Construction Update

Preview:

Citation preview

ConstructionUpdate

Lone Star College – CyFairSeptember 2010

Academic/Student Svcs Building

Academic/Student Services Building

– Located west of current LRNC Building– Description• 138,937 SF• 44 Classrooms• 10 Computer Labs• Offices – 3 Faculty Suites, 1 Dean Suite, 1 CE Suite• Student Services – Approx. 38,000 SF with Areas for

Advising, Counseling, Registration, Assessment, Financial Aid, and Payment Services

Science Building

Science Building

• Located east of current HSC building• Description– 52,809 SF– 7 Science Labs– 4 Computer Labs– 15 Classrooms– Offices – 1 Faculty Suite

Student Activity Area Renovation

Student Activity Area Renovation

• Description– 18,000 SF– Zones – Student Government Offices, Staff

Offices, Recreational/Game Area, TV Area, Meeting Rooms

Parking/Loop Road

Additional Parking/Infrastructure

• Description– 1,100 New Parking Spaces– New Road– Campus Core/Landscaping• Green Space• Community Garden

LSC-Cypress Center

LSC-Cypress Center

• Description– Location – Clay Road/Fry Road Area– 83,918 SF– 14 Classrooms– 8 Computer Labs– 4 Workforce Training Labs– Offices – 2 Faculty Suites– 600 Parking Spaces

Current Construction Status

• All underslab utilities complete-both buildings• Slab on grade complete on Science, 90% on Academic/Student

Services• Steel erection complete on Science, 90% on Academic/Student

Services• Electrical, HVAC ductwork, plumbing 60% complete on Science,

not started on Academic/Student Services• Interior framing 45% complete on Science, not started on Acad….• Still on schedule to occupy buildings in early summer 2011• Loop road complete, new parking complete (1,100 spaces)• Cypress Center has been delayed due to permit issues with Harris

County—Fall Semester, 2011 opening is in jeopardy

Current Construction Photos

Current Construction Photos

Current Master Plan

Long Range Master Plan