Page 1: ECM study - strategy, management & technology

Slide: 1

Strategy, Management &

Technology

Lessons learned for ECM at EUMETSAT

Page 2: ECM study - strategy, management & technology

Slide: 2

Contents

• EUMETSAT

• The ECM Study

• Phase 1

• Phase 2

• Next Steps

• Lessons Learned

• Discussion

Page 3: ECM study - strategy, management & technology

Slide: 3

EUMETSAT overview

Mission ... to deliver operational satellite

meteorological and climate data

and products that satisfy data

requirements of its Member

States – 24/7 hours a day, 365

days a year

Intergovernmental

21 Member States

550 employees

30+ nationalities

Page 4: ECM study - strategy, management & technology

Slide: 4

ECM infrastructure

• Multiple ECM systems – Document management - Open Text (Hummingbird)

– Web content mgt - Stellent

– Images - Imagine

– Bespoke applications

– Large amount of information in GroupWise & File System (Tb)

• Fragmented information management approach – Many local practices

– Limited awareness of overall policy

– Overall policy not kept up to date

Page 5: ECM study - strategy, management & technology

Slide: 5

The ECM Study

• Identify options to better integrate current systems – Enhance support for business processes

– Gain increased value from corporate information

– Better manage risks and uncertainties

• Phase 1: review current state & identify options

• Phase 2: explore selected options in more depth

• Constraints – Operational systems and data out of scope

– Avoid major disruption to EUMETSAT staff

Page 6: ECM study - strategy, management & technology

Slide: 6

Phase 1 - Approach

• Survey current information and systems – Document review (40+ docs defining systems and standards)

– Interviews (29 people)

• Develop overview and refine via 2 workshops – Content and systems matrices

– Key issues

• Analyse root causes & hence frame findings

Page 8: ECM study - strategy, management & technology

Slide: 8

Phase 1 - Hard to find information

“It’s hard to know where to go to for the master version. i.e. a lot of docs aren’t covered by ECM.”

“I lose a lot of time looking for info – I may need to open several docs to find one I’m looking for.”

“I need some sort of mind-map to help me find the information I’m looking for.”

“Once a document is created it goes into a black hole and you find it by searching.”

“Everyone creates their own folder structure: there are no clear rules” General agreement on the

difficulty of assigning and managing access permissions

Page 9: ECM study - strategy, management & technology

Slide: 9

Phase 1 - Inconsistent processes

Inconsistent processes across different units

Inconsistent enforcement of approval processes, e.g. due to reliance on manual processes

Inconsistent use of document versioning (eg. use of draft documents)

Duplicate registration of documents in Mail Registration system

Overheads of existing processes (e.g. to walk physical documents around approvers)

Reliance on manual processes to ensure documents are consistent across systems

Page 10: ECM study - strategy, management & technology

Slide: 10

Phase 1 - Strengths & Weaknesses

Strengths Areas for Improvement

Governance (Structures for decision making and alignment)

1) Alignment between Information Management and organisational objectives

Document management is embedded within

organisational processes and quality management

systems through ISO9001.

Web information is not covered – Stellent is not

a recognised system within the QMS.

2) Alignment between Information Management and ICT systems

Web management and document teams established

and functioning to make decisions about priorities for

systems development.

Organised by system, rather than having an

overview of broader objectives.

3) Management of policies and standards

Groups to discuss policies and standards (e.g. web and

document user groups) are established and meet

regularly.

Organised by system. Authority to define policy

is not clear. Would welcome training on

information management.

4) Operational management of information

Key roles are in place (e.g. document controllers) and

appear to be operating effectively.

Processes are often manual, and differ across

divisions/units.

Page 11: ECM study - strategy, management & technology

Slide: 11

Strengths Areas for Improvement

Policies and Standards (Guidance on how to manage information)

1) File Plans (e.g. defined folder structures for storing records)

Well defined in programme document management

plans. Appear to be understood & adhered to.

Not defined at organisational level. Not

embedded in Hummingbird DMS.

2) Information types (e.g. definition of types & processes for managing them)

Are well defined for some information types (e.g. in

PRC001).

PRC001 out of date and incomplete. Differing

interpretations of its application.

3) Classification schema (e.g. controlled vocabularies, keywords, taxonomies, etc)

Some teams have keyword schemes for local use. Generally very fragmented.

4) Confidentiality and security policies

Policies are documented and everyone appears to be

well aware of their existence.

Many people expressed difficulty in knowing

how to apply them.

5) Archiving and retention policies

Policies appear to exist, at least for some information

types.

As above, people expressed difficulty knowing

how to apply them.

6) Supporting training and guidance

Training courses for tools available & run regularly. Widespread desire for additional training.

Phase 1 - Strengths & Weaknesses

Page 12: ECM study - strategy, management & technology

Slide: 12

Strengths Areas for Improvement

Systems and Tools

1) Repositories (e.g. databases and document stores)

Suite of enterprise-class applications are generally well

matched to functional requirements. EUMETSAT has a

good pool of skills to manage and extend these

systems.

Integration between Stellent and Hummingbird

could be improved (e.g. as being addressed by

current projects).

