance with that order.221 Amounts deferred to the account in a test period are recovered
over the following test period. As a result, ratepayers only pay for the actual storm restoration
costs incurred and these costs are recovered over a reasonably short period of time.222
142. The output of the five-year average used in the current Application had increased
relative to the Previous Application because BC Hydro had experienced greater storm activity in
recent years.
143. Storm restoration costs increased further in the Evidentiary Update because more
severe storms, including the December 2018 storm, resulted in higher than planned storm
restoration costs in fiscal 2019. The variance was deferred to the Storm Restoration Costs
220 Exhibit B-1, Application, p. 5-22. 221 BCUC Order No. G-16-09, Decision on BC Hydro’s Fiscal 2009 to Fiscal 2010 Revenue Requirements
Application, Directive 42: “The Commission Panel directs BC Hydro to include in its base OMA for the test period average storm‐related restoration costs in 2009 dollars for F2009, and 2010 dollars for F2010, respectively, to be calculated as the average of actual costs for the five most recent “normal weather” years: e.g. F2003, F2004, F2005, F2006, and F2008 would be used for F2009; and to record any variance from the average amount for each test year in a separate regulatory account (“the Storm Damage Regulatory Account”) to be dealt with in its next RRA.”
222 Exhibit B-12, BCUC IR 2.232.4.
- 68 -
301539.00025/94161307.1
Regulatory Account, consistent with the BCUC’s order, for amortization over the current Test
Period, which increased the required recovery in fiscal 2020 and fiscal 2021.223
144. The impact of the amortization of a larger fiscal 2019 starting balance in the Storm
Restoration Costs Regulatory Account is a different issue than whether the five year average
should be updated to include fiscal 2019 actuals when forecasting costs in the current Test
Period. The latter issue is addressed in Part Twelve.
(b) The Employer Health Tax and Rising Cost of Health Care Contribute to Standard Labour Rate Increases
145. In the current Test Period, the Standard Labour Rates are forecasted to increase due to
the Employer Health Tax,224 which is a new tax that must be paid by employers.
146. Statutory benefits (e.g., Employment Insurance premiums), over which BC Hydro has no
discretion, are increasing over time.225 Costs for the existing employee benefit programs are
increasing over time due to the rising cost of health care, such as dental fees and prescription
drug costs.226 BC Hydro has taken steps to minimize cost impacts such as implementing a
generic drug policy and requiring prior authorization for certain prescription drugs.227
147. It is unrealistic to suggest that BC Hydro should have reduced benefits coverage,
whether unilaterally for management and professional employees or through collective
bargaining for union employees. As discussed next, BC Hydro salaries are, on average, 11%
below the market median and it is only by virtue of the pension and other benefits that total
compensation approaches the market median (BC Hydro is 2% below market when total
compensation is considered). Benefit programs are a part of the overall package necessary to
remain competitive with market rates and to be able to attract and recruit employees.228
223 Exhibit B-19, Evidentiary Update, p. 12. 224 Exhibit B-5, BCUC IR 1.42.1. 225 Exhibit B-5, BCUC IR 1.42.1. 226 Exhibit B-5, BCUC IR 1.42.1. 227 Exhibit B-5, BCUC IR 1.42.1. 228 Exhibit B-5, BCUC IR 1.42.1.
- 69 -
301539.00025/94161307.1
(c) Salary Increases Are Needed to Keep Pace With the Market After Years of Restraint
148. Planned salary increases over the Test Period are 2% for union employees and 2.5% for
management and professional employees. The evidence is that these increases are, in any
practical sense, necessary.
Compensation Levels Will Remain 2% Below Market Even With Increases
149. Annual union salary percentage increases from fiscal 2012 through to fiscal 2019
averaged only 1.43%.229 The planned increase of 2% per year for unionized employees is
consistent with the bargaining mandate set by the Public Sector Employers Council (“PSEC”).230
BC Hydro’s evidence was that it is improbable that collective agreements could be renewed
without providing an increase that is consistent with this mandate.231
150. BC Hydro has similarly had limited ability to increase management and professional
salaries since 2012, due to the PSEC prior salary freeze policy.232 No salary increase was
provided from 2012 to 2014.233 The maximum annual increase that could be provided under
PSEC guidelines to an individual employee between 2015 to 2018 was 2% per year, but
increases averaged well below that amount.234 Annual management and professional
percentage increases from fiscal 2012 through to fiscal 2019 averaged 1.0%, i.e., one-third less
than union increases.235
229 Exhibit B-5, BCUC IR 1.42.5. 230 The bargaining mandate established by the Government of B.C. provides the contract term and maximum
general wage increase that can be provided by the employer in union collective bargaining. The current mandate, which applies from April 1, 2019 to March 31, 2022 at BC Hydro, requires a three year contract term with maximum annual general wage increases of 2 per cent for union employees: Exhibit B-13, BCOAPO IR 2.117.1.
231 Exhibit B-5, BCUC IR 1.42.1. 232 Exhibit B-1, Application, p. 5-22. 233 Exhibit B-12, BCUC IR 2.219.1. 234 Exhibit B-12, BCUC IR 2.219.1. 235 Exhibit B-5, BCUC IR 1.42.5.
- 70 -
301539.00025/94161307.1
151. Independent benchmarking prepared by Morneau Shepell236 indicates that, on an
average total cash basis, BC Hydro employees earn 11% less than median market rates. After
factoring-in the value of pension benefits and time off programs, BC Hydro’s compensation
package is still 2% below median market rates.237
152. Local and Canadian market salary surveys indicate that the median salary increase
forecast for 2019 is 2.6%.238 As such, even with the planned increases during the test period,
BC Hydro will only be maintaining its current position relative to market median rates.
Employee Retention is Critical, and Compensation is a Factor in Retention
153. In its Decision on the Previous Application, the BCUC had stated that the costs and
benefits of BC Hydro’s total rewards initiatives239 were unclear. The additional information that
BC Hydro has provided on compensation benchmarking and its voluntary turnover rate provide
compelling evidence of value. Specifically, BC Hydro has been able to achieve above average
employee retention — as demonstrated by a voluntary turnover rate of 1.9% in fiscal 2019240,
which is below the 3.8% average for the power utilities industry241 — at compensation levels
that are below median market rates.
154. The importance of maintaining this low voluntary turnover rate cannot be understated.
Many of the skillsets required by BC Hydro are specialized, and the complexity of the assets and
operations requires an experienced workforce. These skills and experience are difficult to find
in the market and require significant time and costs to develop.242
236 Exhibit B-1, Application, p. 5-47; Exhibit B-5, BCUC IR 1.52.3. Please refer to Exhibit B-6, BCOAPO IR 1.6.1, for a
copy of the Morneau Shepell report and summary of market rates compared to BC Hydro rates by job and affiliation. In the confidential response to Exhibit B-12, BCUC 2.227.2. BC Hydro provided the 2017 Morneau Shepell assessment in Attachment 1 and a summary of the total rewards comparison by job in Attachment 2.
237 The benchmarking is discussed further in Section I of this Part. 238 Exhibit B-5, BCUC IR 1.42.6. The Conference Board of Canada forecasted the average pay increase for non-
unionized Canadian employees to be 2.6 per cent in 2019: Exhibit B-13, Zone II IR 2.35.2. 239 BC Hydro’s total rewards offer includes salary, pension, benefits and time off. 240 Exhibit B-5, BCUC IR 1.62.13.3. 241 Exhibit B-1, Application, p. 5-47. 242 Exhibit B-1, Application, p. 5-47.
- 71 -
301539.00025/94161307.1
155. Falling further behind median market rates would pose a challenge to attraction and
retention of employees.243 BC Hydro’s Chief Human Resources Officer, Carolynn Ryan,
explained:
We’re in a little bit of a catch up period and we are trying to stay consistent with market increases which, according to the Conference Board of Canada, are anticipated to be 2.6 percent. So in order to keep our rates competitive to attract and retain the employees that we need at BC Hydro in the management/professional job categories, we don’t want to fall further behind. So there is a little bit of catch up there.244
Incentive Pay Structure Also Drives Value for Customers
156. The incentive pay component of the total rewards program also drives value.
157. There are two types of incentive pay at BC Hydro:
● Approximately 1% of BC Hydro’s management and professional employees
receive incentive pay, in the form of a salary holdback.245 The maximum annual
award an employee can receive is 10% (for the President and non-executive
positions) and 20% (for all executive positions except the President). Awards are
based on the results achieved on BC Hydro’s Service Plan performance measures
(i.e., corporate measures) and individual performance objectives.246 Each
Executive’s personal performance is measured against, among other things,
meeting operating and capital budgets.247
● Unionized employees receive gainsharing which provides a maximum annual
award of 5% of the union employee’s wages paid in the fiscal year based on BC
243 Exhibit B-5, BCUC IR 1.42.1. 244 Tr. 8A, p. 1123, ll. 8-16 (Layton). 245 Exhibit B-5, BCUC IR 1.42.10. 246 Exhibit B-5, BCUC IR 1.42.10.1. 247 Tr. 6, p. 734, ll. 4-9 (Wong).
- 72 -
301539.00025/94161307.1
Hydro’s Service Plan performance measures and results achieved on department
specific objective(s).248
158. BC Hydro’s salary holdback program reinforces the high performance expectations of BC
Hydro’s Executive and Director-level employees. It is performance pay in the truest sense of
the word, and employees cannot take for granted that they will receive it. The evidence is that,
in fiscal 2019:
● No eligible employees received their full holdback amount;
● No eligible employees received the full corporate component of the holdback;
● The average individual rating was 0.72, meaning that, on average, employees
who were eligible for holdback pay received 72% of the individual component of
their holdback pay; and
● Only 13% of eligible employees received 100% of the individual component of
their holdback pay, since it is awarded for exceptional performance only.249
(d) Changes in the Discount Rate Increased BC Hydro’s Pension Costs
159. Changes in interest rates between the time BC Hydro filed its Application and the
Evidentiary Update increased BC Hydro’s forecast operating costs due to the corresponding
impact on pension discount rates, which is outside of BC Hydro’s control.
160. The discount rate is based on ‘AA’ Canadian Corporate bonds and is calculated by BC
Hydro’s external actuary. The discount rate used to value BC Hydro’s pension costs decreased
from 3.83% as of September 30, 2018 to 3.33% as of April 1, 2019. The discount rate decrease
248Exhibit B-12, BCUC IR 2.220.2. 249 Exhibit B-37, BC Hydro Undertaking No. 10.
- 73 -
301539.00025/94161307.1
resulted in higher current service pension costs, relative to the Application, by $15.9 million in
fiscal 2020 and $16.1 million in fiscal 2021.250
161. BC Hydro, consistent with its standard practice, made no adjustments to the discount
rates provided by its external actuary.251 As Mr. Layton explained “we rely on Morneau
Shepell’s expertise to give us the correct rate for BC Hydro and they did so in that e-mail. In
other words, no subsequent information changed that rate in that e-mail, that is the rate that
we used and it’s always been the correct rate.”252
162. While AMPC appears to prefer the original discount rate from the Application,253
accounting rules require BC Hydro to use the discount rate at the start of the fiscal year to
determine current service costs for fiscal 2020.254 BC Hydro’s external actuary had provided BC
Hydro with a new discount rate in the ordinary course of business. It followed the timing cycle
dictated by BC Hydro’s year end (an updated discount rate is a requirement for BC Hydro’s
annual financial statements).255 The timing was also consistent with what had been done in the
compliance filing for the Previous Application.256 This is discussed further in Part Twelve.
F. BC HYDRO HAS USED A NUMBER OF MEANS TO CONTROL COSTS AND ABSORB NEW UNCONTROLLABLE OPERATING COST PRESSURES
163. BC Hydro has achieved material offsetting savings and absorbed new work and cost
pressures through a variety of means, including: the Workforce Optimization Program; the
250 Section 1.3 of the Evidentiary Update, as corrected by Exhibit B-11-2. The lower discount rate also increased BC
Hydro’s fiscal 2019 non-current pension costs. However, this increase is deferred to the Non-Current Pension Cost Regulatory Account (i.e., it does not affect operating expenses) and is amortized into rates over a 13-year period, which increases the required recovery by $40.8 million in both fiscal 2020 and fiscal 2021. Current pension costs are captured in Schedule 5.7 of the Evidentiary Update (Exhibit B-11) as “Corporate Costs”: Exhibit B-17, AMPC IR 3.6.1.
251 Exhibit B-17, AMPC IR 3.5.1. 252 Tr. 7, p. 869, ll. 10-15 (Layton). 253 Exhibit C11-11, InterGroup Report, Recommendation 17. 254 Exhibit B-28, BC Hydro Rebuttal Evidence, pp. 14-15. 255 When BC Hydro filed its Evidentiary Update (Exhibit B-11), BC Hydro’s current service pension costs and non-
current pension costs were updated to reflect the actual pension discount rate as at March 31, 2019 (i.e., BC Hydro’s most recent fiscal year-end).
256 Exhibit B-17, AMPC IR 3.5.3.
- 74 -
301539.00025/94161307.1
Accenture repatriation; the consistent approach to a vacancy factor; re-purposing the
unallocated funds budget; lease consolidations; reduced spending on advertising; paperless
billing; the Work Smart Program; and, the “making it easier to get work done” initiative. The
diversity of these initiatives highlights that, after several years of cost containment, the “low
hanging fruit” is already harvested.
(a) Replacing Contractors with Internal FTEs (Workforce Optimization) Has Decreased Total Costs by $18.5 Million Annually
164. The Workforce Optimization Program, which was created in fiscal 2016 and is now
closed, primarily allows BC Hydro’s KBUs to replace external contractors with internal FTEs
when it is beneficial to do so.257 The Workforce Optimization Program resulted in the addition
of 706 FTEs in total. The Program has decreased BC Hydro’s total costs by an estimated $18.5
million annually. These benefits continue to accrue during the Test Period and are reflected in
the requested rates.
165. Table 5-9 from the Application,258 reproduced below, provides a summary of annual net
(i.e., operating, capital and deferred) savings from the Workforce Optimization Program for
fiscal 2020, by Business Group.
257 Exhibit B-1, Application, p. 5-29. BC Hydro has provided examples of Workforce Optimization initiatives. Exhibit
B-1, Application, p. 5-33. 258 Exhibit B-1, Application, p. 5-29.
- 75 -
301539.00025/94161307.1
166. The BCUC, in its Decision on the Previous Application, inquired about whether BC Hydro
was giving adequate consideration to the longer term costs of replacing contractors with
employees. BC Hydro has answered this concern in its evidence. Under the Program,
insourcing decisions require a workforce adjustment request document that provides both
quantitative and qualitative support for converting a contractor to an employee.259
167. The financial analysis calculates the costs associated with the FTE(s) being requested,
including labour costs at the standard labour rate as well as travel and business expenses. It
compares those costs to the expected savings from reducing the budget for the resources being
replaced by the workforce adjustment position(s). The analysis accounts for both the short-
term and long-term effects and costs of hiring contractors as employees (e.g., including pension
costs which represent the largest long-term cost difference between contractors and
employees).260 BC Hydro elaborated:
Both the immediate and ongoing costs (over the term of employment) and future costs (i.e. retirement costs) associated with hiring internal FTEs rather than continuing to use contractors are considered in each workforce adjustment request.
The FTE labour cost included in each request is calculated at BC Hydro’s Standard Labour Rate which includes the immediate on [sic — and] ongoing costs such as base salary/wages and other benefits, as well as future costs such as pension. While the Standard Labour Rates for internal employees will increase annually, these increases are not expected to exceed the rate of increase for external contractor rates.
In addition to FTE labour costs, each workforce adjustment request considers the on-going nature of the work for the requested FTEs so that FTEs are only added for on-going and sustainable resourcing needs.261
259 Exhibit B-1, Application, p. 5-29. See also, Exhibit B-5, BCUC IR 1.46.1. 260 Exhibit B-1, Application, p. 5-34 provides additional information on this point. In its Previous Decision, the BCUC
expressed concern that there did not appear to be an assessment of the long-term effects and costs of hiring contractors as employees. BC Hydro has now provided the information to demonstrate that such matters are, in fact, considered.
261 Exhibit B-5, BCUC IR 1.46.4.
- 76 -
301539.00025/94161307.1
168. In some cases, there are additional non-financial benefits to replacing contractors with
employees. BC Hydro provided the example of cybersecurity:
The program supports workforce stability as employees are typically retained as part of BC Hydro’s workforce for a longer period than contractors. This helps secure resources for high-demand positions that may at times be difficult to source from contractor labour. For example, the Technology KBU has brought critical cybersecurity monitoring and response capability in-house. While the impact of this change was cost neutral it reduces the risk of not being able to source contractor resources for this in-demand and limited supply labour function going forward. It also avoids potential cost escalation that could occur due to supply and demand imbalance.
The program also supports workforce stability by retaining the same resources who are familiar with our business and systems. For example, retaining Engineers that we need on a continuous basis ensures a consistent approach and the benefit of existing knowledge of our system such as a particular piece of equipment or facility.262
169. While non-financial benefits are considered and can be material, financial
considerations are paramount. No Business Group had a net cost increase as a result of the
Workforce Optimization Program.263 There were “no instances where FTEs were hired in lieu of
contractors when it was less cost-effective to hire FTEs on a long-term basis.”264
A Small Number of Workforce Optimization Program FTEs Were Associated With Non-Labour Savings, Repurposed Vacancies and New Revenues
170. BC Hydro was asked about the small number of FTEs accounted for as part of the
Program that did not involve conversion of contractors. For context, the vast majority of FTEs
associated with the Workforce Optimization Program — 673 of 706, or 95% — were funded
entirely by reductions to external contractor costs.265 The categorization of the remaining 5%
262 Exhibit B-5, BCUC IR 1.47.7 263 Exhibit B-12, BCUC IR 2.224.6. Note in Exhibit B-12, BCUC IR 2.224.3 BC Hydro provided a corrected version of
the original attachment provided in Exhibit B-5, BCUC IR 1.46.2, such that the results now show no net cost increases.
264 Exhibit B-5, BCUC IR 1.46.3. 265 Exhibit B-12, BCUC IR 2.225.8. Exhibit B-5, BCUC IR 1.47.5 provides a breakdown of all FTEs added through the
Workforce Optimization Program, by funding source.
- 77 -
301539.00025/94161307.1
as being related to the Program was only to take advantage of the Program’s existing
governance structure. The benefits to customers, while different, are nonetheless clear.
171. In every case, there was an offsetting cost savings or revenue source:
● Two FTEs (i.e., 0.3% of the total Workforce Optimization FTEs) were funded
through the reduction of non-labour expenditures.266
● 24 FTEs (i.e., ~3% of the total Workforce Optimization FTEs) represented
repurposed vacancies.267 BC Hydro followed the same principles for re-purposing
vacant positions as followed for the conversion of external contractors to
internal FTEs. This includes calculating the cost reduction of the vacancy
compared to the labour cost of the additional FTEs.268
● Seven FTEs (i.e., less than 1% of the total Workforce Optimization FTEs) were
added in fiscal 2019 to manage the Customer Crisis Fund, which were funded
through the rate rider approved by BCUC Order No. G-166-17 to recover the
overall costs of this pilot program.269 The Program provided a useful framework
for the assessment of these FTEs because the objective was similar, i.e., ensuring
that any FTE additions were funded without increasing KBU base operating
budgets.
266 Exhibit B-5, BCUC IR 1.47.5. In Exhibit B-5, BCUC IR 1.47.3, BC Hydro provided an example: “In the Supply Chain
KBU, a Materials Coordinator FTE addition was approved to support and manage the logistics flow for contractors to pick up materials at a centralized location in order to improve efficiencies and controls for both BC Hydro and the contractor crews. This position was funded through transportation cost savings which result from centralizing the location of contractors to pick up materials.”
267 This refers to positions repurposed to fund a higher priority position or area where increasing workloads required additional resourcing (refer to Exhibit B-12, BCUC IRs 2.225.3 and .225.5) and to additional FTEs that were absorbed within the existing labour budget by taking into account temporary vacancy periods for the existing FTEs within the group (refer to Exhibit B-12, BCUC IR 2.225.5).
268 Exhibit B-12, BCUC IR 2.225.6. 269 In the Application these were grouped in with the “reduction of other expenditures category”, which was
somewhat of a misnomer.
- 78 -
301539.00025/94161307.1
172. The inclusion of these exceptional cases under the umbrella of the Workforce
Optimization Program made sense from a governance perspective. The Workforce
Optimization Program provided a framework that required rigour around any staffing decisions.
As BC Hydro put it: “While contractor conversions were the focus, the Program was used to
manage all regular time FTE additions. This consistent governance model was used so that
optimal labour resourcing decisions were made in all situations and not just for work previously
done by contractors.” 270
The Workforce Optimization Program Has Achieved its Objective and is being Discontinued
173. BC Hydro expects to have all planned conversions implemented by the end of fiscal
2020. There are no planned contractor conversions in fiscal 2021.271 While the Workforce
Optimization Program has achieved its objective and is being closed, “BC Hydro will continue to
manage its labour resources in an optimal manner to execute our work plans.”272
(b) Accenture Repatriation Provides $8.2 Million of Annual Savings During the Test Period
174. In May 2018, BC Hydro successfully transitioned important services previously
performed by Accenture back into BC Hydro.273 The Test Period revenue requirements include
approximately $8.2 million in annual savings associated with the repatriation of work from
Accenture. The annual net savings from repatriation have exceeded BC Hydro’s original
projections by $1.2 million.274 Table 5-11 in the Application breaks down the annual savings:275
270 Exhibit B-12, BCUC IR 2.225.2. 271 Exhibit B-5, BCUC IR 1.48.2. 272 Exhibit B-12, BCUC 2.224.7. 273 In Exhibit B-1, Application, pp. 5-40 and Exhibit B-16, CEC IRs 1.31.1 to 1.31.4 BC Hydro elaborated on the
evolving customer needs and expectations that led to BC Hydro’s decision to repatriate the services provided by Accenture.
274 Exhibit B-1, Application, p. 5-40; Exhibit B-5, BCUC IRs 1.49.1 and 1.63.4 explains why the savings exceeded expectations.
275 Exhibit B-1, Application, p. 5-41. Exhibit B-6, CEC IR 1.26.3 confirms that the costs in the table are fully loaded. They are based on BC Hydro’s forecast standard labour rate, as well as incremental employee related costs such as travel, training and professional dues. It includes all Management and Professional positions required for supervision of the repatriated services. There are no changes in space requirements or related costs.
- 79 -
301539.00025/94161307.1
175. BC Hydro’s immediate objective for the transfer from Accenture has been to repatriate
services on a “like-for-like” basis to mitigate the risks that could be caused by wide-scale
process and organizational changes. BC Hydro carried over the staff and retained favourable
terms and conditions (e.g., wage scales) from the Accenture-MoveUP collective agreement.276
It is reasonable to expect that the staffing and cost structure of the repatriated services was
appropriate. Accenture was financially motivated to minimize the costs of delivering its
services, and therefore had a strong focus on process improvement and cost reduction.277
176. With post-repatriation operations now stabilized, BC Hydro has begun assessing
whether there are opportunities to improve the cost structure. Its current assessment is that
“the staffing levels seem appropriate.”278 However, the Contact Centre and Billing Operations
department in the Customer Service KBU has several operational reviews underway, described
in BC Hydro’s response to BCUC IR 2.226.6, to identify areas for process improvements that
could lead to cost savings. These initiatives started only recently so it is premature to estimate
276 Exhibit B-5, BCUC IR 1.49.11.2 277 Exhibit B-12, BCUC IR 2.226.6; Exhibit B-5, BCUC IRs 1.49.4 and 1.49.9. 278 Exhibit B-5, BCUC IR 1.49.4. See also, Exhibit B-5, BCUC IR 1.49.9; Exhibit B-5, BCUC IR 1.49.8 includes a
discussion on how BC Hydro determined staffing requirements.
- 80 -
301539.00025/94161307.1
the potential cost savings that may be achieved or the enhancements to IT systems that may be
necessary to implement them.279
(c) BC Hydro Has Reflected Vacancy Factor Savings in the Revenue Requirements
177. A vacancy factor is a reduction in the labour budget to recognize that positions would
not remain filled 100% of the time.280 The practice had been applied inconsistently by the KBUs
in past budgets. BC Hydro has achieved forecast annual savings of $5.6 million starting in fiscal
2020 by applying a consistent approach to identifying vacancy factor savings.281
178. There is considerable rigour behind the $5.6 million estimate of vacancy factor savings.
BC Hydro assessed each KBU individually. It considered (i) historical operating labour
expenditures, (ii) estimated future vacancies, and (iii) charge out expectations (i.e., operating
labour costs excluding labour costs charged to capital or maintenance work programs).282 The
factor applied differed by KBU.283 Mr. Layton explained this approach, stating:
If I can add a little bit of colour to that, so if I was going to talk to a KBU manager, say Ms. Ryan, you would look at both the historical experience that her KBU has experienced, so in other words, is it a KBU that tends to have a lot of vacancies throughout the year or is it one that doesn’t? But we also look at the future. In other words, we don’t accept that the past is necessarily an indicator of the future. Perhaps there’s a unique circumstance operating in Ms. Ryan’s department coming up and she might say, for example, “I had a vacancy in this area last year, we didn’t fill that for whatever reason but we’re going to be filling it very soon.” And so yes, that position’s been vacant but it’s not going to continue that way. And so that would be one that we would look at and consider both – in other words both the past and our expectations of the future. Of
279 Exhibit B-12, BCUC IR 2.226.6. 280 BC Hydro has provided a list of all vacancies approved for recruitment as of March 31, 2019 as an attachment to
Exhibit B-5, BCUC IR 1.35.1. The file includes the KBU, department, position title, date the recruitment requisition was created, and the reason for postings that have been open for more than six months. Further explanation is provided in the response to Exhibit B-5, BCUC 1.35.1.2.
281 Exhibit B-1, Application, p. 5-25, Table 5-6. See also, Exhibit B-5, BCUC IR 1.40.6; Exhibit B-5, BCUC IR 1.35.1.1; Exhibit B-5, BCUC IR 1.43.1; Exhibit B-12, BCUC IR 2.229.4.
282 Exhibit B-12, BCUC IR 2.230.7. 283 Exhibit B-12, BCUC IR 2.230.7. Vacancy factor savings are embedded into BC Hydro’s forecast labour costs for
the test period. Accordingly, the amounts shown in Exhibit B-1, Application, Appendix A, Schedules 5.0 to 5.7 are net of the $5.6 million vacancy factor savings for the test period: Exhibit B-12, BCUC IR 2.230.1.1.1.
- 81 -
301539.00025/94161307.1
course we don’t have actual data for the future. I can’t go to Ms. Ryan and say, “How many vacancies will you have next year?” Don’t know. We have to, again, look at historical data to help us and future expectations on the work and the circumstances in a given department, those are the two factors there. And then the charge out expectations are, some workers charge to what we call “work,” which may be capital in nature, and if we expect some of those percentages are going to be changing in a specific business, then we’d want to consider that as well as we build the vacancy factor for that KBU.284
179. BC Hydro provided the following example of how the approach was applied in the
Regulatory and Rates KBU:
For example, vacancy factor savings of $0.05 million were applied to the Regulatory and Rates KBU for fiscal 2020 and fiscal 2021. While Regulatory and Rates is a small KBU (28 FTEs), due to the complex and technical nature of the positions, recruitment for vacancies, when they arise, can take some time to fill. The vacancy factor savings applied to the KBU reflect these circumstances and are informed by a review of the historical vacancy trends within the KBU.285
180. Estimating future expectations is a more appropriate approach than solely examining
the number and type of vacancies at any particular point in time. A point in time tally is
unlikely, on its own, to be indicative of future results.286
181. Vacancy factor savings relate to operating costs. Vacancy factor savings were not
specifically applied during the Test Period for capital and deferred labour costs and FTEs.
Internal labour vacancies for capital and deferred projects and programs are balanced and
managed through the deployment of external contractors.287
(d) BC Hydro Has Eliminated the Unallocated Funds Budget
182. The Test Period revenue requirements reflect (a) $15 million in annual incremental
savings from the re-purposing of unallocated funds, and (b) a further $1.9 million in annual
284 Tr. 8A, p. 1161, l. 7 to p. 1162, l. 12 (Layton). 285 Exhibit B-12, BCUC IR 2.230.8. 286 Exhibit B-12, BCUC IR 2.230.7. 287 Exhibit B-12, BCUC IR 2.230.2.
- 82 -
301539.00025/94161307.1
incremental savings from the re-purposing of budget that had been set aside in fiscal 2019 for
unanticipated trailing costs associated with the Accenture repatriation.288
183. In the Previous Application, an unallocated funds budget had been included in
Corporate Costs.289 The unallocated funds budget was held centrally to facilitate managing the
funding of ad hoc projects and unanticipated expenses incurred by the Business Groups
throughout the fiscal year.290 Over the course of the fiscal 2017 to fiscal 2019 test period,
additional net savings of $8.5 million were identified and added to the unallocated funds
budget, increasing it to $15.0 million.291 Over the fiscal 2017 to fiscal 2019 test period, the
unallocated funds budget was used to fund additional lines and stations maintenance work. It
was also used for unplanned initiative costs, such as the planning work for the acquisition of the
remaining two-thirds of Waneta and the planning work for the Accenture repatriation.292
184. During the Test Period, there is no unallocated funds budget of any kind.293 All funding
of unplanned work demands and unanticipated cost pressures will need to come through
budget target adjustments that equal zero on a net basis or will result in a direct impact to the
shareholder, all else equal.294
288 Exhibit B-5, BCUC IR 1.63.4. 289 Exhibit B-5, BCUC IR 1.63.5. 290 Exhibit B-5, BCUC IR 1.63.2.1. 291 Exhibit B-5, BCUC IR 1.63.2. 292 Exhibit B-5, BCUC IR 1.63.3. BC Hydro responded to a number of information requests regarding the
unallocated funds budget, as well as its use and management during the Previous Application proceeding. Two of these responses are provided as Attachment 1 and Attachment 2 to Exhibit B-5, BCUC IR 1.63.5. See also, Exhibit B-12, BCUC IR 2.231.10.
293 Exhibit B-5, BCUC IR 1.63.2; Exhibit B-12, BCUC IR 2.231.2. 294 Exhibit B-5, BCUC IR 1.36.3.
- 83 -
301539.00025/94161307.1
185. BC Hydro underscored that “Without the unallocated funds budget…it will be a
significant challenge to manage within the overall operating budget during the test period.”295
As Mr. Layton reiterated the point:
And maybe just speaking for the overall budgeting perspective, I think we’ve talked a little bit this week about how we’re about nine and a half months into the year, and I think you’ve heard evidence from a number of members that the budget this year is very, very tight. There’s no doubt that in previous applications, we did – and we’ve talked about this, we had some unallocated funds that grew over time. For example, when we repatriated Accenture, that helped create an unallocated funds amount in the previous fiscal years and that helped be able to absorb increases in cost pressures that were happening across our business. As you know, in this application there’s no unallocated funds budget and therefore those two fact, the fact that we are very, very tight in our budget nine and a half months into the year, and that we have no allocated funds to deal with cost pressures, again I think speaks to what Mr. Wong said, which [would] be that reductions in any case would be impactful.296
(e) Eliminating a Property Lease is Expected to Generate Additional $1.2 Million in Savings
186. BC Hydro consolidated its lease at Central Park Place in Burnaby, eliminating three floors
of office space. It relocated staff into BC Hydro owned buildings through increased space
utilization in those buildings. The initiative resulted in forecast savings of $1.2 million.297
(f) BC Hydro Has Reduced the Communications Budget by an Additional $1.2 Million
187. BC Hydro reduced planned advertising and marketing costs, resulting in forecast annual
savings of $1.2 million.298
(g) Expansion of Paperless Billing Expected to Generate Additional $1 Million in Savings
188. BC Hydro has continued to reduce the number of paper bills, which is resulting in an
additional $1 million in annual savings during the Test Period.299
295 Exhibit B-12, BCUC IR 2.231.2. 296 Tr. 8A, p. 1092, l. 24 to p. 1093, l. 18 (Layton). 297 Exhibit B-1, Application, p. 5-25, Table 5-6; Exhibit B-5, BCUC IR 1.40.7. 298 Exhibit B-1, Application, p. 5-25, Table 5-6; Exhibit B-5, BCUC IR 1.40.7. 299 Exhibit B-1, Application, p. 5-25, Table 5-6.
- 84 -
301539.00025/94161307.1
(h) Work Smart Program Creates Capacity to Manage Workload and Avoids Costs
189. The Work Smart Program is BC Hydro’s program for continuous process improvement.
It is based upon widely-recognized Lean Six Sigma principles.300 As discussed below, the
Program has been very successful.301 Ratepayers benefit from the capacity hours gained under
the Program, since they represent an avoided cost.
Work Smart Has Been Very Successful and BC Hydro Is Continuing to Invest in It
190. Mr. Layton explained that, while BC Hydro employees strive to make improvements in
their work every day, the Work Smart Program provides a structure to enable more
fundamental improvements:
I think employees every day in BC Hydro look to make improvements in the way they do their work and their processes. Those are generally, I think, fairly smaller kind of improvements. Hopefully, I think we all do that, we look for ways to do everyday tasks better and smarter. What Work Smart’s doing though is coming in and looking at a process. We’re not trying to improve it a little bit, we’re trying to improve it a lot, and I think that kind of big improvement takes a lot more effort and a lot more structure and framework and that’s what we’re able to do through Work Smart that employees probably just on their own would struggle to be able to achieve.302
191. BC Hydro’s response to BCUC IR 1.39.3303 provides a good example of a completed Work
Smart initiative.
192. Successful Lean Six Sigma programs select capacity gained or costs avoided as their key
metric.304 As of the end of fiscal 2018, BC Hydro has realized an estimated 80,000 annual
300 Exhibit B-1, Application, p. 5-16. Lean is a business philosophy focusing on streamlining work as well as
identifying and eliminating non-value-added activities. Mr. Layton elaborated on the history and methodology of the Lean initiatives at the hearing: Tr. 8A, p. 1150 l. 21 to p. 1152 l. 3.
301 Exhibit B-5, BCUC IRs 1.38.4 and 1.38.4 302 Tr. 8A, p. 1141, ll. 5-18 (Layton). 303 Exhibit B-5. 304 Exhibit B-5, BCUC IR 1.39.5. Exhibit B-5, BCUC IR 1.39.6 provides information showing how the objectives of the
successful programs at Results Washington and ICBC are similar to BC Hydro’s objectives for Work Smart.
- 85 -
301539.00025/94161307.1
capacity hours gained305 as a result of Work Smart program initiatives. The estimated realized
hours gained exceed the forecast amount of 46,550 annual hours by the end of fiscal 2018,
provided by BC Hydro in the Previous Application.306 Mr. Layton noted that, as of the end of
fiscal 2019, BC Hydro has realized an estimated 100,973 annual capacity hours gained.307
193. The cost / benefit analysis for Work Smart tells a compelling story. BC Hydro has
imputed a value to the capacity hours gained using the average hourly compensation of
employees participating in processes improved through the program. The following table308
provides a summary of the cost / benefit analysis for Work Smart, based on the imputed values:
194. For the period from inception to the end of fiscal 2018, the life to date incremental cost
of the program was approximately $1.5 million. The estimated benefit (imputed value) was
$7.6 million. In other words, the life to date imputed value over that period was is 5.0 times
the incremental costs.309 The $7.6 million represents an estimate of how much costs would
have increased if not for the initiatives delivered through the Work Smart program. In other
305 Exhibit B-1, Application, p. 5-16. Capacity hours gained is the difference between the work effort of the process
before the Work Smart initiative is undertaken and after the implementation of the Work Smart recommendations. Exhibit B-5, BCUC IR 1.38.1 explains the methodology for calculating/determining capacity hours gained.
306 Exhibit B-1, Application, p. 5-16. 307 Tr. 7, p. 996, ll. 13-16 (Layton). 308 Exhibit B-5, BCUC IR 1.38.9. 309 Exhibit B-5, BCUC IR 1.38.9.
- 86 -
301539.00025/94161307.1
words, without Work Smart initiatives to date, BC Hydro estimates that its annual costs would
be $7.6 million higher than applied for in the Application.310
195. Based on its success to date, the Work Smart program is expected to continue for the
foreseeable future.311 Planned costs for the Work Smart program in fiscal 2020 are
approximately $953,000. The increase from fiscal 2018 ($460,831) to fiscal 2020 ($953,359) is
due to the addition of 2.5 FTEs to support a greater volume of projects, training offerings, and
new tools including Design Thinking and Lean Daily Management.312 BC Hydro expects to
implement 31 Work Smart initiatives in fiscal 2020, which is more than previous years.313 The
initiatives for fiscal 2021 are not yet available. However, planned costs in fiscal 2021 are
expected to be consistent with fiscal 2020 plus any adjustments to the standard labour rate.
Capacity Hours Gained Represent an Avoided Cost for Customers
196. In its Decision, the BCUC expressed its belief that the efficiency savings generated by BC
Hydro’s Work Smart program should result in incremental cost savings.314 In fact, the Program,
as designed, is generating savings for ratepayers by avoiding costs.
197. As indicated above, in the absence of the Work Smart initiatives to date, BC Hydro’s
annual costs “would be $7.6 million higher than applied for in the Application.”315
198. The increasing complexity of BC Hydro’s regulatory and compliance environment is
increasing the demands on BC Hydro’s workforce, and new Work Smart initiatives are playing a
key role in avoiding the need to add staff to perform the work. BC Hydro explained:
BC Hydro is focused on managing operating costs to limit or absorb costs increases within the existing operating cost budget. Over the Test Period and
310 Exhibit B-12, BCUC IR 2.223.9. 311 Program momentum will be maintained through the means identified in Exhibit B-5, BCUC IR 1.37.2. 312 Exhibit B-5, BCUC IR 1.38.13.1; Exhibit B-12, BCUC IR 2.223.3. 313 Exhibit B-12, BCUC IR 2.223.11. Exhibit B-6, BCUC IR 1.38.13 provides a list of Work Smart projects planned for
fiscal 2020. Exhibit B-5, BCUC IR 1.38.3 discusses the associated expected capacity hours gained. 314 Previous Decision, p. 34. 315 Exhibit B-12, BCUC 2.223.9. See also, Exhibit B-5, BCUC IR 1.38.11.1.
- 87 -
301539.00025/94161307.1
beyond BC Hydro continues to implement initiatives such as Work Smart to achieve efficiencies and process improvements. These efficiencies help absorb cost pressures resulting from the increasing complexity of work such as those described in BC Hydro’s response to BCUC IRs 1.64.1 and 2.214.1. For example, the increasing compliance requirements resulting from the North American Electric Reliability Corporation Critical Infrastructure Protection (NERC CIP) program results in significant cost pressures. Initiatives such as the Work Smart program are critical to ensuring BC Hydro is able to absorb these types of cost pressures.316
199. BC Hydro confirmed that in the absence of Work Smart BC Hydro would expect its
operating costs to be driven higher as a direct result of increased regulatory and compliance
requirements.317
200. BC Hydro submits that ratepayers would be ill-served by the adoption of an approach
that had as an objective using capacity hours gained to reduce the current labour budget or
number of FTEs:
BC Hydro notes that a number of questions, as well as comments in the BCUC’s decision from the Previous Application, seek to understand why capacity hours gained (which can be considered avoided costs) are BC Hydro’s measure of the effectiveness of the Work Smart program instead of other measures such as incremental savings and headcount reductions. A fundamental principle of the Work Smart program is that employees have the solutions to improve processes and their participation in Work Smart initiatives is vital in identifying and implementing them, which leads to capacity hours gained that enable employees to deal with workload challenges and focus on the highest value work. Work Smart team members do not have these solutions – instead, Work Smart provides the tools, facilitation skills, and structure to collaboratively identify and implement the solutions from employee teams.
As noted in BC Hydro’s response to BCUC IR 1.64.1, BC Hydro faces a growing and more complex workload caused by a number of factors. Since BC Hydro’s headcount (excluding Workforce Optimization, Accenture Repatriation, and Site C) has not been growing as shown in Table 5-12 of Chapter 5 of the Application, and since BC Hydro has been unable to fund many cost pressures as discussed in BC Hydro’s response to BCUC IR 1.34.3, capacity hours delivered through Work Smart initiatives are a critical way for BC Hydro to make its processes more
316 Exhibit B-12, BCUC IR 2.213.2. 317 Exhibit B-12, BCUC IR 2.214.4.
- 88 -
301539.00025/94161307.1
efficient, enable a growing workload to be absorbed, and to minimize cost increases.
If, on the other hand, Work Smart solutions were required to deliver incremental cost and headcount savings (instead of avoiding higher costs), the program would not be successful. More specifically, employees and teams facing a growing and more complex workload would not participate since they would not obtain the capacity hours gained that they need. Instead, they would be disincented to participate and offer the best solutions to improve processes as their position could be terminated as a result. Without positive participation from employees involved in the process, Work Smart initiatives would be unsuccessful.
Our approach is also consistent with that of other companies with similar Work Smart programs.318
201. At the hearing, Mr. Layton added a tangible example of why focussing on avoided costs
is preferable:
We continue to focus on avoided costs and I appreciate the panel’s feedback but we do feel very strongly that Work Smart is a program about productivity savings. It is not a program, in our view, about reducing costs. If in the examples that I used, I’ll take Site C for example, we freed up a whole bunch of time for them to carry on the project through those leave to commence processes. If we came to them and said, “Hey, we saved you guys 22 days per each of those instances and you have 100 of them each year, that’s 2200 hours, therefore, we’re going to reduce your budget by two people,” we don’t think that’s a valid concept, because as we know that project is facing many, many challenges and that process was simply taking too long for them in the first place and, therefore, just causing their workers to work harder and not get to the tasks they need to get to. So if we came to them and said, “Help us improve this process, and then we’ll take away some of your people and some of your budget,” they would never engage in the first place, and in our estimation, that’s not a practice that we’d want to see.319
202. The Work Smart program is a critical means by which BC Hydro has been able to remain
within budget during the Test Period. BC Hydro will continue to measure the annual number of
capacity hours gained and the imputed value of the capacity hours gained.320 In years following
318 Exhibit B-12, BCUC IR 2.223.9. 319 Tr. 8A, p. 1144, l. 12 to p. 1145, l. 8 (Layton). 320 Exhibit B-12, BCUC IR 2.223.12.
- 89 -
301539.00025/94161307.1
the implementation of a Work Smart initiative, the improved processes are revisited on a
sample basis with the process owner to ensure the approved future state is still in effect and
that the capacity hours gained remain.321
(i) “Making it Easier to Get Work Done” Initiative Offsets Increased Complexity of Work
203. The new “making it easier to get work done” initiative is similar to Work Smart in that it
is intended to help BC Hydro avoid operating cost increases.322
204. The initiative is focused on making “relatively small but meaningful improvements to
tools, information, processes and workflow for frontline workers, to offset increasing
complexity in their daily tasks.”323 BC Hydro’s response to BCUC IR 2.214.2324 provides a list of
projects/activities currently being undertaken as part of the “make it easier to get work done”
initiative.
