  • Ques.1. Andy Arthurson is an independent computer software consultant. After completing his

    most recent project, he had five jobs awaiting completion. Following are the estimated work

    times required to complete each job and the due dates requested by customers

    Job Processing time (Days) Due Date(days from present)

    A 12 52

    B 16 37

    C 8 28

    D 20 57

    E 6 31

    Construct job sequence using the SPT,EDD, STR and CR rules and compute the average flow time,

    average number of jobs in the system, average tardiness per job and number of jobs tardy for

    each sequence.

    Ques.2. Marine Electro-Plating has six customized electroplating jobs to process through its two-

    stage production system. The estimated processing times for the jobs at each stage are given

    below. Use Johnsons rule to construct a production sequence that minimizes the make span

    time.

    Job Stage 1 Stage 2

    A 12 9

    B 21 13

    C 10 17

    D 8 15

    E 16 11

    F 19 14

  • Ques.3. The track and field coach of Chesterfield High School must assemble a medley realy

    team for a track meet. The relay race requires four runners to run legs of 200, 400, 800, and

    1600 meters. The coach has five runners from whom to form the team and has estimated the

    likely running times for each distance as follows:

    Runner

    Distance(m) 200 400 800 1600

    Nancy 26 54 140 295

    Sue 27 59 147 325

    Jennifer 27 58 144 298

    Alex 25 53 139 300

    Beth 29 60 142 305 Times in Seconds

    The coach must decide which four runners will be on the relay team and which race each will run.

    Ques.4. Robert Crump is a student at Pomville University. Robert has five term papers due soon,

    and he must decide in what order to complete them. Below are the estimated number of days

    required to complete each paper and the due dates. Because all the instructors deduct 5 points

    per day for any term paper that is tardy. Robert wants to minimize tardiness.

    a. Use the SPT,EDD, CR, and STR rules to sequence the jobs. Which one(s) results in the least

    average tardiness?

    b. Which result(s) in the fewest tardy papers?

    Course Estimated time(Days)

    Due Date

    History 3.5 7

    Finance 3.0 8

    P/OM 6.0 12

    Accounting 4.5 17

    Math 2.5 16

  • Ques.5. Suppose a company wanted to complete six jobs using a three-stage flow process with

    the stage times given below. Construct the sequence in which the jobs should be run to minimize

    the make span time.

    Job Stage times(hr.) Stage 1 Stage 2 Stage 3

    A 9 12 17

    B 13 7 14

    C 14 10 15

    D 10 9 20

    E 15 11 13

    F 8 5 15