2) Business process (e.g. workflow and related logic)

ECM and ERP applications provide a suite of tools to

define and manage business processes. Again,

EUMETSAT has a good pool of skills to do this.

Not fully exploiting capabilities of existing tools.

Need to manage overlapping capabilities

across WCMS, DMS and SAP.

3) Search

Individual tools (Stellent, Hummingbird) have

reasonable search engines.

No enterprise-wide search facilities.

4) General adoption and development of ECM systems

DMS and WCMS are widely used.

DMS, in particular, is very widely used throughout the

organisation.

Phase 1 - Strengths & Weaknesses

Page 13: ECM study - strategy, management & technology

Slide: 13

Phase 1 - Technology risk

• Major concern for EUMETSAT and a key reason for initiating the study – they had major commitment to 2 vendors, both of whom had subsequently been acquired.

• The study’s conclusion: – Technology risk is manageable – evolve and integrate current

applications (unless/until vendors force change)

– Focus on information management policies and guidelines

Page 14: ECM study - strategy, management & technology

Slide: 14

Phase 2 - Mandate

• Three out of four options

– Information Organisation Standards

– Workflow Architecture

– Collaborative Document Management pilot

– Workflow and Sign-off pilot

Page 15: ECM study - strategy, management & technology

Slide: 15

Phase 2 - Organisation

Project Manager

Niklas Sinander

Project Support

Paul Breindel

Paul Macneil

Graham Oakes

Sara Redin

Janus Boye

Steering Committee

Florentin Albu

IO Ref Group

Repr from Div x

Repr from Div y

Repr from Div z

.

.

.

IO Team

Repr from Div a

Repr from Div b

Repr from Div c

.

.

Page 16: ECM study - strategy, management & technology

Slide: 16

Phase 2 - Priorities

• Recommended approach:

– Subteams to refine the IO documentation

(1) Overview and type catalogue

(2) Classification

(3) One document type

– Pilot one of the other 4

IO Documentation

Classification Schemes

Security & Access

Permissions Archiving Policies

External Access

Registration

Signatures and

VISA loops

Simplify and reduce

duplication

Single Work Queue

Page 17: ECM study - strategy, management & technology

Slide: 17

Planning

Tutorials

Homework

Homework

Homework

Workflow Pilot

Roadmap

Page 18: ECM study - strategy, management & technology

Slide: 18

IO Documentation Structure

• Information types – Summary of the information types covered by the IO architecture

– Template for definition of information types

– Detailed definitions (following the template) for each information type

• Information organisation – File plan

– Facets and keywords

• Processes – Document generic processes (applying to multiple information types)

– Workflow specification

• User documentation

– Glossary

– Reference guides

– How To’s

– Training

• Governance

– Roles and Responsibilities

– Processes for maintaining IO policies

and standards

– Processes for ensuring IO policies and

standards are followed

Page 19: ECM study - strategy, management & technology

Slide: 19

Page 20: ECM study - strategy, management & technology

Slide: 20

Governance Options

• Who defines policies and standards? – Ad hoc – individual units define their own standards

– Council – members of individual units come together to decide

– Central – central unit defines standards

• Who approves policies and standards? – Devolved – whoever defines them is also empowered to approve them

– Executive – executive body oversees and approves

• Who enforces policies and standards? – Self – people/units are assumed to follow them (really guidelines)

– Audit – audit function identifies breaches, for executive to deal with

– Police – central unit audits and enforces

• Who implements policies and standards? – Self – people/units implement

– Central – central support function implements stds (e,g, archivists)

Page 21: ECM study - strategy, management & technology

Slide: 21

Typical Structures

Definition

Imp

lem

en

tati

on

Central Devolved

Devolved

Central IM Unit

IM CoE

with Audit

IM Centre of

Excellence IM Council Anarchy

Central

Processing Unit

Page 22: ECM study - strategy, management & technology

Slide: 22

Page 23: ECM study - strategy, management & technology

Slide: 23

Lessons: Three layers to delivering info

Layer Strengths Weaknesses

Strategic Mgt

Organisational

commitment and focus

Recognise need to commit

resources

Fragmented and highly

bureaucratic structure and culture

Visibility of commitment?

Information Mgt

Appropriate policies,

processes & resources

Strong commitment of

resources (people) to information

mgt, e.g. doc controllers

Lack key skills and policies

(e.g. metadata)

Policies and processes are

fragmented and weakly

disseminated

Technology

Appropriate systems and

tools

Strong suite of systems

Fit for purpose

No major impl. issues

Widely adopted

Could make better use of

systems in some areas

(collaboration, workflow)

Page 24: ECM study - strategy, management & technology

Slide: 24

Lessons

• The issues were primarily about policy and direction

• But the initial symptoms were in the technology

• It’s hard to work from the bottom up – Difficulty getting people’s time

– Team not confident of their authority

– Conflicting messages to team

– Conflicting messages to rest of organisation

– But this is often the way we need to work: gain evidence & build support

• Defining policy requires time and thought

• Managing upwards is essential

Page 25: ECM study - strategy, management & technology

Slide: 25

Thank You

Niklas Sinander

[email protected]

Graham Oakes

[email protected]