(1) foot vertical should consider surface measurements to calculate areas forpayment purposes.

(2) Methods 2 and 3 The procedures that will be used to determine the amount ofwork satisfactorily completed for progress payment should be identified in

Section 7.

Options may include:

- an on-site agreed-to estimate of the percent of work satisfactorilycomplete at time of progress payment preparation; or

- require the contractor to provide invoices (Method 3) to support hisincurred costs to satisfactory complete work at time of progress payment;or

- other suitable and fair methods, one of which could be related to theconstruction schedule.

When specifications are prepared electronically and all but one method aredeleted for use in a contract specification, delete "All Methods The followingprovisions apply to all methods of measurement and payment.” and left justify theremaining text.

NRCS-IL-URB 6 - I - 2 11/97