Works executed by K.V. Prateek Enterprises

S.

No.

Client /

Principal

Employer /

Site

Site Employer Cable Laid Year of

Execution

400 KV Cable Laying

1 Voith Siemens Sainj, Hydel

Plant, H.P.

Tiahan Cables,

Korea

3600 mtrs. 2016

220 KV Cable Laying

1 Reliance

JERP,

Jamnagar,

Gujrat

Jam Nager,

Gujarat

Siemens Ltd. 11500 mtrs. 2007

2 Delhi Transco

Ltd.

Masjid

Moth to

Maharani

Bagh

Larsen &

Toubro Ltd.

23,614 mts. 2010 - 11

3 Delhi Metro

Rail

Corporation

Ltd.

Vasant Kunj JV of KEI

Industries Ltd.

and BRUGG

Kables,

Switzerland

12960 mtrs. 2015

Total Cable Laid 48,074 mtrs.

66 KV Cable Laying - Turnkey Projects

1 Delhi Metro

Rail

Corporation

Ltd.

Delhi Gate Larsen &

Toubro Ltd.

1866.15 mtrs. 2013

2 Haryana

Vidyut

Prasaran

Nigam Ltd.

Gurgaon IL&FS Engg.

&

Construction

Co. Ltd.

6769 mtrs. 2015

3 Haryana

Vidyut

Prasaran

Nigam Ltd.

Sector 68

Gurgaon

Pareena

Infrastructures

Pvt. Ltd.

3192 mtrs. 2016

Total Cable Laid 11,827.15

mtrs.

33 KV Cable Laying - Turnkey Projects

1 Delhi Metro

Rail

Corporation

Ltd., Phase - II

Adarsh

Nagar Stn to

Jahangir

Puri

DMRC Ltd. 4047 mtrs. 2007

2 at Azadpur 2750 mtrs. 2007

3 Delhi Metro

Rail

Corporation

Ltd., Phase -

III

Near

Shalimar

Bagh of

Line 7

(MKP to

Shiv Vihar)

DMRC Ltd. 2465 mtrs. 2014

4 near

Shekhavati

Sub station

of MES in

Delhi Cantt.

of

(JKP to

BoG Line)

1058 mtrs. 2014

Total Cable Laid 10,320 mtrs.

11 KV Sub-station and External Lighting - Turnkey Projects

1 Rail Coach

Factory, Rae

Bareli

RCF Rae

Bareli

(Sub-

stations)

IRCON

International

Ltd.

8 nos.

Auxiliary

Substations

2015

2 RCF Rae

Bareli

(External

Lighting

and Power

Supply

System)

25 mtrs. High

masts,

10 mtrs.

Masts,

Power Cables

2015

Laying of 3 Core x 300 sq. mm 66 KV Cable

(IN TUNNEL, ON GROUND AND VIADUCT)

for SIEMENS – DMRC Project

1 M/s Sterlite

Power

Transmission

Ltd.

Dhaula

Kuan - INA,

Delhi

Siemens Ltd. -

DMRC Ltd.

4826 mtrs. Work is

under

Execution

2 Vasant Kunj

to Andheria

Bagh

BSES

Rajdhani

Power Ltd.

9618 mtrs.

Total Cable Laid 14,444 mtrs.

66 KV Single Core Cable Laying

1 Delhi Metro

Rail

Corporation

Ltd.

(Phase-I)

Rajghat to

New Delhi

RSS

IRCON

International

Ltd.

31800 mtrs. 2005

2 Delhi Metro

Rail

Corporation

Ltd.

(Phase-I)

Subhash

Nagar to

Pappan

Kalan

ABB Ltd. 24000 mtrs. 2005

3 Delhi Metro

Rail

Corporation

Ltd.

(Phase-II)

Mundka ILJIN Electric

Co., Ltd.

32834 mtrs. 2011

Sarita Vihar

23343 mtrs. 2011

Sushant Lok 27600 mtrs. 2011

4 Delhi Metro

Rail

Corporation

Ltd.

