Introduction to Construction Industry: Final Project

FNBE APRIL INTAKE 2014INTRODUCTION TO CONSTRUCTION INDUSTRY

FINAL PROJECT REPORT

Name: Canisius Bong Wei PhengStudent ID: 0318914

Name: Ong Jia MinStudent ID: 0318003

Page 2: Ici final project

Introduction to Construction Industry: Final Project

CONTENT

Introduction to final project

Site analysis and observation

Understanding of rest area

Purpose

Site plan

Concept

Perspective

Application for building plan approval

Costing

Benefits

Conclusion

Page 3: Ici final project

Introduction to Construction Industry: Final Project

Introduction to Final Project

For this final project, it is a group work that consists with only 2 people. In our

group there are only two of us, Canisius Bong Wei Pheng and Ong Jia Min. This final

project required us to find a specific land within Taylor’s University Lakeside

Campus to initiate a small construction project. The size of the land shall not be

more than 30m x 30m. Every group has to choose one out of five purpose which

include Recreation Area, Study Enhancement Area, Rest Area, Food and Beverage

(dining area) as well as Commercial Area. So, for us we’ve chosen rest are as our

purpose for this final project.

Page 4: Ici final project

Introduction to Construction Industry: Final Project

Site Analysis and Observation

After understanding the final project brief of Introduction to Construction

Industry, we had chosen a 30m x 30m site to initiate our small

construction project. So our 30m x 30m site is located near the lake which

is in between the commercial block and block C,D and E building. The

whole lake measure approximately 30m x 60m and to build this rest area

we only require 30m x 30m of the entire space will be used which is half

of it. Towards to the west from our site, which is the commercial block

which we can see most of the restaurant place there. Towards to the south

from our site, besides seeing the lake we can also see car park and the

futsal court. Towards to the east from our site, it is our Campus block C,

block D and block E buildings. Towards to north from our site, it is our

Campus block A, block B and offices.

Page 5: Ici final project

Introduction to Construction Industry: Final Project

A top view of our 30 x 30m site

This is the North view from our site.

Page 6: Ici final project

Introduction to Construction Industry: Final Project

This is the East view from our site.

This is the South view from our site.

Page 7: Ici final project

Introduction to Construction Industry: Final Project

However, the commercial block will be the West view from our site.

A different perspective view of our site to initiate rest area.

Page 8: Ici final project

Introduction to Construction Industry: Final Project

Site Analysis- Measurement

Page 9: Ici final project

Introduction to Construction Industry: Final Project

Site Analysis- View Surrounding Site

60m

30m

Taylor Campus Block A and Block B

Page 10: Ici final project

Introduction to Construction Industry: Final Project

Understanding of Rest Area

Block CBlockDBlock E

Futsal and basketball court, lake and car park

Commercial Block

Page 11: Ici final project

Introduction to Construction Industry: Final Project

Rest area is a place where people able to relax themselves and put all their problems aside.

Most of the rest area provides comfortable resting chairs and a very quiet and peaceful environment so that people can relax themselves.

Rest area can be located in anywhere as long as there are people around that area.

Besides our own home or bedroom, public area can also have a rest area to let people to rest whenever they are tired.

The purposes of having a rest area is mend to let people to have their own sweet time and relax their mind.

Purpose

The purpose we choose to initiate our site as a rest area is to

Page 12: Ici final project

Introduction to Construction Industry: Final Project

provide more resting area for students, lecturers and visitors because

there are limited places especially rest area in Taylor’s University

Lakeside Campus as Student Life Centre and library are the only places to

have a good and comfy place to sleep and rest.

The rest area also consist of cafeteria and vending machines so that

people don’t need to walk a long distance to grab themselves foods and

drinks. At the same time it can help to earn some income

This rest area is located around the lakeside in between the

commercial block and buildings of block C, D and E because it is a center

point in the campus as it is convenient for people to walk there within a

short period

Site PlanCafeteriaSlide and projector

Page 13: Ici final project

Introduction to Construction Industry: Final Project

Concept

Beanbag Chair

Wooden Bench

Walkway bridgePlants

Page 14: Ici final project

Introduction to Construction Industry: Final Project

The whole concept of this rest area design is to let people to rest, relax and

chill in a peaceful and quiet environment with many facilities provided

there. This rest area is divided into four part along with a walkway bridge.

The first two section are the theater room together with slide and projector

and red beanie chair. The third section is the cafeteria that sell light foods

where is convenient for people to grab some light food. The last section of

this rest area is the the bench area which there are only benches in this

section. People can just sit down and enjoy the peaceful and scenery of the

rest area.

The projectors and slides are provided in the rest area theater rooms for people to spend their time and watch movie. All type of movies will be showing in different day and time. The list of movies will be renew from time to time.

Page 15: Ici final project

Introduction to Construction Industry: Final Project

Meanwhile, there are also red beanbags provided around the whole room of the theater room of the rest area. People can choose either to rest on and watch a movie or sleep on it.

This set of table and chair will be the concept for our cafeteria’s dining furniture in our rest area.

Page 16: Ici final project

Introduction to Construction Industry: Final Project

Besides beanbag, wooden benches will also be provided in fourth section of our rest area. So, there will be sufficient space for people to rest, chill and relax.

