1 Implementing Project Controls Preparing for the establishment of the Integrated (Cost and Schedule) Baseline in the Earned Value Management Process Matthew T. Gonzales, Jet Propulsion Laboratory Manager, Program and Project Business Leadership 818-354-3629 [email protected] [email protected]

Gonzales.matthew

  • Upload
    nasapmc

  • View
    19

  • Download
    0

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Gonzales.matthew

1

Implementing Project ControlsPreparing for the establishment of the Integrated (Cost and Schedule) Baseline in the Earned Value Management Process

Matthew T. Gonzales, Jet Propulsion LaboratoryManager, Program and Project Business Leadership

[email protected]

[email protected]

Page 2: Gonzales.matthew

2

‘Failing to prepare, is preparing to fail’

John Wooden

[email protected]

Page 3: Gonzales.matthew

3

Introduction

• The establishment of the Integrated (Cost and Schedule) Performance Measurement Baseline is the result of a systematic approach that steps the project through each phase of the planning process.

• Each phase results in a set of tangible products

• Each subsequent phase builds on the previous phase such that at the end of the planning cycle, all required documents are completed and integrated

• The approach is documented in Project Planning Guidelines, a project specific document that describes programmatic, cost and schedule assumptions, constraints and planning guidelines. Guidelines are developed as early as possible in Phase B and issued to the project team.

[email protected]

Page 4: Gonzales.matthew

4

What is

• Project Management: The discipline of planning, organizing, and managing resources to bring about the successful completion of specific project goals and objectives.

• How can we get on track• Total impacts to reserves

• Project Controls (Cost and Schedule): Consists of those processes performed to observe project execution so that potential problems can be identified in a timely manner and corrective action can be taken.

Project Controls asks: • Where we are• Where we should be

[email protected]

Page 5: Gonzales.matthew

5

Cost (Budget) versus Funds

Budgeting is NOT Funding• Budgeting is the time-phased planning of the total resources required to satisfy the project’s contractual requirements

[email protected]

Page 6: Gonzales.matthew

6

‘If you can't describe what you are doing as a process, you don't know what you're doing.’

W. Edward Deming

[email protected]

Page 7: Gonzales.matthew

7

The End to End Planning Process

The business lead develops the overall process and obtains concurrence from project manager.

The documented process will be your communication vehicle to the entire project team.

• Keep it simple. The process is the road map from Authorization to Proceed to establishment of a performance measurement baseline.

• Keep it serial. The recipe is simple when each the phase is executed in the correct order. Modifying the sequence will result in “redo’s” or a non integrated baseline

• Keep it real.Although each project is unique, the process to develop a baseline is not. Adapt the core serial process to your specific application

[email protected]

Page 8: Gonzales.matthew

8

The Planning Process

Major planning phase/emphasis Product

1. Scope of the project Statement of WorkIntegrated Management Plan

2. Development Approach Integrated Product Team (IPT)Organization Breakdown Structure

3. Organize the work Work Breakdown Structure (WBS)WBS Dictionary

4. Assign the Work Responsibility Assignment Matrix

5. Schedule the Work Integrated Critical Path NetworksIntegrated Master ScheduleKey Interfaces(Receivables/Deliverables)

[email protected]

Page 9: Gonzales.matthew

9

The Planning Process

Major planning phase/emphasis Product

6. Identify Resources Work Packages/Planning PackagesLabor, Material, ODC, Subcontract,

7. Estimate the Cost the Work Current forward pricing rates,Time-phased (monthly) cost profile

8. Negotiate and approve plan Control Account Plan concurred by Project Control Account Manager(PCAM), Project Manager and LineManager (or IPT lead)

9. Develop Earning Methodology BCWP ‘algorithmic earning’ consistent with BCWS profile

[email protected]

Page 10: Gonzales.matthew

10

Sample 1 Project Planning Process

Figure 1. Project that employed Integrated Product Teams and Integration Master Plans and Integrated Master Schedules

[email protected]

Page 11: Gonzales.matthew

11

Sample 2 Project Planning Process

Figure 2. Project that employed tradition ‘matrix’ approach

[email protected]

Page 12: Gonzales.matthew

12

‘In preparing for battle I have always found that plans are useless, but planning is indispensable.’

Dwight D. Eisenhower

[email protected]

Page 13: Gonzales.matthew

13

Schedule the Process

• Develop an end-to-end schedule for the planning cycle

• Schedule should show interdependencies between phases and phase products

• Determine appropriate period of performance for the phases based on customer requirements

• First submittal of performance reports• IBR date

• Schedule is a communication vehicle• Ensure responsibilities are delineated• Clearly identify due dates• Include data review and approval cycle in planning process

[email protected]

Page 14: Gonzales.matthew

14

‘Waterfall’ Planning Schedule

Task Name Responsible Time Line

Set-up

Bus team (people, process, tools) in place Bus Lead

Develop Phase CD Planning Guidelines Bus Lead

Approval of Phase CD Planning Guideline Project Mgr

Issue Phase CD Planning Guidelines Bus Lead

Conduct Planning Kick-off Meeting Bus Lead

Planning Infrastructure

Identify Project Team and CAMS Project Mgr

Map team to Initial Project WBS Bus Lead

Develop Responsibility Assignment Matrix Bus Lead

Develop/Refine Statement of Work PCAM

Develop WBS to Control Account Level PCAM

Develop WBS Dictionary to Control Account Level PCAM

Schedule Development

Obtain Master Schedule Sched Analyst

Develop CA End-to-End Critical Path Network Sched Analyst/PCAM

Reconcile with Project Master Schedule Sched Analyst

Identify External Hand-offs (REC/DEL) Sched Analyst/PCAM

Negotiate External Hand-offs Sched Analyst/PCAM

Integrated all Control Account Schedule Sched Analyst

Develop and Analyze End-to-End Project Critical Path Sched Analyst

Issue Final Project Schedules to Control Account Level Sched Analyst

[email protected]