205. BC Hydro has not attempted to quantify the capacity hours gained associated with these
initiatives, since the initiatives are aimed at improving employee experience.325 However, there
is no doubt that most of the projects/activities listed indirectly contribute to capacity hours
gained. BC Hydro confirmed that, like Work Smart, in the absence of this initiative “BC Hydro
would expect its operating costs to be driven higher, as a result of increased regulatory and
compliance requirements.”326
G. FTE NUMBERS REFLECT WORK ON SITE C AND COST-EFFECTIVE INSOURCING
206. In its Decision on the Previous Application, the BCUC reviewed BC Hydro’s FTEs over
time.327 BC Hydro submits that it is in the best interest of customers for BC Hydro to continue
managing the business with a focus on total cost, rather than the number of FTEs per se. Actual
321 Exhibit B-5, BCUC IR 1.38.7.2. See also, Exhibit B-5, BCUC IRs 1.38.5 and 1.38.6.1. 322 Exhibit B-12, BCUC IR 2.214.4. 323 Exhibit B-12, BCUC IR 2.214.4. See also, Exhibit B-12, BCUC IR 2.214.2. 324 Exhibit B-12. 325 Exhibit B-12, BCUC IR 2.214.3. 326 Exhibit B-12, BCUC IR 2.214.4. 327 Previous Decision, pp. 34 to 35 and 87.
- 90 -
301539.00025/94161307.1
FTEs in recent years and Planned FTE’s for the Test Period reflect BC Hydro’s work on Site C and
the two initiatives (discussed above) that involved adding FTEs to generate savings —
Workforce Optimization and Accenture Repatriation.
(a) FTE’s Have Remained Relatively Flat Since Fiscal 2012 Except For Capital Projects
207. The following figure and table,328 reproduced from the Application, shows BC Hydro’s
FTEs over a ten year period (8 years of actual plus the plan for the Test Period) categorized by
(a) operating, (b) capital, and (c) deferred.329 The key take-away from this information is this:
apart from growth in the workforce directly related to increased capital investment and the
Accenture repatriation, BC Hydro’s FTEs have remained relatively flat since fiscal 2012 and are
forecast to remain flat over the Test Period.330 BC Hydro submits that this track record reflects
BC Hydro’s governance around vacancy management.
328 Exhibit B-1, Application, p. 5-42. 329 Exhibit B-11, Application, pp. 5-41 and 5-42. In Exhibit B-5, BCUC IR 1.50.1, BC Hydro confirmed that the
method for calculating FTEs in the Application is consistent with the method applied for fiscal 2012 to fiscal 2019.
330 Exhibit B-11, Application, p. 5-42, fn. 168. The numbers referenced exclude FTEs related to the Accenture Repatriation, the Smart Metering Infrastructure Project and the Site C Project. These FTEs were removed to avoid skewing the trend line. All FTEs related to the Workforce Optimization Program, are included.
- 91 -
301539.00025/94161307.1
(b) Site C Project is the Only Organizational Need Driving Net New Positions in the Test Period
208. The Site C Project is the only organizational need driving the addition of net new
positions, and the related costs are not affecting the Test Period revenue requirements.331
FTEs, including overtime, are otherwise flat during the test period, as shown in the figure
below,332 reproduced from the Application.
331 Labour costs on Site C are capitalized to the project once Site C goes into service. 332 Exhibit B-1, Application, p. 5-44.
- 92 -
301539.00025/94161307.1
209. The following table,333 reproduced from the Application, shows the composition of FTE
changes for fiscal 2019 Plan to fiscal 2020 Plan.334 There are 61 FTE additions related to the
Workforce Optimization Program, but these are replacing existing contractor resources and are
generating savings.335 Those FTEs are also to be fully offset by planned reductions of 61 FTEs in
fiscal 2020 and 18 FTEs in fiscal 2021 associated with reduced requirements for apprentices and
trainees and less planned overtime.336 Site C thus accounts for all but one of the planned
increase of 72 FTEs from fiscal 2019 plan to fiscal 2020.337 There are an additional 12 FTEs
planned for Site C in fiscal 2021.338 Labour costs associated with FTEs working on the Site C
333 Exhibit B-1, Application, p. 5-45. 334 The change from fiscal 2019 RRA Plan (i.e., the forecast in the Previous Application) to fiscal 2019 forecast in the
Application is explained in Exhibit B-6, CEC IR 1.27.1. The change was associated with Site C, Workforce Optimization and Accenture repatriation, the latter two generating additional savings.
335 The increase of 61 FTEs planned in fiscal 2020 related to the Workforce Optimization Program includes 13 FTEs required for BC Hydro to perform the Reliability Coordination function (Exhibit B-13, BCOAPO IR 2.114.1). Further details on these FTEs are provided in Exhibit B-5, BCUC IR 1.85.5.
336 Exhibit B-5, BCUC IR 1.35.2. BC Hydro explained in Exhibit B-5, BCUC IR 1.51.1 how the reduction to Apprentices and Trainees will be achieved. In Exhibit B-5, BCUC IR 1.51.2 BC Hydro explained that the reduction of 29 FTEs in planned overtime between fiscal 2019 forecast and fiscal 2020 plan is primarily due to the reduction in the planned number of apprentice and trainee intakes and the associated overtime FTEs planned (Learning and Development KBU).
337 FTEs are increasing by from 7,405 (fiscal 2019 forecast) to 7,477 (fiscal 2020 plan), for a net increase of 72 FTEs. A breakdown of these FTEs by KBU is provided in Table 5-23 of of the Application.
338 Exhibit B-5, BCUC IR 1.35.2.
- 93 -
301539.00025/94161307.1
Project are capitalized to the project, which means that they do not affect the Test Period
revenue requirements.339
(c) BC Hydro Uses Overtime Only When it Makes Financial Sense
210. BC Hydro uses overtime where it is cost-effective to do so, and has (as discussed
immediately above) reduced the amount of planned overtime.
211. Overtime at BC Hydro is primarily used in the Operations Business Group, which is
responsible for the ongoing maintenance of the system. In response to information requests,
BC Hydro identified factors that can result in the use of overtime being an efficient
management strategy. The factors included, for instance, responding to emergent customer
outages and equipment issues outside of regular business hours, and supporting planned work
outside of regular business hours to minimize customer disruptions.340 Hiring additional short-
term or permanent employees to reduce overtime in such circumstances would be neither
feasible, nor cost-effective. The current collective bargaining agreements preclude BC Hydro
from reclassifying overtime hours to regular hours. Seasonal work demands and compressed
work schedules are time limited in duration. It is typically more efficient and/or cost effective
to utilize existing employees who are trained, qualified and authorized to perform work, than to
hire external service contractors.341
339 Exhibit B-1, Application, p. 5-28, fn 159. 340 Exhibit B-5, BCUC IR 1.51.6. 341 Exhibit B-5, BCUC IR 1.51.6.
- 94 -
301539.00025/94161307.1
212. BC Hydro explained that overtime has been budgeted for the Test Period considering
factors such as project(s), work location(s) and expected work requirements in the coming
year.342 Once the budget has been set, BC Hydro actively manages overtime using the following
strategies:343
● Setting overtime targets: KBUs set targets to manage monthly and annual
overtime.
● Pre-approval: Planned overtime must be pre-approved by the manager.
● Approvals and tracking: Managers approve employee time sheets and review
weekly and monthly overtime reports. The monthly report includes a list of IBEW
employees trending over the departmental targets for annual overtime.
● Resource Management: BC Hydro has implemented a work allocation process
that compares the capacity of internal workers to the anticipated demand.
● Power Line Technician/Apprentice Overtime Management Working Groups: BC
Hydro and the IBEW meet regularly to manage the process of allocating and
incurring overtime so that scheduled overtime, on average, is at or below KBU
overtime targets.
213. These strategies have resulted in the overtime hours for the Operations Business Group
being within 1% of Plan from fiscal 2017 to fiscal 2019.344
H. BC HYDRO IS OPTIMIZING POWER SYSTEM MAINTENANCE
214. Maintenance costs are accounted for in BC Hydro’s operating costs, and are thus
discussed here. However, they are integral to BC Hydro’s broader asset management strategy
that involves capital investments as well. BC Hydro’s witnesses on Panel 4, who are responsible
342 Exhibit B-12, BCUC IR 2.221.3. 343 Exhibit B-5, BCUC IR 1.51.6. 344 Exhibit B-12, BCUC IR 2.221.2. The response provides a detailed breakdown of overtime by KBU.
- 95 -
301539.00025/94161307.1
for asset planning, thus spoke to both maintenance and capital investments. Capital costs are
addressed in Part Seven below.
215. Strong business practices have enabled BC Hydro to mitigate increases in Power System
maintenance expenditures in recent years, despite a growing Power System asset base, aging
assets, higher delivery costs, outstanding condition-based and corrective maintenance needs,
and additional regulatory and compliance requirements.345 While BC Hydro has continued with
that approach in the Test Period, it expects budgets will need to increase after this Test Period.
(a) BC Hydro Uses Industry-Leading Maintenance Practices
216. BC Hydro describes in detail in Chapter 5 of the Application the exercise it goes through
to determine the extent of preventative, condition-based, and corrective maintenance.346 Mr.
Kumar explained that “when we are dealing with maintaining or replacing a capital, it’s all
about risk management.” He added that maintenance is an essential complement of
sustainment capital investments:
So initially when we replace capital, our risk goes down because we put a new asset in place and all our safety, environmental and financial risks are lower.
As you go through the lifecycle of that asset, you actually keep that risk profile of that asset low by doing adequate maintenance. So capital replacement and maintenance are actually complimentary to each other as opposed to thinking in terms of should we maintain or should we invest capital. You actually have to invest capital and then maintain it to get the full economic life of that asset.347
217. In broad terms, the overall maintenance budget amounts are based on three factors:
● A review of historic planned and actual spending levels;
● Changes (improvements or degradation) in asset condition and system
performance, as indicated by asset health ratings and performance measures;
and
345 Exhibit B-1, Application, pp. 5-66 and 5-67. 346 Exhibit B-1, Application, starting at p. 5-68. 347 Tr. 11, p. 1891, l.9 to p. 1892, l. 4 (Kumar).
- 96 -
301539.00025/94161307.1
● The amount of new assets added to the system less any asset retirements.348
218. BC Hydro’s cost mitigation initiatives have included improvements to grid intelligence
and control, system automation, crew utilization and business processes, strategic asset
management and capital investment planning.349
219. Navigant has identified business practices used by BC Hydro as being used by “leading
performers”. In fact, BC Hydro was using these practices over 10 years ago, and in some cases
almost 20 years ago.350 A report by the Office of the Auditor General of BC stated that: “BC
Hydro has good asset management practices, not by accident, but as a result of a decade-long
plan and associated efforts.”351
(b) BC Hydro Benchmarks Very Well on Maintenance Costs
220. BC Hydro’s use of industry-leading practices comes through in the results of
maintenance cost352 benchmarking undertaken in the ordinary course of business. While there
are inherent limitations in all benchmarking,353 the results do provide additional evidence that
BC Hydro is managing costs appropriately.
Favourable Results on Distribution and Transmission Maintenance Costs
221. First Quartile provides an annual comparison of the transmission and distribution line
maintenance costs of approximately 40 utilities. First Quartile uses a variety of normalizing
348 Exhibit B-12, BCOAPO IR 2.125.1. 349 Exhibit B-1, Application, p. 5-66. 350 Exhibit B-1, Application, p. 5-62; Exhibit B-5, BCUC IRs 1.58.3 and 1.61.4. 351 Exhibit B-1, Application, section 6.2.1.1 and Appendix F. 352 BC Hydro defines maintenance costs as costs of work activities incurred to preserve or restore an asset’s
operational condition without extending its useful life or increasing the service value of the asset: Exhibit B-5, BCUC IR 1.58.1.
353 Exhibit B-5, BCUC IR 1.59.1. BC Hydro also noted in Exhibit B-5, BCUC IR 1.59.1.2 that “The distribution peer group for the fiscal 2018 study included 31 companies and the transmission peer group included 23 companies. There is a significant diversity amongst this peer group, which makes it difficult to draw definitive conclusions from the results.”
- 97 -
301539.00025/94161307.1
factors in presenting their benchmarking results, such as the number of customer accounts,
number of circuit miles, or total MWh sold.354 First Quartile has found that:
● BC Hydro’s operations and maintenance costs were below the average for the
utilities included in the distribution category, as shown in the figure below from
the Application.355
● BC Hydro’s operations and maintenance costs were below average for the
utilities included in the transmission category, as shown in the figure below from
the Application.356
354 Exhibit B-5, BCUC IR 1.58.5. 355 A corrected version of the figure was provided in Exhibit B-5, BCUC IR 1.59.1. 356 Exhibit B-1, Application, p. 5-58.
- 98 -
301539.00025/94161307.1
● BC Hydro’s vegetation operations and maintenance costs are below average
when compared to utility peers.357
222. The First Quartile results were particularly notable because the distribution and
transmission peer groups included some U.S. utilities with less challenging terrain and climate
than BC Hydro’s service area. BC Hydro’s mountainous terrain and colder climate could be
expected, other things being equal, to increase maintenance costs.358
Generation Station Maintenance Costs Are Low Compared to Stations of Similar Age and Size
223. External benchmarking of generation station maintenance costs, commissioned from
Navigant in the ordinary course of business, reveals a similar pattern to distribution and
transmission maintenance costs. Navigant has reviewed 16 of BC Hydro’s stations, comparing
them to stations of similar type, age and size owned by other utilities.359 Controlling for type,
357 A Exhibit B-1, Application, p. 5-60. Factors that affect benchmarking results for vegetation maintenance costs
are discussed in Exhibit B-5, BCUC IR 1.60.1. 358 Exhibit B-1, Application, p. 5-58 and 5-59 (line maintenance), and p. 5-60 (vegetation maintenance). 359 Navigant’s comparables included generating stations of numerous Canadian utilities, as well as international
stations. See Exhibit B-6, CEC IR 1.36.2.
- 99 -
301539.00025/94161307.1
size and age of generation facilities removes the influence of the inherent economies of scale
associated with BC Hydro’s large hydroelectric generation.360 The results showed that 88% of
BC Hydro’s stations sampled were performing as expected or better in maintenance and
operations costs, where “better” represents lower costs than expected.361
(c) The Increases Planned in the Test Period Provide for Only Limited New Activity
224. The maintenance budgets have increased from fiscal 2019 to fiscal 2020. However, the
increases will not translate into a significant amount of new planned maintenance work being
undertaken. The following table shows that:362
● Close to half of that amount ($11.1 million of $27.0 million) is uncontrollable,
being the product of reflecting recent storm activity in the rolling five-year
average used to budget for storm restoration costs.363
● Almost one-third of the increase ($7.9 million of $27.0 million) from fiscal 2019
plan is covered by the re-purposing of unallocated funds discussed in Section F
above (the unallocated funds no longer exist). This is, in large measure, a
recognition of the current state rather than a true increase. In prior years, BC
Hydro’s maintenance budgets were insufficient and unallocated funds had to be
used to fund necessary maintenance activities.364
● “Net Re-organization impacts” were net neutral to BC Hydro.
360 Exhibit B-1, Application, p. 5-62. Exhibit B-5, BCUC IR 1.58.4: The Navigant study results are segmented into
various groups based on the area being analyzed (e.g., station group capacity, age or net capacity factor). The use of these segments “makes it easier to compare facilities on an “apples to apples” basis, despite differences among the companies themselves.”
361 Exhibit B-1, Application, p. 5-61. 362 The corrected table is in Exhibit B-13, BCOAPO IR 2.125.3. For further information on the increase in
maintenance funding from fiscal 2019 to fiscal 2020, please refer to Exhibit B-5, BCUC IR 2.233.1 and Exhibit B-6, BCOAPO IR 2.125.3.
363 Exhibit B-1, Application, p. 5-67. 364 Exhibit B-1, Application, p. 5-67.
- 100 -
301539.00025/94161307.1
● The Standard Labour Rate increases are the only other driver, and reflect a small
portion of the overall increase. The reason for Standard Labour Rate increases is
discussed in Section E above.
225. The largest planned increase is for stations asset maintenance. Generation
maintenance funding has remained stable from fiscal 2015 through fiscal 2019. Actual
expenditures for preventative maintenance and condition-based maintenance are showing
upward trends while corrective maintenance is relatively flat. These trends indicate a shift
towards more proactive maintenance work, which is more cost effective because the work can
be planned and scheduled.365 The pressure on substation maintenance budgets is discussed in
BC Hydro’s responses to BCOAPO IR 2.127.4366 and BCUC IR 2.233.1.367
(d) Vegetation Management is a Priority and Will Need Additional Investment After this Test Period
226. BC Hydro was asked whether sufficient vegetation maintenance is being planned. The
answer for the Test Period is “yes”, but the evidence suggests that increases will be necessary
thereafter.
365 Exhibit B-5, BCUC IR 1.61.2.1. Exhibit B-1, Application, Chapter 5, section 5.8.1. The appropriateness of the level
of maintenance spending in fiscal 2020 and fiscal 2021 on generation is discussed in Exhibit B-6, BCOAPO IR 2.127.2.
366 Exhibit B-13. 367 Exhibit B-12.
- 101 -
301539.00025/94161307.1
227. It is true that vegetation management costs have been relatively static in recent years,
as shown in the table below:368
Vegetation Program
F2015 Actual
F2016 Actual
F2017 Actual
F2018 Actual
F2019 Forecast
F2020 Plan
F2021 Plan
Transmission 19.5 16.8 17.5 18.0 17.7 17.7 17.8
Distribution 23.9 24.1 23.8 23.4 24.2 24.4 24.4
228. Nevertheless, BC Hydro’s maintenance program does include measures to mitigate
wildfire risk. For instance:
● BC Hydro has developed and implemented a wildfire probability/consequence
risk model to prioritize vegetation maintenance and fuel debris management to
reduce the risk of spread of wildfire along power line corridors. It facilitates
taking preventative mitigation actions in high fire prone areas.369
● BC Hydro inspects the transmission and distribution powerline corridors to
inform its preventative maintenance. On the overhead transmission system, BC
Hydro inspects the entire length of every circuit for vegetation growth once per
calendar year. In some cases, circuits in higher vegetation growth areas may
receive two or more vegetation inspections per year. On the overhead
distribution system, the vegetation maintenance inspection cycle varies across
the province from three to five years, depending on growth rates and vegetation
species.370
229. Mr. O’Riley expressed the view that spending on vegetation management will likely
need to increase in future test periods to address regulatory standards and growing public
aversion to wildfire risk:
And I think the approach of utilities towards vegetation is changing significantly and it’s changing for three reasons. One is the seemingly increased prevalence of
368 Exhibit B-5, BCUC IR 1.63.15. 369 Exhibit B-5, BCUC IR 1.63.14. 370 Exhibit B-5, BCUC IR 1.79.2.
- 102 -
301539.00025/94161307.1
storms that we’re experiencing and the reliability effects of that particularly in rural areas. So we’re having more and more development in rural areas of the province and seeing reliability effects of that and customer complaints on that.371
…
We are also increasingly concerned in our industry about forest fires, and you’ve seen the extraordinary situation in California and of course in Australia which is a cautionary tale for us all, but the one in California is very close to home. And you know, we’ve certainly reviewed that situation and the legal context there is quite different, and I’m not suggesting that would apply here at all, but you know, I think the tolerance around starting forest fires from power systems is not what it was years ago, five, ten, twenty years ago, and I think that is going to push utilities, including BC Hydro, towards more vegetation management on lines for distribution and transmission. And then the third is we have these mandatory reliability standards that govern vegetation, and what that does is really increase the penalty cost if you find yourself with a violation. And I think that’s going to drive up our management and quality control, and quality assurance and the actual spend on vegetation.372
I. BRATTLE REPORT AND INDICATIVE COMPARISON SUPPORTS THE REASONABLENESS OF BC HYDRO’S OPERATING COSTS
230. The BCUC expressed an interest in benchmarking in its Decision on the Previous
Application. In addition to providing information on benchmarking that BC Hydro undertakes in
the ordinary course of business, BC Hydro undertook operating cost benchmarking and
comparisons specifically for the purposes of addressing the BCUC’s comments. Although
inherent limitations in any benchmarking preclude definitively ascribing particular causes to
that favourable performance, the strong showing should provide additional reassurance that BC
Hydro is on track when it comes to controlling costs.373
371 Tr. 5, p. 505, ll. 3-10 (O’Riley). 372 Tr. 5, p. 505, l. 18 to p. 506, l. 12 (O’Riley). 373 Exhibit B-5, BCUC IR 1.62.14. BC Hydro put it this way: “Benchmarking studies are used to provide a high-level
point of comparison with a peer group. They represent one point of data in testing the organization’s performance compared to peers, and on their own are not used to make specific management decisions or draw definitive conclusions. In cases where BC Hydro is significantly out of line with comparators, additional review may be useful to understand why this is the case.”
- 103 -
301539.00025/94161307.1
(a) BC Hydro Benchmarks Favourably Against U.S. Peer Group on Operating Costs (Brattle Report)
231. BC Hydro retained Brattle, which has expertise in benchmarking.374 Brattle’s
methodology is summarized in the Application,375 and detailed in its report (“Brattle
Report”).376 The Brattle Report shows that BC Hydro’s operating costs benchmark favourably
against a peer group of U.S. utilities,377 regardless of the metric used. The peer group data was
compiled from annual reports using the Federal Energy Regulatory Commission (“FERC”)
Uniform System of Accounts.378
232. A useful comparison can be made with respect to BC Hydro’s non-power production
costs (which Brattle refers to as “non-power production NFOM”). BC Hydro’s very low power
production unit costs are influenced favourably by the inherent efficiencies that BC Hydro
enjoys by virtue of having large hydroelectric facilities. In contrast, the non-power production
costs (which include distribution, transmission and customer-facing functions), tend to be
driven by size and number of customers, as well as various other factors, such as density,
topography and climate.379 The Brattle Report states that the non-power production cost
comparison “provides a meaningful indicator for BC Hydro’s comparative cost performance”.380
In response to information requests, Mr. Zarakas of Brattle reaffirmed his confidence in the
usefulness of the results for non-power production costs:
Differences among utilities will always exist. The fact that the utilities discussed here are not identical to BC Hydro does not disqualify them from inclusion in a peer panel. Rather, it is important to rely on judgment to ensure that the comparison utilities are sufficiently similar on the dimensions that are the most
374 Exhibit B-1, Application, p. 5-50. See also curriculum vitae of Mr. Zarakas, filed as part of the Brattle Report. 375 Exhibit B-1, Application, p. 5-50. 376 Exhibit B-1, Application, Appendix T, Brattle Group Benchmarking Study. 377 Mr. Zarakas of the Brattle Group explained why the peer group was appropriate in his responses to Exhibit B-5,
BCUC IRs 1.53.1 and 1.53.1.1. In Exhibit B-5, BCUC IR 1.53.3, he explained that changing the peer group does not affect the results; BC Hydro still performs well even if the peer group is changed. He has included figures showing the results.
378 Exhibit B-1, Application, p. 5-51. 379 Exhibit B-5, BCUC IR 1.53.2. See also, Exhibit B-5, BCUC IR 1.55.2. 380Exhibit B-1, Application, Appendix T, Brattle Group Benchmarking Study, p. 29, para. 54.
- 104 -
301539.00025/94161307.1
relevant to the benchmarking exercise. As I discuss in the response to BCUC IR 1.53.2, the lack of U.S. utilities that have hydroelectric facilities on the scale of BC Hydro should not unduly affect the benchmarking exercise with respect to non-power production NFOM, or with respect to the functional NFOM levels that comprise non-power production NFOM.381
233. Brattle benchmarked non-power production costs as a whole, and by transmission,
distribution and administrative sub-functions. BC Hydro performs very well in each case, and
appears to be improving relative to the other companies in the peer group. Brattle noted that:
“BC Hydro was in the 2nd quartile of unit cost performance for this metric in the early years of
this study (2013) and improved to the 1st quartile by 2015, mainly due to improvements in its
cost performance in transmission and distribution.”382 The results for non-power production
costs ($/customer and $/delivered MWh), to which Brattle was referring, are shown below.
The equivalent graphs by sub-function (transmission, distribution, administrative) are included
in the Brattle Report, and reinforce the above conclusion.383
234. The extent of BC Hydro’s favourable performance relative to the U.S. utilities in the peer
group may well be understated. BC Hydro is subject to significant environmental requirements,
a duty to consult with First Nations, and many regulatory compliance and safety requirements.
381 Exhibit B-5, BCUC IR 1.53.1. 382 Exhibit B-1, Application, Appendix T, Brattle Group Benchmarking Study, p. 29. 383 Exhibit B-1, Application, pp. 5-52 and 5-53.
- 105 -
301539.00025/94161307.1
In addition, as a Crown Corporation, BC Hydro may be subject to regulations that are not
applicable to utilities in the peer group.384
(b) BC Hydro Compares Well in Indicative Canadian Utility Comparison
235. In recognition that the Brattle Report used a peer group of U.S. utilities, BC Hydro also
undertook a high-level indicative comparison of its operating costs against those of three other
major Canadian hydroelectric utilities.385 BC Hydro compares well (lowest on cost per customer
and “middle of the pack” on cost per MWh).386 While the results provide only a high level
indication due to limitations in the methodology, the fact that BC Hydro is in the same range as
other utilities when it comes to operating costs provides some additional reassurance that BC
Hydro is on the right track when it comes to managing operating costs.
236. In the Canadian utility cost comparison, BC Hydro’s operating costs per MWh of sales
and customers are shown as increasing. This is largely due to two factors: (a) accounting
treatment changes related to capitalization that may not be applicable to the other utilities;
and (b) sustainment costs related to the Smart Metering Infrastructure Program, which had
been deferred in fiscal 2015 and fiscal 2016 and started to be included in base operating costs
in fiscal 2017.387
(c) Value of Continuing to Prepare Uniform System of Accounts Must Be Weighted Against Other Priorities and Costs
237. BC Hydro has requested to discontinue preparing information for regulatory purposes
using the BCUC’s Uniform System of Accounts (Directive 57 of the BCUC’s Decision on BC
384 Exhibit B-5, BCUC IR 1.55.4. 385 The benchmarking methodology used, and its limitations, are described in Exhibit B-1, Application, pp. 5-53 and
5-54. BC Hydro explained why it selected FortisBC, Manitoba Hydro, Hydro Quebec as comparable utilities in its response to Exhibit B-6, CEC IR 1.34.1. Additional information on the data sources and the steps taken to improve the comparability of data are described in Exhibit B-5, BCUC IRs 1.56.1, 1.56.4 and 1.57.2.
386 Exhibit B-1, Application, pp. 5-55 and 5-56. BC Hydro emphasized: “Consistent with the caution by The Brattle Group about the limits of benchmarking, we recognize that extraneous factors can influence these metrics. … As such, when evaluating these results, we look more to the fact that BC Hydro is within the same range as these utilities when it comes to operating costs, as opposed to any particular rank ordering.”
387 Exhibit B-5, BCUC IR 1.57.3; Exhibit B-6, CEC IR 2.103.1.1.1. The accounting changes related to overhead costs, which are no longer eligible to be capitalized under IFRS.
- 106 -
301539.00025/94161307.1
Hydro’s Fiscal 2009 to Fiscal 2010 Revenue Requirements Application).388 As BC Hydro
explained:
Rescinding Directive 57 would not prevent BC Hydro from preparing USoA financial schedules in the future, if those schedules were required for additional benchmarking analysis. Rather, it would provide BC Hydro management with the discretion to determine whether and how often to prepare these schedules.
Preparing the USoA financial schedules is labour intensive and would create additional cost pressures. In BC Hydro’s view, having the discretion to prioritize these pressures against other requirements is an important part of our ongoing efforts to limit overall base operating cost increases.389
238. While Brattle was able to use the BCUC’s Uniform System of Accounts to inform its
benchmarking study, the BCUC’s Uniform System of Accounts is different from the FERC
Uniform System of Accounts, which was the source of the peer group data used in the Brattle
Report.390
239. BC Hydro noted that if the BCUC and interveners found the Brattle Report valuable, then
reporting based on the FERC Uniform System of Accounts would likely provide greater value,
going forward, compared to reporting based on the BCUC Uniform System of Accounts. BC
Hydro explained that there would be some initial effort to set-up a Uniform System of Accounts
reporting framework and to manage this work on an ongoing basis.391
240. However, as Mr. O’Riley explained, there have been many opportunities put forward by
interveners and, in aggregate, the costs of these opportunities add up and push against BC
Hydro’s ability to keep rates affordable and competitive.392 The additional costs of presenting
BC Hydro’s accounts according to the FERC Uniform System of Accounts should be evaluated
within this context. BC Hydro submits that the value of taking this step is insufficient at the
388 Exhibit B-1, Application, p. 1-33. 389 Exhibit B-13, BCOAPO IR 2.123.1. 390 Tr. 7, p. 1012, l. 24 to p. 1013, l. 23 (Layton). 391 Tr. 7, p. 1013, ll. 1-6 (Layton); Tr. 7, p. 1014, l. 20 to p. 1015, l. 24 (Layton). 392 Tr. 5, p. 443. l. 24 to p. 444, l. 10 (O’Riley).
- 107 -
301539.00025/94161307.1
present time to justify a directive that would remove the ability of management to prioritize
this work against other pressures, as appropriate.
J. CONCLUSION AND REQUESTED FINDINGS
241. The BCUC should find, based on the evidence discussed above, that the forecast
operating expenses in the Test Period are reasonable.
- 108 -
301539.00025/94161307.1
PART SEVEN: CAPITAL EXPENDITURES AND ADDITIONS
A. INTRODUCTION
242. This Part of BC Hydro’s Final Submissions discusses BC Hydro’s forecast capital
expenditures and additions in the Test Period. BC Hydro’s forecast capital expenditures and
additions are summarized in Tables 6-1 and 6-2 of the Application.393 The evidence discussed
below demonstrates the reasonableness of BC Hydro’s Test Period capital forecasts.
243. We highlight the following supporting points:
● First, BC Hydro has provided a significant amount of evidence in support of the
Test Period capital forecasts, consistent with BC Hydro’s approved Capital Filing
Guidelines.
● Second, BC Hydro’s Test Period capital forecast is the product of a robust capital
planning process that incorporates top-down limitations, and risk-based project
prioritization to balance affordability, system performance and risk. BC Hydro
has developed an ex-plan governance process to respond to evolving needs.
● Third, BC Hydro has reduced its capital forecast to balance affordability, system
performance and risk.
● Fourth, BC Hydro delivers capital projects efficiently and effectively, as
demonstrated by its ability to deliver it portfolio of projects within 5% of Original
Approved Expected Cost.
● Fifth, BC Hydro’s capital asset management processes have been endorsed by
third parties, including the Auditor General and project management
organizations.
393 Exhibit B-1, Application, pp. 6-6 and 6-7.
- 109 -
301539.00025/94161307.1
● Sixth, BC Hydro’s Amortization of Capital Additions Variance Accounts will ensure
that customers only pay actual costs.
● Seventh, BC Hydro has answered specific issues raised in the proceeding relating
to planning, project execution and cost recovery.
● Eighth, BC Hydro is managing its industrial load interconnection requests well,
with study times comparing well against BC Hydro’s own business practice
timelines and the practices at other utilities. BC Hydro is also continuing to look
for opportunities to improve the process.
B. BC HYDRO’S EVIDENCE SUPPORTING CAPITAL FORECASTS IS SUBSTANTIAL AND ACCORDS WITH APPROVED CAPITAL FILING GUIDELINES
244. BC Hydro has filed a significant volume of evidence supporting its capital forecasts for
the Test Period, including the evidence listed below. The nature of the information filed is
consistent with BC Hydro’s Capital Filing Guidelines as proposed at the time of filing.
● Chapter 6 of the Application describes in detail BC Hydro’s capital planning and
delivery processes, as well as BC Hydro’s forecast capital expenditures and
additions over the Test Period. It includes descriptions of key drivers and
explanations of changes in the forecast from year to year;
● Appendix F is the Auditor General’s December 2018 audit of Capital Asset
Management in BC Hydro, which found that BC Hydro has good asset
management practices as a result of a decade-long plan and associated efforts
and had no recommendations for improvement;
● Appendix G explains variances between planned and actual capital additions and
expenditures for fiscal 2017 and fiscal 2018 (while Appendix G of the Evidentiary
Update explains variances for fiscal 2019);
● Appendix H is BC Hydro’s Fiscal 2020 to Fiscal 2024 Capital Plan (“Capital Plan”);
- 110 -
301539.00025/94161307.1
● Appendix I is a detailed spreadsheet with information on all projects and
programs over $5 million, and all Technology projects over $2 million;
● Appendix J provides a summary of all capital projects over $20 million;
● Appendix K provides an overview of the current state of BC Hydro’s Power
System and a summary of the capital strategies, plans and studies that are
related to the projects described in Appendix I or J;
● Appendix L is BC Hydro’s Technology Strategy and 5-Year Plan;
● Appendix M is asset health statistics for BC Hydro’s generation assets;
● Appendix N is asset health statistics for BC Hydro’s transmission and distribution
assets; and
● Leading up to the oral hearing, BC Hydro has also filed updates to the
information on its capital projects to keep the BCUC and interveners informed of
key changes.394
245. Seven witnesses, including the executives responsible for capital planning and delivery,
testified.395 These individuals have extensive experience in their areas. Witnesses on Panel 4
were involved in the preparation of the current Capital Plan.396
C. BC HYDRO HAS A ROBUST CAPITAL PLANNING PROCESS
246. BC Hydro’s Test Period capital forecast is the product of an enterprise-wide capital
planning process. It incorporates top-down limitations, and risk-based project prioritization to
balance affordability, system performance and risk. BC Hydro has developed an ex-plan
394 Exhibit B-26 and Exhibit B-29. 395 Mr. Morison (information technology), Ms. Pinksen (portfolio optimization and management), Ms. Daschuk
(executive responsible for capital planning), Mr. Darby (stations), Mr. Kumar (transmission and distribution), Ms. Holland and Mr. Leonard (executives responsible for project delivery).
396 Tr. 11, p. 1839, ll. 3-19 (Kumar and Pinksen).
- 111 -
301539.00025/94161307.1
governance process to respond to evolving circumstances. BC Hydro submits that the rigour
applied to capital planning through these processes should provide considerable comfort that
the forecast expenditures and additions in the Test Period are reasonable.
(a) The Top-Down and Bottom-Up Approach Permits Balancing Affordability, System Performance and Risk
247. BC Hydro’s top-down/bottom-up capital planning process is detailed in section 6.3 of
the Application and summarized below.
Step 1: Top-Down Strategic Direction and Capital Program Parameters
248. The first step in the annual enterprise capital planning process is the Executive Team’s
direction on long-term capital investment levels.397 The top-down strategic direction provided
by the Executive Team is important for constraining both operating and capital spending levels.
Mr. O’Riley commented in his Opening Statement:
As a result of a changing operating environment, a lot of rigour goes into our budgeting process. The Commission had questions about our budgeting coming out of our last revenue requirements application and my strong view is that our top-down and bottom-up budgeting process has limited operating and capital cost increases and that a fully zero-based budgeting approach that lacks the top-down constraint would see greater cost increases.398
249. As discussed in Section D below, the strategic direction from the Executive Team in
relation to the Capital Plan resulted in a reduction in capital expenditures compared to the
previous capital plan.
Step 2: Bottom-Up Planning and Portfolio Development by Asset Category
250. In the second step, BC Hydro uses a bottom-up process to develop forecast capital
investments for each asset category (i.e., Power System (including Generation, Transmission
and Distribution), Technology, Properties and Fleet).399 The bottom-up process is tailored to
397 Exhibit B-1, Application, p. 6-19. 398 Tr. 5, p. 358, ll. 11-19 (O’Riley). 399 Exhibit B-1, Application, p. 6-28.
- 112 -
301539.00025/94161307.1
the characteristics of each asset category and is scaled as required. For example, Power System
portfolios, being the largest and most complex, generally require more complex and detailed
planning processes. They also involve a broader discussion with internal stakeholders across BC
Hydro.400
251. In general, these bottom-up processes identify recommended capital investments in the
planning period based on an understanding of the issues, risks and opportunities associated
with the particular asset category. During these bottom-up processes, BC Hydro considers
changes in need, regulation, priorities, strategies and circumstances to determine what projects
and programs are required and the appropriate timing of the investments.401
Step 3: Collaborative Prioritization Within Corporate Investment Framework
252. In the next step of the process, BC Hydro consolidates the capital planning information
for collaborative peer reviews at the enterprise level, validates alignment with BC Hydro’s
strategic direction and priorities, and identifies any potential areas for improvement in the
process for the next annual capital planning cycle.402
253. BC Hydro classifies its investments into one of three categories: (1) mandatory
investments driven by legal and regulatory requirements (including customer interconnection
requests); (2) committed investments not to be postponed; and (3) investments to be
prioritized, which includes projects that could be re-prioritized without significant costs,
impacts to system reliability or compromising BC Hydro’s ability to connect new customer load.
Under this framework, BC Hydro assesses investments based on the primary driver, considering
the financial, reliability, safety, environmental and reputational impacts associated with
delaying the investment:403
400 Details on the specific bottom-up planning process for the Generation, Transmission and Distribution,
Technology, Properties and Fleet asset categories are set out in sections 6.4.2, 6.4.4, 6.5.3, 6.6.2, 6.7.1 and 6.8 of the Application, respectively.
401 Exhibit B-6, BCOAPO IR 1.64.3. 402 Exhibit B-1, Application, pp. 6-29 and 6-30. 403 Exhibit B-1, Application, p. 6-29; Exhibit B-13, BCOAPO IR 2.134.1.
- 113 -
301539.00025/94161307.1
● investments that primarily mitigate risk are scored for prioritization using a
methodology that is aligned with the BC Hydro Corporate Risk Matrix;404 and
● investments that primarily create value are scored for prioritization using a net
value per dollar invested metric.
254. BC Hydro considers the resulting risk or value scores and other criteria, including
resource and outage constraints, when making prioritization decisions.405 Ms. Pinksen
explained that the risk and value scores are just one tool used in the prioritization process.406
Mr. Kumar elaborated:
…a risk score is an input into our prioritization. It is not something that defines what the outcome of a capital plan looks like. Because if we actually ended up taking just the risk score and compared the risk score of a dam safety project versus a feeder project, we would never be building anymore feeders… So that’s why…you also…have to look at what the driver for the project is, what part of the system we are serving. And we collectively sit down and take that into account in terms of criticality of the system, the risk score, what are the risks we are trying to avoid, so all those are inputs into it. It’s not just you get a risk score of 11 and it trumps a project that is a risk score of 8. It doesn’t happen like that. You have to look at it in totality in terms of what the impact of those projects is going to be.407
Step 4: Senior Management and Board Review
255. In the final step, the Executive Team and Board of Directors assess whether the plan
meets BC Hydro’s overall business objectives and provides a consistent and appropriate
management of risks across all asset categories.408
404 BC Hydro’s Capital Panel explained how to read the risk matrix. In essence, the capital risk matrix has two
components, severity and probability. The risk is not a project delivery risk, rather (per Ms. Pinksen) “It's more of a risk to BC Hydro if we don't undertake the investment.” Mr. Kumar added: “So we define risk in terms of environmental, financial, public safety, reputation, so those are the different categories we define the risk on. And depending on what project we are looking at we pick the highest risk that the project is exposing the organization to.” Tr. 11, p. 1848, l. 17 to p. 1849, l. 22 (Pinksen, Kumar and Daschuk).
405 Exhibit B-13, BCOAPO IR 2.134.1. 406 Tr. 12, p. 2304, ll. 6-10 (Pinksen). 407 Tr. 13, p. 2382, l. 17 to p. 2383, l. 11 (Kumar). 408 Exhibit B-1, Application, p. 6-30.
- 114 -
301539.00025/94161307.1
(b) Affordability is Reflected Throughout the Capital Planning Process
256. Ms. Pinksen confirmed that affordability considerations are reflected throughout the
capital planning process:
Well, I would actually say affordability is captured on three tiers in our capital planning process. The first tier would be in the setting of our strategic objectives and establishing the financial targets for our capital plan. The second would be during bottom-up planning, when we are identifying the specific projects to undertake. And then the third tier would then be in the prioritization phase of the capital planning and ensuring that we are undertaking the projects that are bringing the greatest value within our financial targets.409
(c) BC Hydro Has Improved the Governance Framework for Ex-Plan Projects
257. BC Hydro’s Capital Delivery Management Committee monitors the approved capital plan
on an ongoing basis to assess whether actual and forecast capital expenditures remain aligned
with the original capital plan. BC Hydro may reallocate the budget within the capital plan as
new information becomes available, considering financial impacts, the enterprise risk profile,
and labour resource availability.410 This may include making changes to the timing of other
investments to fund a required ex-plan investment.411
258. Decisions to reallocate the budget to accommodate an ex-plan project are referred to as
the ex-plan governance process.412 BC Hydro described the ex-plan governance process as
follows:
BC Hydro considers an ex-plan project as a project that was not included in the approved Capital Plan (fiscal 2020 to fiscal 2024) or a project that was in the approved Capital Plan outside of the current test period, but that is required to address an immediate need such that the project must be advanced into the current year.
When submitting a project as ex-plan, the responsible KBU must validate that the project meets the ex-plan criteria described above. In addition, the
409 Tr. 11, p. 1850, ll. 4-15 (Pinksen). 410 Exhibit B-1, Application, pp. 6-30 and 6-31. 411 Exhibit B-12, BCUC IR 2.254.1. 412 Exhibit B-1, Application, p. 6-31.
- 115 -
301539.00025/94161307.1
responsible KBU will determine if the ex-plan project’s capital expenditures in the current fiscal year can be accommodated within its own current fiscal year capital plan. If the KBU cannot manage the additional investment within their current fiscal year capital plan, redirection from another KBU will be considered based on the latest portfolio forecasts.
For capital ex-plan investments driven by the need to connect new customers and/or expand the system to serve load growth, offsets in the form of contribution in aid and/or expected increases to revenue are also considered when determining if redirection or plan reductions are required.413
259. Ms. Pinksen explained that the ex-plan governance process represents an improvement
since the Previous Application in two respects:
What I would characterize as new in this application compared to previous applications is two things. So first of all the governance around the initiation of ex-plan projects. We have established a clear governance through our capital delivery and management committee, which establishes thresholds for the levels of review required depending on the size of the project. So a very small project, about 100K, myself as a member of the working group, the enterprise working group, I would be able to endorse the initiation. And what I want to make clear is that that’s not superseding the financial approval, it’s really just an assessment of yes this project merits initiation at this time as an ex-plan project as opposed to waiting to the next capital planning cycle. And so those tiers move all the way up to a review by the entire capital delivery management committee for projects over 10 million. So that’s one thing that’s new is that that level of governance.