(Phase-III)

Harsh Vihar

to Yamuna

Vihar

Siemens Ltd. 98369 mtrs. 2015-16

Palam

3661 mtrs. 2015-16

RK Puram

1806 mtrs. 2015-16

Dhaula

Kuan

1081 mtrs. 2015-16

Pappan

Kalan to

Subhash

Nagar

15209 mtrs. 2016-17

5 Delhi Metro

Rail

Corporation

Ltd.

(Phase-III)

Gopal Pur

to

Mukundpur

IRCON

International

Ltd.

24770 mtrs. 2015

Mukundpur

to Jahagir

Puri

18322 mtrs. 2016

INA to RK

Puram

21680 mtrs. 2016

6 BSES

Rajdhani

Power Ltd.

Hastsal to

Guru

Gobind

Singh

Hospital

BSES

Rajdhani

Power Ltd.

45071 mtrs. 2011

7 BSES

Yamuna

Power Ltd.

near

Akshardham

Temple

BSES Yamuna

Power Ltd.

17050 mtrs. 2010

Mayur

Vihar - I -

Mayur

Vihar I

15996 mtrs. 2013

Mayur

Vihar - I to

Akshardham

10393 mtrs. 2015

PPG to

Khichdipur

8032 mtrs. 2016

Total Cable Laid 4,06,078

mtrs.

22 KV Cable Laying for Mumbai Mono Rail Projects

1 Mumbai

Metropolitan

Region

Development

Authority

Phase - I Larsen and

Toubro Ltd.,

30413 mtrs. 2012

2 Mumbai

Metropolitan

Region

Development

Authority

Phase - II Larsen and

Toubro Ltd.,

43,655.9 mtrs. 2016

Total Third Rail / Conductor Rail Installed 74,068.9

mtrs.

220 KV Sub-station Erection Work

1 Govt. of

Islamic

Republic of

Afghanistan

Aibak,

Afghanistan

IRCON

International

Ltd.

1 2013

2 Mazar-e-

Sharif,

Afghanistan

1 2013

132 KV Sub-station Erection Work

1 Delhi Metro

Rail

Corporation

Ltd, Phase - II

Botanical

Gardens

IRCON

International

Ltd.

30 MVA - 2

nos.

15 MVA - 2

Nos.

2009

66 KV Sub-station Erection Work

1

Delhi Metro

Rail

Corporation

Ltd, Phase - II

Power

Transformers

Mundka and

Andheria

More

IRCON

International

Ltd.

30 MVA - 2 +

1 nos.

15 MVA - 2

Nos.

2009-10

2 Sushant Lok

30 MVA - 2 +

2 nos.

2010

3 Sarita Vihar 30 MVA - 2 +

2 nos.

2010

4 Chattarpur

30 MVA - 1 +

2 nos.

2011

33 KV Sub-station Erection Work

1 Delhi Metro

Rail

Corporation

Ltd, Phase - I

Phase - I Best and

Crompton

Engg. Ltd.

2 Nos.

Auxiliary

Substations

2002

Phase-I,

Line 3

ABB Ltd. 4 Nos.

Auxiliary

Substations

2002

Delhi Metro

Rail

Corporation

Ltd, Phase - II

SYS 2

Project

RC-7B

Project

IRCON

International

Ltd.

11 Nos. Aux.

Stns.

2 Nos. Aux.

Stns.

2004-05

CSTM-

HUDA &

Badarpur

ABB Ltd. 13 Nos.

Auxiliary

Substations

2010-11

Delhi

Airport

Metro

Express

Line

Siemens Ltd. 14 Nos.

Auxiliary

Substations

2011

Delhi Metro

Rail

Corporation

Ltd, Phase -

III

CE08, LOT

1

Siemens Ltd. 21 Nos.

Auxiliary

Substations

2016

Total Auxiliary Sub-Stations Erected 67 Nos.

Auxiliary

Substations

Annual Maintenance of 33 KV Grid Sub-station and Overhead Transmission

Lines

1 BSES

Yamuna

Power Ltd.

East BSES Yamuna

Power Ltd.

From Nov.

2002 to

31.07.2017

2 Tata Power

Delhi

Distribution

Ltd.

System

North and

North

Central

Tata Power

Delhi

Distribution

Ltd.

From May

2003 to

31.12.2019

Recommended