(1) foot vertical should consider surface measurements to calculate areas forpayment purposes.
(2) Methods 2 and 3 The procedures that will be used to determine the amount ofwork satisfactorily completed for progress payment should be identified in
Section 7.
Options may include:
- an on-site agreed-to estimate of the percent of work satisfactorilycomplete at time of progress payment preparation; or
- require the contractor to provide invoices (Method 3) to support hisincurred costs to satisfactory complete work at time of progress payment;or
- other suitable and fair methods, one of which could be related to theconstruction schedule.
When specifications are prepared electronically and all but one method aredeleted for use in a contract specification, delete "All Methods The followingprovisions apply to all methods of measurement and payment.” and left justify theremaining text.
NRCS-IL-URB 6 - I - 2 11/97