…
And I did want to say the second thing that’s new is we are now tracking [ex-]plan projects as part of our scorecard. And the reason for doing that is we want to look for opportunities to improve our process. So if we start to see a number of [ex-]plan projects being identified we want to go back and say, “was there something we can do better in our process of establishing the original plan to try to capture those as part of the capital planning process.” So those two things are new for us.414
413 Exhibit B-5, BCUC IR 1.110.1. 414 Tr. 11, p. 1873, l. 21 to p. 1875, l. 20 (Pinksen).
- 116 -
301539.00025/94161307.1
260. Mr. Kumar emphasized that the governance is intended to limit the ex-plan process to
system requirements:
So we are actually managing that project quite judiciously and making sure that process is not used for just bringing in any need that arises on the system, we actually have a fairly strict and robust process to make sure that we actually move that project through only if there’s a need for that project from a system perspective.415
261. Ms. Pinksen gave the example of having to initiate a NERC CIP v. 7 project as an ex-plan
project in order to achieve compliance by a standard deadline. In the case of this ex-plan
project, BC Hydro had to delay some other projects until fiscal 2021 to accommodate the
project within the existing budget.416
(d) New Value-Based Assessment Approach Represents the Evolution of BC Hydro’s Capital Prioritization Process
262. Mr. Kumar explained that the current risk-based framework does a good job of
prioritizing to address risk, and that project benefits are reflected under the risk-based
approach.417 The new value-based approach that BC Hydro is investigating involves recasting
the risk and benefits in terms of value. It is the next step in the evolution of the prioritization
process:
So over the last 12 years Hydro has actually worked quite hard in terms of developing an industry leading framework that is based on a risk prioritization tool, and it’s aligned with our objectives at a corporate level. And you’ve got great feedback from the Auditor General in terms of our planning process that we used. What Ms. Pinksen was talking about is the next evolution of the capital planning process, which is going from a risk-based framework over to a value-based framework which helps us define the value of projects it’s providing as opposed to the risk that the project is avoiding. They are both sides of the same coin, it’s just a different way of defining how you move forward with the project.
415 Tr. 11, p. 1876, ll. 13-19 (Kumar). 416 Tr. 11, p. 1877, l. 20 to p. 1878, l. 3 (Pinksen). 417 Tr. 11, p. 1855, l. 17 to p. 1856, l. 13. (Kumar).
- 117 -
301539.00025/94161307.1
So I would say our capital plan is well-defined in terms of cost effectiveness by using a risk-based framework. What we are talking about here is taking that framework to the next level and defining it in a level that allows us to capture the value of the project, not just the risk side of a project.418
D. BC HYDRO HAS REDUCED THE CAPITAL FORECAST TO BALANCE AFFORDABILITY, SYSTEM PERFORMANCE AND RISK
263. The 2020-2024 Capital Plan reflects a 13 percent reduction in BC Hydro’s capital forecast
relative to the previous Capital Plan, as shown in the figure below, reproduced from the
Application.419 The evidence, discussed below, demonstrates that this material reduction was
warranted as a means of balancing affordability, system performance and risk.
Figure 6-5: Comparison of Fiscal 2020 to Fiscal 2024 Planned Capital Additions
(a) Strong System Performance and Slower Demand Growth Created Opportunity for Moderating Capital Spending
264. During step two of the annual capital planning process (bottom-up planning and
portfolio development by asset category), BC Hydro determined that there was an opportunity
to moderate the planned investment in sustainment to mitigate impacts on customers without
418 Tr. 11, p. 1854, l. 16 to p. 1855, l. 11 (Kumar). 419 Exhibit B-1, Application, p. 6-20, Figure 6-5.
- 118 -
301539.00025/94161307.1
materially impacting system performance.420 This opportunity arose due to BC Hydro’s strong
system performance, as indicated by the following:421
● In the past decade, BC Hydro’s “all events” System Average Interruption
Duration Index (“SAIDI”) trend performed as well as or better than the Canadian
Electricity Association (“CEA”) composite, with the exception of fiscal 2016 due
to the August 2015 summer wind storm.422
● BC Hydro’s “all events” System Average Interruption Frequency Index (“SAIFI”)
trend also consistently outperformed the CEA SAIFI composite.423
● Normalized SAIDI was 3.28 hours in fiscal 2017 — a strong result. It further
improved to 3.07 hours in fiscal 2018.424
● Normalized SAIFI was 1.59 disruptions in fiscal 2017 — also a strong result. It
further improved to 1.51 disruptions in fiscal 2018.425
● The reliability scores in BC Hydro’s Customer Satisfaction Index indicate that
customers continue to be satisfied with the level of reliability they are
receiving.426
● Asset related safety incidents on the transmission and distribution system have
declined, indicating that BC Hydro’s investment plans are addressing safety
related risks on the system.427
420 Exhibit B-1, Application, pp. 6-19 to 6-25. 421 Exhibit B-1, Application, pp. 6-20 and 6-21. 422 Exhibit B-1, Application, p. 6-21. 423 Exhibit B-1, Application, p. 6-22. 424 Exhibit B-1, Application, pp. 6-22 and 6-23. Normalized SAIDI measures the total outage duration with storm
impact adjustments experienced by an average customer in a year. 425 Exhibit B-1, Application, pp. 6-23 and 6-24. Normalized SAIFI measures the number of sustained disruptions per
year excluding major events. 426 Exhibit B-1, Application, pp. 6-24 and 6-25. 427 Exhibit B-1, Application, p. 6-25.
- 119 -
301539.00025/94161307.1
265. Given the strong system performance, BC Hydro eliminated a previously planned ramp-
up of sustainment expenditures in the Capital Plan relative to the previous plan. The majority
of reductions were realized in fiscal 2025 to fiscal 2029.428 However, as shown in Figure 6-5 of
the Application above, BC Hydro also reduced the overall level of planned sustainment capital
additions in the fiscal 2020 to fiscal 2024 period.429 BC Hydro did not reduce dam safety
expenditures.430
266. In addition, the demand for electricity is growing at a more moderate rate than
previously anticipated, which allowed BC Hydro to delay some planned investments to expand
the system beyond the ten year time frame of the Capital Plan.431 The deferral or cancellation
of growth investments based on an expected change in load growth is beneficial for
customers.432
267. Based on system performance and the demand for electricity, the reductions to the
Capital Plan consist of:
● reductions due to decisions to defer investments; and
● updates to forecasts for active projects which resulted in a net reduction in
capital expenditures or additions within the period, primarily due to project
schedule changes.433
268. Over the Test Period, the reduction is $682 million or 22.3 percent as follows:434
428 Exhibit B-1, Application, p. 6-26. 429 Exhibit B-1, Application, p. 20. 430 Exhibit B-1, Application, p. 6-26. 431 Exhibit B-5, BCUC IRs 1.108.2 and 1.108.1.1. 432 Exhibit B-5, BCUC IR 1.108.1.3. 433 Exhibit B-5, BCUC IR 1.108.1.1. 434 Exhibit B-5, BCUC IR 1.108.1.
- 120 -
301539.00025/94161307.1
269. Approximately $137 million of the reduction over the Test Period is attributable to
decisions to defer investments.435 These investments were deferred considering the risk score
assessment, along with the latest project cost forecast, system performance data and asset
information.436 The remainder of the reduction is due to updates to forecasts for active
projects.437
(b) Asset Condition and Performance Will Be Monitored
270. The impact on asset health of moderating capital spending is expected to vary across
the system.438 BC Hydro explained:
• BC Hydro’s generation facilities are categorized as “Key”, “Strategic” or “Available” according to the significance of the facility to BC Hydro’s system. Under the Capital Plan, the condition of BC Hydro’s “Key” and “Strategic” generation facilities is expected to improve. For example, investments are planned for the G.M. Shrum, Mica, Bridge River and Cheakamus facilities; and
435 Exhibit B-5, BCUC IR 1.108.1. 436 Exhibit B-5, BCUC IR 1.108.2. 437 Exhibit B-5, BCUC IR 1.108.1. 438 Exhibit B-1, Application, pp. 6-26 and 6-27.
- 121 -
301539.00025/94161307.1
• The recent trend of asset health degradation within some parts of the Power System is expected to continue at this level of capital investment. For example, over the next five years, the percentage of substation assets in Poor and Very Poor condition is expected to increase from 16 per cent to 19 per cent and the percentage of distribution assets in Poor and Very Poor condition is expected to increase slightly from 13 per cent to 14 per cent. The condition of the assets within BC Hydro’s “Available” generation facilities, which provide less than 1 per cent of BC Hydro’s annual energy, are expected to continue to deteriorate.
271. BC Hydro does not expect any operational impacts from the deferral of sustainment
projects, although it has accepted the potential for additional maintenance of some assets.439
The deferral or cancellation of sustainment investments is not expected to have a material
impact on customer reliability due to asset redundancy and the installation of automated
devices on the system.440
272. BC Hydro will carefully monitor asset condition and performance and will respond as
needed.441 BC Hydro monitors system performance and forecast demand for electricity at both
a system and regional level. If system performance were to decline or if forecast demand were
to change, BC Hydro may adjust the level of asset condition driven replacements, update
operational or maintenance practices, or bring forward ex-plan projects. Changes in system
performance and load forecasts are likely to materialize over time, giving time for BC Hydro to
respond to changes if needed.442
(c) Additional Reductions in Capital Spending Would Be Undesirable
273. Overall, based on forecast load growth and system performance, BC Hydro’s planned
level of capital investment from fiscal 2020 to fiscal 2024 reflects an appropriate balance of
system performance, risk and affordability.443 BC Hydro’s evidence is that any further
439 Exhibit B-5, BCUC IR 1.108.1.2. 440 Exhibit B-1, Application, p. 6-27; Exhibit B-5, BCUC IR 1.108.1.3. 441 Exhibit B-1, Application, pp. 6-26 and 6-27. 442 Exhibit B-1, Application, p. 6-27. 443 Exhibit B-1, Application, p. 6-28.
- 122 -
301539.00025/94161307.1
reductions to forecast capital expenditures would degrade asset condition and asset health
more than anticipated, with a corresponding negative impact on customer service levels.444
E. BC HYDRO DELIVERS CAPITAL PROJECTS EFFICIENTLY AND EFFECTIVELY
274. The evidence, discussed below, demonstrates that BC Hydro has implemented delivery
processes tailored to the size and complexity of projects, is engaged in continuous
improvement of those processes, has rigorous financial approval processes in place, and has
been delivering its portfolio of projects on budget.
(a) BC Hydro’s Planning and Delivery Functions Work Together to Ensure Seamless Transition and Accountability
275. BC Hydro’s planning and delivery functions are well integrated.445 Mr. Kumar
emphasized the high level of interaction throughout the capital management process, including
that the Project Delivery function must account for whether project objectives have been
achieved:
So I think just to add to what Ms. Holland was saying, for all the projects that are implements by Ms. Holland’s team, the initiator, which is Andy [Darby], myself and Mr. Schubak, we would be heavily involved in all the different processes for moving the project forward and we don’t sign off on the project completion report unless the objectives of those projects have been delivered, because that’s what we are looking from an asset management perspective.
So I think there’s a enough checks and balances within the organization that the deliver group has to come back to the initiating group to make sure that objectives of the project have been delivered as we expected it to. So I think that’s another area that we have it controlled within the organization of making sure that our objectives are met for the delivery side.446
(b) BC Hydro’s Delivery Processes Are Tailored to the Size and Complexity of Projects
276. BC Hydro uses delivery processes that are appropriate for the size and complexity of the
projects being delivered.
444 Exhibit B-12, BCUC IR 2.255.3. 445 Exhibit B-1, Application, pp. 6-56 and 6-58. 446 Tr. 11, p. 1859, l. 23 to p. 1860, l. 13 (Kumar).
- 123 -
301539.00025/94161307.1
Project Delivery KBU Uses the Program and Portfolio Management System to Deliver Larger, More Complex Projects
277. The Project Delivery KBU is responsible for delivering the larger, more complex Power
System projects, which comprise approximately 54% of the planned capital investments in the
Power System for fiscal 2020 to fiscal 2021. It uses the Project and Portfolio Management
(“PPM”) system for consistent management of project risk, scope, schedule and cost. PPM
reflects the principles of ISO 9001, 2008 Quality Management Systems Requirements, and other
industry standards such as the Project Management Institute’s Project Management Book of
Knowledge and the Association for the Advancement of Cost Engineering International
Recommended Practices.447
278. In broad terms, the delivery lifecycle of PPM projects uses a staged approach to project
definition and gate approvals. The lifecycle is divided into four phases: Initiation, Identification,
Definition and Implementation. Each phase is further divided into various stages. As projects
move through the lifecycle, they become more defined and cost estimates are developed and
updated. At various points of the project lifecycle, there are formal approval points (gate
approvals), where key information on project cost, schedule, scope, procurement and risk is
presented to the Gate Board.448 The Application details the key components of the PPM
system, including practices, tools and learning.449 It also describes BC Hydro’s governance
structure, including providing a description of each role.450 The PPM project lifecycle is
depicted in Figure 6-13 of the Application, reproduced below.
447 Exhibit B-1, Application, p. 6-59. 448 Exhibit B-1, Application, p. 6-64. 449 Exhibit B-1, Application, sections 6.4.7.2 to 6.4.7.4. 450 Exhibit B-1, Application, pp. 6-69 to 6-74.
- 124 -
301539.00025/94161307.1
Figure 6-13 PPM Project Lifecycle
identification definitioninitiation
Initiation Needs ConceptualDesign
FeasibilityDesign
PreliminaryDesign
RegulatoryApprovals
DetailedDesign CompletionProcurement Construction Commissioning
& Acceptance
StudyApproval
LeadingAlternativeIdentified
Preferred Alternative Confirmed
Full Funding Implementation
ApprovalIn-Service
DateProject
Completion
Conceptual Estimate
+100 / -35%
Feasibility Estimate
+50% / -15%
Preliminary Estimate
+15% / -10%
implementation
gate TechnicalCheckpoint phase
stage estimate
Where total project forecast is > $50M – Board approval of
Preferred Alternative. Not a financial approval.
Board Approval
Where total project forecast is > $50M – Board approval of Full
Implementation Funding Request.
Where total project forecast is > $50M – Board approval
of Project Completion & Evaluation Report.
BC Hydro Uses a Simplified Framework for Routine Power System Investments
279. The Program and Contract Management KBU delivers less complex and repetitive Power
System capital investments on BC Hydro’s Power System, which comprise approximately 26% of
planned capital investments in the Power System for fiscal 2020 to fiscal 2021.451 These capital
investments are typically “like for like” replacements based on pre-defined design standards,
are routine in nature, have a lower risk profile and require minimal, if any acquisition of
property or rights of way.452
280. The Program and Contract Management KBU applies a simplified version of the PPM
practices, given the lower complexity of the projects it delivers. It develops annual program
and project delivery plans in collaboration with the KBUs in the Integrated Planning and Capital
Infrastructure Project Delivery Business Groups. Internal FTEs are used to deliver a significant
volume of the small capital work, with external contractors being used to provide scalability
due to fluctuations in demand. When specialized services, equipment or materials are
required, standing blanket services contracts or master purchasing agreements are used.453
These standardized processes are efficient and effective for the nature of the capital
investments being undertaken.
451 Exhibit B-1, Application, pp. 6-74 and 6-75. 452 Exhibit B-1, Application, pp. 6-74 and 6-75. 453 Exhibit B-1, Application, pp. 6-74 and 6-75.
- 125 -
301539.00025/94161307.1
BC Hydro Uses a Standardized Process for Routine Customer Driven Work
281. The Distribution Design and Customer Connections KBU is responsible for work related
to customer requests for new or upgraded connections to BC Hydro’s distribution system under
5MW, which comprises approximately 16% of the planned capital investments in the Power
System for fiscal 2020 to fiscal 2021.454 This KBU provides technical design services and project
management for customer driven new connections work under 5 MW in size. As explained by
Ms. Daschuk, the Distribution Design and Customer Connections KBU manages approximately
35,000 simple customer connections and approximately 5,000 more complex design
interconnections each year.455 The Distribution Design and Customer Connections KBU designs
to standards, with engineering support where required. It follows a project management
structure that involves standardized work order packages, with environmental, archeological,
safety and job planning processes and checklists. This simplified process enables project cycle
times to align with customer requirements.456
Technology Projects Use Information Technology Delivery Standard Practices
282. BC Hydro manages its Technology projects using a technology-specific delivery
framework called Information Technology Delivery Standard Practices (“ITDSP”). ITDSP aligns
with PPM Practices and uses standard PPM phases with uniquely defined stages. Gate approval
points are positioned at the end of project stages so that management can confirm that the
proposed project solution remains in alignment with business drivers, and is ready to progress
to the next phase or stage. Each gate is a formal approval point, where key information is
presented to the gate board, typically related to cost, schedule, scope, procurement, and
risk.457
454 Exhibit B-1, Application, p. 6-76. 455 Tr. 12, p. 2101, l. 14 to p. 2102, l. 7 (Daschuk). These customer connections are distinguished from the
customer interconnections of over 5 MVA and over $2 million. 456 Exhibit B-1, Application, p. 6-76. 457 Exhibit B-1, Application, pp. 6-146 and 6-147.
- 126 -
301539.00025/94161307.1
(c) BC Hydro is Continuously Improving its Delivery Processes
283. BC Hydro has demonstrated that it is engaged in continuous improvement of its capital
delivery processes. In the Application, BC Hydro provided a lengthy list of improvements that it
has made to its Power System delivery processes.458 BC Hydro also annually updates its
ITDSP.459 As discussed in Subsection (g) below, BC Hydro’s delivery of its Technology projects
has improved using this ITDSP updating process.
(d) BC Hydro Has Rigorous Financial Approval Processes in Place for All Investments
284. BC Hydro’s Management and Accounting Policies and Procedures and Financial Approval
Authority Policy set the funding approvals required for capital investments through each phase
of the project lifecycle. The policies and procedures apply to all groups delivering BC Hydro’s
capital investments.460 The required financial approvals under these policies depend on the
type of capital investment and the nature of the risk it represents:461
● Phased capital projects require phase-by-phase funding approval: Capital
projects delivered using the standard PPM phases are the highest risk projects.
Accordingly, they require funding approval prior to the commencement of work
for each stage or phase. The financial approver level is dependent on the stage
or phase as well as the funding amount being requested.
● Non-phased capital projects require business case and authorization: Non-
Phased Capital Projects are similar to a one-time capital investment, such as the
purchase of new equipment or office furniture. Non-phased capital investments
over $0.5 million require an approved business case and Expenditure
Authorization Request form prior to any capital spending. These authorization
documents are approved based on the total investment amount.
458 Exhibit B-1, Application, pp. 6-82 and 6-83. 459 Exhibit B-1, Application, p. 6-142. 460 Exhibit B-1, Application, p. 6-77. 461 Exhibit B-1, Application, p. 6-78 to 6-81.
- 127 -
301539.00025/94161307.1
● Recurring capital investments are approved annually: Recurring Capital
Investments are generally lower risk, involving like-for-like unit replacements
(e.g., the annual distribution wood pole replacement program). These
investments are authorized at the beginning of each fiscal year using the
Recurring Capital Annual Expenditure Authorization Form.
● Approved work orders are required for low cost recurring capital projects:
Expenditure Authorization Request Exempt Capital Investments are recurring
capital projects with a low cost and high volume. Examples include work
activities to connect distribution customers, which are required under the
Electric Tariff and cost less than $1 million. These investments are approved
through BC Hydro’s Work Order system.
(e) BC Hydro Evaluates Power System Projects Upon Completion
285. A key outcome of the Implementation Phase of Power System projects is a Project
Completion and Evaluation Report.462 Chairman Morton asked how BC Hydro assesses whether
project objectives have been achieved in circumstances where the benefits are expected to
accrue over time. Mr. Darby explained that the vast majority of BC Hydro’s capital investments
are intended to mitigate risks and, therefore, benefits are realized immediately upon
completion.463 In such cases, “you get the benefits instantly” by virtue of the project having
been completed.464
286. Citing Sustaining capital projects related to polychlorinated biphenyl (“PCB”) reduction
or generation asset replacement as an example, Mr. Darby noted: “So once you’ve
implemented those projects and you get the benefits we wouldn’t track them over time
because the risk has been mitigated.”465 Mr. Darby explained that the same logic applies for
most of the Growth portion of BC Hydro’s capital portfolio, including spending related to
462 Exhibit B-1, Application, p. 6-68. 463 Tr. 11, p. 1861, ll. 9-16 (Darby); Exhibit B-6, CEABC IR 1.13.1. 464 Tr. 11, p. 1861, ll. 9-16 (Darby). 465 Tr. 11, p. 1861, ll. 19-21 (Darby).
- 128 -
301539.00025/94161307.1
customer connections and building capability of the system to allow for the retirement of end-
of-life assets. This leaves only a small portion of the growth portfolio for which benefits are
realized over time:
If we turn to the growth portion of the portfolio, we then noted it’s important to understand how that’s broken out. So a significant portion of that is customer connections, so again with those, those are customer driven. We’ll get the benefits as soon as the customer is connected, so again that isn’t something that we would track over time. A portion of those are benefits associated with building capability of the system so that we can potentially retire other assets. So for example I can use a substation as an example, we might build or grow an existing substation so that we can retire a separate substation somewhere else. So again that, while it’s in the growth portfolio you’d achieve the benefits as soon as you’ve done it or as soon as you’re retired the other asset. Because it’s—while in the growth portfolio it is still very much around risk avoidance and risk mitigation.
The only portion really where you’d be tracking benefits over time for growth perspective, I think, would be for example a DCAT where you’d be looking at if you build a line has the growth materialized and how does that achieve—how is that achieved over time.
So it’s mostly a very small portion of the portfolio as a whole, and I think we’ve captured that through the ongoing planning processes where as a cyclical nature we’ll look at how are things growing, do we need to add additional infrastructure to the system? And that is the little bit that we would have to look at over time in terms of getting the benefits. And I’m not sure that we would look at it specifically in terms of the benefits, I think it would just fold into the broader planning process.
But I do want to highlight that it’s very small portion of the portfolio. The vast majority of it is risk based and you get the benefits instantly.466
287. Further, to track benefits of projects that primarily create value (as opposed to mitigate
risk), BC Hydro is piloting a benefits-realization methodology.467
(f) BC Hydro Has Delivered its Capital Portfolio On Budget
288. BC Hydro has performed very well in delivering its Capital Plan.
466 Tr. 11, p. 1862, l. 8 to p. 1863, l. 18 (Darby). 467 Exhibit B-1, Application, pp. 6-149 to 6-151.
- 129 -
301539.00025/94161307.1
BC Hydro Delivered its Overall Portfolio Within 0.40% of Budget Over the Last Five Years
289. The key performance metric BC Hydro uses to evaluate the performance of delivering
capital projects is to compare the actual project costs for in-service projects to the Original
Approved Expected Cost (also called First Full Funding), over an aggregated five-year period.468
This performance measure is included in BC Hydro’s Service Plan, with a target of actual costs
falling within +5% / -5% of the Original Approved Expected Cost in aggregate, excluding project
reserve amounts. This metric is calculated using the results of all Generation and Transmission
projects as well as major Distribution and Properties projects.
290. Table 6-3 of the Application,469 reproduced below, shows that BC Hydro has met its
Service Plan metric over the past five years. For the most recent five year period shown below
(fiscal 2014 to fiscal 2018), BC Hydro delivered 493 projects within 0.40% of budget.470
Table 6-3 Five-Year Aggregate Project First Full Funding to Actual Cost (2010 to 2018)
Capital Infrastructure Project Delivery Project Budget to Actual Cost (2010 - 2018)
F2010-F2014 F2011-F2015 F2012-F2016 F2013-F2017 F2014-F2018
# of Projects 661 563 563 540 493
Original Aggregate Budget ($ millions)
3,330 3,924 6,491 6,363 6,936
Actual Aggregate Cost ($ millions)
3,184 3,852 6,479 6,303 6,963
Aggregate Cost Variance ($ millions)
-146.2 -71.8 -12.0 -59.9 27.9
% variance from original budget -4.39 -1.83 -0.18 -0.94 0.40
291. Consideration of five-year aggregate costs, rather than performance on an individual
project basis, is appropriate. The Original Approved Expected Cost is a P50 cost estimate for
most projects, such that there is an expectation that the estimate would be exceeded 50 per
468 Exhibit B-12, BCUC IR 2.228.3. 469 Exhibit B-1, Application, p. 6-11. 470 Negative variances indicate that the actual aggregate cost was less than (under) the original aggregate budget.
- 130 -
301539.00025/94161307.1
cent of the time.471 Probabilities dictate that there will be projects that are over budget and
others that are under budget.472 Therefore, delivering the portfolio of projects within the
capital performance metric targets is an indication that BC Hydro is prudently managing capital
expenditures on a portfolio basis.
A Strong Majority of Projects of All Sizes Come in Under Budget
292. BC Hydro also considers budget performance on individual projects,473 and the data on
individual projects tells the same story.
293. Approximately two-thirds (66.5%) of the 493 projects included in the analysis for BC
Hydro’s Service Plan metric had an actual cost that was less than the Original Approved
Expected Cost. The median project was 7.7% below the Original Approved Expected Cost. This
is illustrated in Figure 6-2 of the Application,474 which is reproduced below.
Figure 6-2 Summary of Actual Cost to Original Approved Expected Cost
471 Exhibit B-12, BCUC IR 2.228.3.1. 472 Exhibit B-5, BCUC IR 1.76.2. 473 Exhibit B-5, BCUC IR 1.76.2. 474 Exhibit B-1, Application, p. 6-12.
- 131 -
301539.00025/94161307.1
294. BC Hydro has performed well for projects of all sizes, including large projects. From
fiscal 2014 to fiscal 2018, the average variance between the Original Approved Expected Cost
and actual cost is:
● 1.20% for projects greater than $50 million;
● 0.27% for projects between $20 million and $50 million;
● 2.83% for projects between $5 million and $20 million; and
● -9.82% for projects less than $5 million.
295. These results are illustrated in Figure 6-3 of the Application,475 which is reproduced
below.
Figure 6-3 In-Service Projects (Expected Cost vs Actual Cost) – Fiscal 2014 to Fiscal 2018
475 Exhibit B-1, Application, p. 6-13.
- 132 -
301539.00025/94161307.1
KBU-Specific Measures Similarly Show Favourable Performance
296. The Project Delivery, Technology and Properties KBUs, which deliver the majority of BC
Hydro’s capital plan, have KBU-specific capital expenditure performance measures:476
● Project Delivery KBU - Number of projects placed in-service within the Original
Approved Expected Amount;
● Technology KBU - Percentage of Technology projects completed within the
Original Approved Expected Amount; and
● Properties KBU - Percentage of completed projects with total spend within the
Original Approved Expected Amount.
297. These KBUs have succeeded in meeting their capital performance measures in the
majority of years.477 For example, the Technology KBU completed a total of 94 projects
between fiscal 2016 and fiscal 2018, with total Original Approved Expected Amount of $135.1
million and total actual costs of $134.5 million. This represented a favourable variance of $0.6
million or -0.4%.478
Achievement of Service Plan Reliability Metrics is Another Indicator of Success
298. Mr. Kumar also cited, as another measure of success, the fact that BC Hydro is meeting
reliability metrics in the Service Plan:
I think the capital plan actually has a huge impact on our ability to deliver on the metrics and the service plan. So for example, if you look at the reliability [metrics] that we use in the service plan, like the SAFI and the SADI which is reflection of our frequency of outages and duration of outages, and even the forced factor that we use for our generation side. All those are driven by the success of development of a comprehensive capital plan and a maintenance plan. Because if you are not able to deliver comprehensive capital and
476 Exhibit B-12, BCUC IR 2.228.3. 477 Exhibit B-12, BCUC IR 2.228.3.2. 478 Exhibit B-1, Application, p, 6-148.
- 133 -
301539.00025/94161307.1
maintenance plans, you won’t be able to deliver on those metrics across the system.479
(g) Improvements in Technology Processes Have Brought Strong Results
299. BC Hydro’s practice of annually updating its Information Technology Delivery Standard
Practices,480 as described earlier in this Part, has improved the company’s delivery of its
Technology projects. This is shown in Figure 6-17 of the Application,481 reproduced below. It is
a summary of BC Hydro’s performance in delivering Technology capital projects, comparing
total approved First Full Funding for projects to total actual project costs.482
Figure 6-17 Number of Technology Projects Completed Within Total Approved First Full Funding Amount
300. The strong results above compare favourably to the industry generally. The Project
Management Institute’s Pulse of the Profession Report stated in its global project management
survey that 57% of technology projects are completed on budget.483
479 Tr. 11, p. 1852, l. 4 to p. 1853, l. 9 (Kumar); Tr. 11, p. 1857 l. 20 to p. 1858, l. 6 (Kumar). 480 Exhibit B-1, Application, p. 6-142. 481 Exhibit B-1, Application, p. 6-148. 482 For technology projects, the estimated accuracy range for the First Full Funding Approval cost is +15 per cent / -
10 per cent, which is equivalent to an AACE International Class 3 cost estimate. Exhibit B-6, CEC IR 1.64.2. 483 Exhibit B-1, Application, pp. 6-148 and 6-149.
- 134 -
301539.00025/94161307.1
301. BC Hydro is also piloting a Technology benefits realization process that will track the
realization of benefits claimed in the business cases of Technology projects.484 The benefits
realization methodology is being piloted on four of BC Hydro’s non-mandatory, business-driven
technology initiatives.485 BC Hydro provided detailed reports on the status of the Technology
projects in the pilot, including variances between benefits of the projects in their respective
businesses cases and benefits realized to date.486 BC Hydro expects the pilot to continue
through fiscal 2020. BC Hydro will then prepare a report, which it anticipates will be available
for review in the next RRA proceeding.487 BC Hydro expects to use its experience from the pilot
to develop a benefits realization process for all Technology projects.488
F. BC HYDRO’S CAPITAL MANAGEMENT PROCESSES HAVE BEEN ENDORSED BY THIRD PARTIES
302. Over the past decade, BC Hydro has demonstrated consistent and ongoing efforts to
improve its capital planning and delivery processes. The results of these efforts have been
recognized by third parties.489
● A December 2018 report by the Office of the Auditor General cited BC Hydro’s
advanced level of maturity in asset management practices:490
BC Hydro has a generally advanced level of maturity in asset management. Its success in this regard is a result of concerted effort over several years by a set of skilled professionals focused on ensuring that a reliable source of electrical power will be supported by a mature asset management practice.
The Auditor General, for the first time in many years, made no recommendations
for improvement.491
484 Exhibit B-1, Application, p. 6-149. 485 Exhibit B-1, Application, pp. 6-149 and 6-150. 486 Exhibit B-5, BCUC IR 1.114.2. 487 Exhibit B-13, CEC IR 2.127.1; Tr. 7, p. 853, ll. 11-22 (Morison); Tr. 7, p. 858, l. 23 to p. 859, l. 9 (Morison). 488 Exhibit B-6, CEC IR 1.66.2 and 1.66.3. 489 Exhibit B-6, CEC IR 1.4.2. 490 Exhibit B-1, Application, p. 6-9.
- 135 -
301539.00025/94161307.1
● In 2016, BC Hydro completed its second Organizational Project Management
Maturity Model Assessment, receiving the highest score among approximately
50 participating organizations from around the world. A highly experienced
auditor performed the independent assessment492 and BC Hydro received an
overall score of 91%. It achieved 100% in meeting best practices in project
management, program management and portfolio management.493
● In 2016, BC Hydro received the Project Management Office of the Year Award
from the Project Management Institute.494
303. Third-party recognition provides added assurance that BC Hydro’s capital planning and
delivery processes are mature and in line with industry best practices.
G. AMORTIZATION OF CAPITAL ADDITIONS REGULATORY ACCOUNT WILL ENSURE THAT CUSTOMERS ONLY PAY ACTUAL COSTS
304. The Amortization of Capital Additions Regulatory Account captures the differences
between the forecast and actual amortization of capital additions, with variances recovered
over the next test period.495 Actual capital expenditures and additions are expected to vary
from forecast due to factors such as changes in project timing and scope changes. The account
ensures that customers will only pay for actual costs when this occurs.
491 Exhibit B-1, Application, p. 6-9. The full report of the Independent Audit of Capital Asset Management in BC
Hydro is included as Appendix F of the Application. See also, Tr. 11, p. 1852, l. 4 to p. 1853, l. 9 (Kumar). 492 Exhibit B-6, CEC IR 1.45.4. The auditor who performed the assessment was Claudia M. Baca from Project
Management Consulting Services. Ms. Baca has Project Management Office experience in multiple industries across all disciplines of portfolio, program, and project management. Ms. Baca has written five books and co-authored papers on the effective development of Project Management Offices and was the chair and co-author for Managing Change in Organizations: A Practice Guide, published by the Project Management Institute.
493 Exhibit B-1, Application, p. 6-10; Exhibit B-6, CEC IR 1.45.2. 494 Exhibit B-1, Application, p. 6-10. 495 Exhibit B-1, Application, p. 7-36.
- 136 -
301539.00025/94161307.1
305. For clarity, the amortization of existing assets is not within the scope of the
Amortization of Capital Additions Regulatory Account; therefore, variances between forecast
and actual amortization of existing assets are to the account of the shareholder.496
H. EXPENDITURES ON RIP RAP FOR W.A.C. BENNETT DAM WERE PRUDENT
306. BC Hydro’s $700,000 expenditure for the riprap stockpile for the W.A.C. Bennett Dam
was prudently incurred and should be recovered in rates.
307. The BCUC rejected BC Hydro’s request for approval of $4.3 million for stockpile costs in
BC Hydro’s November 13, 2015 application to upgrade the riprap on the W.A.C. Bennett Dam.
The BCUC directed that, in future revenue requirement applications, BC Hydro should either
confirm that no expenditures relating to emergency stockpile riprap were included in the
revenue requirements or explain otherwise. BC Hydro followed the approach of providing a
rationale for its new plan and by seeking recovery of the associated costs in the Application.
This does not require any reconsideration of the BCUC’s past determinations.497
308. The actual cost for the riprap stockpile was $700,000, i.e., $3.6 million less than the
original amount.498 BC Hydro was able to realize significant cost savings on the stockpile costs
by using smaller rocks and restricting the volume to what it could produce from waste rock left
over from the quarrying of Class 1 riprap rock. BC Hydro also saved on overhead and interest
during construction, since the costs were much lower than expected and were expended at the
end of the project timeline.499
309. The stockpile will provide substantial benefits, which makes the $700,000 a highly cost-
effective investment. BC Hydro’s Application described the benefits as follows:500
496 Exhibit B-13, BCOAPO IR 2.136.1. Amortization variances on existing assets may arise as a result of a reduction
in the useful life of an asset or a write-off of an asset during a test period. 497 Exhibit B-5, BCUC IR 1.112.1. 498 Exhibit B-1, Application, pp. 6-90 and 6-91. 499 Exhibit B-5, BCUC IR 1.112.2. 500 Exhibit B-1, Application, pp. 6-92 and 6-93. See also, Exhibit B-5, BCUC IR 1.112.4.
- 137 -
301539.00025/94161307.1
• An inexpensive way to extend the life of the project – The expected 50 year life of the riprap could be extended by 50 to 100 per cent with proper maintenance and repair, utilizing limestone rock from the MES [Maintenance and Emergency Stockpile of riprap]. Any type of rock has natural variability, such as freeze/thaw splitting or breakage characteristics and a significant storm event could happen at any time, causing damage that could impact the underlying dam structure if it is not quickly identified and addressed. If BC Hydro was required to implement a reactive maintenance program, it would cost considerably more than $0.7 million;
• Higher quality rock – A pre-existing sandstone stockpile at the W.A.C. Bennett Dam is not acceptable for maintenance or emergency purposes. Sandstone riprap does not have the same life expectancy as limestone riprap and repairs using sandstone riprap would require subsequent replacement in the future, ultimately leading to higher costs. A temporary fix, in an emergency situation, followed by a subsequent replacement project would also likely require reservoir re operation which would result in lost revenue or higher energy costs from other sources;
• A Readily Available Source of Limestone Riprap – As the Riprap Upgrade project has now been completed, the quarry would need to be re-opened to acquire additional limestone rock, which would require additional permitting, consultation with First Nations, and securing a contractor willing to take on the relatively small production. This would likely take one to two years, or more, to complete. While there is a limestone quarry located 170 kilometres from the W.A.C. Bennett Dam, quarrying from this site would also require lengthy consultation, permitting and procurement processes; and
• Best practice for maintenance and emergency purposes – In 2018, BC Hydro polled the members of the Center for Energy Advancement through Technical Innovation (CEATI) Dam Safety Interest Group to confirm whether it was best practice to stockpile rock for maintenance and emergency purposes. BC Hydro received 20 responses, and all respondents, except for those that have ready access to emergency quarry supplies and transportation, indicated that they also maintain maintenance and emergency stockpiles and that this is considered best practice. BC Hydro does not have ready access to maintenance and emergency quarry supplies for the W.A.C. Bennett Dam.
310. The evidence that this expenditure is cost-effective and beneficial for customers is
compelling, and the costs should be recovered in rates.
- 138 -
301539.00025/94161307.1
I. VARIANCE OF DIRECTIVE 3 IS WARRANTED AND MIN TO LNG CANADA PROJECT IS EXEMPT
311. BC Hydro has requested that the BCUC reconsider and vary Directive 3 of the BCUC’s
Decision on the Previous Application501 to remove the direction to BC Hydro to file a CPCN
application for the Northwest Substation Upgrade project, which was designed to serve LNG
Canada’s load interconnection request. The BCUC has requested that BC Hydro address in
argument: “Whether the Minette Station to LNG Canada Interconnection project meets the
requirements of the Transmission Upgrade Exemption Regulation, as amended by B.C. Reg.
160/2018, to exempt the project from Part 3 of the Utilities Commission Act”.502
312. The original Northwest Substation Upgrade project that was the subject of Directive 3
has been cancelled due to LNG Canada splitting its load interconnection request into two
phases. The new MIN to LNG Canada Interconnection project facilitates the first phase of the
LNG Canada load interconnection request and includes scope items that were formerly part of
the exempt Northwest Substation Upgrade Project.503 The capital expenditures for the Test
Period for the MIN to LNG Canada Interconnection project are $28.2 million in fiscal 2020 and
$26.6 million in fiscal 2021.504 Under its Facilities Agreement with BC Hydro, LNG Canada will
provide security for the capacitor banks and substation expansion and a cash payment for the
double-circuit transmission line from MIN to LNG Canada.505 Since the in-service date is after
the Test Period, the project has no impact on the Test Period revenue requirements.506
501 Exhibit B-1, Application, p. 32. 502 Exhibit A-31. 503 Exhibit B-5, BCUC IR 1.1.1; Tr. 12, p. 2291, ll. 6-14 (Holland). 504 Exhibit B-1, page 4 of Appendix I of the Application, (Transmission, Line 20, IPID 93786). 505 Tr. 12, p. 2292, ll. 8-15 (Kumar); Exhibit B-57, BC Hydro Undertaking No. 43. 506 Exhibit B-5, BCUC IR 1.1.9.
- 139 -
301539.00025/94161307.1
313. The MIN to LNG Canada Interconnection project is exempt pursuant to the Transmission
Upgrade Exemption Regulation.507 Specifically:
● Section 2(1)(e) of the Transmission Upgrade Exemption Regulation exempts,
from Part 3 of the UCA, the addition of shunt capacitors at the Minette
substation, including associated protection and control equipment, which is part
of the MIN to LNG Canada Interconnection project.
● The MIN to LNG Project is necessary to provide service to LNG Canada’s LNG
facility in the District of Kitimat. Section 2(2) of the Transmission Upgrade
Exemption Regulation exempts from Part 3 of the UCA: “the construction or
operation of a plant or system, or an upgrade or extension of either, to provide
service for the following: (a) an LNG facility in the vicinity of the District of
Kitimat; (b) a facility necessary for the construction of an LNG facility in the
vicinity of the District of Kitimat.” Further to the requirement in section 2(3) of
the Transmission Upgrade Exemption Regulation, BC Hydro reasonably expects
that the MIN to LNG Canada Interconnection project will be in service before
October 1, 2025.
314. LNG Canada has yet to make a decision to proceed with phase 2 of its load
interconnection request.508 BC Hydro’s projects to serve phase 2 would also be exempt.509
315. BC Hydro acknowledges that the cancellation of the Northwest Substation Upgrade
project means that the directive to file a CPCN for that project is no longer applicable.510
However, varying Directive 3 would clarify that no CPCN would be required or expected by the
BCUC for the original project, for the MIN to LNG Canada interconnection, or for other potential
507 Exhibit B-12, BCUC IR 2.247.2. 508 Tr. 12, p. 2293, ll. 3-12 (Holland and Daschuk); Tr. 13, p. 2461, l. 18 to p. 2462, l. 8 (Holland). 509 Exhibit B-12, BCUC IR 2.247.2. 510 Exhibit B-5, BCUC IR 1.1.1.
- 140 -
301539.00025/94161307.1
projects associated with LNG Canada’s updated request that are expected to come into service
before October 1, 2025.
J. BC HYDRO HAS ANSWERED SPECIFIC ISSUES RAISED
316. The subsections below address issues raised in the information requests and at the oral
hearing.
(a) The PRES Project is a Prescribed Undertaking
317. The PRES project511 is a prescribed undertaking under section 18 of the Clean Energy Act
and section 4(2) of the GGRR.512
318. Section 4(2) of the GGRR describes a class of prescribed undertaking, as follows:
(2) A public utility’s undertaking that is in a class defined as follows is a prescribed undertaking for the purposes of section 18 of the Act:
(a) for the purpose of reducing greenhouse gas emissions in British Columbia, the public utility constructs or operates an electricity transmission or distribution facility, or provides for temporary generation until the completion of the construction of the facility, in northeast British Columbia primarily to provide electricity from the authority to
(i) a producer, as defined in section 1 (1) of the Petroleum and Natural Gas Royalty and Freehold Production Tax Regulation, B.C. Reg. 495/92,513 or
(ii) an owner or operator of a natural gas processing plant;
(b) the public utility reasonably expects, on the date the public utility decides to carry out the undertaking, that the facility will have an in-service date no later than December 31, 2022.
511 This project is summarized in Exhibit B-1, Appendix J, p. 71. 512 Exhibit B-5, BCUC IR 1.119.2. 513 In the Petroleum and Natural Gas Royalty and Freehold Production Tax Regulation, "producer" means (a) a
holder of a location who markets or otherwise disposes of oil, natural gas or both, that has been produced by (i) the holder of the location, or (ii) a person authorized to do so by the holder of the location, and (b) a person authorized by a holder of a location to produce and market or otherwise dispose of, on the holder's behalf, oil, natural gas or both.