The artificial bushes has a purpose to make our rest area looks greener and more eco-friendly.

Page 17: Ici final project

Introduction to Construction Industry: Final Project

Vending machines will also be included in the rest area for everyone convenient to grab some snacks or drinks.

Page 18: Ici final project

Introduction to Construction Industry: Final Project

Perspective

Purple Persian Shield plant and Purple Hydrangea plant are used to make our rest area more colorful and lively. Purple represent spiritually which will attract people’s attention.

Pink color represent nature and culturally. It brings nature one step closer to people and also additionally brings joy and colors to our rest area. Besides that, people will get attracted by the color pink and also the fragrance of Pink Azalea plant.

Page 19: Ici final project

Introduction to Construction Industry: Final Project

A perspective view of our proposed rest area on our selected site.

Page 20: Ici final project

Introduction to Construction Industry: Final Project

The view of our theater room in the rest area.

Perspective view of the wooden benches for people to sit at the rest area.

Page 21: Ici final project

Introduction to Construction Industry: Final Project

Application for Building Plan Approval

Document Required

Application letter using original letter head indicating application

reference and proposed construction.

A copy of landownership or land title which has been certified as

true copy by commissioner of Oaths or Justice of Peace.

Copies of valid documents such as power of attorney or sales and

purchase agreement or tenancy agreement if the owner is different

from the list of names in the landownership or land title.

Six sets of building plans properly arranged and folded in A4 size

which has been prepared by a professional consultant. Examples

architect/engineer or registered draughtsman in accordance to

their respective limitations for submission of building plans.

Page 22: Ici final project

Introduction to Construction Industry: Final Project

Page 23: Ici final project

Introduction to Construction Industry: Final Project

Page 24: Ici final project

Introduction to Construction Industry: Final Project

Page 25: Ici final project

Introduction to Construction Industry: Final Project

Page 26: Ici final project

Introduction to Construction Industry: Final Project

CostingBILL OF MATERIALS(COST ESTIMATION)

ITEM DESCRIPTION UNIT/SIZE RATE(RM) QUANTITY AMOUNT AMOUNTA HARDSCAPE WORK

1 SLIDE PROJECTOR M² 799 2 15982 WOODEN TABLE NOS 500 6 30003 WOODEN BENCH NOS 270 4 10804 WOODEN CHAIR NOS 80 12 9605 BEANBAG CHAIR NOS 250 30 75006 WOODEN PLANK FLOORING FT² 9 165 14857 UMBRELLA SHELTER FT² 500 1 5008 LONG FOLOWER POT NOS 20 6 1209 CEILING FANS M² 250 4 1000

HARDSCAPE TOTALB SOFTSCAPE WORKS

10 PINK AZALEANOS (POT) 55 15 825

11 PURPLE PERSIAN SHIELD PLANTNOS (POT) 34 15 510

12 FERTILIZERS KG 15 20 300

13 HYDRANGEA FLOWERNOS (POT) 40 15 600

14 SOIL KG 30 30 900

15 ARTIFICIAL BUSHNOS (PIECE) 200 8 1600

SOFTSCAPE TOTALSUB TOTAL

CORRECTION TOTAL

Page 27: Ici final project

Introduction to Construction Industry: Final Project

MAINTAINANCE BILL

ITEM DESCRIPTION UNIT/SIZE USAGE LISTRATE(RM

)QUANTIT

YAMOUN

T AMOUNT

1 WATER USAGE MONTH (M³)

0-20 0.57 20 11.4>20-35 1.03 15 15.45>35 2 965 1930

2ELECTRIC

USAGE MONTH 0-200 0.218 74.4 16.21923 GARDENER MONTH 800 1 800

SUB TOTALCORRECTION TOTAL

Page 28: Ici final project

Introduction to Construction Industry: Final Project

Benefits

Creating more rest area in this campus, there is a limited place for students in Taylor’s to chill especially during their break time so they can come to our site and rest.

This resting area can be an attraction of this campus and it can also attract more students, parents or lecturers to come and visit it.

It can make our campus more lively especially during the night time because most of the shops are closed in the campus but only our resting area is still open for people to chill.

Most importantly students who don’t drive to campus can chill or spend time in our rest area before their parents pick them up from campus.

Our proposed rest area can also be a good place for people to meet up and chit-chatting because there are also vending machines and cafeteria for them to chill.

Conclusion

Page 29: Ici final project

Introduction to Construction Industry: Final Project

In a nutshell, this 30m X 30m site are proposed to initiate as a rest area

for students, lecturers, staff and visitors in Taylor’s University Lakeside

Campus as there are limited rest area in the campus for people to rest. So, this

project to build a rest area around the lake serves as a solution to solve the

issues of limited rest area in the campus.

As soon as we fully understand our site, we started planning our site

based on our chosen concept which is rest area in order to serve as its purpose.

We came out with some ideas which is to provide a movie theater together

with beanbags in our rest area in order to create a different atmosphere as a

rest area. The whole concepts of the rest area along with the plants, furniture

and others also required to plan well to make sure it is suitable for it.

Last but not least, it require us a lot of procedures to get some items such

the documents from the authority. I’d like to thanks our lecturers and tutor for

giving us advice when we needed it and also some helps when we face the

problems doing this assignment.