- 141 -
301539.00025/94161307.1
319. The PRES project satisfies the in-service date requirements of section 4(2)(b) of the
GGRR. The planned in-service date for the PRES project is October 2021.514
320. Consistent with section 4(2)(a) of the GGRR, BC Hydro’s written evidence and testimony
is that the purpose of the PRES project is to construct and operate electricity transmission
facilities to reduce GHG emissions in B.C. by enabling the electrification of natural gas
production, processing and compression in the South Peace region.515 The majority of the
existing and forecast load in this region is from natural gas producers.516 The PRES project will
reduce GHG emissions by targeting these new loads, and BC Hydro estimates that GHG
reductions will be 560 tonnes of CO2e per GWh.517 In the absence of the PRES project, these
new gas processing loads would have no choice but to combust fossil fuels for power supply,
resulting in a significant increase in greenhouse gas emissions in the province.518 As an
additional benefit, the PRES project also increases reliability for existing customers.519
321. There is abundant evidence that the PRES project is consistent with and driven by
provincial and federal GHG policy. The Government of B.C. has expressed its support for the
PRES project in that context:
(a) In August 2017, the provincial government’s Mandate Letter identified
“advancing government’s climate action strategies including through fuel
switching and electrification initiatives in the transportation, oil and gas, and
other sectors” as a key responsibility for BC Hydro. This mandate placed an
expectation on BC Hydro that it should be in a position to meet the
electrification needs of customers in the Peace Region, as accomplished by the
PRES project.520
514 Exhibit B-23, CEABC IR 4.59.1; Exhibit B-5, BCUC IR 1.119.2. 515 Exhibit B-12, BCUC IR 2.250.1; Tr. 7, p. 1064, ll. 2-12 (Fraser); Tr. 12, p. 2312, l. 23 to p. 2313, l. 18 (Kumar). 516 Exhibit B-5, BCUC IR 1.119.3. 517 Exhibit B-23, GJOSHE IR 4.1.8. 518 Exhibit B-5, BCUC IR 1.119.1. 519 Exhibit B-12, BCUC IR 2.250.7; Tr. 12, p. 2262, l. 19 to p. 2263, l. 2 (Kumar). 520 Exhibit B-1, Appendix J, Capital Expenditures > $20 million, Attachment 1, p. 71.
- 142 -
301539.00025/94161307.1
(b) The CleanBC Plan, released in December 2018, included the goal of increasing
access to clean electricity for planned natural gas production in the Peace Region
and increasing access to clean electricity for large operations with new
transmission lines and interconnectivity to existing lines.521 The PRES project is
explicitly referred to in the CleanBC Plan, at page 43: “the Peace Region
Electricity Supply (PRES) project will make it easier to replace natural gas
combustion with electricity. Switching to clean electricity will make B.C.’s natural
gas the cleanest in the world.”
(c) In April 2019, the Government of Canada announced that it is providing up to
$83.6 million towards the PRES project through the Investing in Canada Plan,
which is designed to facilitate the expansion of transmission systems that result
in the reduction of greenhouse gas emissions.522
(d) In August 2019, the Government of Canada and the Government of B.C.
announced a Memorandum of Understanding to support the electrification of
the natural gas sector in British Columbia (the “MOU”). The preamble of the
MOU states: “The governments of British Columbia and Canada have a shared
interest in electrifying natural gas production and liquefied natural gas
production to build Canada’s clean energy brand as a supplier of the world’s
cleanest natural gas.” The MOU refers to the PRES project as an example of the
investments that BC has been making in its grid to enable electrification of the
natural gas industry.523
521 CleanBC Plan, p. 9.
Online: https://blog.gov.bc.ca/app/uploads/sites/436/2019/02/CleanBC_Full_Report_Updated_Mar2019.pdf. 522 Exhibit B-23, INCE IR 4.16, referencing the Memorandum of Understanding between the Government of Canada
and the Government of B.C. to support the electrification of the natural gas sector in British Columbia, online: https://pm.gc.ca/en/news/backgrounders/2019/08/29/memorandum-understanding-between-government-canada-and-government; Tr. 11, p. 2098, ll. 5-14 (Daschuk and Holland).
523 Exhibit B-23, INCE IR 4.16, referencing the Memorandum of Understanding between the Government of Canada and the Government of B.C. to support the electrification of the natural gas sector in British Columbia, online:
https://pm.gc.ca/en/news/backgrounders/2019/08/29/memorandum-understanding-between-government-canada-and-government.
- 143 -
301539.00025/94161307.1
322. BC Hydro submits that the BCUC must allow BC Hydro to recover the costs of the PRES
project pursuant to section 18 of the Clean Energy Act and the GGRR.
(b) Bear Mountain Terminal to Dawson Creek Transmission Voltage Conversion and North Montney – Transmission Development Projects May Also be Prescribed Undertakings
323. BC Hydro also identified two other projects related to transmission system upgrades for
the LNG and oil and gas sectors in the Peace Region: the Bear Mountain Terminal to Dawson
Creek Transmission Voltage Conversion, and the North Montney Transmission Development.524
BC Hydro advanced these two projects, along with the Prince George to Terrace Capacitors
project, as ex-plan525 projects in order to:526
● Encourage new load growth and revenue, and ensure that BC Hydro is able to
provide transmission services in the timeline required for customer need and
desire to electrify their operations;527
● Support the CleanBC Plan to provide clean electricity to planned natural gas and
LNG production;528 and
● Access federal investment to reduce costs to BC Hydro’s customers.529
324. Ms. Pinksen explained why they were brought forward as ex-plan projects:
So our capital plan is updated annually, but we use the ex-plan process when we find in between those cycles of update, we need to initiate the project prior to the approval of the next plan. And so these projects were initiated between the approval of the Fiscal ‘20 capital plan, and the Fiscal ‘21 capital plan. And they were brought forward to our capital delivery management committee, and presented as to why it was prudent to initiate them at that time. And it was
524 Exhibit B-12, BCUC IR 2.254.2 and 2.247.6.1. 525 Tr. 12, 2272, l. 12 to p. 2275, l. 10 (Pinksen). 526 Exhibit B-12, BCUC IR 2.254.2. 527 Tr. 9, p. 1514, l. 21 to p. 1515, l. 8 (Rich); Tr. 9, p. 1517, ll. 12-21 (Rich). 528 Tr. 9, p. 1517, ll. 12-21 (Rich). 529 Tr. 12, p. 2275, l. 24 to p. 2276, l. 13 (Daschuk and Kumar).
- 144 -
301539.00025/94161307.1
really about preserving the potential in-service date, and needing to initiate the project as opposed to waiting for the next cycle.530
325. BC Hydro has advanced the projects to allow for more meaningful discussions with
potential customers about their load and electrification, while minimizing cost outlay.531
326. Both these projects are referenced in the MOU as projects that the Canada-British
Columbia Clean Power Planning Committee will advance.532 In light of the purpose of these two
projects, they may qualify as prescribed undertakings pursuant to section 18 of the Clean
Energy Act, and as such may be exempt from Part 3 of the UCA.533
327. Chairman Morton commented during the hearing that it would be useful if there was a
mechanism for the BCUC assess to the applicability of the GGRR in advance.534 Mr. O’Riley
expressed openness to look at the issue.535 BC Hydro confirms that, following this proceeding,
it will be considering the legal and practical issues around Chairman Morton’s question and will
initiate further discussions with BCUC Staff to explore potential options.
(c) Electric Vehicle Investments are Added to Rate Base per Direction No. 8
328. The BCUC requested that BC Hydro address in its argument the following:
Whether British Columbia Hydro and Power Authority’s investments in electric vehicle charging infrastructure should be included in rate base during the current test period and recovered from ratepayers or be separately tracked and excluded from rate base until the British Columbia Utilities Commission directs otherwise, given the developing landscape of the electric vehicle charging stations market in BC.536
530 Tr. 2274, ll. 12-23 (Pinksen). 531 Tr. 12, p. 2281, ll. 5-23 (Kumar). 532 The MOU is available online at:
https://pm.gc.ca/en/news/backgrounders/2019/08/29/memorandum-understanding-between-government-canada-and-government.
533 Exhibit B-12, BCUC IR 2.250.3. 534 Tr. 6, p. 742, l. 20 to p. 743, l. 14 (Morton). 535 Tr. 6, p 743, l. 15 to p. 744, l. 7 (O’Riley). 536 Exhibit A-31.
- 145 -
301539.00025/94161307.1
329. BC Hydro’s capital additions related electric vehicle charging stations, net of any
contribution from Government or third parties,537 are included in rate base pursuant to section
1 of Direction No. 8.538 Given the effect of Direction No. 8, the BCUC cannot direct BC Hydro to
exclude its investments in electric vehicle charging stations from its rate base.
330. However, amounts included or excluded from rate base have no practical effect during
the Test Period because BC Hydro’s net income is not dependent on a specific rate base
amount. Rather, BC Hydro’s net income is currently prescribed by section 3 of Direction No. 8
to be a specific dollar amount of $712 million per fiscal year in each of fiscal 2020 and fiscal
2021.539
331. Whether investments in electric vehicle charging stations should be included in rate
base in the future should not be considered in this proceeding. First, the matter has no
relevance to the Test Period revenue requirements or rates. Second, the BCUC has held an
Inquiry into the Regulation of Electric Vehicle Charging Service and has made its
recommendations to Government in its Phase Two Report.540 At this time, BC Hydro is
expecting Government to respond with legislation clarifying the role of BC Hydro in the electric
vehicle area. Until this clarification is provided, it would be inappropriate to deny recovery in
rates or to make determinations on the treatment of future investment in electric vehicle
charging stations.
(d) BC Hydro is Managing Cybersecurity Risks
332. Cybersecurity risk is a significant issue for BC Hydro. The evidence, discussed below,
demonstrates that BC Hydro has been managing that risk appropriately. It is likely, however,
537 Exhibit B-5, BCUC IR 1.122.4. 538 Direction No. 8. 539 Direction No. 8. 540 Inquiry into the Regulation of Electric Vehicle Charging Service, Phase Two Report, dated June 24, 2019. Online:
https://www.bcuc.com/Documents/Proceedings/2019/DOC_54345_BCUC%20EV%20Inquiry%20Phase%20Two%20Report-web.pdf.
- 146 -
301539.00025/94161307.1
that additional investment will be required following the Test Period given the increasing
challenges faced by the company.541
333. In response to increasing cybersecurity risks, BC Hydro continually assesses
cybersecurity risks and its management of those risks, improves security processes, and
assesses its resourcing requirements.542 As an illustration of these efforts, BC Hydro is
responding to recommendations from internal and third party audits and, in particular, will be
expanding investment and efforts on assets not covered by MRS.
Strong Governance Structures and Best Practices Underpin Cybersecurity Efforts
334. The foundation for BC Hydro’s cybersecurity is strong governance structures and
following best practices:
● BC Hydro’s Security Policy and Standards follow the International Organization
for Standardization 27001 Framework. BC Hydro also follows the Center for
Internet Security standards for baseline configurations of devices and operating
systems.543
● There are 40 FTEs across BC Hydro with cybersecurity work as their main job
function.544 Their work is overseen by two steering committees: the MRS
Steering Committee and the Cybersecurity Oversight Committee.545 The former
is accountable for ensuring BC Hydro meets all MRS compliance requirements,546
while the latter is accountable for enterprise-wide cybersecurity of all
Technology systems including Critical Infrastructure Protection (CIP)
cybersecurity. BC Hydro’s Chief Information Officer (CIO) sits on both the
541 Tr. 5, p. 358, l. 21 to p. 359, l. 8 (O’Riley); Tr. 7, p. 981, l. 2 to p. 982, l. 6 (Morison). 542 Tr. 6, p. 730, ll. 8-19 (Wong). 543 Exhibit B-5, BCUC IR 1.123.6. 544 Exhibit B-5, BCUC IR 1.123.8. 545 Exhibit B-5, BCUC IR 1.123.9. 546 BC Hydro’s Senior Vice President of Safety and Compliance is designated as BC Hydro’s Compliance Officer, is
responsible for BC Hydro’s MRS compliance program and leads the MRS Steering Committee, which provides governance for the MRS program.
- 147 -
301539.00025/94161307.1
cybersecurity and MRS governance committees, to coordinate the efforts of
these governance functions.547
● BC Hydro conducts regular internal and external compliance reviews, has a
cybersecurity awareness program for employees, and requires vendors to
complete an annual review of BC Hydro’s cybersecurity policies and standards.548
● BC Hydro tests its Cybersecurity Incident Response Plan at least once every 15
months, participates in bi-annual mock cyber-attack exercises, and conducts
quarterly IT Service Continuity Management Plan table top exercises.549
BC Hydro Has Made Ongoing Investments in Cybersecurity
335. Another aspect of maintaining effective cybersecurity is ongoing investment. BC Hydro
has made significant investments to upgrade electronic and physical security for equipment
used to control and monitor industrial control systems connected to the bulk electric system to
meet critical infrastructure standards prescribed by NERC. As of March 31, 2019, BC Hydro has
invested $30.2 million on the NERC CIP version 5 compliance initiative.550 BC Hydro forecast
$17.3 million in capital expenditures on the NERC CIP version 5, version 6 and version 7
initiatives over the test period.551 BC Hydro applies learnings from the MRS program to other
assets, as appropriate.552
336. BC Hydro also continuously improves security processes and implements new controls
through active projects. For example, BC Hydro improved security controls for transient and
removable devices in its facilities through the NERC CIP version 6 project, is improving its
Cybersecurity Incident Response Plan, and is investigating the feasibility of a 24x7 Cybersecurity
547 Exhibit B-12, BCUC IRs 2.257.15 to 2.257.18. 548 Exhibit B-5, BCUC IR 1.123.7. 549 Exhibit B-12, BCUC IR 2.257.28. 550 Exhibit B-5, BCUC IR 1.123.3; Exhibit B-12, BCUC IR 2.257.9. 551 Exhibit B-5, BCUC IR 1.123.12. 552 Exhibit B-12, BCUC IR 2.257.11.
- 148 -
301539.00025/94161307.1
Operations Center.553 BC Hydro is also completing the Station Gateway System which will
replace manual processes with an inventory of cyber assets with the capability to automatically
collect configuration data from BC Hydro’s industrial control systems.554 This project will
reduce the risk of cybersecurity incidents and compliance violations and improve efficiency of
sustainment processes in transmission stations related to maintaining the CIP standards.555
BC Hydro Performs Ongoing Risk Assessment and Implements Audit Recommendations
337. BC Hydro maintains a cybersecurity risk register, which includes key cybersecurity
threats and a qualitative risk assessment. BC Hydro assesses its cybersecurity risks and its
management of those risks through the advice of third-party experts and its own audits.556
338. The Marsh Data Breach Quantification report and the Bitsight assessment of BC Hydro’s
cybersecurity profile are good examples of BC Hydro’s use of external expertise.557
339. BC Hydro’s 2016 internal audit provided a baseline for measuring the overall
effectiveness of the cybersecurity program, and BC Hydro implemented the internal audit
recommendations.558 BC Hydro’s 2019 Internal Cybersecurity Audit focused on enterprise-wide
and critical areas of threat vulnerability management and incident response, and a newly
emerging threat in vendor management.559 The 2019 audit generally affirmed that BC Hydro is
on the right track when it comes to managing cybersecurity risk, but made some
recommendations that BC Hydro is implementing.560 The audit found that:561
553 Exhibit B-12, BCUC IR 2.257.5. 554 Exhibit B-12, BCUC IR 2.257.13. 555 Exhibit B-12, BCUC IR 2.257.13. 556 Exhibit B-12, BCUC IR 2.257.2.2. 557 Exhibit B-5, BCUC IR 1.123.4. 558 Exhibit B-5, BCUC IR 1.123.5. 559 Exhibit B-12, BCUC IR 2.257.21.3. 560 Exhibit B-5, BCUC IR 1.123.5. 561 Exhibit B-12, BCUC IR 2.257.18.2. The 2019 audit is attached as Confidential Attachment 1 to BCUC IR 2.257.21.
- 149 -
301539.00025/94161307.1
● Effective processes are in place to detect and respond to cybersecurity incidents
in the Information Technology and NERC CIP regulated Operational Technology
environments;
● Potential cybersecurity incidents are directed to Cybersecurity Operations for
immediate triage and analysis. Handling of declared incidents is prioritized based
on urgency and impact; and
● Large scale, joint incident response exercises occur on a regular basis with key
participants across the enterprise. These exercises strengthen BC Hydro’s
capability to identify and respond to cyber incidents and receive appropriate
support from senior management and participating business units.
340. The Auditor General also conducted a review of BC Hydro’s cybersecurity efforts related
to Industrial Control Systems, including those not covered by MRS. The Auditor General
generally found that BC Hydro was doing well in managing cybersecurity risks on the parts of
system covered by MRS, but needs to increase effort on parts that are not subject to MRS.
Consistent with BC Hydro’s risk-based and compliance approach to cybersecurity and
information protection,562 BC Hydro has focussed on meeting mandatory requirements on
higher-risk bulk electric system assets. The facilities not under MRS are lower risk because
disruptions in non-bulk electric system facilities are expected to have low or no impact on the
interconnected grid. Many are in remote areas with very limited network connection, and
many serve a relatively small number of customers compared to other facilities.563 However, in
response to the audit, BC Hydro is conducting a risk assessment of the environments identified
by the Auditor General’s report. Following the results of this assessment, BC Hydro will
prioritize investments and efforts that will address the audit recommendations, including
extending MRS requirements to assets not covered by those standards as appropriate.564
562 Exhibit B-1, Appendix L, BC Hydro Technology Strategy and 5-Year Plan, p. 15; Exhibit B-12, BCUC IR 2.257.10.1. 563 Exhibit B-5, BCUC IRs 1.123.1 and 1.123.1.1. 564 Exhibit B-5, BCUC IR 1.123.1; Exhibit B-12, BCUC IR 2.257.10.
- 150 -
301539.00025/94161307.1
Cybersecurity Risk Management Can Be Expected to Drive Higher Costs in the Future
341. The audit results, reinforced by BC Hydro’s ability to handle cybersecurity incidents to
date, demonstrate that BC Hydro’s cybersecurity response structure, investments, and
processes are meeting current needs.565 However, there is no question that cybersecurity
complexity and risks are increasing due to:
(a) the increasing number and complexity of threats;
(b) the expansion of cybersecurity monitoring of BC Hydro’s power system and the
resulting alerts; and
(c) the further digitization of power systems.566
342. BC Hydro will be assessing its current capabilities in fiscal 2020, which may result in
recommendations with regards to facilities, services, processes, tools, and people.567
(e) BC Hydro is Appropriately Coordinating Projects in the Same Location and Individual Projects at the Same Location Should Not Be Combined
343. BC Hydro was asked questions directed at determining whether the company takes
appropriate steps to coordinate projects in the same location. The evidence, discussed below,
demonstrates that BC Hydro coordinates projects when it is operationally necessary or where
there are opportunities for efficiencies and/or risk reduction. It avoids otherwise entangling
disparate projects in a way that would increase risk.568 BC Hydro submits that this approach is
appropriate.
BC Hydro Avails Itself of Opportunities for Efficiency and/or Risk Reduction
344. BC Hydro explained that it coordinates projects to take advantage of, for example,
common outages, common procurement strategies and planned reservoir operations.
565 Exhibit B-12, BCUC IR 2.257.18 series and 2.257.27; Tr. 7, p. 981, ll. 2-4 (Morison). 566 Exhibit B-12, BCUC IR 2.257.18.3; Tr. 8A, p. 1117, ll. 10-14 (Morison). 567 Exhibit B-12, BCUC IR 2.257.18 series; Tr. 7, p. 981, l. 2 to p. 982, l. 6 (Morison). 568 Exhibit B-12, BCUC IRs 2.252.3 and 2.252.4.
- 151 -
301539.00025/94161307.1
Coordinated project planning and construction activities can reduce risk and achieve
efficiencies where there is a need for managing items such as the use of site laydown space, the
use of common resources and the risk related to asset interfaces. For example, BC Hydro has
coordinated the MCA 1-4 Transformer Replacement and the MCA Digital Controls projects
because they take place in the powerhouse, have some common interfaces and share an
outage.569
345. BC Hydro also considers strategic or planning decisions related to the work on a single
facility in its facility asset plans, examples of which are included in Attachment K of the
Application. This approach enables BC Hydro to optimize capital resources across all sites and
all asset types.
Disparate Projects at Same Site Should Not Be Combined
346. While opportunities for coordination should be (and are) taken, individual projects at
the same site should not be combined into a single project or “Program of Projects”. The
evidence is that this approach would be detrimental.
347. BC Hydro explained how projects at a single site can have different drivers and
requirements:
The projects taking place at a single site do not constitute a Program of Projects. A Program of Projects is intended for situations where a common business driver results in multiple similar projects in response, all of which together achieve the common objectives articulated in the business case. The projects at a single site, however, can vary greatly in their nature, ranging from heavy civil construction, such as blasting and quarrying, to upgrades of mechanical systems such as gates and hoists, to installation of sophisticated electronic control and communication systems.
BC Hydro does not view all individual projects at a single site to be a single overarching project. A project is time-bound, one time undertakings to buy, to replace, to maintain, or to rehabilitate a distinct asset, a set of assets, or a group of assets to achieve specified set of objectives. In contrast, the projects planned
569 Exhibit B-12, BCUC IR 2.252.3.
- 152 -
301539.00025/94161307.1
for, and delivered at, a single site can be numerous, with new projects continually being identified over time, with varying objectives.570
348. BC Hydro has shown that projects at a single site can differ drastically, have different
drivers, and lack any interdependencies or opportunities for coordination.571 BC Hydro
explained that managing such disparate activities as a single project would increase risk, not
reduce it. It would require greater supervision and management effort, would extend
timelines, and would make project estimates less certain.572
349. Ms. Pinksen explained that BC Hydro’s internal project management practices and
policies ensure that projects are appropriately defined:
So what we demonstrated in [the Review of Capital Expenditures and Projects] proceeding was that we really use our internal capital management practices and particularly our financial approval practices to ensure that what we’re defining as a project has a standalone benefit. And what that means is that when we put that project in service, we are not dependent on any future project to ensure that we’re delivering what we anticipated under that project.
And so it’s really through our financial policy that we’re performing that oversight and governance. And so I think maybe what Mr. Darby can speak to then is around how, when we look at the facility, either the individual facilities on the Bridge River system, that we are looking at ensuring that each of these defined projects are undertaken, will deliver their own benefit and we aren’t making any formal financial commitment to require a future project in order to deliver those benefits.
And I think really what we explored with the panel in the capital expenditures and projects review, that it was the level at which we approved projects internally at BC Hydro is the appropriate way for us to then present those projects to the Commission for approval, either through a CPCN or section 44.2.573
350. In its Order No. G-313-29 and Decision on the Review of Capital Expenditures and
Projects, the BCUC agreed with BC Hydro’s proposals with regards to how to review projects:
570 Exhibit B-12, BCUC IR 2.252.4. 571 Exhibit B-12, BCUC IRs 2.252.1, 252.2, 2.252.3, 2.253.1 and 2.253.3. 572 Exhibit B-12, BCUC IR 2.253.3. 573 Tr. 13, p. 2448, l. 18 to p. 2449, l. 21 (Pinksen).
- 153 -
301539.00025/94161307.1
Subject to the additional information requirements identified below, the Panel finds BC Hydro’s proposals related to projects and programs information to be filed with the BCUC are appropriate.
…
Regarding the question of whether the individual project, as defined by BC Hydro, is the appropriate level for the BCUC’s review of capital expenditures, as noted above, the Panel considers it optimal for the BCUC to review capital expenditures at the same level they are required to be approved under BC Hydro’s implemented capital expenditure approval policies (i.e. its Financial Approval Authority Limits).574
351. While the BCUC indicated that “the BCUC can inquire into the potential linkages
between projects and can order joint CPCNs for extension projects where the BCUC considers
this is appropriate,”575 there are no projects identified in this proceeding where a joint CPCN
would be appropriate.
352. A good example of a situation where treating disparate activities at a single site as a
single project would be detrimental is the MCA Townsite Augment Accommodations Capacity
project and the MCA Recoat Intake Maintenance Gates & Draft Tube Maintenance project.
These projects have different technical requirements, different construction timing and
durations, use very different design and supply vendors, are located in different areas at the
site, and have very limited use of common project resources.576
353. The projects on the Bridge River system are another example of disparate projects that
should be managed separately. These projects are in various states of the project lifecycle577
and each addresses specific risks to specific assets.578 As explained above, each of these
574 BC Hydro Review of the Regulatory Oversight of Capital Expenditures and Projects, Decision and Order No. G-
313-19, December 2, 2019, at pp. 22-23.
Online: https://www.bcuc.com/Documents/Proceedings/2019/DOC_56448_2019-12-02-BCH-Review-of-BCH-Capital-Expenditures-Decision.pdf (“Capital Expenditures Decision”).
575 Capital Expenditures Decision, p. 24. 576 Exhibit B-12, BCUC IR 2.252.3. 577 Tr. 13, p. 2447, l. 23 to p. 2448, l. 1 (Darby). 578 Tr. 13, p. 2450, ll. 10-21 (Darby).
- 154 -
301539.00025/94161307.1
projects will vary greatly in their nature and combining them would increase risk and
uncertainty.
354. In particular, the Bridge River 1 Replace Units 1 to 4 Generators project (“Bridge 1 to 4
Project”) and the Bridge River Transmission Project should not be linked. While the Bridge
River Transmission Project is needed to use the extra 8 MW of capacity resulting from the
Bridge River 1 to 4 Project (based on operations within the existing water licence), this does not
represent a substantial linkage between the projects. In fact, the need for each project is
independent of the other:
(a) The Bridge River 1 to 4 Project is a Sustaining capital project driven by asset
condition and the need for reliable water conveyance and generation. The
project description in Appendix J reads:579
The purpose of the project is to improve generation reliability due to the Poor and Unsatisfactory health conditions of the Bridge River 1 Generating Facility Units 1 to 4 generators and related equipment, and to provide reliable water conveyance capacity within the Bridge River system.
As Mr. Darby stated: “There just happens to be an incidental opportunity to
increase the capacity of the plant and I believe it’s by about eight megawatts. So
it’s not a lot.”580
(b) The Bridge River Transmission Project is needed to support the area as a whole,
even without the 8 MW from the Bridge River 1 to 4 Project. As set out in the
project description, the capacity of 2L90 is already insufficient to accommodate
Bridge River generation, and BC Hydro is currently restricting Bridge River
generation to prevent overloads of 2L90.581 As Mr. Kumar and Mr. Darby
explained, the transmission system was sufficient for BC Hydro’s Bridge River
579 Exhibit B-1, Appendix J, p. 50. 580 Tr. 13, p. 2458, ll. 14-16 (Darby). 581 Exhibit B-1, Appendix J, Capital Expenditures > $20 million, Attachment 1, p. 75.
- 155 -
301539.00025/94161307.1
generation, but BC Hydro has added about 400 MW of IPP generation in the area
with an additional 50 MW of IPP generation forecast.582 Therefore, the Bridge
River Transmission Project is needed even if the 8MW from the Bridge River 1 to
4 Project were not to be added.
355. Consistent with BC Hydro’s approved Capital Filing Guidelines, BC Hydro plans to file a
section 44.2 application for the Bridge River 1 to 4 Project.583 BC Hydro will also file a CPCN for
the Bridge River Transmission Project if it is over $100 million. This will give the BCUC an
opportunity to review BC Hydro’s most significant investment in this system, and the broader
context of the Bridge River system as a whole.584
(f) Strategic Property Purchases in Vancouver Support Substation Projects and Will Be Included in Future Substation CPCN Applications
356. BC Hydro made two strategic property purchases in Vancouver to advance two
substation construction projects, for which BC Hydro will file separate CPCN applications to the
BCUC in due course. In each case, customers are well-served by BC Hydro’s decision to
purchase the properties in advance of CPCN proceedings. In the CPCN proceedings, the BCUC
will have the opportunity to review all alternatives for the substations.
DVES: West End Substation - Property Purchase
357. There are two components to the DVES: West End Strategic Property Purchase project:
the purchase of the subsurface land at Lord Roberts Annex School and the acquisition of the
distribution and transmission statutory rights-of-way through Nelson Park. Neither of these
purchases are amortized for accounting purposes, so there will be no amortization expense
over the Test Period.585
582 Tr. 13, p. 2453, l. 8 to p. 2458, l. 18 (Kumar and Darby). 583 Exhibit B-5, BCUC IR 1.115.2. The project will result only in the restoration of the capacity of the existing plant.
This project is described in detail in Exhibit B-1, Appendix I, p. 52. Appendix J, p. 50 and Appendix K, p. 7. 584 Tr. 13, p. 2450, l. 22 to p. 2451, l. 7 (Darby). 585 Exhibit B-53, BC Hydro Undertaking No. 46.
- 156 -
301539.00025/94161307.1
358. In fiscal 2019, BC Hydro acquired the underground property rights from the Vancouver
School Board at the location of the Lord Roberts Annex School for $66.8 million.586 The
property rights will allow construction of a new underground substation in the West End of
downtown Vancouver as part of the West End Substation Construction and System
Reinforcement Project.587 The substation will replace the existing Dal Grauer substation as part
of the first stage of the 30-year Downtown Vancouver Electricity Supply (“DVES”) Plan.588
359. Acquiring property to accommodate a new substation is an important step to mitigate
risk. The need to replace the aging Dal Grauer substation is clear. More than half of the assets
are expected to degrade to poor or very poor condition in the next 10 to 20 years, presenting a
reliability risk. Physical space constraints at Dal Grauer make redevelopment of the substation
in its current location a challenge.589 At the same time, BC Hydro was constrained by the
limited supply of suitable properties in the West End that could meet the technical
requirements for the substation.590 Mr. Leonard explained that technical requirements can be
particularly constrained in a downtown urban core.591 BC Hydro summarized the requirements
for the property, as follows:
The required property attributes include a minimum size of the parcel (approximately a half-city block), a minimum number of sides available for transmission cable ingress and distribution feeder egress, minimum length required on one side to accommodate the transformers, reasonable access and constructability, acceptable geotechnical and environmental conditions, proximity to customer load, proximity to existing transmission infrastructure and proximity to existing substations for off-loading.592
586 Exhibit B-16, BCUC IR 3.291.2; Tr. 12, p. 2244, ll. 9-18 (Kumar and Leonard). 587 Exhibit B-4, update to Appendix J - Attachment 1, p. 69. BC Hydro’s West End Substation Construction and
System Reinforcement Project will involve a new 230/12 kV to 25 kV, 400 MVA, underground substation. 588 The project is described in Exhibit B-1, Appendix J - Attachment 1, p. 80; the Downtown Vancouver Electricity
Supply Plan is summarized in Exhibit B-1, Appendix K - Attachment 1, p. 54; Tr. 11, p. 1905, ll. 6-24 (Kumar). 589 Exhibit B-1, Appendix J - Attachment 1, p. 80. 590 Exhibit B-5, BCUC IRs 1.117.1 and 1.117.1.1. 591 Tr. 12, p. 2247, l. 23 to p. 2248, l. 7 (Leonard). 592 Exhibit B-5, BCUC IR 1.117.1.
- 157 -
301539.00025/94161307.1
360. The acquired property meets these requirements. BC Hydro performed a 30-year
present value analysis on the site and worked closely with brokers in moving forward with the
acquisition.593
361. BC Hydro’s acquisition serves to confirm the viability of the preferred long-term solution
for the project.594 As Mr. Leonard explained, BC Hydro acquired the land well in advance of the
operation of the new substation to provide BC Hydro with certainty with respect to the site,
cost and schedule.595 Ms. Holland similarly emphasized the importance of knowing where the
substation property will be in order to prepare designs and an estimate that can be reviewed by
the BCUC as part of a CPCN application.596 She stated:
And if we don’t know where a project is going to be located we really have no hope of preparing any reasonable estimate, nor addressing some of the other issues that the Commission would review in a CPCN, including stakeholder consultation and other items.597
362. Ultimately, the BCUC will be able to review the West End Substation Construction and
System Reinforcement Project when BC Hydro files for a CPCN for the project, which is
currently anticipated to be in fiscal 2023.598 The funds spent on acquiring property rights will
be accounted for in the CPCN application.599 In its CPCN application, BC Hydro will explain the
alternatives considered to supply the Downtown Vancouver area, the process to select a
preferred alternative, the reasons why building a new substation in the West End neighborhood
is the preferred alternative, and site options within the West End neighborhood suitable for a
substation.600
593 Tr. 12, p. 2246, l. 17 to p. 2247, l. 4 (Leonard). 594 Exhibit B-1, Appendix J - Attachment 1, p. 80; Exhibit B-5, BCUC IRs 1.117.1 and 1.117.1.1. 595 Tr. 12, p. 2245, l. 15 to p. 2246, l. 7 (Leonard). 596 Tr. 12, p. 2247, ll. 11-22 (Holland). 597 Tr. 12, p. 2247, ll. 11-22 (Holland). 598 Tr. 12, p. 2244, ll. 22-24 (Leonard). 599 Exhibit B-5, BCUC IR 1.118.1. 600 Exhibit B-5, BCUC IR 1.117.1.1; Tr. 12, p. 2249, l. 19 to p. 2250, l. 1 (Leonard); Tr. 12, p. 2251, ll. 3-9 (Holland).
- 158 -
301539.00025/94161307.1
New Murrin Strategic Property Purchase - East Vancouver Substation
363. The New Murrin Strategic Property Purchase – East Vancouver Substation project
involved the fiscal 2017 purchase of an East Vancouver property.601 The property will be used
for a new substation that is an integral component of BC Hydro’s 30-year DVES Plan.602 BC
Hydro has identified the substation project as requiring a CPCN.603 The purchase of this
property represented prudent risk management because the need for a new site is clear, and
suitable properties are scarce.
364. BC Hydro’s evidence is that a new substation on a new site is required because the
Murrin substation:604
● presents a reliability risk as it was built in 1947 and is getting close to end-of-life
with more than half of the assets expected to degrade to poor or very poor
condition in the next 10 to 20 years;
● is on seismically unstable soil, with approximately half of the switchyard
vulnerable to severe earthquake damage from liquefaction and settlement; and
● has physical space constraints which make redevelopment of the substation in
its current location challenging and costly.
365. There is a limited supply of suitable properties in East Vancouver with the specific
property attributes required for the replacement substation. The purchased property meets the
requirements for the substation project, as it is:605
601 Exhibit B-16, BCUC IR 3.291.5; Tr. 12, p. 2244, ll. 9-21 (Kumar and Leonard). 602 The East Vancouver – Substation Construction Project will replace the Murrin substation by building a new
230/12 kV to 25 kV, 400 MVA, station in the Eastside/Strathcona neighbourhood of Downtown Vancouver as part of the second stage of the 30-year Downtown Vancouver Electricity Supply Plan. The project is described in Exhibit B-1, Appendix J, Attachment 1, p. 79; the Downtown Vancouver Electricity Supply Plan is summarized in Exhibit B-1, Appendix K, Attachment 1, p. 54.
603 Exhibit B-1, Appendix I, Capital Expenditures > $5 million, p. 4. 604 Exhibit B-13, BCOAPO IR 2.133.2. 605 Exhibit B-13, BCOAPO IR 2.133.2.
- 159 -
301539.00025/94161307.1
● close to the established transmission cable (which is in the lane adjacent to the
property) and close to an eventual second transmission cable on Hastings Street,
avoiding the need for higher incremental transmission costs to connect it to the
power system;
● on seismically stable ground;
● in the middle of the load serving area, avoiding the need for higher incremental
distribution costs to connect to customers; and
● in a light industrial area, minimizing future stakeholder issues.
366. Further, the property is currently leased to a creditworthy commercial tenant, which
minimizes BC Hydro’s holding costs until the construction of the East Vancouver Substation is
initiated.606
367. As with the West End Substation, acquiring the land well in advance provides certainty
with respect to the site, cost and schedule.607 BC Hydro performed a 30-year present value
analysis on the site and worked closely with brokers in moving forward with the acquisition.608
368. The BCUC will review the East Vancouver – Substation Construction project when BC
Hydro files for a CPCN for the project. The funds spent on acquiring property rights will be
accounted for in the CPCN application.609 As with other major projects, BC Hydro’s application
will address the need for and alternatives to the project, including alternative sites.610
606 Exhibit B-13, BCOAPO IR 2.133.2. 607 Tr. 12, p. 2245, l. 15 to p. 2246, l. 7 (Leonard); Tr. 12, p. 2247, ll. 11-22 (Holland). 608 Tr. 12, p. 2246, l. 17 to p. 2247, l. 4 (Leonard). 609 Exhibit B-5, BCUC IR 1.118.1. 610 Exhibit B-5, BCUC IR 1.118.2.1; Tr. 12, p. 2249, l. 19 to p. 2250, l. 1 (Leonard); Tr. 12, p. 2251, ll. 3-9 (Holland).
- 160 -
301539.00025/94161307.1
(g) Project Write-Offs Demonstrate Maturity of Capital Planning and Delivery Processes
369. BC Hydro’s Test Period revenue requirements include a forecast of project write-offs.611
BC Hydro’s approach is reasonable because the write-offs reflect prudent capital management
practices.
370. BC Hydro evaluates its capital plans and projects on an ongoing basis. It adjusts plans
with updated information, including on the load forecast, asset health information, and cost
estimates. BC Hydro’s approach reflects the maturity of the company’s asset management
practices, which (as described in Section F above) have been endorsed by the Auditor General
and other third party experts. Mr. Layton explained:
So I think I’d refer back to the page where we started with, on page 8-21 and you can see starting on line 7 some of the logic here. And I think the way I would summarize it is that sometimes write-offs are a very prudent decision to make. In other words, sometimes it makes sense to stop a project and that can be part of a very mature project management practice.
And that’s what we’ve seen, that rather than blindly go forward with a project that doesn’t make sense to continue, it sometimes makes very good sense to stop. And when we make those kind of prudent decisions, write-offs can happen. And so our proposal is to have a budget amount for that. We think, again, those are prudently incurred costs and, therefore, the ratepayers should be willing to pay for a reasonable amount there. As I said, amounts above and beyond that we propose to remain to the account of the shareholder.612
371. BC Hydro exceeded the forecast of write-offs for the Test Period with the write-off
related to the Metro North project.613
(h) BC Hydro Has Explained Variances from Plan on Past Projects
372. As discussed in Section E above, BC Hydro has completed its capital portfolio on budget.
BC Hydro explained variances between plan to actual capital expenditures and additions in
611 Exhibit B-1, Application, p. 8-21. 612 Tr. 7, p. 1003, l. 13 to p. 1004, l. 5 (Layton). 613 Tr. 7, p. 1004, ll. 6-18 (Layton). See also, Exhibit B-56, BC Hydro Undertaking No. 49.
- 161 -
301539.00025/94161307.1
Appendix G of the Application and the Evidentiary Update. It elaborated in responses to
information requests.614 The evidence demonstrates that these variances occurred in the
context of prudent project management by BC Hydro.
373. AMPC asked a number of questions about the Interior to Lower Mainland (“ILM”)
Project, suggesting that an arbitration decision related to the Project (as discussed in the ILM
Project’s Completion and Evaluation Project615) reflected imprudence on the part of BC Hydro.
There are two answers to this suggestion.
● First, the arbitration concerned the appropriate allocation of cost under the
contract, not an assessment of prudence. The work that was the subject of the
dispute was necessary. BC Hydro and its contractor just disagreed about who
was responsible for certain costs. The arbitrator decided in favour of the
contractor in relation to some — but certainly not all — of those costs. BC Hydro
demonstrated appropriate contract management by seeking to hold its
contractors to the terms of their contracts over the course of a large and
complex project.616
● Second, in any event, the ILM Project came into service in 2015, such that
project costs are recoverable in rates pursuant to Direction No. 8.617
374. Counsel for AMPC also questioned past decisions by BC Hydro to conduct geotechnical
investigations in the Implementation Phase, rather than earlier project phases.618 BC Hydro
makes the following points in response:
614 Exhibit B-5, BCUC IR 1.107.2 and Exhibit B-13, AMPC IR 2.36.2. 615 Exhibit B-17, AMPC IR 3.20.1. 616 Exhibit B-17, AMPC 3.20.1, ILM Project Completion Report, p. 8 of 52, and May 16, 2018 Letter from BC Hydro
President & COO to BCUC on Interior to Lower Mainland Transmission Line arbitration decision (Online: https://www.bchydro.com/news/press_centre/news_releases/2018/bchydro-ilm-project-decision.html).
617 Section 4(a) of Direction No. 8 provides that the BCUC must not disallow for any reason the recover in rates of the costs incurred by BC Hydro with respect to the construction of extensions to BC Hydro’s plant or system that came into service before fiscal 2017.
618 Tr. 12, p. 2196, l. 13 to p. 2198, l. 3 (Holland); Tr. 12, p. 2203, l. 9 to p. 2221, l. 23 (Holland).
- 162 -
301539.00025/94161307.1
● First, geotechnical conditions exist and will result in costs regardless of when
they are identified. As Ms. Holland emphasized: “whether you find them later or
you find them earlier they’re going to result in cost and schedule.”619
● Second, while BC Hydro’s practice was mixed in the past, BC Hydro made it its
general practice to conduct geotechnical investigations prior to the
Implementation Phase because doing so results in better cost and schedule
estimates by the end of the Definition Phase.620 Ms. Holland stated:
We changed the practice so that at the end of the definition phase we can get a much better estimate of the work that will be done during the construction phase. We want to have a really good first full funding estimate that includes a well-informed understanding of the work that we’re going to be faced with. And if there’s very difficult geotech conditions, we want to know that before we get the first full funding approved so that we can include that into the schedule, as well as into the cost estimate.621
● Third, it is an accepted principle that prudence should be judged without the
benefit of hindsight.622 BC Hydro has only learned through experience on a
number of projects that it is better to do geotechnical investigations prior to the
Implementation Phase.623
● Fourth, waiting until implementation did not result in any material redundant
costs on the projects in question. For the Campbell River Substation Capacity
Upgrade Project, “geotechnical issues required design additions such as the
design of piles, a new retaining wall, new seismic keys, new drainage, and
619 Tr. 12, p. 2210, ll. 14-20 (Holland). 620 Tr. 12, p. 2196, ll. 19-26. (Holland). 621 Tr. 12, p. 2209, l. 20 to p. 2210, l. 4 (Holland). 622 Enbridge Gas Distribution Inc. v. Ontario (Energy Board), 2006 CanLII 10734 (ON CA) (“Enbridge”), at paras. 8-12.
Online: https://www.canlii.org/en/on/onca/doc/2006/2006canlii10734/2006canlii10734.html.
In its Reasons for Decision, BC Hydro F2009 and F2010 Revenue Requirements, dated March 13, 2009, p. 38, the BCUC determined that two-part test articulated in Enbridge should apply when conducting prudence reviews. Online: https://www.bcuc.com/Documents/Proceedings/2009/DOC_21286_BCH-2009RR_WEB.pdf.
623 Tr. 12, p. 2209, ll. 12-17 (Holland).
- 163 -
301539.00025/94161307.1
additional soil replacements”; however: “There was no design redundancy, and
there was no additional costs related to demobilization or idle time caused by
design changes.”624 For the Big Bend Substation Project, costs related to design
redundancy for piling estimates are estimated to be less than $50,000.625
(i) Industrial Load Interconnection: BC Hydro Has and Is Improving the Process
375. BC Hydro was asked a number of questions at the hearing, primarily by AMPC and
CEABC, about its load interconnection practices. The evidence discussed below demonstrates
that BC Hydro is managing its industrial load interconnection requests well, with study times
comparing well against BC Hydro’s own business practice timelines and the practices at other
utilities. BC Hydro is, however, continuing to look for opportunities to improve the process.
Distribution and Transmission Interconnection Processes Are Governed by the Tariff and Published Business Practices
376. Industrial Load interconnections follow either the Large Industrial Connection
(Transmission Service) process or the Large Industrial Connection (Distribution Service) process.
Transmission load interconnection requests are governed by Tariff Supplement No. 6, as
approved by the BCUC. Distribution load interconnection requests are governed by section 8 of
the Electric Tariff, as approved by the BCUC. A step-by-step guide for both processes appears
on BC Hydro’s website.626 BC Hydro also has a queue management business practice for
applications under Tariff Supplement No. 6, which is used to determine the order for initiating
load interconnection studies, cost allocation for infrastructure required to supply a new load,
and the customer’s obligations for remaining in the queue.627
624 Exhibit B-56, BC Hydro Undertaking No. 41. 625 Exhibit B-56, BC Hydro Undertaking No. 41. 626 Exhibit B-13, AMPC IRs 2.35.2 and 2.35.4. 627 The queue business practice is available on BC Hydro’s website (Business Practice for Load Interconnection
Queue Management) at: https://app.bchydro.com/content/dam/BCHydro/customer-portal/documents/corporate/regulatory-planning-documents/regulatory-matters/00-2014-11-18-queue-management-business-practice.pdf
- 164 -
301539.00025/94161307.1
BC Hydro Has Engaged in Continuous Improvement of Interconnection Processes
377. The evidence shows that BC Hydro has made numerous improvements to its customer
interconnections process over the past years.
378. More than 4 years ago, BC Hydro commissioned Black & Veatch to review the overall
effectiveness of its interconnection processes. Black & Veatch’s report of April 2016 made a
number of recommendations to improve processes. However, it also observed that many
utilities were dealing with the same issues:
While this report documents a number of issues and recommendations for improvement, Black & Veatch believes that BC Hydro’s T&D Interconnections Group and other departments and groups involved in various parts of its Transmission Generator and Load Interconnection processes to be professional and dedicated. At the core, these processes require BC Hydro to balance: 1) the need to be responsive in addressing the issues faced by Transmission Generators and Load Customers, 2) the need to protect the interest of ratepayers, and 3) the obligation to meet all applicable reliability standards (MRS; Western Electricity Coordinating Council, WECC; North American Electric Reliability Corporation, NERC; etc.). Furthermore, the peer utilities interviewed by Black & Veatch as part of this project indicated that many of them have dealt with or are currently addressing many of the same issues facing BC Hydro.628 [Emphasis added.]
379. Black & Veatch also described the actions BC Hydro had or was in the process of
undertaking to improve the interconnections processes, as follows:629
● Efforts to improve process efficiency, especially for projects with low
complexity, and improvements to the project delivery process to increase
accuracy of the cost and schedule estimates. In February 2015, BC Hydro
underwent a corporate reorganization that resulted in the creation of
Capital Infrastructure Project Delivery Group, which is led by the Deputy
CEO. This resulted in a standardization of the project delivery approach
and philosophy for all major capital projects including interconnection
projects.
628 Exhibit B-47, BC Hydro Undertaking No. 32, Attachment 1, p. 5 of 76. 629 Exhibit B-47, BC Hydro Undertaking No. 32, Attachment 1.
- 165 -
301539.00025/94161307.1
● Update of the guide and requirements for new Load Interconnections.
Consultation with various industry advocacy groups and select customers
has occurred over the last two years. A revised guide will be ready in
2016 for final stakeholder review.
● Initiation of the RDA Module 2 in 2014, which includes the review and
revision of Tariff Supplements 5 and 6 which apply to Transmission Load
Interconnection projects. The target date to submit BC Hydro
recommendations to the BC Utilities Commission (BCUC) is mid‐2017.
● Development of Indirect Interconnection Tariff (Tariff Supplements 87
and 88). This new tariff enables BC Hydro to serve new Transmission Load
Customers who are connected to BC Hydro’s system via third‐party
owned facilities. The Indirect Interconnection Tariff was approved on
March 6, 2016.
● Increasing transparency and collaboration with customers throughout
the interconnection process by:
• Providing more detailed cost estimates and schedules, and
collaborating on key project risks and decision points.
• Improving current data tracking and metrics so key milestones for
interconnection projects can be reported to our customers and
key stakeholders. The target date to issue the first report is Q1
2017.
• Improving BC Hydro’s external websites to provide more up‐to‐
date and useful information to the customers.
• Revising study cover letters and report templates to highlight
critical information such as assumptions used for cost estimates,
- 166 -
301539.00025/94161307.1
clarification on cost accuracy range, comments on the schedule,
etc.
• Developing the Transmission Load Interconnection Queue
Management Business Practice. The latest version (November
2014) is posted on the website and was reviewed by stakeholders
at one of the RDA workshops.
• Reviewing and implementing opportunities for customers to
perform BC Hydro’s scope of work for Load Interconnection
projects. For example, the customer’s contractor can design and
construct the tap on behalf of BC Hydro.
380. Since the 2016 Black & Veatch report, BC Hydro has undertaken internal changes to
address organizational structure issues, matured the delivery process for interconnection work,
and made several process improvements.630 BC Hydro highlighted the various actions it has
taken to improve interconnection timelines for new industrial load interconnection requests.
BC Hydro has:631
● streamlined the project’s hand over process from the Integrated Planning
Business Group to the Capital Infrastructure Project Delivery Business Group;
● expedited the transmission interconnection process for new load requests at
sites that already have transmission service and have capacity available with no
system reinforcements required to meet the new load;
● implemented a process allowing customers to design and build transmission taps
on BC Hydro’s behalf in order to give the customer more control over the project
schedule and costs;
630 Exhibit B-47, BC Hydro Undertaking No. 32. 631 Exhibit B-13, AMPC IR 2.35.8. See also, Tr. 11, p. 1921, l. 14 to p. 1923, l. 10 (Kumar).
- 167 -
301539.00025/94161307.1
● re-structured the Capital Infrastructure Project Delivery Business Group to create
a project delivery team that focuses on interconnection projects and scaling the
delivery process;
● developed performance metrics for interconnection study timelines to track
performance against targets, to identify trends and to evaluate the effectiveness
of interconnection process improvement; and
● initiated three ex-plan projects to ensure that BC Hydro is able to provide
transmission services in the timeline required for customer need and desire to
electrify their operations.
Interconnections Are Prioritized in the Capital Planning Process and Well Supported
381. BC Hydro’s focus on customer connections translates directly to how BC Hydro
undertakes its capital planning. BC Hydro’s planning approach is to prioritize customer
interconnections over other work. Mr. Kumar explained:
One thing that I would like to add is from a planning perspective, my group and Mr. Darby’s group are looking at these studies. The number one priority we assign from a planning perspective is to excel customer requests. Whether it is IPPs or load customers. So those are the highest priority.632
Prioritizing customer connections over other capital work means that any resource or capital
challenges associated with increased interconnection activity would be reflected in other non-
customer driven projects.633
382. Ms. Daschuk elaborated on the efforts of BC Hydro to support the interconnection
process through adequate resourcing and Executive oversight:
By Hydro has done a number of things to support the customer interconnection process. One of them is, by example, we have executive committees that
632 Tr. 11, p. 1937, ll. 19-24 (Kumar). 633 Tr. 12, p. 2181, l. 19 to p. 2182, l. 5 (Holland); Tr. 12, p. 2288, l. 6 to p. 2289, l. 12 (Daschuk); Tr. 13, p. 2354, l.
11 to p. 2355, l. 2. (Kumar).
- 168 -
301539.00025/94161307.1
provide support. So myself, Mr. Leonard, Ms. Fraser, we meet on a, I think it’s a monthly basis and we review customer interconnection requests from various sectors, including the oil and gas sector, the mining sector and transportation. The purpose of that group is to understand if there are any roadblocks that are preventing these interconnections from moving forward, and our goal is to support that.
Also, within the interconnections team, with the indefinite suspension of the standing offer program, all of the resources that had previously been working on generator interconnections, for the most part those have been reallocated to the transmission load interconnections. As I mentioned, we had a dedicated project delivery group. We also have completed a work smart initiative and the work smart initiative was looking at the processes for interconnections and identifying ways in which it could be improved.
We’re also taking a look at whether we should be initiating some projects in advance of having a committed customer. Those are the examples that I’ve given previously, which is the Prince George to Terrace capacitors project, the Bear Mountain voltage conversion and the North Montney project. And by doing some work up front we’re able to potentially reduce the amount of time.634
383. Mr. Leonard also spoke of the emphasis placed on customer connections at the
Executive level of BC Hydro:
I mean, the only other thing that I would add to this is being one of the fellow executives that sits on this committee and, as Ms. Daschuk mentioned, we meet on a monthly basis. You know, it takes a number of areas of our organization to ensure that we’re fulfilling these needs. And so myself and Ms. Fraser and Ms. Daschuk, this is an area of keen focus for us and then we in turn are asked upon in many circumstances to help if there is direction that is needed or if one of our organizations is requiring something, we are there to help move those things along. Realizing that at the end of this we have a customer that is asking for, you know, a product or a service and that is our role to deliver that. So I can’t stress enough the role of the executive in this.635
384. Ms. Daschuk, Mr. Leonard and Ms. Holland also noted that the compensation of senior
management and executives responsible for the planning and capital delivery functions are tied
634 Tr. 11, p. 1919, l. 2 to p. 1920, l. 5 (Daschuk). 635 Tr. 11, p. 1942, l. 25 to p. 1943, l. 14 (Leonard).
- 169 -
301539.00025/94161307.1
to meeting interconnection timelines.636 Appropriate incentives are in place to maintain the
company’s focus on continuous improvement.
BC Hydro Is Engaging with Customers on its Interconnection Processes
385. BC Hydro has ongoing discussions with new interconnection customers on its
interconnection process and tariff.637 BC Hydro has also conducted a number of workshops and
engagement sessions with industrial stakeholders on its interconnection processes and
associated interconnection tariffs.638 BC Hydro surveyed customers in 2017 and solicited
feedback as part of its continuous improvement process.639
BC Hydro Has Been Meeting its Internal Targets and Also Benchmarks Favourably
386. There is objective evidence, in the form of both performance against internal targets
and benchmarking, that BC Hydro is carrying out interconnection work in a diligent manner.
387. BC Hydro sets internal targets each year for the time to deliver on the studies to
facilitate a load interconnection.640 The targets are based on the average duration of the
studies, since timelines for each type of study vary significantly depending on the size, location,
type of load, type of interconnection, and the complexity of the system upgrades required to
serve the new load interconnection request.641 At the transmission level, the targeted average
duration for System Impact Studies is 150 days and the targeted average duration for Facilities
Studies is 180 days. At the distribution level, the targeted average duration for Planning Studies
is 60 days and the targeted average duration for Facilities Studies is 365 days.
636 Tr. 11, p. 1949, l. 21 to p. 1951, l. 6 (Daschuk, Leonard and Holland). 637 Tr. 11, p. 1922, l. 17 to p. 1923, l. 10 and p. 1925 ll. 12-14 (Kumar). 638 Exhibit B-47, BC Hydro Undertaking No. 33 (PDF pp. 139-140). 639 Exhibit B-47, BC Hydro Undertaking No. 34 (PDF pp. 141-149). 640 Exhibit B-13, AMPC IR 2.35.7. 641 Mr. Kumar gave the example of adding a significant LNG load to a radial line to Kitimat, which would be
inherently more complex than adding a smaller load to a strong system in the Lower Mainland where there is ample capacity: Tr. 11, p. 1923, l. 11 to p. 1924, l. 23 (Kumar).
- 170 -
301539.00025/94161307.1
388. The table below shows that BC Hydro has completed its studies on average within its
targets:642
389. Ms. Daschuk noted the improvement from fiscal 2019 to fiscal 2020 year to date:
A couple of things I wanted to mention in terms of performance. Last year, in our Fiscal 2019, we completed 79 percent of the studies on time. That’s not a number that we were happy with. This year, year to date, 97 percent of all of the studies have been completed on time. I think that’s a real reflection of some of the significant effort that we’ve been putting in as an organization to improve the interconnection process to make it easier for our customers to connect.643
390. Ms. Daschuk confirmed that the timelines for the studies reflect dates agreed to with
the customer.644
391. The April 2016 Black & Veatch report included benchmarking on the duration and cost
of customer interconnections, although it cautioned that there are differences between
jurisdictions that make benchmarking challenging.645 Given the improvements made since
2016, the benchmarking conducted by Black & Veatch is now out of date.646 However, as
642 Exhibit B-13, AMPC IR 2.35.5. 643 Tr. 11, p. 1920, ll. 6-15 with errata noted in Tr. 15 (Daschuk). 644 Tr. 11, p. 1920, ll. 23-24 (Daschuk). 645 Exhibit B-47, BC Hydro Undertaking No. 32 Attachment 1, pp. 33 and 34 of 76. Potential differences identified
include ownership and governance, size of territory, nature of terrain and system characteristics, generation types (e.g. hydroelectric), and whether there is an independent system operator managing interconnections.
646 Exhibit B-47, BC Hydro Undertaking No. 32 Attachment 1, pp. 34 and 35 of 76.
- 171 -
301539.00025/94161307.1
shown in the table below, BC Hydro’s targets compare well to other utilities using information
published as of April 2019.647
BC Hydro Will Continue to Improve Interconnection Process
392. While progress has been made and BC Hydro’s interconnection process is performing
well, BC Hydro will continue to improve its customer interconnection process. As stated by Ms.
Daschuk:
I’m pleased with the performance and the improvements that we’ve made on the interconnections process. That’s not to say that we are perfect or there aren’t further things that could be done, because there are, and I’m hoping that you’re seeing the commitment from Mr. Leonard and myself and from everyone on this panel that we will continue to work to drive improvements in that process.648
K. CONCLUSION AND REQUESTED FINDINGS
393. BC Hydro submits that the evidence shows that BC Hydro has well-developed planning
and delivery processes and that BC Hydro is delivering its projects effectively and efficiently.
The BCUC should find that the resulting planned capital additions and expenditures for the Test
Period are reasonable.
647 Exhibit B-13, AMPC IR 2.35.6. See also, Exhibit B-49, BC Hydro Undertaking No. 38. The figures in the table
below for BC Hydro, Sask Power and Hydro One are the ranges of their published target durations. The figures for AESO are the median durations of greenfield load projects completed in the previous two-year period.
648 Tr. 11, p. 1945, l. 3 to p. 1946, l. 5 (Daschuk).
- 172 -
301539.00025/94161307.1
PART EIGHT: REGULATORY ACCOUNTS
A. INTRODUCTION
394. All but one649 of BC Hydro’s regulatory accounts are BCUC-approved for ongoing use.650
As such, BC Hydro is seeking very few orders regarding regulatory accounts. It is proposing to
close four regulatory accounts,651 and to make a limited number of changes. It is not
requesting approval of any new regulatory accounts.652
395. While Government has repealed directions regarding some of BC Hydro’s regulatory
accounts, the underlying rationale for the accounts remains sound. The BCUC’s approval of
most of the accounts predated the Government directions, and the Government directions
mirrored regulatory policy reflected in the BCUC’s own guidelines for utilities. The
Government-directed account that faced the most challenges gaining acceptance – the Rate
Smoothing Regulatory Account – has been written-off and BC Hydro is proposing to close it.
There is ample evidence, discussed in this Part, to demonstrate that BC Hydro’s current use of
regulatory accounts, its proposals to close and modify some of them, and its forecasted
additions are just and reasonable.653
396. This Part is organized around the following supporting points:
● First, BC Hydro’s approved regulatory accounts are in accordance with
International Financial Reporting Standards (“IFRS”), and are consistent with the
BCUC’s Regulatory Account Filing Checklist (“BCUC Checklist”).
● Second, the assessment of BC Hydro’s regulatory accounts should focus on the
merits of each account and the benefits it provides to BC Hydro and ratepayers,
not the number of accounts.
649 The Dismantling Cost Regulatory Account. 650 Exhibit B-16, BCUC IR 3.301.6; Exhibit B-5, BCUC IR 1.139.3. 651 Exhibit B-1, Application, Table 7-9, starting on p. 7-60; Exhibit B-5, BCUC IR 1.40.3.1. 652 Exhibit B-1, Application, pp. 7-21 to 7-23. 653 Exhibit B-5, BCUC IR 1.139.3.
- 173 -
301539.00025/94161307.1
● Third, BC Hydro’s current use of regulatory accounts is beneficial to customers.
● Fourth, the Auditor General has removed her qualification on Government’s
financial statements regarding BC Hydro’s use of rate-regulated accounting.654
● Fifth, BC Hydro is taking the necessary steps to manage regulatory account
balances, using appropriate recovery mechanisms and exercising discipline over
controllable costs.
● Sixth, BC Hydro’s proposed changes to accounts are warranted.
● Seventh, BC Hydro’s forecast for Real Property Sales Regulatory Account, as
reflected in the Evidentiary Update, is reasonable for setting rates during the
Test Period.
B. BC HYDRO’S REGULATORY ACCOUNTS ADHERE TO ACCOUNTING STANDARDS AND BCUC GUIDELINES
397. BC Hydro uses regulatory accounts for four purposes: (1) to ensure that customers pay
actual costs (no more, no less) where uncontrollable and unpredictable factors could otherwise
produce unfair results, (2) to defer differences between forecast and actual costs or revenues
due to uncontrollable risks, (3) to smooth out the rate impact of large, non-recurring costs, and
(4) to better match costs and benefits for customers.655 BC Hydro’s use of regulatory accounts
complies with IFRS and the BCUC Checklist.
398. Rate-regulated accounting is permitted under IFRS 14, Regulatory Deferral Accounts.656
654 Exhibit B-12, BCUC IR 2.201.3; Exhibit B-1, Application, pp. 7-7 and 7-8. 655 Exhibit B-1, Application, p. 7-14. Exhibit B-1, Application, p. 7-1. The general purpose of a regulatory account is
to defer costs or revenues for future recovery or refund. In the absence of rate-regulated accounting, costs or revenues would be recognized in the current accounting period.
656 Exhibit B-1, Application, pp. 7-13, 8-25 and 8-26.
- 174 -
301539.00025/94161307.1
399. The BCUC Checklist contemplates five types of regulatory accounts. The following table
summarizes how all of BC Hydro’s accounts fall within the categories identified in the BCUC
Checklist.
BCUC Category BCUC Description of Category BC Hydro Accounts
Forecast variance account
“A forecast variance account captures the variance between forecast costs or revenues and actual costs or revenues.”
Heritage Non-Heritage Trade Income Storm Restoration Costs Amortization of Capital Additions Total Finance Charges Remediation Dismantling Cost Foreign Exchange Gains/Losses Non-Current Pension Costs PEB Current Pension Costs Debt Management Rock Bay Remediation657 Customer Crisis Fund658 Mining Customer Payment Plan659 Real Property Sales660 Arrow Water Systems (applying to close)
Rate smoothing account
“A rate smoothing account can mitigate rate shock resulting from the impact of large forecast onetime items, mitigate rate shock resulting from forecast overall general rate increases, or reduce rate volatility.”
Rate Smoothing (applying to close)
Benefit matching (capital-like) account
“A benefit matching account defers recovery of costs that under Generally Accepted Accounting Principles (GAAP) would otherwise be required to be expensed in the current accounting period to a future period (when the benefits of those costs are realized) if they provide long-term benefits to current and future ratepayers.”
Demand Side Management First Nations Costs Site C Pre-1996 Contributions in Aid of Construction SMI Capital Project Investigation Costs (applying to close)
657 BC Hydro will apply to close this account in its next revenue requirements application. 658 BC Hydro may apply to close this account in a future application. 659 BC Hydro may apply to close this account in a future application. 660 BC Hydro may apply to close this account in a future application.
- 175 -
301539.00025/94161307.1
BCUC Category BCUC Description of Category BC Hydro Accounts
Retroactive expense account
“A retroactive expense account applies only to an uncontrollable cost or revenue that occurs in a period where rates have already been approved and set by the Commission. For example, recover through amortization expense in the revenue requirements or through a rate rider. Recovery timelines may be short term (1 year or less), medium term (1-3 years), or long term (3+ years).”
N/A
Other “While it is expected that the majority of regulatory account requests would fall within the four categories described above, there may be others which the Commission would consider on a case-by-case basis. Example: In certain situations, a regulated entity may recognize a non-cash GAAP provision which results in a request for a Commission-approved regulatory asset account to offset the liability (provision) recorded under GAAP.”
First Nations Provisions Environmental Provisions IFRS Property, Plant and Equipment (IFRS Transition Account)661 IFRS Pension (IFRS Transition Account)662 Arrow Water System Provisions (applying to close)
C. FOCUS ON THE MERITS OF EACH ACCOUNT, NOT THE NUMBER OF ACCOUNTS
400. InterGroup, referencing the number of BC Hydro’s regulatory accounts, recommends
that the BCUC direct BC Hydro to simplify its accounts as a long-term priority.663 Mr. O’Riley, in
response, highlighted the importance of regulatory accounts, and expressed hope for a
consensus that we should move beyond counting the number of accounts.664 Sound logic
underlies Mr. O’Riley’s comments, as explained below.
(a) Regulatory Accounts Are Common and Numbers Vary Widely Among Utilities
401. Regulatory accounts are a widely-accepted and widely-used tool, including in this
jurisdiction. InterGroup identified some utilities that have relatively few accounts. BC Hydro
had no difficulty identifying other examples of utilities that have a similar or greater number of
661 See discussion in Exhibit B-1, Application, pp. 7-18 to 7-20. 662 See discussion in Exhibit B-1, Application, pp. 7-18 to 7-20. 663 Exhibit C11-11, InterGroup Report, Recommendation 7. 664 Tr. 5, p. 430, l. 23 to p. 431, l. 2 (O’Riley).
- 176 -
301539.00025/94161307.1
accounts than BC Hydro.665 This evidence suggests that the use of regulatory accounts differs
among utilities in North America. There is no “gold standard” for the number of accounts.
402. Mr. Layton, during cross-examination by Mr. Keen (counsel for AMPC), elaborated on
why he took issue with focussing on the number of BC Hydro’s accounts relative to other
utilities:
No, I don’t think so. I think all we were trying to say in that sentence is that if one merely looks at the number of regulatory accounts an entity has, it’s a piece of information but it’s only one piece of information that is interesting and relevant if one wants to compare across entities.
I can quote another utility that they amalgamated. Encana Utility has 50 something regulatory accounts. But unless one looks at why they have those accounts, unless one looks at the balances of those accounts, unless one looks at why those were approved and to what they relate, it’s only one piece of the puzzle and our point is simply that only looking at the number of regulatory accounts doesn’t provide a great deal of insight in our view.666
403. Mr. Wong echoed that “what we should be looking at, is what is going into the deferral
accounts, why we are deferring those balances, how we are recovering those costs.”667
404. Direct comparisons of the number of accounts can be challenged by the potential for
different practices regarding how deferred costs are grouped for regulatory accounting
purposes. Mr. Wong observed: “So you could take three or four and put them into one, and say
that is one deferral account. And so I believe, actually, that BC Hydro having the 29 that it does,
we are very clear in itemizing what goes into each deferral account.”668 The fact that BC Hydro
has two Cost of Energy Variance Accounts to differentiate between costs associated with
Heritage and Non-Heritage resources is a tangible example of this; both accounts have the
same amortization period and serve a similar purpose.
665 Tr. 6, p. 822, ll. 2-16 (Layton); Exhibit B-28, BC Hydro Rebuttal Evidence, p. 11. 666 Tr. 6, p. 882, ll. 2-16 (Layton). 667 Tr. 6, p. 707, ll. 9-14 (Wong). 668 Tr. 6, p. 707, ll. 4-8 (Wong).
- 177 -
301539.00025/94161307.1
405. The use of Performance Based Regulation at some utilities adds further complexity to
comparisons based on the number of accounts. “Flow-through” mechanisms (e.g., Y-factors)
achieve the same result as a regulatory account.
(b) BC Hydro is Proposing to Close Four Regulatory Accounts, With Up to Four More Soon to Follow
406. In any event, BC Hydro is closing accounts when the balances are recovered and the
accounts are no longer required.669 BC Hydro anticipates closing up to eight accounts in the
next four years, four of which are to close as an outcome of this proceeding.670 BC Hydro also
plans to limit when it applies for new forecast variance accounts to circumstances where there
is un-forecast and non-controllable expenditures greater than $10 million in a fiscal year.671
D. BC HYDRO’S REGULATORY ACCOUNTS ARE BENEFICIAL TO CUSTOMERS
407. BC Hydro’s use of regulatory accounts is beneficial to ratepayers, which is a more
meaningful way to assess the merits of BC Hydro’s accounts than counting them. We address
below the accounts that were a focus of information requests, questions or the InterGroup
evidence.
(a) Cost of Energy Variance Accounts Manage Uncontrollable Factors and Volatility
408. The Cost of Energy Variance Accounts have been in place since 2004; the BCUC
approved them following the extensive BCUC Heritage Contract Inquiry. They provide a
669 Exhibit B-28, BC Hydro Rebuttal Evidence, p. 8, ll. 15-18. 670 Exhibit B-1, Application, Table 7-9, starting on p. 7-60; Exhibit B-5, BCUC IR 1.40.3.1. BC Hydro is applying to
close the Rate Smoothing Regulatory Account, the Capital Project Investigation Costs Regulatory Account, the Arrow Water Systems Regulatory Account and the Arrow Water Systems Provision Regulatory Account. BC Hydro has also identified an additional four accounts – the Rock Bay Remediation Regulatory Account, the Real Property Sales Regulatory Account, the Customer Crisis Fund Regulatory Account and the Mining Customer Payment Plan Regulatory Account - that may be able to be closed by fiscal 2024. At that point, BC Hydro would have 21 accounts.
671 Exhibit B-1, Application, p. 7-21; Exhibit B-16, BCUC IR 3.301.4. BC Hydro responded to questions about whether a similar threshold should be used to determine whether existing accounts should be closed. This is generally a moot point; most variance accounts experience variances of greater than $10 million. The Cost of Energy variance accounts have experienced variances in the hundreds of millions in recent years. However, there are also important conceptual reasons to avoid this approach: Exhibit B-16, BCUC IR 3.294.3 and Exhibit B-6, CEC IR 1.69.1.
- 178 -
301539.00025/94161307.1
valuable benefit to BC Hydro and ratepayers. They ensure that ratepayers pay the actual Cost
of Energy. They avoid the shareholder and ratepayers experiencing significant windfall gains
and losses due to uncontrollable factors. Specifically:
● The Heritage Deferral Account captures variances between the forecast and
actual cost of Heritage Energy, Market Electricity Purchases, Surplus Sales and
Domestic Transmission costs related to Surplus Sales, and other items approved
by BCUC Order No. G-96-04. These costs vary due to uncontrollable factors that
are difficult to predict such as water inflows, system load requirements, market
commodity prices, exchange rates and transmission rates. From fiscal 2015 to
fiscal 2019, cost variances have ranged from ($154.6) million to $81.7 million
(-38% to +23%).672
● The Non-Heritage Deferral Account captures variances between the forecast
and actual cost of Non-Heritage Energy, which includes IPP purchases and Long-
Term Commitments and Net Purchases (Sales) from Powerex.673 These costs
also vary due to uncontrollable factors that are difficult to predict, including
water inflows, surplus sales, electricity and gas market prices and domestic
load.674
Domestic load is subject to unpredictable volatility due to factors such as
weather and economic conditions. From fiscal 2015 to fiscal 2019, variances
between the actual and forecast Cost of Energy arising from differences between
actual and forecast domestic customer load alone have ranged from ($193.5)
million to $352.7 million.675
672 Exhibit B-16, BCUC IR 3.294.3. 673 Exhibit B-1, Application, p. 7-25. 674 Exhibit B-16, BCUC IR 3.301.5.1. 675 Exhibit B-16, BCUC IRs 3.301.4 and 3.301.5.
- 179 -
301539.00025/94161307.1
409. The BCUC has approved similar mechanisms for FortisBC Inc., the other major electric
utility in this province, to address revenue variances as a result of uncontrollable factors. In its
2012 Decision approving FortisBC Inc.’s revenue variance account, the BCUC stated:
The Commission Panel notes that these accounts for the most part represent variances in current period expenses which are proposed to be trued up in the short-term. In the Panel’s view, the creation of these deferral accounts represents a reasonable attempt to manage the uncertainty and unpredictability associated with accounts which are largely uncontrollable in nature.676
In 2014, as part of FortisBC Inc.’s 2014-2019 performance-based ratemaking plan, the BCUC
maintained the same treatment by ordering that revenue variances be deferred through the
flow-through mechanism.677
410. BC Hydro also included in its Rebuttal Evidence information from Standard & Poor’s that
showed the widespread use of accounts of this nature in the United States.678
(b) Non-Current Pension Cost Regulatory Account Manages Uncontrollable Factors and Volatility
411. The Non-Current Pension Costs Regulatory Account captures (a) variances between the
actual experience gains or losses related to BC Hydro’s pension and other post-employment
benefit plans, and (b) variances between actual and forecast non-current pension costs.679
Actual experience gains and losses are adjustments to the net pension plan liability and the
other post-employment benefit plan liabilities due to changes in discount rates, rates of return
on pension plan assets, and any experience gains or losses or changes in assumptions.
Variances between actual and forecast non-current pension costs are the differences in net
interest expense of the retirement benefit plans, which arise primarily due to the difference in
the rate (i.e., rate of return versus liability discount rate) used to determine the return on plan
676 Order No. G-110-12, p. 110; Order No. G-139-14, p. 228. 677 Order No. G-139-14. 678 Exhibit B-28, BC Hydro Rebuttal Evidence, p. 9, A. 5. 679 Exhibit B-16, BCUC IR 3.300.2.
- 180 -
301539.00025/94161307.1
assets between the Application and the actual results.680 In both cases, most of the factors
impacting these costs are beyond BC Hydro’s control as they are largely market driven.681 The
account thus avoids windfall gains and losses for either the shareholder or ratepayers,
consistent with the purpose of variance accounts as identified in the BCUC Checklist.
(c) Real Property Sales Regulatory Account Allows Ratepayers to Receive Benefits that Would Otherwise Flow to the Shareholder
412. The Real Property Sales Regulatory Account allows ratepayers to receive significant
benefits from planned sales of surplus property and property rights (e.g., statutory rights of
way) that would otherwise flow to the shareholder. As discussed below, proposed rates in the
Test Period would be higher but for this account.
The Law Defaults to Flowing Proceeds of Sale to the Shareholder, Not Ratepayers
413. The underlying legal context is key to understanding the importance of this account to
ratepayers. The Supreme Court of Canada’s 2006 decision in ATCO Gas & Pipelines Ltd. v.
Alberta (Energy & Utilities Board) governs. It held that the shareholder, not ratepayers, is
entitled to the proceeds of sale from properties that are no longer used and useful for utility
purposes. The Court stated, for instance:
The fact that the utility is given the opportunity to make a profit on its services and a fair return on its investment in its assets should not and cannot stop the utility from benefiting from the profits which follow the sale of assets. Neither is the utility protected from losses incurred from the sale of assets. In fact, the wording of the sections quoted above suggests that the ownership of the assets is clearly that of the utility; ownership of the asset and entitlement to profits or losses upon its realization are one and the same.682
Thus, in the absence of BC Hydro’s regulatory account, customers would not receive the
proceeds of sale of surplus properties.
680 Exhibit B-16, BCUC IR 3.300.1. 681 Exhibit B-16, BCUC IR 3.300.5. 682 ATCO Gas & Pipelines Ltd. v. Alberta (Energy & Utilities Board), 2006 SCC 4. See for example, para. 67.
Online: https://www.canlii.org/en/ca/scc/doc/2006/2006scc4/2006scc4.html.
- 181 -
301539.00025/94161307.1
BC Hydro and its Shareholder Want to Flow Net Sale Proceeds to Customers
414. In the current situation, BC Hydro has properties and property rights purchased over the
decades for utility purposes, but that are now surplus to BC Hydro’s requirements.683 Mr.
Leonard gave examples of the types of properties and property rights involved and how they
became surplus to BC Hydro’s requirements. He emphasized that BC Hydro has sold surplus
properties and property rights over the years, and there are currently only a limited number of
properties at issue.684 Prior to the establishment of the Real Property Sales Regulatory
Account, pursuant to Direction No. 7 to the BCUC, net gains from sales of surplus properties
and property rights would have gone to the Government of B.C., as BC Hydro’s shareholder,
consistent with the law outlined above. The government directed the establishment of the
account to help take pressure off rates as part of the 10 Year Rates Plan.
415. Mr. Layton explained that, in the former 10 Year Rates Plan, BC Hydro committed to
achieving $100 million of net proceeds from sales of surplus properties and to provide that
benefit to ratepayers over the period ending in fiscal 2024.685 The desired outcome is achieved
by (1) forecasting an amount of sales revenues for inclusion in the revenue requirements,
combined with (2) the use of the Real Property Sales Regulatory Account to capture variances
between forecast and actual net sale proceeds within each fiscal year.686 As the actual gains
from the sales of these surplus properties are received, it reduces the balance in the account.
Mr. Layton noted that “subject to interest, that account should…self-clear.”687
416. In other words, ratepayers have been getting the benefit of these sales in advance,
annually and on a consistent basis since fiscal 2015. Rates since fiscal 2015 have been lower
than they otherwise would have been had BC Hydro continued to flow those benefits to the
shareholder. Similarly, rates in the Test Period will be lower than they otherwise would be by
683 Mr. Leonard explained that “In order to be deemed surplus, it is not needed for operational business purposes
currently or in the future”: Tr. 13, p. 2525, ll. 18-21 (Leonard). 684 Tr. 13, p. 2530, l. 25 to p. 2532, l. 11 (Leonard). 685 Tr. 8A, p. 1179, ll. 11-26 (Layton); Tr. 8A, p. 1188, ll. 21-23 (Layton). 686 Exhibit B-16, BCUC IR 3.299.3. 687 Tr. 8A, p. 1179, ll. 11-26 (Layton). See also, Exhibit B-16, BCUC IR 3.299.3.
- 182 -
301539.00025/94161307.1
virtue of the inclusion of a forecast $10 million688 of net gains in each of fiscal 2020 and fiscal
2021. The current plan, subject to what the BCUC decides in this proceeding, would be to do
the same in fiscal 2022 to fiscal 2024.
BC Hydro Has Turned a Profit on Every Sale
417. As of March 31, 2019, the balance in the Real Property Sales Regulatory Account was
$49 million, which reflects the fact that actual sales have been less than anticipated at this
point in time.689 However, this is not a “loss” in either the financial sense or from the
perspective of ratepayers:
● BC Hydro has turned a profit on every sale, and expects that to continue.690
● From a ratepayer perspective, it means that customers have received benefit for
some sales that have yet to materialize.691 It is a timing issue that has favoured
(not harmed) current ratepayers. While the intent was for the benefits reflected
in rates each year to approximate the pace that BC Hydro actually realized the
net gains from sales, customers effectively received an “advance” on the
benefits over the past four years to the extent sales did not keep pace.
418. While the BCUC has discretion to discontinue use of this regulatory account, this would
be disadvantageous to customers. First, the account would still have to remain open and the
BCUC would still have to allow recovery of the balance as at March 31, 2019 by virtue of
688 Exhibit B-16, BCUC IR 3.299.3. BC Hydro is forecasting annual net gains on real property sales of $19.1 million.
The difference between the $19.1 million forecast net gains and the $10 million baseline included in the revenue requirements reduces the balance in the Real Property Sales Regulatory Account so that it will self-clear by fiscal 2024.
689 Exhibit B-19, Evidentiary Update, Appendix D, Table D-2. BC Hydro described the reasons for the slower sales in BCUC IR 3.299.1, and they are discussed further later in this Part of the Submissions. BCUC IR 3.299.7 provides a list of properties that BC Hydro has sold, and will be sold, to achieve the $100 million in net gains by the end of fiscal 2024.
690 Tr. 13, p. 2527, ll. 2-14 (Leonard). 691 Tr. 8A, p. 1183, ll. 1-5 and 21-26 (Layton); Tr. 8A, p. 1217, ll. 1-5 (Layton).
- 183 -
301539.00025/94161307.1
Direction 8.692 Second, BC Hydro still expects some combination of these properties to be sold
to achieve a target of $100 million in net gains by fiscal 2024.693 Precluding new additions to
this regulatory account would foreclose the opportunity for customers to benefit from those
sales. It would result in the net proceeds flowing to the shareholder and higher rates (other
things equal) for customers in the Test Period and beyond. Accordingly, the account should
remain in place, and BC Hydro should continue to include forecast net proceeds in annual
revenue requirements until the targeted sales of $100 million are achieved.
419. The question of what amount represents a reasonable forecast of net sale proceeds in
each year of the Test Period is a distinct issue from the merits of the account itself. The former
issue is really a matter of timing (i.e., how fast can BC Hydro reasonably expect to reach the
$100 million target). BC Hydro explains below in Section H of this Part why it is reasonable to
forecast annual sales revenue of $19.1 million in each of fiscal 2020 and fiscal 2021.694
Costs Incurred to Bring Properties to Market Are Dwarfed by the Sale Proceeds
420. BC Hydro was asked at the hearing about the costs of preparing the properties for sale,
and the carrying costs in the interim (e.g., property taxes). Commissioner Mason inquired
whether BC Hydro was, in effect, engaging in property speculation.695 BC Hydro understood the
questions on this topic to be asking whether it was fair for customers to be paying for those
costs through rates, or whether they should be to the account of the shareholder. BC Hydro
submits that it is appropriate for BC Hydro to try to maximize the return on these properties
and that the costs of doing so should be recovered from customers:
692 Section 4 of Direction No. 8 states that the BCUC must not disallow recovery in rates of the balance of BC
Hydro’s regulatory accounts as at March 31, 2019; Exhibit B-1, Application, p. 2-9. 693 Exhibit B-16, BCUC IR 3.299.7. 694 Exhibit B-16, BCUC IR 3.299.3. Annual forecast net gains on real property sales of $19.1 million are included in
the Evidentiary Update. The difference between the $19.1 million forecast net gains and the $10 million baseline included in the revenue requirements reduces the balance in the Real Property Sales Regulatory Account.
695 Tr. 13, p. 2546, ll. 10-15 (Leonard).
- 184 -
301539.00025/94161307.1
● The account, which is what allows ratepayers to benefit from surplus property
sales, is premised on net proceeds (i.e., sale proceeds, less costs) flowing to the
account. Put another way, the shareholder agreed to flow net proceeds to
customers; it did not agree to forego gross sale proceeds while continuing to
bear all associated costs. The current treatment is symmetrical.
● The $100 million target for net proceeds, portions of which have been flowing to
ratepayers annually even before the sales are realized, was premised on BC
Hydro taking prudent steps to bring the property to market.
● The carrying and site improvement costs being paid by customers in rates are
dwarfed by the sale proceeds from which they are benefitting. Customers are
better off under the proposed approach, relative to one in which the
shareholder pays the carrying costs and keeps the sale proceeds.
421. BC Hydro submits that it would be incorrect to characterize BC Hydro’s efforts to
maximize sale proceeds from surplus properties as land speculation. BC Hydro acquired these
properties decades ago for utility purposes, not as an investment or to “flip” for a quick profit.
Mr. Leonard confirmed that BC Hydro is moving the properties to market as they are ready, but
there are challenges that slow the process.696 He also noted that, with unique properties (e.g.,
rights of way), the “market” may consist of one person who is not ready to buy.697
(d) DSM Regulatory Account Ensures Intergenerational Equity by Matching Costs and Benefits
422. BC Hydro’s Demand Side Management Regulatory Account captures all of BC Hydro’s
traditional DSM costs and low-carbon electrification (“LCE”) expenditures, recognizing that
these investments are integral to the success of the DSM portfolio and the achievement of the
benefits. The DSM Regulatory Account matches the recovery of all the costs to achieve the
696 Tr. 13, p. 2547, l. 16 to p. 2548, l. 5 (Leonard). 697 Tr. 13, p. 2545, l. 25 to p. 2546, l. 9 (Leonard).
- 185 -
301539.00025/94161307.1
benefits with the realization of the associated benefits over time.698 Benefit matching is a
recognized principle in the BCUC Checklist, and the deferral of DSM costs is a common
accounting treatment in the industry.699 Mr. Bowman, who generally favours reducing the use
of regulatory accounts, agrees with the use of a benefits matching account to address DSM.700
423. As the entire portfolio of DSM costs is required to generate the savings and other
benefits achieved, it is reasonable and appropriate for all DSM costs to be deferred to the DSM
Regulatory Account. As stated by Mr. Hobson: “we’ve got a combined portfolio, it’s got
programs, it’s got some supporting initiatives, and they all combine as necessary costs to
achieve the stream of savings.”701
424. In particular, Mr. Hobson emphasized the importance of costs for its Public Awareness
Supporting Initiative, which include public awareness, education and outreach, as described in
section 11 of the DSM Plan. This supporting initiative includes communication costs to increase
public education and awareness. As described in the DSM Plan, these are foundational
activities that are designed to overcome barriers to participation in DSM programs: awareness
of activities and programs and acceptance of those programs.702 Mr. Hobson explained:
We don’t measure benefits specific to components, I would say, within our plan in terms of cost components. We do it more based on the program itself in terms of what the offers are to drive up the savings. But the way that we would take a look at it would be the cost that we’re incurring to make customers aware, help customers work through some of the acceptance issues they have with efficiency, are an important cost that are necessary to achieve the benefits.703
425. Mr. Hobson also clarified that, while the Conservation Energy Management group
leverages other parts of the organization to carry out its initiatives, all of these costs are
698 Exhibit B-5, BCUC IR 1.150.7. 699 Exhibit B-5, BCUC IR 1.150.2. 700 Exhibit C11-11, InterGroup Evidence, p. 24. 701 Tr. 15, p. 2892, ll. 20-25. 702 Exhibit B-1, Appendix X, p. 75. 703 Tr. 15, p. 2895, ll. 12-21 (Hobson).
- 186 -
301539.00025/94161307.1
included within the DSM portfolio.704 Therefore, it is reasonable and appropriate that all of the
costs of the DSM portfolio be captured by the DSM Regulatory Account.
426. We explain in Subsection F(c) below why BC Hydro’s amortization period accomplishes
the desired matching.
(e) Remediation Regulatory Account Manages Uncontrollable and Unpredictable Costs
427. The Remediation Regulatory Account captures variances between forecast and actual
asbestos remediation costs and costs related to compliance with polychlorinated biphenyl
(PCB) regulations. The scope of this account had originally been limited to asbestos
remediation costs, consistent with a requirement of Direction No. 7. However, in BCUC Order
No. G-47-18, the BCUC approved the expansion of this account to include variances in PCB
costs. The Decision stated that:
…the Panel concurs with BC Hydro that PCB costs are similar in nature to asbestos costs in that they involve long-term estimates, the actual expenditures are susceptible to variances in amount and timing and differences from forecast due to the timing and scope of work undertaken.705
428. In other words, the BCUC recognized the underlying rationale for including remediation
cost variances in a regulatory account independently of any legislated requirement. The same
rationale applies today. The Remediation Regulatory Account has experienced significant
variances.706
E. BC HYDRO AND GOVERNMENT HAVE ADDRESSED THE AUDITOR GENERAL’S CONCERNS ABOUT REGULATORY ACCOUNTS
429. Phase One of the Comprehensive Review resulted in enhanced BCUC oversight, BC
Hydro fully adopting IFRS, and BC Hydro writing-off the balance in the Rate Smoothing
Regulatory Account.707 As a result, the Auditor General removed her qualification regarding the
704 Tr. 15, p. 2893, ll. 5-16 (Hobson). 705 Exhibit B-1, Application, p. 7-40. 706 Exhibit B-15, BCUC IR 3.301.1. 707 Exhibit B-1, Application, pp. 7-7 and 7-8.
- 187 -
301539.00025/94161307.1
use of rate-regulated accounting at BC Hydro on the Government of B.C.’s fiscal 2019 financial
statements.708 With the Auditor General’s concerns resolved, the BCUC can, and should, make
its determinations regarding BC Hydro’s regulatory accounts by focussing on the purpose
served by each account and how BC Hydro is managing the balances.
F. BC HYDRO IS MANAGING REGULATORY ACCOUNT BALANCES APPROPRIATELY
430. Section 4 of Direction No. 8 states that the BCUC must not disallow recovery in rates of
the balance of BC Hydro’s regulatory accounts as at March 31, 2019; however, the BCUC retains
discretion over how and when the balances are recovered.709 The evidence, outlined below,
demonstrates that BC Hydro is taking the necessary steps to manage regulatory account
balances, using appropriate BCUC-approved recovery mechanisms and exercising discipline
over controllable costs.
(a) Overall Regulatory Balance Has Declined Significantly from its Peak
431. BC Hydro’s regulatory account balances have declined by approximately 30% between
fiscal 2017 and fiscal 2019, from $5.908 billion at the end of fiscal 2016 to $4.193 billion at the
end of fiscal 2019.710 Although a material portion of the reduction in recent years has come
from the write-off of the balance of the Rate Smoothing Regulatory Account, it is also
attributable to ongoing recovery of the balances in almost all of BC Hydro’s regulatory accounts
in rates based on BCUC approved recovery mechanisms, higher than planned Powerex net
income, and the adoption of IFRS 15.711
708 In the Independent Auditor’s Report included in the Public Accounts 2018/19, the Auditor General stated: “For
the year ending March 31, 2019, BC Hydro has implemented International Financial Reporting Standards (IFRS), including IFRS 14 (Regulatory Deferral Accounts). Government has made a number of changes to the regulatory framework, giving the regulator the ability to influence costs and rates. I believe the changes made to the regulatory framework are sufficient to allow me to remove my qualification on the use of rate-regulated accounting for the year ending March 31, 2019.” See also the Office of the Auditor General’s report titled “Understanding Our Audit Opinion on B.C.’S 2018/19 Summary Financial Statements”: Exhibit B-12, BCUC IR 2.201.3.
709 Exhibit B-1, Application, p. 2-9. 710 Exhibit B-19, Evidentiary Update, Appendix D, Table D-2, p. 4 and Exhibit B-1, Application, Table 7-1, p. 7-9. 711 Exhibit B-1, Application, pp. 7-2 and 7-3.
- 188 -
301539.00025/94161307.1
(b) Approximately 80% of the Fiscal 2024 Forecast Balance is Associated With Longer-Term Accounts
432. BC Hydro has BCUC-approved recovery mechanisms to collect, in rates, the balances in
almost all if its regulatory accounts.712 Approximately 80% of the forecast balances in fiscal
2024 resides in five regulatory accounts that are being, or will be, recovered over a longer
period of time to promote intergenerational equity.713 Specifically:
● The First Nations Provisions Regulatory Account, which is drawn down as annual
settlement payments are made over a longer period of time;
● The DSM Regulatory Account, for which the expenditures added each year are
recovered over the 15-year benefit period;
● The Site C Regulatory Account, which is not yet being recovered in rates because
the Site C project is not yet in-service. In a future application, BC Hydro will
propose that the balance in the account be recovered over the average life of
the Site C assets, as that is the period that customers will benefit from those
costs; and
● The two IFRS Transition Accounts, which are being amortized into rates over the
same period of time as under the previous CGAAP accounting rules.714
(c) Appropriate BCUC-approved Recovery Mechanisms Are in Place
433. BCUC-approved mechanisms are in place for the Test Period to recover the balances in
rates, with the exception of three accounts where recovery mechanisms are not yet
required.715 Inquiries about BCUC-approved recovery mechanisms focussed on a limited
712 Exhibit B-1, Application, pp. 7-20 and 7-21. The Mining Customer Payment Plan Regulatory Account, Customer
Crisis Fund Regulatory Account, and the Site C Regulatory Account do not have approved recovery mechanisms as they are not yet required.
713 Exhibit B-19, evidentiary Update, Appendix D, Table D-2 shows the forecast balances for each of BC Hydro’s regulatory accounts to fiscal 2024.
714 Exhibit B-1, Application, p. 7-11. 715 Exhibit B-1, Application, pp. 7-20 and 7-21.
- 189 -
301539.00025/94161307.1
number of accounts, which are addressed below. BC Hydro submits that the mechanisms in
place for each of these accounts reflect the underlying purpose of the account and remain
appropriate.
Recovery of IFRS Transition Regulatory Accounts Maintains Revenue Requirement Impacts of Previous Accounting Rules
434. In fiscal 2013, BC Hydro transitioned to the Prescribed Standards, which were based on
the principles of IFRS, combined with regulatory accounting. The change impacted the method
of accounting for capital overheads. It also required BC Hydro to recognize on its balance sheet
all unamortized actuarial gains and losses on its pension and other post-employment benefit
plans. The IFRS Property, Plant and Equipment Regulatory Account and the IFRS Pension
Regulatory Account capture the financial impact of these changes.716
435. The rates in the Test Period include amounts for the amortization of the account
balances, consistent with the approved methodology. There will be no further additions to the
IFRS Property, Plant and Equipment Regulatory Account after the end of the Test Period. There
are no further additions to the IFRS Pension Regulatory Account. The recovery periods for
these regulatory accounts remain appropriate, since they result in approximately the same
revenue requirement impact as there would have been under the previous accounting rules.717
436. BC Hydro was asked about the ongoing effect of the original BCUC order that addressed
amortization of these accounts (Order No. G-77-12A), given that the order had referenced
specific dollar amounts for recovery in rates during that test period.718 The amounts approved
were determined by applying BC Hydro’s proposed 20 and 40 year amortization periods for the
IFRS Pension and IFRS Property, Plant and Equipment regulatory accounts, respectively. BC
Hydro has interpreted Order No. G-77-12A and subsequent orders regarding these accounts as
endorsement of the 20 and 40 year amortization periods because the amortization periods
were explicit in the evidentiary record. If the BCUC considers that additional clarification
716 Exhibit B-1, Application, p. 7-18. 717 Exhibit B-16, BCUC IR 3.301.6. 718 Exhibit B-5, BCUC IR 1.154.1.
- 190 -
301539.00025/94161307.1
regarding the amortization periods is required prospectively, then BC Hydro respectfully
requests express approval of the current amortization periods.719
Recovery of DSM Regulatory Account Matches Costs and Benefits
437. The current 15-year amortization period of the DSM Regulatory Account is supported by
the average effective measure life (or “persistence”) of DSM initiatives.
438. Effective measure life is used by BC Hydro and other utilities to inform the amortization
period for a DSM regulatory account because it matches costs and benefits.720 BC Hydro
determined effective measure life values with reference to credible third-party research, using
professional judgement in those specific cases where third-party research was unavailable.721
There are a significant number of persistence studies across the DSM industry, and it is
standard industry practice to use these persistence studies to inform effective measure life
assumptions.722 BC Hydro has provided detailed evidence supporting the measure lives values
for its DSM initiatives.723
439. Table 10-14 of the Application, reproduced below, shows that the weighted average
measure life of DSM expenditures over the Test Period is 15 or more years.724
719 Exhibit B-5, BCUC IR 1.154.1. 720 Exhibit B-5, BCUC IR 1.150.2. 721 Exhibit B-1, Application, pp. 10-35 and 10-36. BC Hydro referenced research from the Public Service
Commission of Wisconsin, the California Public Utilities Commission, the 2001 Database for Energy Efficiency Resources, and Skumatz Economic Research Associates Inc., among others.
722 Exhibit B-5, BCUC IR 1.178.1.1. 723 Exhibit B-1, Application, pp. 10-35 to 10-37; Exhibit B-5, BCUC IRs 1.150.2, 1.178.1, and 1.178.1.1; Exhibit B-12,
BCUC IRs 2.275.1 and 2.275.2. 724 Exhibit B-1, Application, p. 10-37.
- 191 -
301539.00025/94161307.1
Table 10-14 Average Measure Life (years)
2-Year Period F2020-F2021
10-Year Period F2020-F2029
GWh Weighted
$ Weighted
GWh Weighted
$ Weighted
Codes and Standards 30.0 30.0 30.0 30.0 Conservation Rates 1.3 1.3 1.2 1.2 DSM Programs 10.4 12.2 11.8 13.2 Low-Carbon Electrification 27.0 24.9 24.4 19.8 Codes and Standards, Conservation Rates, and DSM Programs
18.7 13.5 17.9 14.7
DSM Programs and Low-Carbon Electrification
17.1 15.0 16.2 15.0
440. The values in the above table are conservative because the calculation equates
persistence to the effective measure life of a DSM initiative and does not consider that some
customers will re-install an efficient measure when the initial measure has reached its end-of-
life, rather than revert to an inefficient measure. In these cases, the persistence of the DSM
initiative continues beyond the effective measure life. For this reason, the California Public
Utilities Commission uses a deemed assumption that 50 per cent of savings persist beyond the
expiration of the measure’s life in its Energy Efficiency Policy Manual.725
441. A 15 year amortization period is also reasonable when considering the average measure
life of all DSM measures in the Regulatory Account at the end of fiscal 2021: 14.5 years on an
energy (GWh) weighted basis and 14 years on an expenditure weighted basis.726 Again, these
amounts are conservative as they do not account for reinstallation of efficiency measures, as
accounted for by the California Public Utilities Commission.
725 Exhibit B-1, Application, p. 10-37. 726 Exhibit B-5, BCUC IR 1.150.5.1.
- 192 -
301539.00025/94161307.1
442. Continuing to use the 15 Year amortization period, in light of the evidence above, will
have the following benefits:727
● Matching – the current amortization period of 15 years appropriately matches
the costs with the period of time that the benefits will be realized by customers
(i.e., average measure life of DSM measures);
● Intergenerational equity – as benefits of DSM measures will be realized in future
periods, BC Hydro believes that it is fair and equitable that these costs should be
paid by future customers that will benefit from these expenditures. In other
words, current ratepayers are not unduly burdened by having to pay for the full
DSM costs today when these costs will provide benefits into the future. The
current amortization period of 15 years supports intergenerational equity
between current and future ratepayers; and
● Rate stability - maintains the status quo and therefore does not result in an
adverse rate impact for ratepayers in the current Test Period. A shorter
amortization period would result in higher rates for customers.
443. Shortening the amortization period materially would not be justified based on the
evidence of effective measure life. Amortizing the balance in the Demand Side Management
Regulatory Account over 10 years, for example, would result in over-collecting costs during that
period.728 This would undermine intergenerational equity, as current customers would begin
paying for a higher share of current DSM expenditures, while in past years customers have
been paying for a lesser share based on the lengthy persistence of DSM benefits.729 Further,
shortening the amortization period will result in higher rates for customers. In BC Hydro’s
submission, maintaining the status quo is preferable as it is supported by the average measure
727 Exhibit B-5, BCUC IR 1.150.6.1. 728 Exhibit B-16, BCUC IR 3.298.4. 729 Exhibit B-5, BCUC IR 1.150.6.1.
- 193 -
301539.00025/94161307.1
life, results in customers being treated similarly as in past years, and will avoid unnecessary rate
increases.
Recovery of Non-Current Pension Costs Regulatory Account Matches Updated External Valuation
444. BCUC Order No. G-47-18 approved BC Hydro’s proposal that variances transferred to the
Non-Current Pension Costs Regulatory Account be amortized over the expected average
remaining service life (EARSL) of the active plan members.730
445. The amortization period used in the Application was 12 years, reflecting the EARSL of
the active plan members at the time the Application was being prepared. BC Hydro’s external
actuary subsequently completed an actuarial valuation and EARSL increased to 13 years due to
changes in termination rates and retirement rates. The Evidentiary Update was thus based on a
13-year amortization period.731
446. InterGroup’s report suggested that BC Hydro ought to have recognized in the
Evidentiary Update the favourable impact on non-current pension costs of anticipated changes
in legislation relating to B.C.’s Medical Services Plan. Accounting standards precluded BC Hydro
from recognizing the impact of these changes before the required legislation had been passed.
This meant that the impact was not recorded until this Test Period. The BCUC’s orders require
BC Hydro to record variances arising during this Test Period in the Non-Current Pension Costs
Regulatory Account, for amortization in the next test period.732 Mr. Bowman conceded during
cross-examination that BC Hydro was following the BCUC’s orders.733
(d) Cost Control Measures Are in Place for Deferred Controllable Costs
447. While many deferred costs are uncontrollable (the uncontrollable nature of costs is a
rationale for many accounts), this is not always the case. In some instances, the account is
730 Exhibit B-5, BCUC IR 1.40.3.1. 731 Exhibit B-17, AMPC IR 3.5.4.2. 732 Exhibit B-28, BC Hydro Rebuttal Evidence, p. 14. 733 Tr. 11, p. 2064, ll. 5 to 16 (Bowman).
- 194 -
301539.00025/94161307.1
managing timing uncertainty or matching costs and benefits. The evidence discussed
throughout these Submissions shows that processes and procedures are in place to manage
controllable costs recovered through regulatory accounts.734
G. BC HYDRO’S PROPOSED CHANGES TO REGULATORY ACCOUNTS ARE WARRANTED
448. BC Hydro has demonstrated that its proposed changes to regulatory accounts are
warranted.735 The material changes (with the exception of the proposal to defer low-carbon
electrification expenditures to the Demand Side Management Regulatory Account, which is
addressed in Part Eleven of this Submission) are addressed below.
(a) Proposal to Reduce the DARR and Refund the Balance in the Cost of Energy Variance Accounts over the Test Period Promotes Intergenerational Equity and Rate Stability
449. BC Hydro is proposing to (a) reduce the DARR from 5% to 0% on April 1, 2019, and (b)
refund over the Test Period the fiscal 2019 net closing balance and the forecast fiscal 2020 and
fiscal 2021 net additions and net interest applied to the Cost of Energy Variance Accounts.736
Based on the Evidentiary Update, these proposals result in a refund to the benefit of ratepayers
during the Test Period of approximately $630.8 million.737
450. As between the two Test Years, BC Hydro is proposing to refund most of this amount in
fiscal 2021. The proposed allocation as between the two Test Years avoids the need to adjust
the bill impact associated with the BCUC’s interim rate order for fiscal 2020 (1.76% net bill
increase).738 Avoiding a bill adjustment for fiscal 2020 also eliminates a potential source of
customer confusion, since fiscal 2020 will be over by the time the BCUC renders its decision.
We provide further discussion demonstrating the merits of this approach in Part Twelve Section
B below.
734 Exhibit B-5, BCUC IR 1.40.3.1. See also, Tr. 6, p. 824, ll. 9-17 (Layton). 735 Exhibit B-1, Application, pp. 7-21 to 7-23. 736 Exhibit B-1, Application, p. 7-22. 737 Exhibit B-17, ZONE II RPG IR 3.60.1. 738 BCUC Order No. G-45-19. Exhibit B-19, Evidentiary Update, p. 10.
- 195 -
301539.00025/94161307.1
451. BC Hydro was asked whether the account balance should be amortized over a longer
period of time, e.g., by using the DARR table mechanism. BC Hydro submits that returning the
balance to customers during the Test Period best achieves intergenerational equity. A
significant portion of the net credit balance in the Cost of Energy Variance Accounts is due to a
one-time accounting adjustment of $319 million related to the recognition of revenues under
the Skagit River Agreement. This adjustment resulted in a retroactive decrease in unearned
revenues, which effectively means that previous ratepayers have overpaid. BC Hydro’s request
allows the impact of this adjustment to be returned to ratepayers sooner.739
452. BC Hydro modelled a number of other options put forward by parties and BCUC staff for
returning the balance in the Cost of Energy Regulatory Accounts to customers. These scenarios
are discussed in Part Twelve of these Final Submissions, which addresses Implementation of
rates. Generally speaking, BC Hydro’s proposal is simpler to administer, more transparent, and
produces more stable rates during the Test Period.740
(b) Proposal to Defer Variances Related to EPAs that are Leases Under IFRS 16 to the Non-Heritage Deferral Account Means Ratepayers Will Pay Actual Costs through Stable Rates
453. BC Hydro is proposing to defer to the Non-Heritage Deferral Account any variances
related to the treatment of certain EPAs as leases under IFRS 16.741 The adoption of IFRS 16
impacts the timing of expenses associated with these EPAs. In the absence of the accounting
change, these costs would have been borne by ratepayers in future periods.742 The proposal
places customers in the position they would have been in but for the accounting change, and
promotes rate stability. Ratepayers will pay the actual costs that BC Hydro incurs over the term
of the EPAs.
739 Exhibit B-5, BCUC IR 1.148.5. 740 Exhibit B-16, BCUC IR 3.296.3. Specifically refer to the discussion with regards to Scenarios A, B(i), B(ii) and K. 741 Exhibit B-1, Application, pp. 7-22 and 7-27. 742 Exhibit B-5, BCUC IR 1.146.2; Exhibit B-16, BCUC IR 3.302.3.1.
- 196 -
301539.00025/94161307.1
454. The expenses attributable to EPAs recognized on the balance sheet as leases under IFRS
16 are classified as finance charges and depreciation expense and not as Cost of Energy.
Variances related to finance charges are eligible for deferral to the Total Finance Charge
Regulatory Account. However, depreciation variances attributable to EPA leases are not eligible
for deferral within any existing regulatory account.743
455. BC Hydro prepared the Application using a preliminary estimate of the impacts of IFRS
16. The Evidentiary Update reflected BC Hydro’s complete assessment, which included
discussions with the Office of the Auditor General (BC Hydro’s external financial statement
auditor).744 Consistent with BC Hydro’s proposal, the Evidentiary Update reflects the deferral of
the resulting net change of $82.8 million to the Non-Heritage Deferral Account.745
456. The alternatives to BC Hydro’s proposed treatment would be highly detrimental to
customers:
● Significant rate volatility could be expected if the BCUC were to instead direct
depreciation variances attributable to EPA leases be deferred to the
Amortization of Capital Additions Regulatory Account. The fiscal 2021 net bill
decrease of 1.01% would (other things equal) change to an estimated bill
decrease of 10.0%. It would be followed in fiscal 2022 by an estimated required
bill increase of approximately 19%.746
● Similar extreme volatility could be expected if the BCUC were to decline to defer
the $64.8 million opening balance adjustment to the Non-Heritage Deferral
Account and not direct the deferral of depreciation variances attributable to EPA
leases. The fiscal 2021 net bill decrease of 1.01% in the Evidentiary Update
743 Exhibit B-5, BCUC IR 1.146.1. It does not fall within the scope of, for instance, the Amortization of Capital
Additions Regulatory Account. 744 Exhibit B-16, BCUC IR 3.302.7. 745 Exhibit B-19, Evidentiary Update, Appendix F, p. 1. 746 Exhibit B-16, BCUC IR 3.302.6.
- 197 -
301539.00025/94161307.1
would change to an estimated bill decrease of 10%, with an estimated required
bill increase in fiscal 2022 of approximately 15%.747
457. Additional variances in finance charges and depreciation expense as a result of
accounting treatment could arise in various ways. For instance:
● The Auditor General’s agreement with BC Hydro’s impact assessment in the First
Quarter financial statements was conditional upon completing its audit of BC
Hydro’s annual fiscal 2020 financial statements.748 If the Auditor General does
not agree with BC Hydro’s implementation of IFRS 16 for EPA leases, then BC
Hydro would adjust its financial statements.749 A change in the assessed
accounting treatment from non-lease to a lease for one EPA could result in a
balance sheet adjustment in excess of $100 million.750
● Variances will arise for existing EPAs that are considered leases due to the need
to adjust the measurement of the right of use asset balance and the lease
obligation for actual inflationary increases, which may differ from forecast
inflation assumptions.751
● If a new EPA is recognized, there could be variances due to the timing of the
commencement of recognition or the amount of the depreciation and interest
expenses.752
458. BC Hydro submits that the evidence is compelling that its proposed approach is in the
best interests of the company and customers.
747 Exhibit B-16, BCUC IR 3.302.6. 748 Exhibit B-16, BCUC IR 3.302.7.1. 749 Exhibit B-16, BCUC IR 3.302.7.2 750 Exhibit B-5, BCUC IR 1.146.4. 751 Exhibit B-16, BCUC IR 3.302.2. 752 Exhibit B-16, BCUC IR 3.302.2
- 198 -
301539.00025/94161307.1
(c) Proposal to Defer Variances Between Forecast and Actual Amounts Related to Biomass Energy Program Means BC Hydro Will Recover its Costs, as Directed
459. BC Hydro is proposing to defer any variances between forecast and actual amounts
related to the Biomass Energy Program to the Non-Heritage Deferral Account. The forecast
costs in the Test Period associated with the Biomass Energy Program ($36 million for fiscal 2020
and $81 million for fiscal 2021) have been accounted for as Cost of Energy.753 However, BC
Hydro may be required to account for some of these costs as amounts other than Cost of
Energy (variances related to which would generally be deferred to the Non-Heritage Deferral
Account pursuant to existing orders). BC Hydro will not know the amount of those costs or how
to appropriately account for them until contracts are completed.754 The proposal will ensure
that BC Hydro recovers its costs with respect to the Biomass Energy Program, consistent with
legislative requirements.755
(d) Proposal to Continue Deferring Dismantling Costs Recognizes Uncontrollable Nature and Supports Regulatory Efficiency
460. BC Hydro is proposing to continue to defer to the Dismantling Cost Regulatory Account,
on an annual and ongoing basis, any variances between forecast and actual dismantling costs.
BC Hydro is also proposing (a) to continue to apply interest to the balance of the account, (b) to
recover the forecast interest charged to the account each year, and (c) to continue to recover
the forecast account balance at the end of a test period, over the next test period.756 BCUC
Order No. G-47-18 approved this proposal for the fiscal 2017 to fiscal 2019 test period. In its
Decision, the BCUC stated that, in its view, the timing of dismantling activities is largely within
BC Hydro’s control, but that the establishment of the account for the fiscal 2017 to fiscal 2019
period would allow BC Hydro to gain more experience with forecasting the timing of
753 Exhibit B-5, BCUC IR 1.147.3.1. 754 Exhibit B-1, Application, p. 7-28. 755 Exhibit B-1, Application, p. 7-22; Exhibit B-6, BCSEA IR 1.11.2. Order in Council No. 158/2019 requires the BCUC
to allow BC Hydro to recover the costs associated with the Biomass Energy Program. 756 Exhibit B-1, Application, p. 7-22.
- 199 -
301539.00025/94161307.1
expenditures.757 BC Hydro submits that, based on the evidence in the current proceeding, BC
Hydro’s proposed orders make sense.
461. First, BC Hydro’s recent experience has demonstrated that the timing of dismantling
activities continues to be uncontrollable and difficult to forecast accurately. Since fiscal 2012,
annual variances have ranged from $14.1 million below plan to $31.7 million above plan (a
range between -41% to +89% of plan).758
462. Second, the potential for such significant variances to arise is unsurprising. Dismantling
costs are largely driven by BC Hydro’s capital plan and are impacted by capital project
schedules. Similar to capital projects, dismantling projects may be forecast well in advance of
the actual work taking place. Project estimates may be from an earlier stage of the project
lifecycle and will have different degrees of accuracy depending on the phase of the project.
Any delays or advancements to capital project schedules could result in these expenditures
being incurred earlier or later than planned. In addition, the full scope and cost of dismantling
activities may not be known until the work is underway and emergency dismantling of assets or
unplanned dismantling may be required from time to time.759
463. Third, BC Hydro has significant dismantling costs planned during the Test Period ($67
million in fiscal 2020 and $43 million in fiscal 2021). In the absence of the Dismantling Cost
Regulatory Account, significant gains or losses could accrue to ratepayers or BC Hydro’s
shareholder. Continued use of the account for the Test Period will mean that ratepayers pay
the actual costs of dismantling activities.760
464. Fourth, BC Hydro’s use of the Dismantling Cost Regulatory Account is efficient. In fiscal
2018, BC Hydro had over 300 projects with dismantling costs, including 10 projects with
dismantling costs greater than $1 million. It would be very inefficient to seek approval to defer
757 Exhibit B-1, Application, pp. 7-28 and 7-29. 758 Exhibit B-1, Application, p. 7-29; Exhibit B-5, BCUC IR 1.149.1. 759 Exhibit B-1, Application, pp. 7-29 and 7-30; Exhibit B-5, BCUC IR 1.149.2. 760 Exhibit B-1, Application, p. 7-30.
- 200 -
301539.00025/94161307.1
dismantling costs on a case by case basis.761 The BCUC has previously rejected the approach of
requesting specific deferral treatment for the dismantling costs associated with specific
projects, preferring to address all dismantling costs in a consistent manner in a revenue
requirements application proceeding.762 The resulting uncertainty from having to apply on an
individual project basis could lead to increased project costs and schedule delays.763
465. BC Hydro was asked about the potential for substantial annual variances to offset over a
longer time horizon. BC Hydro submits that the potential for windfalls to shareholders and
customers to offset each other over the longer term in the absence of a variance account would
be an invalid basis for ceasing to use Dismantling Cost Regulatory Account (or, for that matter,
any other variance account). Rates are set based on forecast costs in a particular test period,
and aggregated variances over a period of time are not indicative of future volatility in a
particular test period. Proper regulatory accounting mechanisms should be used to recognize
or shift impacts across multiple test periods.764
H. FORECAST FOR REAL PROPERTY SALES IS REASONABLE
466. Subsection D(c) of this Part outlined why customers are better off as a result of the Real
Property Sales Regulatory Account. This section demonstrates the reasonableness of BC
Hydro’s forecast of real property sales for the Test Period.
467. BC Hydro has forecast net gains on real property (i.e., land and interest in land) sales of
$10 million per year from fiscal 2020 to fiscal 2024. This represents the remainder of BC
761 Exhibit B-16, BCUC IR 3.297.2. 762 BCUC Order No. G-96-17, with regard to BC Hydro’s Salmon River Diversion Ceasing of Operations Application,
stated: “At this time, the Panel does not consider there to be anything special or unique about the costs to Cease Operation and Decommission the Diversion that would warrant alternate treatment from the general dismantling costs treatment that will be determined in the RRA. The Panel considers that treatment of the costs to Cease Operations and Decommission the Diversion should be consistent with the general treatment of BC Hydro’s other dismantling costs.” See also: Exhibit B-16, BCUC IR 3.297.2.
763 Exhibit B-16, BCUC IR 3.297.2. 764 Exhibit B-16, BCUC IR 3.297.1.1.
- 201 -
301539.00025/94161307.1
Hydro’s $100 million target for net gains from surplus real property sales, which BC Hydro
expects to achieve by fiscal 2024.765
468. Mr. Leonard explained that, since BC Hydro set the original target of $50 million in net
sale proceeds by fiscal 2024, the value of surplus real properties increased. BC Hydro also
identified new surplus properties that can be sold. These developments justified increasing the
target to $100 million.766
469. Mr. Leonard provided an update on the sales as of the end of January 2020. He
indicated that BC Hydro has sold 17 properties and a number of rights-of-way. The gains on
those sales have reflected the anticipated amounts. The sales contribute to approximately
$14.65 million in net proceeds.767
470. BC Hydro submits that it is still reasonable to expect sales to occur in the coming years,
despite the slower than anticipated sales activity in previous years. The factors that have
delayed sale completions to-date include: (a) progress of consultation with First Nations on
property dispositions; (b) required subdivision, re-zoning and environmental remediation prior
to sale; (c) fluctuating market interest in the properties; and (d) the time for buyers’ due
diligence and processes to complete a purchase.768 However, property sales have already been
completed in fiscal 2020 with additional sales scheduled to complete. Activities required to
prepare properties for sale, including consultation with First Nations, completion of subdivision,
re-zoning and environmental remediation prior to sale are expected to be completed before
the end of fiscal 2024.769
765 Exhibit B-16, BCUC IR 3.299.3. BC Hydro is forecasting annual net gains on real property sales of $19.1 million.
The difference between the $19.1 million forecast net gains and the $10 million baseline included in the revenue requirements reduces the balance in the Real Property Sales Regulatory Account so that it will self-clear by fiscal 2024.
766 Tr. 13, p. 2522, l. 22 to p. 2524, l. 5 (Leonard). 767 Tr. 13, p. 2525, ll. 6-14 (Leonard). 768 Exhibit B-16, BCUC IR 3.299.1. 769 Exhibit B-16, BCUC IR 3.299.2.
- 202 -
301539.00025/94161307.1
471. BC Hydro filed a (confidential) current list of properties, some combination of which will
be sold to achieve the $100 million in net gains target by the end of fiscal 2024.770
472. BC Hydro provided, in response to an undertaking, the impact on the proposed rates
based on the assumption that the BCUC forecasted zero dollars flowing to this account for the
Test Period. The result was a rate decrease of 0.64% in fiscal 2021 instead of the 1.01% rate
decrease proposed by BC Hydro (i.e., a forecast of zero dollars would increase fiscal 2021 rates
by 0.37%).771 The benefits to ratepayers do not disappear under this scenario, provided that
the regulatory account remains in place; rather, the benefits are shifted to years following the
Test Period. BC Hydro underscores that the continued existence of the account is essential for
net proceeds from the sale of these properties to fiscal 2024 to flow to ratepayers, rather than
the shareholder.
I. CONCLUSION AND REQUESTED FINDING
473. The evidence discussed above is compelling and should be accepted. The BCUC should
find that BC Hydro’s current use of regulatory accounts, its proposals to close and modify some
of them, and its forecasted additions are just and reasonable.
770 Exhibit B-16, BCUC IR 3.299.7, Attachment 1. 771 Exhibit B-58, BC Hydro Undertaking No. 54. For the purpose of forecasting the estimated rate impact, BC Hydro
assumed that the requested rate increase for fiscal 2020 remained the same, and therefore the entire two-year impact of forecasting zero net gains from real property sales (i.e., lower net gains of $10 million per year) would be reflected in rates in fiscal 2021.
- 203 -
301539.00025/94161307.1
PART NINE: OTHER REVENUE REQUIREMENTS ITEMS
A. INTRODUCTION
475. Chapter 8 of the Application covers Other Revenue Requirements Items. This Part of BC
Hydro’s Final Submissions focusses on three aspects of the Other Revenue Requirements Items
that were addressed in AMPC’s evidence: depreciation rates, finance charges and return on
equity. We make the following points:
● First, BC Hydro’s depreciation rates are appropriate for the purposes of setting
rates in the Test Period. BC Hydro’s upcoming depreciation study will provide
stakeholders with additional confidence in BC Hydro’s depreciation rates going
forward.
● Second, regarding BC Hydro’s forecast finance charges:
➢ The forecast finance charges in the Evidentiary Update are reasonable
for the purposes of setting rates during the Test Period, being the
product of independent projections of future interest rates and a
debt management strategy to lock-in interest rates.
➢ BC Hydro’s existing Total Finance Charges Regulatory Account is an
efficient mechanism to ensure that customers will pay the actual
finance charges in circumstances where actual interest rates differ
from those reflected in the forecast finance charges.
● Third, BC Hydro’s return on equity has been determined by Direction No. 8 for
the Test Period. Matters related to the return on equity in future test periods
should be addressed by the BCUC panel hearing the upcoming cost of capital
application.
- 204 -
301539.00025/94161307.1
B. TEST PERIOD REVENUE REQUIREMENTS REFLECT APPROPRIATE DEPRECIATION RATES
476. BC Hydro recognized from the outset of this proceeding that it has been some time
since a comprehensive depreciation study has been completed. The timing of the next
comprehensive depreciation study has been one of those instances, to which Mr. O’Riley
alluded, where BC Hydro management has had to prioritize competing financial and work
demands on the organization.772 BC Hydro has agreed to advance the study (though it will not
be done in time for the next revenue requirements application773), recognizing that a new study
appears to be necessary for some stakeholders to have confidence in BC Hydro’s depreciation
rates going forward.774 The evidence summarized below explains the basis for BC Hydro’s
comfort in deferring a depreciation study until now. It also demonstrates that the current
depreciation rates are reasonable for the purposes of setting rates in the Test Period.
477. First, BC Hydro has regularly reviewed depreciation rates and has reflected new
information as part of meeting accounting standards and audit requirements. International
Accounting Standard (“IAS”) 16 outlines, in paragraph 51, the requirements for annual reviews
of residual values and useful lives:
51 The residual value and the useful life of an asset shall be reviewed at least at each financial year-end and, if expectations differ from previous estimates, the change(s) shall be accounted for as a change in an accounting estimate in accordance with IAS 8 Accounting Policies, Changes in Accounting Estimates and Errors.775
478. BC Hydro complies with this requirement by reviewing, on an annual basis, whether
there have been any changes in the factors that affect the useful lives of asset classes that are
772 Tr. 5 p. 376 l. 1 to p. 377, l.6 (O’Riley); Tr. 5, p. 435, ll. 1-23 (Wong). 773 The last depreciation study took approximately one year to complete from the completion of terms of
reference to the final report. Meanwhile, the next RRA would typically be filed in February 2021 and, in response to feedback from the BCUC, BC Hydro has committed to exploring whether it would be possible to file that application earlier. Additionally, forecast inputs (such as depreciation expense) for Revenue Requirement Applications, are required months before the actual filing. Exhibit B-28, BC Hydro Rebuttal Evidence, p. 16; Exhibit B-43, BC Hydro Response to Oral Hearing Feedback.
774 Exhibit B-43, BC Hydro Response to Oral Hearing Feedback. 775 Exhibit B-13, AMPC IR 2.41.4.
- 205 -
301539.00025/94161307.1
expected to have a material impact on BC Hydro’s depreciation expense. BC Hydro considers
annually whether there are any: (a) impaired assets, (b) assets that are no longer being used, or
(c) any instances of significant write-offs of assets in-service. BC Hydro confirmed that, when it
identifies that assets will be removed from service prior to the end of their expected useful lives
and they have a material book value, the remaining useful life of the asset is reduced to reflect
the change in expected life.776 BC Hydro provided examples where it has reviewed and
subsequently revised the useful lives of its asset classes to reflect new information.777
479. BC Hydro is under an obligation to ensure that its financial statements are free from
material misstatement. The obligation necessitates BC Hydro reviewing assumptions that feed
into the assessment of its material expenses, including depreciation expense, to ensure that
they continue to be reasonable. Mr. Layton explained that BC Hydro’s external financial
statement auditors have reviewed BC Hydro’s depreciation expense and have not identified any
material misstatement:
So if they thought that our depreciation expense was incorrect and resulted in a material error, they would tell us and if we didn’t adjust our financial statements, they would qualify our financial statements and say they’re not materially correct. And even more than that, that materiality can actually be a high number, but what our auditors do is even if they thought it was a couple of million dollars incorrect, they would raise it to management and if we didn’t make adjustments, they would raise it to our board. And what I can tell everyone in the room is that they haven’t raised that concern.778
480. Second, a review conducted by BC Hydro in fiscal 2010 of the useful lives of all of its
assets illustrates that, when considered in aggregate, potential life changes over time are
having a relatively limited impact on depreciation expense. The review indicated that the
776 Exhibit B-13, AMPC IR 2.41.9. 777 For example, the useful lives of analog meters were reduced as approved by BCUC Order No. G-115-11 because
the useful lives were shortened as a result of the meters being replaced prior to end of life as a result of the Smart Metering Initiative. In addition, as identified in section 8.2.1 of Chapter 8 of the Application, the useful lives of Burrard assets were reduced due to changes in the expected useful life of the facility.
778 Tr. 7, p. 944, l. 15 to p. 945, l. 1 (Layton).
- 206 -
301539.00025/94161307.1
aggregate impact of the potential life changes on depreciation expense was less than $1
million.779 Mr. Layton explained:
What was looked at was the classes themselves and working with Gannett Fleming and taking their advice on do we think any of these have changed. And they did identify a couple of potentially changes and what we did in terms of quantitative analysis was if those changes were to be done, what would the impact be? And as we stipulated in an IR, we think that the impact would have been less than a million dollars, and therefore we didn’t make any changes at that time.780
481. Third, analysis completed by BC Hydro in response to an AMPC information request
further underscores that the depreciation expense reflected in the Test Period revenue
requirements is reasonable. AMPC asked BC Hydro to identify any material assets that
exceeded their estimated service life for the particular assets, as set out in the last depreciation
study. Using a materiality threshold of assets with an original cost of $10 million or higher, BC
Hydro did not identify any individual specific assets that had a net book value of zero at March
31, 2019 and were still in use.781
482. InterGroup provided a schedule of asset classes that it suggested may warrant life
extensions, identifying BC Hydro’s useful lives and the useful life ranges used by peer utilities. If
anything, InterGroup’s comparison to other utilities should provide additional comfort about
the reasonableness of the Test Period depreciation expense. BC Hydro’s asset lives are within
the range provided for the peer utilities for nine of the 10 identified asset classes.782
779 Exhibit B-13, AMPC IR 2.41.2. 780 Tr. 7, p. 928, ll. 16-25 (Layton). 781 Exhibit B-13, AMPC IR 2.41.6. 782 Exhibit B-28, BC Hydro Rebuttal Evidence, p. 16.
- 207 -
301539.00025/94161307.1
C. BC HYDRO’S FORECAST FINANCE CHARGES ARE A REASONABLE BASIS FOR SETTING RATES
483. Finance charges are primarily comprised of interest charges on BC Hydro’s debt, but also
include interest related to non-current pension costs and leases recognized as lease obligations
under IFRS 16. BC Hydro’s forecast finance charges reflect:
• Actual interest rates on debt that has already been issued;
• Market forward rates for hedged debt that has not yet been issued; and
• Independent interest rate forecasts from the Treasury Board of the Government of B.C. for unhedged debt that has not yet been issued. 783 784
BC Hydro submits that the forecast finance charges in the Evidentiary Update are reasonable
for the purposes of setting rates during the Test Period.
(a) Hedging Strategy has Mitigated Interest Rate Risk
484. Since fiscal 2017, BC Hydro has locked in interest rates on forecast future long-term
debt issuances by entering into financial contracts that hedge interest rate risk.785 BC Hydro
has hedged approximately 71% of its total forecast borrowing requirements for the Test
Period.786 Hedging provides cost certainty regarding hedged future long-term debt issuances.
485. The purpose of the hedging strategy is to lock in a rate. Mr. Wong explained BC Hydro’s
debt management strategy using the simplifying analogy of a fixed mortgage rate:
And essentially what we want to do is lock in, to create certainty for BC Hydro and ratepayers, the interest rate we’re going to have on our debt that we’re going to be issuing over the next five years. So what we do is we transact interest rate hedges, or we call them here future debt hedges, to lock in the interest rate today. And so it’s very much like if you were to do a mortgage on your house and you take a fixed rate mortgage, you’re locking in that rate on your mortgage for
783 Exhibit B-1, Application, pp. 8-10 and 8-11. 784 The total interest costs that ratepayers will pay in respect of hedged debt is seen in finance charges and via the
Debt Management Regulatory Account. That’s because hedging gains or losses are deferred to the Debt Management Regulatory Account and are amortized over the term of the debt pursuant to BCUC Order No. G-42-16. Exhibit B-31, BCUC Panel IR 2.17.4 provides an explanation of how these factors offset and how ratepayers pay the hedged rate over time as a result.
785 Exhibit B-1, Application, p. 8-10. 786 Exhibit B-28, BC Hydro Rebuttal Evidence, p. 18.
- 208 -
301539.00025/94161307.1
five years at a fixed rate so you’re not subject to the variability of interest rates going up or going down and you have certainty over what your cost is going to be.787
486. Future Debt Hedges fluctuate in value before they are settled as forward interest rates
change. If forward interest rates increase/decrease relative to the hedged rate, then the Future
Debt Hedges will incur an unrealized gain/loss. However, any actual gain/loss on the Future
Debt Hedges will be offset by higher/lower interest costs when the associated future debt is
issued.788 Accordingly, as Mr. Wong explained, the objective of BC Hydro’s hedging strategy is
based on the ability to lock in interest rates based on expected future debt issuances, rather
than targeting a gain/loss that may occur over time.789 It has accomplished its purpose.
(b) Evidentiary Update Used the Most Recent Interest Rates Available for Unhedged Debt
487. BC Hydro uses forecasts that are developed by the Treasury Board of the Government of
B.C. to forecast finance charges for unhedged long-term and short-term debt.790 Mr. Wong
explained:
We have a methodology on how we forecast interest rates, and the Government of B.C. provides the forward curve based on their accumulation of several banks. They are the ones that go and issue debt for us. So BC Hydro has no – I don’t think we have any expertise that would be better than what the province is saying, and so that’s how we come up with our best estimate in the forecast.791
488. The Evidentiary Update used the most recent interest rates forecast available to BC
Hydro from the Government of B.C. at the time the forecast was prepared (as of January 4,
2019).792
787 Tr. 7, p. 953, ll. 2-16 (Wong). 788 Exhibit B-31, BCUC Panel IR 2.17.4. 789 Tr. 7, p. 956, ll. 17-20 (Wong). 790 Exhibit B-1, Application, pp. 8-10 and 8-11. 791 Tr. 7, p. 896, ll. 18-25 (Wong). 792 Exhibit B-28, p. 13. Based on this forecast, the interest rates used to forecast finance charges on unhedged
long-term debt were 3.46% for fiscal 2020 and 3.76% for fiscal 2021 and the interest rates used to forecast finance charges on short-term debt were 2.35% for fiscal 2020 and 2.69% for fiscal 2021: Exhibit B-6, BCOAPO IR 1.72.1.
- 209 -
301539.00025/94161307.1
(c) Regulatory Accounts Are an Efficient Means of Addressing Interest Rate Changes Since the Evidentiary Update
489. InterGroup recommends that, for unhedged debt and sinking funds, BC Hydro further
updates its finance charge forecasts to be based on: long-term debt interest rates that are
consistent with the rates for long-term debt that has been issued since the Evidentiary Update;
updated short-term debt interest rates; and updated sinking fund rates, if applicable.793 BC
Hydro submits that it is unnecessary to update finance charges again in the manner posited by
InterGroup. BC Hydro’s Total Finance Charges Regulatory Account is an efficient mechanism to
ensure that customers will pay the actual finance costs in the event that interest rates emerge
differently from forecasts.794 The reality is that markets change on a daily basis. The BCUC had
directed BC Hydro to create the account in 2009 (i.e., well before Direction No. 7) and the
account has been re-approved in several subsequent orders.795
490. BC Hydro addresses in Part Twelve, Section C why it would be particularly unreasonable
to update finance charges without updating pension costs (which, unlike finance charges,
increase as interest rates decline).
D. INTERGROUP’S RECOMMENDATIONS REGARDING BC HYDRO’S FUTURE RETURN ON EQUITY ARE PREMATURE
491. BC Hydro’s return on equity is fixed by regulation for the Test Period.796 InterGroup
nonetheless makes recommendations relating to BC Hydro’s return on equity in future test
periods, including factors it believes should be considered to determine BC Hydro’s future
return on equity.797 BC Hydro submits that the Panel should not opine on matters related to
the upcoming cost of capital proceeding.798 This Panel cannot fetter the discretion of the BCUC
793 Exhibit C11-11, InterGroup Report, Recommendations 14 to 16. 794 Exhibit B-28, BC Hydro Rebuttal Evidence, p. 13, ll. 10-16. 795 The history of the account is described in the Exhibit B-1, Application, pp. 7-36 and 7-37. 796 Direction No. 8, section 3. 797 Exhibit C11-11, InterGroup Report, Recommendations 4 to 6. 798 Tr. 5, p. 426 ll. 1-17 (O’Riley and Wong).
- 210 -
301539.00025/94161307.1
Panel hearing a future application. In any event, there is an insufficient evidentiary basis for
this Panel to make considered recommendations on this matter to a future BCUC Panel.
E. CONCLUSION AND REQUESTED FINDINGS
492. The BCUC should find that BC Hydro’s depreciation rates and forecast finance charges
are reasonable for the Test Period. It should refrain from making any findings or
recommendations with regards to BC Hydro’s future return on equity.
- 211 -
301539.00025/94161307.1
PART TEN: TRANSMISSION REVENUE REQUIREMENTS
A. INTRODUCTION
493. This Part addresses the Transmission Revenue Requirements (the “TRR”), which are the
subject of Chapter 9 of the Application and Appendix E of the Evidentiary Update.799 The TRR
includes the costs associated with the transmission lines and high-voltage station equipment
that are used to provide transmission service under BC Hydro’s Open Access Transmission Tariff
(“OATT”). BC Hydro’s evidence in the Application, Evidentiary Update and responses to
information requests demonstrates that BC Hydro’s updated OATT rates, which will collect the
TRR from transmission customers, are just and reasonable.
B. THE TRR AND OATT RATES REFLECT ESTABLISHED COST OF SERVICE METHODOLOGY AND APPROVED RATE DESIGN
494. There are two overarching reasons why the BCUC should have confidence in BC Hydro’s
determination of the TRR and OATT rates:
● First, the cost allocation methodology used to derive the TRR is based on cost
causation and is consistent with past practice.800 The allocation and direct
assignment of costs is described in detail in section 9.2, Chapter 9 of the
Application and is depicted in Figures 9-1 and Figure 9-2.801
● Second, the calculation of the OATT rates is consistent with the design of the
OATT rates previously reviewed and approved by the BCUC for BC Hydro and the
British Columbia Transmission Corporation (“BCTC”).802 Past BCUC Orders
approving the OATT rate design begin with Order No. G-43-98 and include over
799 Exhibit B-11. The Evidentiary Update increased the Transmission Revenue Requirement by $43.4 million in
fiscal 2020 and $42.2 million in fiscal 2021. Further information is provided in Appendix E of the Evidentiary Update.
800 Exhibit B-1, Application, p. 9-2. 801 Exhibit B-1, Application, pp. 9-3 and 9-4. 802 Exhibit B-1, Application, p. 9-2.
- 212 -
301539.00025/94161307.1
25 subsequent Orders.803 These subsequent Orders include major rate design
approvals such as Order No. G-58-04, when BCTC became the transmission
provider, and Order Nos. G-102-09 and G-103-09, when the OATT was updated
in response to major reforms to the FERC pro forma OATT in FERC Order No. 890.
495. BC Hydro responded to a number of information requests, providing additional details
on its cost allocation methodology and the OATT rate design. For example:
● BC Hydro explained how the TRR cost allocation methodology relates to BC
Hydro’s 2016 cost of service study (the “2016 COSS”), including explaining why
not all components of the 2016 COSS are applicable to the TRR.804
● BC Hydro explained how the Network Integration Transmission Service (“NITS”)
charge is calculated. Among other things, BC Hydro confirmed that the current
NITS charge is calculated as the residual TRR, as approved by the BCUC in Order
No. G-58-05, and remains consistent with the FERC pro forma tariff.805
● BC Hydro explained that the long-term point-to-point (“LT PTP”) rate design and
use of the maximum capacity supply billing determinant to establish the LT PTP
Rate is consistent with past practice and was also approved by the BCUC through
Order No. G-58-05.806
● BC Hydro explained that the short-term point-to-point (“ST PTP”) discount rate
design remains valid because (a) the main markets that border B.C. are still
fundamentally the same as when the ST PTP discount rates were designed, and
(b) the rates continue to be simple, easy to understand, stable, and help to
803 Exhibit B-31, BCUC Panel IR 2.8.5.2. 804 Exhibit B-31, BCUC Panel IRs 2.8.1 and 2.8.2. 805 Exhibit B-31, BCUC Panel IR 2.14.3. 806 Exhibit B-5, BCUC IR 1.166.3.
- 213 -
301539.00025/94161307.1
balance the objectives of promoting the use of the transmission system and cost
recovery.807
496. BC Hydro submits that all issues raised regarding the TRR and proposed OATT rates have
been addressed in responses to information requests. The evidence demonstrates that the cost
allocation methodology and calculation of the OATT rates are reasonable, consistent with past
practice and past BCUC Orders, and are calculated on a comparable basis to rates in
neighboring jurisdictions in the United States. As such, BC Hydro submits the proposed OATT
rates should be approved as just and reasonable.
C. RE-EXAMINING THE MERITS OF THE OATT RATE DESIGN IS UNNECESSARY
497. BC Hydro responded to a number of information requests that seemed to be directed at
the merits of the OATT rate design itself.808 BC Hydro is not requesting any determination in
this proceeding on OATT rate design, as this revenue requirements proceeding is focussed on
recovery of BC Hydro’s costs during the Test Period. In any event, as discussed below, BC
Hydro’s responses to the information requests show that the OATT rate design remains valid.
498. The OATT rate design has a long and complex history, has implications for the interplay
between BC Hydro’s system and the rest of the Western Interconnection, and has been the
subject of numerous BCUC proceedings and decisions.809 The complexity of BC Hydro’s OATT,
which is publicly available on BC Hydro’s website,810 is readily apparent on its face. BC Hydro
has developed detailed OATT business practices, which are also available online, to describe
how it implements various aspects of the OATT and to assist wholesale transmission
customers.811 BC Hydro and other wholesale transmission customers are sophisticated parties,
well-equipped to navigate the terms and conditions of the OATT and business practices.
807 Exhibit B-5, BCUC IR 1.166.6; Exhibit B-31, BCUC Panel IR 2.16.1.1. 808 E.g., Exhibit B-31, BCUC Panel IRs 2.8.5 to 2.8.8. 809 Exhibit B-31, BCUC Panel IR 2.8.5.2. 810 Online: https://www.bchydro.com/toolbar/about/planning_regulatory/tariff_filings/oatt.html 811 Online: https://www.bchydro.com/energy-in-bc/operations/transmission/transmission-scheduling/business-
practices.html. Exhibit B-5, BCUC IR 16.3.1, Attachments 1 to 9.
- 214 -
301539.00025/94161307.1
499. Significantly, BC Hydro’s maintenance of an OATT consistent with or superior to the
FERC’s pro forma OATT is required for Powerex to sell wholesale electricity at market-based
rates in the United States,812 which generates Trade Income for the benefit of BC Hydro’s
ratepayers.813 The current OATT accomplishes that critical outcome.
500. BC Hydro responded to several information requests that outline the impetus for the
OATT and demonstrate how the OATT provides fair, non-discriminatory access to the wholesale
transmission grid:
● BC Hydro provided a review of the development of the electric industry and
markets within the western interconnection, including British Columbia, and how
the OATT rates were developed to be reflective of these developments.814
● BC Hydro discussed how an eligible customer can become a transmission
customer and how PTP can be used to deliver energy from a generator to a load,
including for the import and export of electricity.815 Indeed, the OATT was
established in response to government policy to enable private sector
investment in B.C. to access the wholesale transmission grid to take advantage
of trade opportunities in wholesale power markets. While these developments
did not materialize in B.C., the OATT remains in place to facilitate this activity
should markets change.816
● BC Hydro explained how NITS is used to supply domestic load customers from
designated network resources and how network economy service, a secondary
service under NITS, can be used to supply network load from non-designated
generation resources.817
812 Exhibit B-5, BCUC IR 1.162.2. 813 Exhibit B-31, BCUC Panel IR 2.8.5.1. 814 Exhibit B-31 BCUC Panel IRs 2.8.5 to 2.8.5.1. 815 Exhibit B-5, BCUC IRs 1.163.1 to 163.1.4. 816 Exhibit B-31 BCUC Panel IR 2.8.5.1. 817 Exhibit B-5, BCUC IR 1.163.5; Exhibit B-31 BCUC Panel IRs 2.12.1.1 and 2.12.3.
- 215 -
301539.00025/94161307.1
501. BC Hydro has also demonstrated in response to information requests that it is
continuing to monitor changes made to FERC’s pro forma OATT and is regularly bringing
forward applications to the BCUC to amend its OATT to maintain consistency with FERC’s pro
forma and to address changes in the market.818 For example, BC Hydro is currently engaging
with transmission customers and interested parties to develop its response to three FERC
Orders related to generation interconnection procedures and ancillary rates schedules to take
into account the speed and accuracy of regulation resources.819
D. CONCLUSION AND REQUESTED FINDINGS
502. The BCUC should find that the Test Period OATT rates as filed in Exhibit B-11-2820 are
just and reasonable and should be approved.
818 Exhibit B-5, BCUC IR 1.162.2; Exhibit B-31, BCUC Panel IRs 2.8.5, 2.8.5.1, 2.8.5.2 and 2.8.6. 819 Exhibit B-31, BCUC Panel IR 2.8.5.1. 820 Exhibit B-11-2 is the corrected version of the Evidentiary Update filed on January 21, 2020. The OATT rates are
in Appendix E.
- 216 -
301539.00025/94161307.1
PART ELEVEN: DEMAND-SIDE MANAGEMENT
A. INTRODUCTION
503. This Part addresses BC Hydro’s traditional821 DSM expenditures and LCE expenditures,
which are the subject of Chapter 10 of the Application.
504. BC Hydro is seeking acceptance pursuant to section 44.2 of the UCA of its traditional
DSM expenditure schedule set out in Table 10-1 of the Application, as amended in BC Hydro’s
Evidentiary Update.822 BC Hydro’s traditional DSM expenditure schedule consists of traditional
DSM expenditures of $90.8 million in fiscal 2020 and $89.1 million in fiscal 2021. These
expenditures are described in detail in the Fiscal 2020 to Fiscal 2022 Demand Side Management
Business Plan in Appendix X of the Application (the “DSM Plan”).
505. BC Hydro’s LCE expenditures are described in detail in the Low Carbon Electrification
Program in Appendix Y of the Application, as updated in Attachment 1 to BCUC Panel IR
2.18.2.823 They are recoverable in rates by virtue of being prescribed undertakings pursuant to
section 18 of the Clean Energy Act and section 4 of the GGRR. BC Hydro is also requesting
approval to defer its LCE expenditures over the Test Period to the DSM Regulatory Account, as
per the Direction to the BCUC Respecting Undertaking Costs.
506. The following points, each of which is demonstrated in this Part, support findings that
BC Hydro’s traditional DSM expenditure schedule is in the public interest and that BC Hydro’s
LCE expenditures should be deferred to the DSM Regulatory Account:
● First, BC Hydro’s moderation approach continues to be a reasonable response to
the energy surplus and need to limit forecast rate increases.
821 As explained on page 10-4 of the Application, BC Hydro uses the term “traditional” DSM to refer to its energy
efficiency and conservation as well as capacity-focused initiatives. Traditional DSM does not include LCE initiatives.
822 Exhibit B-11. The Evidentiary Update reduces BC Hydro’s DSM expenditure schedule by $27.2 million in fiscal 2021 from $116.3 million to $89.1 million because two projects that BC Hydro expected to proceed under the Thermo-Mechanical Pulp Program did not submit applications by the required deadline. This update was first provided in Exhibit B-5, BCUC IR 1.182.1.
823 Exhibit B-31, BCUC Panel IR 2.18.2, Attachment 1.
- 217 -
301539.00025/94161307.1
● Second, BC Hydro’s DSM expenditure schedule reflects changes that address
directions and recommendations from the Commission’s Decision in the Previous
Application, the priorities of the Government of BC, and the Demand-Side
Measures Regulation (the “DSM Regulation”).
● Third, the Commission should rescind Direction 61 from Order No. G-96-04 as it
is inconsistent with the DSM Regulation and industry standard practice and is
inappropriate for marginal decision making regarding DSM programs.
● Fourth, BC Hydro’s traditional DSM expenditure schedule is aligned with the
Clean Energy Act, UCA and DSM Regulation.
● Fifth, BC Hydro is no longer forecasting expenditures over the Test Period in its
Thermo-Mechanical Pulp Program, and the requested expenditure schedule
reflects this change.
● Sixth, BC Hydro’s LCE expenditures are within a class of prescribed undertakings
described in section 4 of the GGRR, and the BCUC has been directed to defer the
LCE expenditures to the DSM regulatory account.
● Seventh, BC Hydro is reasonably and effectively managing its traditional DSM an
LCE initiatives.
B. MODERATION APPROACH CONTINUES TO BE A REASONABLE RESPONSE TO ENERGY SURPLUS
507. BC Hydro’s proposed DSM expenditure schedule continues the moderation approach
first recommended in the 2013 IRP, given the continued energy surplus and continued need to
manage upward pressure on rates. In accordance with this moderation approach, BC Hydro has
maintained a similar overall level of spending on traditional DSM as in the previous test period.
- 218 -
301539.00025/94161307.1
It continues to use a market price screening filter to ensure that traditional DSM spending
lowers BC Hydro’s revenue requirements overall.824
508. In its Decision in the Previous Application, the BCUC found that the moderation strategy
provided a balanced approach:
The Panel finds the overall size of the funding envelope in BC Hydro’s proposed DSM expenditure schedule provides a balanced response to a reduction in the load forecast and the need to meet certain targets under the 2013 10 Year Rates Plan. The Panel agrees with BC Hydro that key considerations are the changing system needs and the ability of BC Hydro to meets its rate objectives.
BC Hydro now expects to be in an energy surplus situation until F2022 (without committed resources) and F2032 (with committed resources). The Panel acknowledges concerns raised by interveners that cost-effective DSM decreases customer bills overall, but considers that, given the energy surplus situation, the use of a market priced screening filter to identify cost-effective DSM is reasonable.
The Panel also considers that higher levels of DSM spending could challenge BC Hydro’s ability to meet targets under the 2013 10 Year Rates Plan and place further upward pressure on the size of the rate smoothing account. In the absence of this pressure on rates, the benefits of spending more on cost-effective DSM programs would have been given greater consideration.
The Panel also considered in its deliberations the Minister’s letter supporting BC Hydro’s reduction in DSM spending compared to the 2013 IRP and BC Hydro’s submission that it would meet the CEA objective of reducing BC Hydro’s expected increase in demand by the year 2020 by at least 66 percent (even if energy savings from codes and standards are excluded). …825
509. The BCUC’s reasoning, as quoted above, remains applicable in the Test Period. First, BC
Hydro remains in a surplus position and continues to need to limit forecast rate increases.826
Thus, BC Hydro’s continued use of a market priced screening filter827 for traditional DSM
824 Exhibit B-1, Application, pp. 10-19 to 10-20; Exhibit B-6, BCNPHA IR 1.2.0. 825 Decision on Previous Application, pp. 78-79. 826 Exhibit B-1, Application, p. 10-15. 827 The market price used in the Utility Cost Test is a forecast of prices with values that vary from year to year. The
levelized value of $30/MWh (fiscal 2018$) is a reference point, calculated based on the market price forecast over a 15-year period from fiscal 2020 to fiscal 2034 (Exhibit B-6, AMPC IR 1.5.9).
- 219 -
301539.00025/94161307.1
programs is reasonable as it ensures that any surplus energy generated will reduce BC Hydro’s
overall revenue requirements and reduce overall customer bills.828 In other words, without the
use of a market price screening filter, traditional DSM programs could result in increased
surplus energy that BC Hydro would have to sell at a loss, resulting in a higher revenue
requirement and an increase in overall customer bills.
510. Second, the Government of B.C. continues to support the moderation approach. It
reviewed the DSM Plan as part of Phase One of the Comprehensive Review829 and found:
Demand Side Management is an important part of BC Hydro’s resource plan, providing the flexibility to meet future supply needs or build efficient load, depending on system needs. Demand Side Management is a low cost energy resource with little to no environmental impact. This area was examined, and, consistent with the government’s focus on affordability, in its upcoming Revenue Requirements Application, BC Hydro will be proposing to increase the amount of spending for the residential sector and low income ratepayers, while keeping Demand Side Management expenditures at the same level overall.830
511. Third, BC Hydro’s planned traditional DSM initiatives continue to meet the target set out
in section 2(b) of the Clean Energy Act: “to take demand-side measures and to conserve energy,
including the objective of the authority reducing its expected increase in demand for electricity
by the year 2020 by at least 66%”.831
512. Fourth, BC Hydro’s DSM Plan retains the ability to ramp-up traditional DSM activities in
the future in response to the next IRP or the CleanBC Plan. Using the results of the
conservation potential review (“CPR”), BC Hydro is considering options for the level of DSM in
future years to be examined as part of the next IRP.832 Over the Test Period, BC Hydro is
828 Exhibit B-1, Application, pp. 10-28 and 10-29. Exhibit B-13, BCOAPO IR 2.155.1. 829 Exhibit B-1, Application, Appendix C, Comprehensive Review of BC Hydro Phase 1 Final Report, p. 40. 830 Exhibit B-6, BCNPHA IR 1.2.0. 831 Exhibit B-1, Application, p. 10-15 and Exhibit B-5, BCUC IR 1.173.1. 832 Exhibit B-1, Application, p. 10-21; Tr. 14, p. 2784, ll. 5-9 (Hanlon).
- 220 -
301539.00025/94161307.1
maintaining its program offerings and partnerships with key businesses and trade allies in order
to be able to respond to any future direction that may come out of the IRP or CleanBC Plan.833
513. Therefore, BC Hydro submits that the level of traditional DSM spending proposed is a
reasonable and balanced approach and is in the public interest.
C. BC HYDRO’S TRADITIONAL DSM PLAN RESPONDS TO BCUC DIRECTIVES, GOVERNMENT PRIORITIES AND DSM REGULATION
514. While keeping within a similar level of spending as in the previous test period, BC Hydro
made a number of changes to the DSM Plan in response to BCUC direction, to support
Government priorities related to residential affordability, and to respond to changes to the
DSM Regulation. As discussed in the sections below, the changes improve the balance in
spending amongst customer sectors, demonstrate BC Hydro’s responsiveness to feedback, and
support BC Hydro’s view that the DSM expenditures schedule is in the public interest.
(a) BC Hydro Has Increased Residential Initiatives by Approximately 50%
515. BC Hydro’s proposed traditional DSM expenditure schedule reflects an increase of
approximately 50% in residential initiatives.
516. The increase is responsive to Directive 21 of the BCUC’s Decision on the Previous
Application. It recommended that BC Hydro consider more DSM programs directed at
residential customers due to “the relatively low level of DSM spending for residential customers
(including low income customers)”.834 The increase in spending on the residential sector is also
consistent with the Mandate Letter of the Government of B.C. and the outcome of the Phase
One of the Comprehensive Review.835
833 Exhibit B-6, BCSEA IR 1.35.4. However, it would be challenging to ramp up expenditures in the Test Period given
the lead times required for the implementation of customer projects (Exhibit B-6, BCSEA IR 1.35.2). 834 Exhibit B-1, Application, pp. 10-7 to 10-8. 835 Exhibit B-5, BCUC IR 1.171.1 and Exhibit B-12, BCUC IR 2.273.2.
- 221 -
301539.00025/94161307.1
517. A key focus of BC Hydro is on continuing to increase participation in the low-income
program.836 As a result of BC Hydro’s focus in this area, low Income expenditures and
participation rates have been steadily increasing since fiscal 2016. BC Hydro’s fiscal 2021
planned expenditures are approximately double actual expenditures in fiscal 2018. The
planned number of participants in fiscal 2021 is 27,310, which is approximately 10,000 higher
than the actual participation of 17,089 in fiscal 2018.837
518. Another key focus of BC Hydro has been on increasing participation in the Home
Renovation Rebate Program through additional measures and increased incentives. The Home
Renovation Rebate Program focuses on customers who can make their electricity bills more
affordable by reducing their space heating load. BC Hydro increased incentives for measures
such as insulation. It also expanded the number of measures available for incentives, such as
heat pumps and smart thermostats.838
519. BC Hydro was able to accommodate the increase in residential sector by reducing in the
commercial and industrial sectors of the DSM portfolio in alignment with expected spending in
these sectors.839 The redirection of funding was aligned with BC Hydro’s updated projections of
commercial and industrial sector participants, which was lower than previously planned, and
lower incentive levels needed for commercial projects.840 Mr. Hobson explained:
I think we outlined some of our reasons for the adjustment that we made in the commercial forecast of expenditures and it had, I think, more to do with taking a look at…the offering that we had put in place coming out of the last application, and as a result of that, seeing what projects we anticipated coming forward, what expenditures we were going to need to move those projects ahead in terms of incentive levels, and those were probably the bigger factors that we
836 Exhibit B-1, Application, Appendix X, pp. 3 and 30; Exhibit B-6, Zone II RPG IRs 1.19.3 and 1.25.8; Exhibit B-6,
Ince IR 1.12.5; Exhibit B-12, BCUC IR 2.276.1; Exhibit B-13, Zone II IR 2.43.1. 837 Exhibit B-6, BCSEA IR 1.44.1. 838 Exhibit B-1, Application, pp. 10-8, 10-9 and 10-24 and Appendix X, p. 34; Exhibit B-6, BCSEA IRs 1.43.2.1,
1.43.2.2, 1.43.2.3., 1.43.2.4, 1.43.3.5 and 1.46.1; Exhibit B-13, Zone II IR 2.43.1. 839 Exhibit B-6, AMPC IR 1.5.6. 840 Exhibit B-6, BCSEA IR 1.43.1; Exhibit B-12, BCUC IR 2.273.2.
- 222 -
301539.00025/94161307.1
were seeing at the time in terms of making adjustments in this application to the commercial expenditures.841
520. As result of the increase in residential expenditures, the percentage split amongst the
residential, commercial/light industrial and large industrial categories is now relatively even at
30%, 38% and 32%, respectively.842 The reallocation of funding also better aligns the portfolio
with the fully allocated cost of service allocation referenced in the BCUC’s Decision on the
Previous Application.843
(b) BC Hydro Has a New Commercial Social Housing Initiative
521. As part of the Leaders in Energy Management – Commercial program, BC Hydro
launched a new Social Housing Retrofit Support Offer for Multi-Unit Residential Buildings, which
is designed to help housing providers identify and implement energy-efficient projects.844 The
offer includes energy study funding, implementation support (engineering design, tendering
and project management), and a wide variety of incentives for qualifying equipment, such as
commercial kitchen equipment, commercial refrigeration equipment, heat pumps and electric
water heaters, LED lighting and controls, and variable speed drives.845
522. BC Hydro responded in detail to concerns raised with respect to its initiatives in the
social housing sector, describing its extensive efforts in this area since fiscal 2007.846 The new
Social Housing Retrofit Support Offer expands on past initiatives, and will supplement
incentives offered through the Residential Low Income Program.847 BC Hydro will continue to
monitor program performance, market barriers, and technology advancements, will continue to
841 Tr. 14, p. 2647, l. 23 to p. 2648, l. 8 (Hobson). 842 Exhibit B-1, Application, p. 10-8, Table 10-3. 843 Exhibit B-1, Application, Table 10-4; Exhibit B-6, AMPC IR 1.5.6. 844 Exhibit B-1, Appendix X, pp. 15 and 45. 845 Exhibit B-17, BCSEA IR 3.85.2. 846 Exhibit B-17, BCSEA IR 3.85.1. 847 Exhibit B-17, BCSEA IR 3.85.2.
- 223 -
301539.00025/94161307.1
engage with related organizations, and will modify the program as needed to adapt to changing
market conditions.848
(c) BC Hydro Has Increased its Activities in Non-Integrated Areas
523. BC Hydro increased its activities in non-integrated areas (“NIA”) in response to Directive
23 from the Decision in the Previous Application, which, amongst other things, directed BC
Hydro to report back on how it addressed the DSM concerns raised by Non Integrated Areas
Ratepayers Group (NIARG) and Zone II Ratepayers Group (Zone II) regarding the activities in the
NIA.849 BC Hydro’s increased activities in the NIA are also aligned with the Government’s policy
mandate regarding affordability, and are a natural progression from BC Hydro’s pilot initiatives
in the NIA.850
524. The new NIA program is a comprehensive program that builds on the pilot work
conducted to explore delivery approaches and efficiency measures tailored for the NIA.851 The
NIA program includes new residential and commercial program offers to assist NIA customers in
saving electricity, reducing utility bills and improving home comfort.852 It also includes
Community Support, which BC Hydro described as follows:
Within Community Support, we have planned to provide financial and technical resources to Indigenous communities in Non-Integrated Areas to support them in pursuing energy upgrades. This includes:
• Salary support to Indigenous Bands to hire community members who will visit homes in the community to review energy upgrade opportunities and install basic energy saving products.
• Training for these community members on how to review energy upgrade opportunities and install basic energy saving measures in homes.
848 Exhibit B-6, BCNPHA IR 1.3.0; Exhibit B-6, Zone II RPG IR 1.20.2. Also see Zone II RPG IR 1.20.1 and 1.20.1.1
regarding the role of the Low Income Advisory Council. 849 Exhibit B-1, p. 10-11 to 10-12. 850 Tr. 15, p. 2856, ll. 20-23 (Hanlon). 851 Exhibit B-6, Zone II RPG IR 1.26.1; Exhibit B-13, Zone II RPG IR 2.52.2. 852 Exhibit B-1, Application, pp. 10-11 and 10-12 and Appendix X, section 5.5.
- 224 -
301539.00025/94161307.1
• Training to Indigenous Bands that are planning to lead their own home renovation work and participate in our residential rebates. This training will be based on the Best Practice Guide: Air Sealing and Insulation Retrofits for Single Family Homes (2018 Second Edition).
• Other support as necessary to encourage energy upgrades and conservation behaviours in the community (e.g., presentations at community meetings, Elder and youth engagement, engagement with facility managers, etc.).853
525. The NIA program accounts for unique considerations for the NIA, including:
● increasing the incentives on energy saving measures, including weatherization
measures, to address the higher cost of products and services and more extreme
weather in the NIA;
● adding energy saving measures, such as freezers, to support the need for food
storage in remote and Indigenous communities;
● removing the income qualification requirement for energy-savings kits (“ESKs”)
for NIA residential customers to increase access to basic energy saving measures
for all households;
● offering both full service/direct install and do-it-yourself delivery methods; and
● hiring a dedicated resource to support community access to DSM programs.854
526. The cost effectiveness of the NIA program has been calculated from the bottom up,855
and benefits from a higher avoided cost of energy due to the cost of diesel generation.856 This
853 Exhibit B-6, Zone II RPG IR 1.26.8. Note that the Community Support initiative is separate from the Indigenous
Communities Support element of the Codes and Standards initiatives, which is described in Exhibit B-6, Zone II RPG IR 1.22.2.1 (Exhibit B-6, Zone II RPG IR 1.26.8.1).
854 Exhibit B-5, BCUC IR 1.185.2.1. 855 Exhibit B-5, BCUC IRs 1.185.2 and 1.185.2.1. 856 Exhibit B-5, BCUC IR 1.185.1.
- 225 -
301539.00025/94161307.1
accounts for the positive benefit cost ratio of the NIA program, even without the 40% adder
under the DSM Regulation.857
527. The budget for the NIA program is based on the expenditures required to deliver the
program to the estimated level of participation.858 As explained by Mr. Hobson, increasing
participation in the NIA program relies heavily on relationships and working within the
community.859 This makes the designated NIA program manager and relationship lead
positions860 integral parts of the NIA program’s success. While uptake of the offers has been
slower than expected in fiscal 2020, BC Hydro expects participation to pick up in fiscal 2021
based on agreements signed with communities in fiscal 2020 and the interest of communities
within the NIA.861
528. The NIA program is included in BC Hydro’s longer-term DSM planning, illustrating BC
Hydro’s expectation that it will be available long-term.862
529. While BC Hydro believes the NIA program is a comprehensive offer, BC Hydro is open to
considering new information and opportunities.863 Ms. Hanlon emphasized that “it is a new
program, and we want to continue to engage with communities and get feedback on how to
increase the participation estimates, and so we are very interested in working with
communities on how we can increase participation.”864 Therefore, BC Hydro will continue to
work with Indigenous communities on the specific issues and barriers they face with respect to
conservation and energy management.865
857 Exhibit B-5, BCUC IR 1.185.2; Exhibit B-13, BCOAPO IR 2.152.3.2; Exhibit B-13, Zone II IR 2.46.7; Tr. 15, p. 2880,
p. 12 to p. 2881, l. 7 (Hanlon). 858 Exhibit B-6, Zone II RPG IR 1.26.3. 859 Tr. 15, p. 2870, l. 23 to p. 2871, l. 15 (Hobson). 860 Tr. 15, p. 2871, l. 16 to p. 2872, l. 22 (Hanlon and Hobson). 861 Tr. 15, p. 2870, l. 6 to p. 2871, l. 15 (Hanlon and Hobson); Exhibit B-57, BC Hydro Undertaking No. 66. 862 Exhibit B-6, Zone II RPG IR 1.26.6. 863 Exhibit B-6, Zone II RPG IR 1.26.4.1. 864 Tr. 15, p. 2870, ll. 17-22 (Hanlon). 865 Exhibit B-1, Application, p. 10-12.
- 226 -
301539.00025/94161307.1
(d) BC Hydro Has Updated How it Presents its Codes and Standards Savings
530. BC Hydro updated its practice for presenting savings from codes and standards in
response to Directive 22 from the Decision in the Previous Application. The BCUC had
expressed concern that the cost effectiveness results for codes and standards could be
overstated or that other program cost effectiveness results could be understated. The BCUC
therefore directed BC Hydro to review if its approach for attributing savings that occur from the
implementation of codes and standards was consistent with industry practice.866
531. BC Hydro retained a third party expert, the Cadmus Group, to assess industry practice.
The Cadmus Group concluded that industry practice regarding codes and standards attribution
is varied. Approaches include: not quantifying or attributing any savings from codes and
standards; quantifying savings from codes and standards to reflect their impact on load
forecasts and revenue requirements; and, attributing a portion of the savings from codes and
standards to utility efforts.867
532. BC Hydro took the following steps to improve the presentation of its codes and
standards savings:
First, we have excluded codes and standards savings from benefit cost calculations and levelized costs. This means that those results are not distorted at the portfolio level by the codes and standards savings; and
Second, BC Hydro is not attributing codes and standards savings to individual programs. Instead, codes and standards savings are presented as a stand-alone bucket of energy and associated capacity savings, separate from programs. BC Hydro is not claiming these savings (or a portion of them) as a credit towards DSM cost effectiveness calculations. Rather, a forecast of codes and standards savings is provided and incorporated into BC Hydro’s Load Forecast. As shown in the Cadmus report, this aligns with the approach taken in the two Canadian jurisdictions (Ontario and Manitoba).868
866 Exhibit B-1, Application, p. 10-9. 867 Exhibit B-1, Application, pp. 10-9 and 10-10. The Cadmus Group report attached as Appendix CC to the
Application. 868 Exhibit B-1, Application, p. 10-10.
- 227 -
301539.00025/94161307.1
533. In short, while BC Hydro has extensive codes and standards support activities as
outlined in section 9 of Appendix X of the Application, BC Hydro has chosen not to quantify or
attribute the contribution of its support for codes and standards. This ensures that there is no
distortion to the cost-effectiveness results of the traditional DSM programs. As BC Hydro’s
codes and standards expenditures are still included at the portfolio level, the result is that the
cost effectiveness of the DSM portfolio is more conservative than if the codes and standards
savings were included. However, all of BC Hydro’s traditional DSM initiatives are cost-effective
without any attribution from codes and standards.869
(e) BC Hydro Has Extended the Funding Period for Capacity Focused Initiatives
534. The DSM Plan continues to include capacity focused pilots and trial offers directed at
shifting the timing of peak demand in areas where BC Hydro faces capacity constraints. BC
Hydro has extended the timeline for these initiatives by two years (to fiscal 2021) and reduced
(by 12%) the overall budget for these initiatives over the fiscal 2017 to fiscal 2021 period. It
was necessary to extend the time period due to the complexity of assessing the impacts and
value of capacity focused DSM to BC Hydro’s system, and to incorporate past learnings into new
activities, to consider changing technologies, and to accommodate the long lead times required
for some customer projects.870
535. BC Hydro provided a detailed description of the results of the pilots and trial offers to
date.871 Over the Test Period, BC Hydro will continue to conduct demand response trials in the
residential, commercial and industrial sectors.872 BC Hydro anticipates that the majority of
technical trials will be complete by the end of the Test Period, and that the resource options in
the upcoming IRP will be informed by the findings of the capacity-focussed DSM trials and
pilots.873
869 Exhibit B-1, Application, pp. 10-10 and 10-11; Exhibit B-5, BCUC IR 1.184.1. 870 Exhibit B-1, Application, pp. 10-21 to 10-22. 871 Exhibit B-5, BCUC IR 1.183.1. 872 Exhibit B-1, Application, p. 10-22. 873 Exhibit B-13, BCSEA IR 2.72.1.
- 228 -
301539.00025/94161307.1
(f) BC Hydro Has Re-categorized Energy Management Activities to Align with DSM Regulation
536. BC Hydro re-categorized its energy management activities into a new program called
Energy Management Activities within each sector. The change aligns with 2017 amendments to
the DSM Regulation that added “Energy Management Program” (meaning a program to assist
customers to optimize energy use) to the definition of “Specified Demand Side Measure”.
Energy Management Activities assist customers in managing and optimizing their energy use by
bringing energy specialists directly into customer operations, increasing customers’ knowledge
of their options, encouraging behavior change, and providing knowledgeable trades in the
industry that can help customers make the right choices.874 Section 4(4) of the DSM Regulation
requires that the cost effectiveness of “Specified Demand Side Measures” be evaluated at the
portfolio level, meaning that the costs of Energy Management Activities should not be
evaluated as part of the costs of other programs.
D. DIRECTION 61 REGARDING ALLOCATION OF PORTFOLIO COSTS SHOULD BE RESCINDED
537. BC Hydro is requesting that the BCUC rescind Directive 61 from its October 2004
Decision on BC Hydro’s Fiscal 2005 to Fiscal 2006 Revenue Requirements Application.875
Pursuant to this direction, BC Hydro was required to allocate a prorated amount of costs from
portfolio level initiatives to the cost of each program based on the energy savings. However, BC
Hydro submits that for the following reasons, that costs should only be attributed to programs
if they are solely connected to a specific program:
(a) Consistent with the DSM Regulation: BC Hydro’s proposed approach is
consistent with section 4(4) of the DSM Regulation. It requires that “specified
demand side measures”, which include energy efficiency training, community
engagement and energy management programs, be evaluated at a portfolio
874 Exhibit B-1, Application, pp. 10-38 to 10-40 and Appendix X, pp. 2, 37-41, 49-53 and 59-62; Exhibit B-5, BCUC IR
1.181.3.1; Exhibit B-13, BCOAPO IR 2.153.2.1. 875 Exhibit B-1, Application, p. 10-33. Directive 61 requires portfolio level costs to be allocated to programs, as
follows: “Portfolio Level Costs should be allocated to programs, and BC Hydro is directed to use the same allocation methodology based on kWh savings as used in Exhibit B1-81.”
- 229 -
301539.00025/94161307.1
level. Directive 61 is inconsistent with this requirement. These types of
programs could be considered portfolio level costs, which Directive 61 would
require be allocated to programs.876
(b) Consistent with Industry Practice: BC Hydro’s proposed approach is consistent
with industry practice which has developed over the 16 years since the BCUC
issued Directive 61. Notably, the National Standard Practice Manual issued in
May 2017 states that “fixed portfolio-level costs should not be allocated to
programs for the purpose of assessing the cost-effectiveness of individual
programs”. In addition, BCUC Order No. G-10-19 issued in 2019 indicates that
FortisBC Energy Inc. is not required to allocate portfolio-level costs to programs.
In step with industry practice, BC Hydro should now only allocate costs to
programs if they are solely connected to the specific programs.877
(c) Facilitates Marginal Decision Making: It is appropriate to consider portfolio level
costs only when looking at the cost effectiveness of the overall portfolio, so that
decisions on individual programs are based entirely on the merits of the program
itself. The inclusion of portfolio level costs when assessing cost effectiveness of
a program could shift the result for a program from a net benefit to a net cost,
which could lead to a decision not to implement a program that actually has a
net benefit.878
E. TRADITIONAL DSM IS ALIGNED WITH THE UCA, CLEAN ENERGY ACT, AND DSM REGULATION
538. BC Hydro’s expenditure schedule for traditional DSM is aligned with the framework of
the UCA, Clean Energy Act, and the DSM Regulation. The parameters on the BCUC’s discretion
876 Exhibit B-5, BCUC IR 1.172.1. 877 Exhibit B-5, BCUC IR 1.172.1. 878 Exhibit B-5, BCUC IR 1.172.1.
- 230 -
301539.00025/94161307.1
when considering a DSM expenditure schedule, and each of the four factors that the BCUC
must consider,879 are addressed below.
(a) The UCA Constrains the BCUC’s Discretion in Relation to a DSM Expenditure Schedule
539. BC Hydro files its demand-side measures expenditure schedule pursuant to subsection
44.2(1)(a) of the UCA. Subsection 44.2(3) of the UCA provides that the BCUC must accept an
expenditure schedule if it considers that making the expenditures referred to in the schedule
would be in the public interest, or reject the schedule. Alternatively, the Commission may
accept or reject a part of the expenditure schedule. In its Decision on the Previous Application,
the BCUC commented on the extent of its discretion when accepting or rejecting a demand-side
measures expenditure schedule as follows:
The Panel agrees with BC Hydro that section 44.2 of the UCA does not provide the Commission with the authority to direct BC Hydro to file a DSM expenditure schedule, make additions to a DSM expenditure schedule, or change the design of a particular DSM program. However, the Panel notes that, under subsection 44.2(2), BC Hydro would not be able to recover DSM costs in final rates unless these costs have been accepted by the Commission under section 44.2.880
540. BC Hydro agrees with this interpretation of the BCUC’s jurisdiction under section 44.2.
(b) BC Hydro’s Traditional DSM Is in the Interest of Customers
541. The evidence in this proceeding demonstrates that the proposed traditional DSM
expenditures are in “the interests of persons in British Columbia who receive or may receive
service from [BC Hydro]” per s. 44.2(a) of the UCA. BC Hydro’s proposed expenditures reflect a
broad and cost effective range of DSM initiatives that
879 The factors that the BCUC must consider under section 44.2 of the UCA are as follows:
(a) The interests of persons in British Columbia who receive or may receive service from BC Hydro;
(b) British Columbia’s energy objectives as set out in section 2 of the Clean Energy Act;
(c) An applicable Integrated Resource Plan approved under section 4 of the Clean Energy Act; and
(d) The extent to which the demand side measures are cost effective within the meaning prescribed by the Demand Side Measures Regulation.
880 Decision and Order No. G-47-18, dated March 1, 2018, at page 73 of 118.
- 231 -
301539.00025/94161307.1
● provide significant energy savings and capacity benefits;881
● provide customers with the opportunity to save electricity and lower their bills;
and
● reduce BC Hydro’s revenue requirements.882
542. Other benefits include GDP impacts, employment, provincial revenues, non-energy
customer benefits, and GHG reductions.883 BC Hydro submits that the benefits are significant
and that the proposed traditional DSM expenditures are in the interest of BC Hydro’s
customers.
(c) BC Hydro’s Traditional DSM Supports British Columbia’s Energy Objectives
543. BC Hydro summarized how its traditional DSM expenditures support the energy
objectives in the Clean Energy Act in Table 10-6 of the Application.884 In particular, the DSM
Plan meets the objective of reducing BC Hydro’s “expected increase in demand for electricity by
the year 2020 by at least 66 per cent”.885 In fact, BC Hydro’s traditional DSM is forecast to
reduce BC Hydro’s increase in electricity demand by the end of fiscal 2021 by approximately
103%.886
881 The forecast energy and capacity savings are detailed in section 10.5.1 of the Application. 882 Exhibit B-1, Application, p. 10-14. 883 These are summarized in section 10.5.2 of the Application and detailed further in section 3.3 of Appendix X of
the Application. 884 Exhibit B-1, Application, pp. 10-14 to 10-15. 885 BC Energy Objective 2(b) refers to a target for energy efficiency and conservation initiatives and not low carbon
electrification programs (Exhibit B-5, BCUC IR 1.173.2). 886 Exhibit B-1, Application, p. 10-14. BC Hydro illustrated this calculation and provided supporting data in its
response to Exhibit B-5, BCUC IR 1.173.1.
- 232 -
301539.00025/94161307.1
(d) Traditional DSM is Consistent with the IRP
544. BC Hydro’s continuation of a moderation approach, given the ongoing energy surplus
and need to limit forecast rate increases, is consistent with the 2013 IRP. The moderation
approach was originally recommended in the 2013 IRP for fiscal 2014 to fiscal 2016.887
(e) BC Hydro’s Traditional DSM is Cost-Effective as Defined by the DSM Regulation
545. The portfolio as a whole, as well as rate structures and all programs, are cost effective
using the modified total resource cost test required by the DSM Regulation.888 The Test Period
portfolio as a whole, as well as rate and all programs, also are cost effective under the more
stringent requirements of the total resource cost test excluding non-energy benefits and utility
cost test.889
546. Under the DSM Regulation, the long-run marginal cost of clean energy is an input into
the total resource cost test. BC Hydro used the most recent, but outdated, long-run marginal
cost of $105.890 However, all DSM programs and the portfolio as a whole would be cost
effective using a long-run marginal costs as low as $52/MWh.891 This is sufficient for the
portfolio to be cost effective using the most recent estimates of wind costs, including delivery
to the Lower Mainland, which are between $54 and $80/MWh.892 BC Hydro will update the
long-run marginal cost for its next IRP.893
(f) Traditional DSM Meets Adequacy Requirements Under the DSM Regulations
547. Section 44.1 requires that a long-term resource plan filed by a utility must show that the
utility is pursuing “adequate” DSM, as prescribed in section 3 of the DSM Regulation. While
887 Exhibit B-1, Application, p. 10-15. 888 Exhibit B-5, BCUC IR 1.175.1. See also, Exhibit B-1, Application, Appendix X, Appendix A-7. 889 Exhibit B-5, BCUC IR 1.175.1. See also, Exhibit B-1, Appendix X, Appendix A-7. The Utility Cost and Total
Resource Cost tests are standard cost tests used in the DSM industry to assess cost effectiveness (Exhibit B-1, Application, p. 10-28).
890 Exhibit B-1, Application, pp. 10-29 and 10-30. 891 Exhibit B-12, BCUC IR 2.274.1. 892 Exhibit B-5, BCUC IR 1.175.3. 893 Exhibit B-1, Application, pp. 10-29 and 10-30.
- 233 -
301539.00025/94161307.1
BC Hydro is not currently required to meet the adequacy requirements in section 44.1 of the
UCA, BC Hydro’s DSM Plan has been designed to be consistent with the adequacy
requirements, as shown in Table 10-7 of the Application.894
(g) BC Hydro Retains Flexibility to Reallocate Costs in Response to Challenges and Opportunities
548. BC Hydro has submitted its DSM Plan with the intention of carrying it out as designed.
However, BC Hydro retains discretion to reallocate its DSM costs during the Test Period, and
this ability is important for the company and customers.
549. BC Hydro’s ability under the UCA to reallocate funds is clear based on section 44.2 of the
UCA, which permits BC Hydro to file a statement of DSM expenditures that it “anticipates
making”. Thus, the BCUC may accept DSM expenditures on a forecast basis, and, similar to BC
Hydro’s other forecast costs over the Test Period, actual expenditures on DSM may vary from
forecast.895 Acceptance of an expenditure schedule of anticipated DSM spending indicates that
the BCUC has found the expenditure schedule, as presented, to be in the public interest. If
prudently executed as described in the expenditure schedule, it is reasonable to expect that the
expenditures can be recovered through rates.896
550. It is important for BC Hydro to have the flexibility to respond to challenges or
opportunities in the market. For instance, if an initiative is over-performing or under-
performing, then BC Hydro may need to reallocate funds to maintain the overall portfolio
performance and portfolio balance. BC Hydro’s spending may also vary from plan due to
factors that are fully or in part outside its control, such as the timing of large customer projects
or slower than anticipated participation in a program due to economic conditions.897
894 Exhibit B-1, Application, p. 10-17. 895 Exhibit B-5, BCUC IR 1.174.1.1. 896 Exhibit B-12, BCUC IR 2.269.1. 897 Exhibit B-5, BCUC IR 1.174.1.
- 234 -
301539.00025/94161307.1
551. Appropriate checks and balances are in place regarding reallocations made during the
test period:
● Any reallocations of DSM expenditures are approved by individuals with the
required financial signing authority based on BC Hydro’s Financial Approval
Authority Policy and are reported to BC Hydro’s Board of Directors.898
● BC Hydro annual DSM reports provide an opportunity for the Commission to
review BC Hydro’s actual DSM expenditures. These reports describe any
expenditure or savings variances compared to the accepted expenditure
schedule, and any mitigation measures undertaken or planned.899
● BC Hydro understands that a significant deviation from the expenditure
breakdown shown in the expenditure schedule could result in cost recovery risk.
For instance, BC Hydro recognizes that underspending on a program as a result
of a BC Hydro decision (as opposed to customer driven timing/decisions or
market uptake), could give rise to cost recovery risk if the portfolio was no longer
cost effective.900
F. THE EXPENDITURE SCHEDULE EXCLUDES THERMO-MECHANICAL PULP EXPENDITURES
552. BC Hydro’s expenditures on the Thermo-Mechanical Pulp Program provide funding to
increase the electrical efficiency of mills that use thermo-mechanical pulping processes.901 The
Direction to the BCUC Respecting the Authority’s TMP Program requires the BCUC to allow BC
Hydro to recover up to $100 million in costs incurred to carry out the program, and allow BC
Hydro to defer these costs to the Demand Side Management Regulatory Account.902 However,
BC Hydro is no longer forecasting expenditures on the Thermo-Mechanical Pulp Program in the
898 Exhibit B-5, BCUC IR 1.174.1.1. 899 Exhibit B-1, Application, Appendix Z, Annual DSM Reports to the BCUC. 900 Exhibit B-12, BCUC IR 2.269.1. 901 Exhibit B-1, Application, p. 10-18 and Appendix X, pp. 57 and 58. 902 Exhibit B-1, Application, p. 10-18 and Appendix D.
- 235 -
301539.00025/94161307.1
Test Period, as no applications from eligible customers were received by the application
deadline.903 Therefore, BC Hydro amended it proposed expenditure schedule to remove
expenditures on Thermo-Mechanical Pulp Program.904
G. LOW CARBON ELECTRIFICATION EXPENDITURES ARE PRESCRIBED UNDERTAKINGS AND COST RECOVERY IS MANDATED
553. BC Hydro requests approval to defer its LCE expenditures to the DSM Regulatory
Account on the basis that they are prescribed undertakings pursuant to section 18 of the Clean
Energy Act and section 4(3)(a) to (d) of the GGRR.905
554. BC Hydro’s LCE expenditures are described in Appendix Y of the Application, as updated
in Attachment 1 to BCUC Panel IR 2.18.2.906 BC Hydro’s LCE expenditures can be divided into
two categories: (1) the “Initial LCE Projects”; and (2) the “LCE Program”. BC Hydro has referred
to these two categories together as “LCE Project/Programs”. BC Hydro’s LCE Projects/Programs
expenditures do not include infrastructure projects, such as the PRES project, which are
included in the class of undertakings described in section 4(2) of the GGRR.907
(a) Section 18 of the Clean Energy Act Requires Cost Recovery for Prescribed Undertakings
555. Sections 18(1) to 18(3) of the Clean Energy Act state that the BCUC must set rates to
allow BC Hydro to recover the costs of prescribed undertakings, and must not exercise any
power that would prevent BC Hydro from carrying out prescribed undertakings. The effect of
section 18 of the Clean Energy Act is that the BCUC need only consider whether the LCE
expenditures are prescribed undertakings as described in the GGRR. If the BCUC concludes that
903 Exhibit B-5, BCUC IR 1.182.1. 904 Exhibit B-11, Evidentiary Update, p. 4. 905 B.C. Reg. 77/2017, O.C. 100/2017.
Online: http://www.bclaws.ca/civix/document/id/complete/statreg/77_2017. 906 Exhibit B-31, BCUC Panel IR 2.18.2, Attachment 1. 907 Exhibit B-1, Application, Appendix Y, p. 3. For a discussion of BC Hydro’s infrastructure projects, see section 4 of
the Greenhouse Gas Reduction (Clean Energy) Regulation Fiscal 2019 Annual Report (Exhibit B-31, BCUC Panel IR 2.18.1 Attachment 1).
- 236 -
301539.00025/94161307.1
they are, then it must approve rates to allow BC Hydro to collect sufficient revenue to recover
the costs of the prescribed undertakings.
(b) Acceptance of a Section 44.2 Expenditure Schedule is Not Required
556. BC Hydro is not required to seek acceptance of an expenditure schedule under section
44.2 for the LCE expenditures, since section 44.2 does not impose an obligation on a public
utility to file an expenditure schedule.908 This is the case even if the LCE expenditures were also
to qualify as a “demand-side measure”. The accepted rules of statutory interpretation require
that section 44.2 of the UCA and section 18(2) of the Clean Energy Act be read together
harmoniously.909 On the one hand, section 18(2) of the Clean Energy Act states that the BCUC
must set rates to recover the costs of prescribed undertakings. On the other hand, section
44.2(2) of the UCA states that the BCUC may not approve a rate to recover the costs of a
demand-side measure unless an expenditure schedule is filed and accepted under section 44.2.
However, section 18(3) states that the BCUC “must not exercise a power under the Utilities
Commission Act in a way that would directly or indirectly prevent a public utility referred to in
subsection (2) from carrying out a prescribed undertaking”. Reading these provisions together,
section 18(2) and 18(3) of the Clean Energy Act create an exception to the otherwise general
rule in section 44.2(2). In effect, section 18(2) of the Clean Energy Act reflects a public interest
determination by the Government of B.C. that negates the need for an expenditure schedule to
be accepted by the BCUC as being in the public interest. Therefore, it is not necessary for BC
Hydro to seek or obtain the BCUC’s acceptance under section 44.2 of the LCE expenditures,
even if they were to qualify as a “demand-side measure”.
908 Section 44.2 uses permissive language, saying that a utility “may” file an expenditure schedule under section
44.2. 909 In Rizzo & Rizzo Shoes Ltd. (Re), [1998] 1 S.C.R. 27, the Supreme Court of Canada relied on the following
statement from Elmer Driedger in Construction of Statutes (2nd ed. 1983): “Today there is only one principle or approach, namely, the words of an Act are to be read in their entire context and in their grammatical and ordinary sense harmoniously with the scheme of the Act, the object of the Act, and the intention of Parliament.” Online: https://www.canlii.org/en/ca/scc/doc/1998/1998canlii837/1998canlii837.html.
- 237 -
301539.00025/94161307.1
(c) BC Hydro’s LCE Expenditures are Prescribed Undertakings
557. There are two broad requirements for the LCE expenditures to fall within the class of
prescribed undertakings in sections 4(3)(a) to (d) of the GGRR:
(a) The LCE expenditures must meet the descriptions in sections 4(3)(a), 4(3)(b),
4(3)(c), or 4(3)(d) of the GGRR; and
(b) At the time BC Hydro decided to undertake the LCE expenditures meeting the
descriptions in sections 4(3)(a), 4(3)(b), BC Hydro must have reasonably expected
the LCE expenditures to be cost effective as set out in section 4(4) of the GGRR.
The LCE Expenditures Meet the Descriptions of Prescribed Undertakings
558. Sections 2 and 3 of Appendix Y910 describe how BC Hydro’s LCE expenditures on Initial
LCE Projects and the LCE Program meet the descriptions of prescribed undertakings in sections
4(3)(a), 4(3)(b), 4(3)(c), and 4(3)(d) of the GGRR, which are as follows:
(3) Subject to subsection (4), a public utility’s undertaking that is in a class defined in one of the following paragraphs is a prescribed undertaking for the purposes of section 18 of the Act:
(a) a program to encourage the public utility’s customers, or persons who may become customers of the public utility, to use electricity, instead of other sources of energy that produce more greenhouse gas emissions, by
(i) educating or training those customers respecting energy use and greenhouse gas emissions, carrying out public awareness campaigns respecting those matters, or providing energy management and audit services, or
(ii) providing funds to those persons to assist in the acquisition, installation or use of equipment that uses or affects the use of electricity;
(b) a program to encourage the public utility’s customers, or persons who may become customers of the public utility, to use electricity instead of other sources of energy that produce more greenhouse gas emissions, by
910 As updated in Attachment 1 to Exhibit B-31, BCUC Panel IR 2.18.2.
- 238 -
301539.00025/94161307.1
(i) educating, training, providing energy management and audit services to, or carrying out awareness campaigns respecting energy use and greenhouse gas emissions for, or
(ii) providing funds to
persons who
(iii) design, manufacture, sell, install or, in the course of operating a business, provide advice respecting equipment that uses or affects the use of electricity,
(iv) design, construct, manage or, in the course of operating a business, provide advice respecting energy systems in buildings or facilities, or
(v) design, construct or manage district energy systems;
(c) a project, program, contract or expenditure for research and development of technology, or for conducting a pilot project respecting technology, that may enable the public utility’s customers to use electricity instead of other sources of energy that produce more greenhouse gas emissions;
(d) a project, program, contract or expenditure supporting a standards-making body in its development of standards respecting
(i) technologies that use electricity instead of other sources of energy that produce more greenhouse gas emissions, or
(ii) technologies that affect the use of electricity by other technologies that use electricity instead of other sources of energy that produce more greenhouse gas emissions;
559. Appendix Y911 demonstrates that the LCE expenditures fall within the descriptions of
prescribed undertakings above. For example, the LCE Program includes energy management
studies, incentives, and public awareness campaigns consistent with section 4(3)(a) and (b) of
the GGRR.912
911 As updated in Attachment 1 to Exhibit B-31, BCUC Panel IR 2.18.2. 912 Exhibit B-1, Application, Appendix Y, p. 10, Table 3-1.
- 239 -
301539.00025/94161307.1
BC Hydro Reasonably Expected the LCE Expenditures under subsections 4(3)(a) to 4(3)(b) of the GGRR to be Cost Effective
560. In addition to meeting the above descriptions, there is only one other requirement for
the LCE expenditures to be prescribed undertakings. Namely, for the LCE expenditures that are
in a class of undertakings defined in subsections 4(3)(a) and 4(3)(b) of the GGRR, BC Hydro must
reasonably expect at the time it decides to carry out the undertakings that they are cost
effective. Subsection 4(4) of the GGRR sets out this requirement
(4) An undertaking is within a class of undertakings defined in paragraph (a) or (b) of subsection (3) only if, at the time the public utility decides to carry out the undertaking, the public utility reasonably expects the undertaking to be cost- effective.
561. The meaning of the cost-effectiveness test is set out in the following definitions in
section 4(1) of the GGRR:
“benefit”, in relation to an undertaking in a class defined in subsection (3) (a) or (b), means all revenues the public utility reasonably expects to earn as a result of implementing the undertaking, less revenues that would have been earned from the supply of undertaking electricity to export markets;
“cost”, in relation to an undertaking in a class defined in subsection (3) (a) or (b), means costs the public utility reasonably expects to incur to implement the undertaking, including, without limitation, development and administration costs;
“cost-effective” means that the present value of the benefits of all of the public utility’s undertakings within the classes defined in subsection (3) (a) or (b) exceeds the present value of the costs of all of those undertakings when both are calculated using a discount rate equal to the public utility’s weighted average cost of capital over a period that ends no later than a specified year;
562. In summary, the cost-effectiveness test measures all the revenues BC Hydro expects to
earn as a result of all of the undertakings that fall within subsections 4(3)(a) and 4(3)(b) of the
GGRR (less revenues that would have been earned from the sale of that electricity to export
markets), against the costs that BC Hydro expects to incur to implement all of the undertakings
in those two subsections. The GGRR cost-effectiveness test does not require each individual
component to be cost effective, nor does it require the BCUC to definitively determine whether
- 240 -
301539.00025/94161307.1
the prescribed undertakings will in fact be cost effective. Rather, the requirement is that BC
Hydro must reasonably expect all of the undertakings in those two subsections on a cumulative
basis to be cost-effective at the time BC Hydro decides to carry them out.
563. The NPV of all of BC Hydro’s LCE expenditures that fall within the class of undertaking
prescribed under sections 4(3)(a) and 4(3)(b) of the GGRR is $118.6 million and therefore is cost
effective.913
(d) Deferral of LCE Expenditures is Required by Regulation
564. The Direction to the BCUC Respecting Undertaking Costs requires the BCUC to allow BC
Hydro to defer its LCE expenditures to the Demand Side Management Regulatory Account. This
direction states that the “commission must allow the authority to defer to the DSM regulatory
account amounts equal to the undertaking costs”. It defines “undertaking costs” as “all costs
incurred by the authority to implement an undertaking within a class defined in section 4 (3)
(a), (b), (c) or (d) of the Greenhouse Gas Reduction (Clean Energy) Regulation.”914 The LCE
expenditures are costs incurred by BC Hydro to implement undertakings that are within these
classes of undertakings.
H. BC HYDRO IS MANAGING ITS TRADITIONAL DSM AND LCE INITIATIVES EFFECTIVELY
565. BC Hydro is identifying and mitigating delivery risks and effectively managing the
performance of its traditional DSM and LCE initiatives.915 Information requests focused on BC
Hydro’s evaluation processes. BC Hydro’s evaluation reports, copies of which have been
913 Exhibit B-31, BCUC Panel IR 2.18.2, Attachment 1 LCE Program Updated in December 2019, p. 14; Exhibit B-5,
BCUC IR 1.186.2. 914 B.C. Reg. 77/2017, O.C. 100/2017.
Online: http://www.bclaws.ca/civix/document/id/complete/statreg/77_2017. 915 See Exhibit B-1, Application, pp. 10-41 to 10-42 and Appendix X, section 4, Appendix Z, section 4 of each Annual
Report, and Appendix AA.
- 241 -
301539.00025/94161307.1
provided in this proceeding, demonstrate the professional, detailed and thorough review of
programs undertaken by BC Hydro.916
566. The independence of BC Hydro’s evaluation function is established through the
organizational structure.917 Highly qualified external advisors play a critical role in the
evaluation process.918 BC Hydro explained the benefits of its mix of staff and contractors in the
evaluation process as follows:
1. BC Hydro is a Crown corporation without an incentive mechanism that would make it profit from DSM impacts, and thus is not in a conflict of interest with respect to the evaluation or measurement and verification of DSM impacts. Without a DSM incentive mechanism, BC Hydro does not profit from the over-estimation of DSM impacts. This is in contrast to a number of other jurisdictions in North America, including California, where electricity is delivered by investor-owned utilities with incentive mechanisms for DSM. In these jurisdictions, utilities are in a conflict of interest with respect to the evaluation or measurement and verification of DSM impacts, since evaluation results influence incentive payments to utilities for DSM. In many of these jurisdictions, the majority of measurement and verification, and evaluation work is outsourced to contractors;
2. Costs are lower due to our use of BC Hydro staff instead of contractors. Average hourly costs for measurement and verification, and evaluation contractors are close to twice that of equivalent BC Hydro staff;
3. Quality is higher due to our use of BC Hydro staff instead of contractors. As noted above, BC Hydro measurement and verification, and evaluation staff understand BC Hydro DSM initiatives and data and, as a result, deliver better quality evaluations to support our internal client needs; and
4. Privacy requirements prevent BC Hydro from using contractors for some evaluation work. In its handling of personal information, including electricity consumption and other data pertaining to residential customers, BC Hydro must comply with the BC Freedom of Information and Protection of Privacy Act. The Act requires BC Hydro to safeguard
916 Exhibit B-12, BCUC IR 2.271.2, with links to three completed evaluation reports. 917 Exhibit B-1, Appendix AA, p. 5-6. 918 Exhibit B-5, BCUC IR 1.188.2; Exhibit B-12, BCUC IR 2.271.1.1; Exhibit B-31, BCUC Panel IR 2.21.1 and 2.21.2.
- 242 -
301539.00025/94161307.1
personal information and contains prohibitions on the storage and access of personal information outside Canada. BC is one of only two Canadian provinces with such prohibitions (the other being Nova Scotia). These prohibitions effectively mean that BC Hydro cannot outsource evaluation analytical work on residential DSM initiatives to contractors based in the United States without Canadian subsidiaries and data servers. This is significant since the vast majority of DSM evaluation consulting firms in North America are based in the United States.919
567. In fiscal 2017, BC Hydro’s Audit Services conducted an audit to assess whether effective
processes and controls are in place over DSM activities and programs. BC Hydro’s Audit
Services operates independently within BC Hydro and adheres to professional standards.920 BC
Hydro’s Audit Services engaged independent experts from GDS Canada Consulting Ltd. to help
assess whether effective processes and controls were in place for the DSM activities and
programs.921 The audit found that processes and controls are in place for DSM planning,
program development, implementation and evaluation.922
568. With respect to program evaluation, the audit found:923
● Evaluations of overall programs and the measurement and verification of
individual projects are effective. Standard industry protocols are followed for all
work. Energy savings are verified with the repayment of incentives when
required.
919 Exhibit B-1, Application, Appendix AA, Demand-Side Management Measurement, Verification and Evaluation,
pp. 6 and 7. 920 Exhibit B-5, BCUC IR 1.187.6. Audit Services is independent from management by virtue of its functional
reporting line to the Audit and Finance Committee of BC Hydro’s Board of Directors, its Charter, and the requirement to follow internal auditing standards. Audit recommendations require management action plans, follow-ups and ongoing monitoring by Audit Services and the status is reported on a quarterly basis to the Audit and Finance Committee of BC Hydro’s Board of Directors. The International Standards for the Professional Practice of Internal Auditing is included in Exhibit B-5, BCUC IR 1.12.3. See also, BCUC IR 1.12.4 regarding the process by which an entity can claim compliance with this standard.
921 Exhibit B-1-4; Exhibit B-5, BCUC IR 1.187.6. 922 Exhibit B-1, Application, p. 10-42; Exhibit B-1-4. GDS Canada Consulting Ltd. has over 40 years of experience in
market evaluations and managing energy efficiency programs. 923 Exhibit B-1-4, Attachment 1, p. 3 of 4.
- 243 -
301539.00025/94161307.1
● Evaluation, and measurement and verification work is performed in a reasonable
time period based on complexity and duration of data collection.
● Energy savings are manually tracked; however, an initiative is underway to
automate the process. To ensure continuous improvement, action plans are
developed to address findings from program evaluations.
569. In response to the suggestion that BC Hydro perform an DSM audit for each expenditure
schedule application, BC Hydro explained that the timing of audits should be left to Audit
Services to determine based on the risk within BC Hydro:
BC Hydro Audit Services prepares a two year audit plan based on areas of risk and exposure within the organization. A decision on when to complete the next DSM audit would depend on an assessment of associated risk in comparison to other areas of the organization.
There is no defined cycle of DSM internal audits. A two-year audit plan was prepared in May 2019 and based on an assessment of overall risk, the decision was made to not include a DSM internal audit in the next two years.
The next audit plan will be prepared in May 2021. At that time, a risk assessment will be performed and a further decision will be made on audits to be performed.924
570. BC Hydro is confident in the Conservation and Energy Management business function,
and the Audit Service’s audit plan appropriately reflects the associated risks of the organization.
The increased cost of performing additional audits, with unknown benefits, outweighs the value
from an audit of each expenditure application.925
I. CONCLUSION AND REQUESTED FINDINGS
571. The evidence demonstrates that BC Hydro’s traditional DSM expenditure schedule is in
the public interest and that BC Hydro’s LCE Projects/Programs expenditures are a prescribed
undertaking under section 18 of the Clean Energy Act. BC Hydro submits that the BCUC should
924 Exhibit B-12, BCUC IR 2.272.3. 925 Exhibit B-5, BCUC IR 1.187.7.
- 244 -
301539.00025/94161307.1
accept the proposed DSM expenditure schedule and approve the deferral of the traditional
DSM and (per the applicable direction) LCE Projects/Programs expenditures to the Demand Side
Management Regulatory Account.
- 245 -
301539.00025/94161307.1
PART TWELVE: IMPLEMENTATION OF RATES AND CONSIDERATION OF NEW INFORMATION
A. INTRODUCTION
572. This Part speaks to the most appropriate way to implement fiscal 2020 and fiscal 2021
rates, in light of the evidence of BC Hydro’s forecast Test Period revenue requirements. The
updated revenue requirements in the Evidentiary Update (as corrected by Exhibit B-11-2) had a
favourable impact on customers, relative to the Application. BC Hydro proposes to implement
this outcome by making the interim fiscal 2020 rates permanent, and decreasing rates by 1.01%
on April 1, 2020. BC Hydro submits that its proposal is just and reasonable and produces the
best outcome for customers.
573. This Part is organized around the following supporting points:
● First, among the number of rate implementation approaches that BC Hydro
considered, its proposed approach best achieves principles that account for cost
recovery and customer impacts.
● Second, BC Hydro’s regulatory accounts are an efficient means of addressing
new developments and changes from the Cost of Energy and finance charge
assumptions reflected in the Evidentiary Update. If the BCUC is nonetheless
minded to base its decision on different information or assumptions, then it
should do so holistically so that the overall result remains reasonable.
B. BC HYDRO’S RATE IMPLEMENTATION PROPOSAL IS IN THE INTERESTS OF BOTH CUSTOMERS AND THE COMPANY
574. BC Hydro’s proposal for the Test Period, based on the Evidentiary Update926, is
summarized in the following table. It involves amortizing the credit balance in the Cost of
Energy variance accounts over the Test Period, with different amounts being credited in fiscal
926 As corrected in Exhibit B-11-2.
- 246 -
301539.00025/94161307.1
2020 and fiscal 2021 so that the permanent rate increase for fiscal 2020 matches the interim
rate increase already approved by the BCUC.927
575. BC Hydro developed its rate implementation proposal using four principles relating to:
recovery of the Test Period revenue requirements; rate stability in the Test Period; avoiding bill
adjustments; and, avoiding the re-introduction of longer-term rate smoothing. Assessed
against these principles, BC Hydro’s implementation proposal is reasonable because:
● BC Hydro will recover its revenue requirements (i.e., its cost of service), in the
Test Period, no more and no less;
● It reduces year over year volatility within the Test Period — Volatility could
create hardship for ratepayers;
● It avoids a one-time true-up bill adjustment to address the difference between
fiscal 2020 interim rates and final rates — This adjustment, which would occur
only after fiscal 2020 is over, could create unnecessary hardship and confusion
for customers; and
● It avoids rate smoothing that spans beyond the Test Period, which may be
undesirable in the present context — Longer-term rate smoothing would require
reintroducing a rate smoothing regulatory account at a time when the balance in
the existing account was only just written-off. BC Hydro made a deliberate
decision to avoid this approach, considering past concerns raised by the Auditor
927 Exhibit B-19, Evidentiary Update, pp. 9-10.
Evidentiary Update: Rate Impacts, Deferal Account
Rate Rider, Bill Impacts
Per Cent Increase / (Decrease) F2020 F2021
Rate Impact 6.85 (1.01)
Cumulative Rate Impact 6.85 5.77
Deferral Account Rate Rider 0.00 0.00
Bill Impact 1.76 (1.01)
Cumulative Bill Impact 1.76 0.73
- 247 -
301539.00025/94161307.1
General.928 Rate smoothing beyond the Test Period is also more challenging to
implement because, as Mr. Wong noted, the revenue requirements for future
test periods will change from what is currently forecasted.929
576. Alternative approaches have shortcomings, and do not measure as well against the
principles identified above. The following table summarizes the bill impacts of all of the
alternative scenarios addressed by BC Hydro in information requests. The comparison shows
that excessive volatility results under some scenarios.930
577. Scenario L (highlighted) involves smoothing over the Test Period alone. BC Hydro
characterized Scenario L as “fairly comparable”931 to its proposal, but noted that Scenario L
involves a one-time bill true-up and the bill impacts from its proposal are already sufficiently
stable.932
928 Tr. 5, p. 492, ll. 3-15 (O’Riley). 929 Exhibit B-16, BCUC IR 3.296.3; Tr. 5, p. 494, ll. 1-12 (Wong). 930 Exhibit B-16, BCUC IR 3.296.3. The figures in the table do not reflect the decrease in the operating cost portion
of the current pension costs of $1.0 million in fiscal 2021 which was corrected in Exhibit B-11-2 filed on January 21, 2020.
931 Exhibit B-16, BCUC IR 3.296.3, p. 3. 932 Exhibit B-16, BCUC IR 3.296.3, p. 30.
- 248 -
301539.00025/94161307.1
C. THE BCUC SHOULD AVOID UPDATING EVIDENTIARY UPDATE INPUTS IN ISOLATION
578. BC Hydro’s proposed rates and the scenarios in the figure above are all premised on the
forecasts in the Evidentiary Update. Parties have suggested changes to certain forecasts used
in the Evidentiary Update. In large measure, these issues arise from the timing and duration of
this proceeding. Despite the Evidentiary Update,
(a) actual data for Trade Income, Domestic Revenues and Cost of Energy is available
for three quarters of fiscal 2020; and
(b) new interest rate forecasts have been released by the Ministry of Finance.
BC Hydro submits that the Evidentiary Update remains a reasonable basis for setting rates in
the Test Period, and that regulatory accounts are a pragmatic and fair means of accounting for
new information emerging during this protracted process. In the event that the BCUC were to
determine that further updates are required in a compliance filing, it is essential to consider
offsetting impacts.
(a) Snapshot: Directional Impact of Changing Evidentiary Update Inputs
579. The directional impacts of new information on various inputs are summarized in the
table below. Some of the impacts push rates up while others push rates down. However, the
recommendations in the InterGroup Report all drive the Test Period rates in one direction:
down. Adopting InterGroup’s Recommendations, without recognizing offsetting factors, could
be expected to necessitate a significant rate increase in fiscal 2022.933
New Information Since Evidentiary Update
Directional Impact on Proposed Rates
InterGroup’s Position on Updating
Trade Income (add fiscal 2019 to average)
Down Yes
Storm Restoration Costs Up N/A (accepted in cross)
933 Exhibit B-16, BCUC IR 3.313.2.2 shows that updating forecast Trade Income to be based on a five year average
from fiscal 2015 to fiscal 2019 would result in a rate decrease of 3.13% in fiscal 2021. All else equal, a larger rate decrease in fiscal 2021 would result in a larger required rate increase in fiscal 2022.
- 249 -
301539.00025/94161307.1
New interest rate forecast from Ministry of Finance
Down Yes
Pension discount rate decline Up No
MSP legislation impact on non-current pension costs
Down Yes
Domestic Sales decline Up N/A
(b) Unfavourable Impact of Lower than Forecast Domestic Sales Revenue Should Be Considered Before Updating Five-Year Averages
580. The merits of using a five-year average for forecasting Trade Income and storm
restoration costs appear to be non-controversial; it is an effective means of smoothing out
inherent volatility and uncertainty. The issue that arose with respect to the five-year averages
was, in essence, whether they should be based on data from fiscal 2014 to fiscal 2018 (per the
Application and Evidentiary Update) or fiscal 2015 to fiscal 2019 (per InterGroup’s
recommendation). BC Hydro submits that it was, and remains, reasonable to set rates based on
the forecasts included in the Evidentiary Update.
InterGroup Agreed that Storm Restoration Costs and Trade Income Should Be Treated the Same Way
581. At the outset, it is worth noting that there is consensus as between BC Hydro and
InterGroup that maintaining symmetry in the preparation of the Trade Income and storm
restoration costs five-year averages is the principled approach. Although InterGroup’s report
was silent on storm restoration costs, Mr. Bowman agreed at the hearing that, regardless of the
approach taken to calculate the averages, the treatment should be the same for both
accounts.934 This is important in the current context because (as shown in the table above), the
impacts of including fiscal 2019 data in the averages are partially offsetting.
934 Tr. 11, p. 2066, ll. 14- 25 (Bowman).
- 250 -
301539.00025/94161307.1
It Was Reasonable for BC Hydro to Retain the Five Year Averages Based on Fiscal 2014 to Fiscal 2018 in the Evidentiary Update
582. The timing of this proceeding gave rise to the novel situation where another year of
actual data (fiscal 2019) for Trade Income and storm restoration costs became available prior to
BC Hydro preparing its Evidentiary Update. In the Evidentiary Update, BC Hydro was
transparent about its decision to continue using fiscal 2014 to fiscal 2018 data to calculate the
averages. BC Hydro submits that its reasoning was sound.
583. There is a logical distinction between:
(a) using actual fiscal 2019 data to update the starting balances in regulatory
accounts that have to be amortized during the Test Period (which BC Hydro did
in the Evidentiary Update); and
(b) updating an input to a forecast methodology (a five-year average), the design of
which is premised on recognition that the actual results during the applicable
test period will almost inevitably differ.
584. Mr. Wong explained that, given the significant volatility associated with both storm
restoration costs and Trade Income, the averages from the Application (based on fiscal 2014 to
fiscal 2018) did not seem any more or less reasonable than the average incorporating fiscal
2019. In both cases, there is every expectation that the actual amount will differ, which is why
the regulatory accounts exist in the first place. The regulatory accounts make this an issue of
timing, and the short amortization periods avoid intergenerational inequity.
585. There are any number of costs that could conceivably be updated in an Evidentiary
Update. Costs change constantly in response to new pressures, and new information
continuously comes available. It is necessary to exercise some judgement over what needs to
be updated, and when, or the revenue requirements process would be unworkable. BC Hydro
submits that it was appropriate to apply a principle that asks “Is the forecast in the Application
still a reasonable basis for setting rates, based on what we know now?” The original five-year
- 251 -
301539.00025/94161307.1
averages for storm restoration costs and Trade Income were still reasonable based on BC
Hydro’s assessment of the current state, and BC Hydro was transparent about that assessment.
Unfavourable Impact of Lower than Forecast Domestic Sales Revenue Should Be Considered Before Updating Five Year Averages
586. Given the elapsed time since the Evidentiary Update, BC Hydro now has nine months of
actual information from fiscal 2020 for Trade Income, Domestic Revenues and Cost of Energy.
It has turned out that Trade Income for the nine months ended December 31, 2019 was $159
million, which is closer to the number produced by updating the five-year average to include
fiscal 2019 actuals.935 Considered in isolation, these results might suggest that the five-year
average for Trade Income should be updated.
587. However, many variables change over time. There was also $36 million in net additions
to the other Cost of Energy Variance Accounts as at December 31, 2019, primarily due to lower
than forecast Domestic Revenues.936 BC Hydro expects actual Domestic Revenues to continue
to be below forecast for the remainder of fiscal 2020. In other words, nine months into the
year, “it appears that roughly offsetting amounts will be deferred to the Cost of Energy
Variance Accounts in fiscal 2020 when taking into account Trade Income, revenue and cost of
energy.”937 Setting rates based on the Evidentiary Update thus produces a reasonable result
overall.
(c) InterGroup’s Recommendation to Update Interest Rate Forecasts While Using an Out of Date Pension Discount Rate Would Produce an Unreasonable Result
588. Despite advocating for updating the forecast finance charges to reflect interest rate
forecasts post-dating the Evidentiary Update, InterGroup opposed BC Hydro’s decision to use 935 This amount is approximately $40 million higher than the five-year average of fiscal 2014 to fiscal 2018. If an
updated five-year average from fiscal 2015 to fiscal 2019 is used, the forecast amount is $176.3 million, which is approximately $15 million higher than actual Trade Income as at December 31, 2019, with one quarter of the year still remaining.
936 Exhibit B-46, BC Hydro Undertaking No. 24. The lower than forecast Domestic Revenues were the result of lower than forecast sales, partially offset by lower than forecast Cost of Energy. Exhibit B-41, BC Hydro Undertaking No. 15 shows that year-to-date fiscal 2020 domestic sales as of December 31, 2019 were 2.6 per cent below forecast.
937 Exhibit B-46, BC Hydro Undertaking No. 24.
- 252 -
301539.00025/94161307.1
the appropriate, updated pension discount rate available when BC Hydro prepared the
Evidentiary Update. InterGroup favoured the continued use of the pension discount rate from
the Application. A common feature of both of InterGroup’s recommendations is that, if
accepted, they would tend to reduce BC Hydro’s proposed rates. BC Hydro submits that
InterGroup’s position would produce an unreasonable result.938
589. First, it was reasonable for BC Hydro to use the March 31, 2019 pension discount rate in
the Evidentiary Update. It was the most recent discount rate prepared by its pension actuary,
provided for use in BC Hydro’s audited fiscal 2019 financial statements. InterGroup conceded
that they had no reason to believe it was unreliable.939
590. Second, reducing finance charges to reflect a decline in interest rates since the
Evidentiary Update, as InterGroup recommends, would necessarily be accompanied by
increasing forecast pension costs. InterGroup’s witnesses, Ms. Davies and Mr. Bowman,
acknowledged that:
(a) movements in pension discount rates are generally correlated with interest rate
movements;
(b) if interest rates go down, other things equal, the discount rates will also go
down; and
(c) lower discount rates will increase pension costs, other things equal.940
591. Mr. Wong thus urged the BCUC to maintain alignment between forecast finance charges
and pension costs:
I guess what I’m recommending to the panel is that if we’re going to benefit the rates by reducing the finance charges because of the lower forecasted interest
938 Exhibit B-28, BC Hydro Rebuttal Evidence, pp. 1-2. 939 Tr. 11, p. 2070, l.23 to p. 2071, l 9 (Bowman). 940 Tr. 11, p. 2071, l. 25 to p. 2074, l. 7 (Bowman and Davies). On the first point, Mr. Bowman elaborated that “The
pension discount rate is tied to hypothetical portfolio of long term bonds and so it’s tied to the yield on those bonds which is basically an interest rate.”
- 253 -
301539.00025/94161307.1
rate, we should also be looking at the pension costs, because that is going to increase the pension cost with the lower discount rate, lower interest rate essentially. So I want to make sure we net the two, we just don’t give back all the reduction and finance charges in the application. And then when we know that the pension costs will go up because of the reduction in interest rates, and that would have to be then deferred and captured in the future years. It’s a timing issue but we want to make sure that we try to incorporate all that in the same period.941
592. Accordingly, it makes sense to maintain the existing interest rates forecast and discount
rate, which are aligned.942 Regulatory accounts address the variances in pension costs and
finance charges in an efficient manner.943
(d) Regulatory Accounts Facilitate Ratesetting in the Context of Uncertainty due to COVID-19 Pandemic
593. The impacts of the novel coronavirus (COVID-19) have increased dramatically since the
topic was first raised in this proceeding at the Oral Hearing. First and foremost, BC Hydro
wishes to express its thoughts and sympathies to customers and their families who have faced
hardships due to the virus, including those who have died, are in hospital or whose health has
been impacted and those who are facing economic challenges and uncertainties.
594. On March 17, 2020, the Government of B.C. declared a provincial state of emergency to
support the response to the COVID-19 pandemic. BC Hydro has created its own pandemic
response plan, which has been filed in this proceeding.944 The plan outlines how BC Hydro will
continue to provide service safely to customers during this time.
595. The BCUC can take judicial notice of the fact that the COVID-19 pandemic is having
ongoing detrimental economic effects and is disrupting daily life in unprecedented ways. BC
Hydro acknowledges the hardships faced by its customers due to the virus, including those who
941 Tr. 7, p. 892, ll. 7-21 (Wong). 942 Tr. 7, p. 892, l. 22 to p. 894, l. 12 (Wong). 943 Exhibit B-1, Application, pp. 7-44 to 7-46. 944 Exhibit B-58, BC Hydro Undertaking No. 44, Attachment 1.
- 254 -
301539.00025/94161307.1
have died, those who are in hospital or whose health has been impacted, and those who are
facing economic challenges and uncertainties.
596. The extent and duration of the impacts of the pandemic on BC Hydro’s revenues and
costs are uncertain. However, BC Hydro’s regulatory accounts will mitigate much of the
uncertainty caused by the pandemic by capturing variances from forecast which can then be
returned to or recovered from customers in the next test period in accordance with existing
BCUC orders. For example:
● Any impacts to cost of energy or load (e.g., potential declines in the commercial
sector load) will be recorded in the Cost of Energy variance accounts.
● Any variances from forecast capital additions due to changes in project
schedules will be recorded in the Amortization of Capital Additions Regulatory
Account.
● Any impacts of movements in interest rates on finance charges are recorded in
the Total Finance Charges Regulatory Account, and any impacts of the correlated
movement of pension discount rates will be recorded in the Non-Current
Pension Cost Regulatory Account.
597. The rationale for these accounts, and the other benefits they provide, are discussed in
Part Eight of these Submissions.
598. Nonetheless, in this unprecedented situation, it is impossible for BC Hydro or any party
to foresee all potential impacts of the pandemic. Therefore, if any particular approval from the
BCUC is required over the remainder of the Test Period due to the pandemic, BC Hydro will
bring forward requests to the BCUC in separate applications as needed. Filing such requests
separately from the current RRA proceeding will enable the BCUC to consider them in a more
expedited manner reflective of the COVID-19 crisis.
599. With this proceeding already extending more than half-way through the Test Period, it
needs to be brought to a conclusion. Therefore, BC Hydro requests that the BCUC approve its
- 255 -
301539.00025/94161307.1
proposed rates, despite the uncertainties caused by the COVID-19 pandemic. As noted above,
BC Hydro’s regulatory accounts will largely mitigate the impacts of the pandemic and BC Hydro
will bring forward any proposals for any particular relief needed over the remainder of the Test
Period in separate applications.
D. CONCLUSION AND REQUESTED FINDING
600. The BCUC should find that the Evidentiary Update remains a reasonable basis upon
which to base Test Period rates.
- 256 -
301539.00025/94161307.1
PART THIRTEEN: CONCLUSION AND ORDER SOUGHT
601. The Evidentiary Update, Appendix B contains a Draft Order that sets out BC Hydro’s
requests, as updated by the Evidentiary Update.945 BC Hydro submits that the BCUC should
approve the orders sought. The proposed rates are just and reasonable, reflecting the
reasonable cost of providing service to customers in the Test Period. The proposed DSM
expenditure schedule plan is in the public interest, and will provide access to appropriate
programs pending the upcoming IRP.
ALL OF WHICH IS RESPECTFULLY SUBMITTED
Dated: April 1, 2020 [original signed by Matthew Ghikas]
Matthew Ghikas
Counsel for BC Hydro
Dated: April 1, 2020 [original signed by Christopher Bystrom]
Christopher Bystrom
Counsel for BC Hydro
Dated: April 1, 2020 [original signed by Tariq Ahmed]
Tariq Ahmed
Counsel for BC Hydro
945 Exhibit B-19, as corrected by Exhibit B-11-2.
Recommended