Page 15: Gonzales.matthew

15

‘Waterfall’ Planning Schedule

Task Name Responsible Time Line

Resource Development

Develop Work Packages Sched Analyst/PCAM

Identify Resources required to execute Work Packages Sched Analyst/PCAM

Develop Time-Phase Resource Plans Sched Analyst/PCAM

Negotiate Resource Availability with Line Organizations Sched Analyst/PCAM

Cost Development

Develop Basis of Estimates for Resources PCAM

Apply current forward pricing rates and factors Cost Analyst

Review WP and CA time-phase cost profiles Cost Analyst/PCAM

Modulate to support project constraints Cost Analyst/PCAM

Review, Negotiate, Approve Plan

Review Control Account Plans PM/PCAM/Line Mgr

Approve Control Account Plans PM/PCAM/Line Mgr

Develop final Phase CD Work Agreements Cost Analyst

Finalize Plan

Develop BCWP plans PCAM

Verify BCWP plans consistent with BCWS plans Cost Analyst/PCAM

Set Cost and Schedule Baseline Cost Analyst

Reserves Analysis Cost Analyst

Establish Management Reserve Log Cost Analyst

Commence Change Control Bus Lead

[email protected]

Page 16: Gonzales.matthew

16

‘Always start out with a larger pot than what you think you need.’

Julia Child

[email protected]

Page 17: Gonzales.matthew

17

The Planning Infrastructure

[email protected]

Page 18: Gonzales.matthew

18

• People

• Process

• Tools

[email protected]

Page 19: Gonzales.matthew

19

The People

The project team needs to be in place prior to developing the Performance Measurement Baseline (PMB)

The Players Roles and Responsibility

Project Manager - Approve project plan- Proactive leadership during planning- Review and approve PMB

Project Business Manager - Develop planning process(aka Deputy PM for Resources) - Brief and obtain PM approval

- Responsible for all planning products for Integrated Baseline

Project Control Analyst - Develop and maintain projects integrated cost database- Work with Control Account Managers in developing integrated baseline data- Produce integrated baseline cost reports- Produce cost performance reports

[email protected]

Page 20: Gonzales.matthew

20

The People

The project team needs to be in place prior to developing the Performance Measurement Baseline (PMB)

The Players Roles and Responsibility

Project Schedule Analyst - Develop and maintain the project’s integrated schedule database- Develop and report project critical path- Work with Project Control Account

Managers in the development of an integrated project schedule. Including REC/DELs

Acquisitions/Subcontracts - Ensures contracts contain DRDs for submittal of integrated baseline- Negotiate deliverables to support project baseline requirements

[email protected]

Page 21: Gonzales.matthew

21

The People

The project team needs to be in place prior to developing the Performance Measurement Baseline (PMB)

The Players Roles and Responsibility

Project Control Account Manager - Responsible for the technical, cost and(PCAM) schedule plans for control account

- Develop and submit integrated schedule and cost plans (with project control and project schedule analyst support- Ensure plan is realistic and achievable- Identify cost and schedule risks

IPT or Line/Resource Management - Review plan resource requirements - Work with CAM to develop an achievable resource plan- Demonstrated approval of plan

[email protected]

Page 22: Gonzales.matthew

22

The Processes

The basic processes that are utilized during the life cycle of the project

0.0 Project Formulation Phase A 1.0 Organization Phase B 2.0 Scheduling Phase B 3.0 Work/Budget Authorization Phase B 4.0 Accounting Phase BCD 5.0 Indirect Management Phase BCD 6-1.0 Managerial Analysis Phase CD 6-2.0 Comprehensive Estimate-at-Completion Phase CD 7-1.0 Change Management (External) Phase BCD 7-2.0 Change Management (Internal) Phase CD 8.0 Material Management Phase BCD 9.0 Contract Management Phase BCD

[email protected]

Page 23: Gonzales.matthew

23

The Process Timeline

0.0 Project Formulation

1.0 Organization2.0 Scheduling (develop)3.0 Work/Budget Authorization

KDP-BPhase A Phase B

6-1.0 Managerial Analysis6-2.0 Comprehensive EAC 7-2.0 Change Management

(Internal)

4.0 Accounting (accounts set up Ph B, ACWP in Ph CD)5.0 Indirect Management (planning and EACs)7-1.0 Change Management (External)8.0 Material Management9.0 Contract Management

Phase CDKDP-C

Phase EKDP-E

2.0 Scheduling (status)

[email protected]

Page 24: Gonzales.matthew

24

The Tools

The basic planning and management tools needs to be in place prior to developing the Performance Measurement Baseline (PMB)

The Tool Function

Scheduling Control Module - Repository for projects integrated schedule- Reports project critical path- Stores and reports REC/DELs- Support JCL requirements

Cost Control Module - Repository for projects integrated cost - Baseline, ACWP, ETC, EAC- Calculates BCWP- Produce integrated baseline cost reports- Produce cost performance reports

Accounting System - Official book of accounts- Captures all actual costs by project

[email protected]

Page 25: Gonzales.matthew

25

The Tools

Additional planning and management tools needed to be in place prior to developing the Performance Measurement Baseline (PMB)

The Tool Function

Quantifiable Back-up Data - Derive EV % complete(QBD) - Used when schedule is not used to derive %

- Under baseline control

Front End Planning Aides - Budgetary planning tools that act as a feeder to cost control system module

Risk Management Tool - Repository for project risks- Used in developing Management Reserve position for the project

[email protected]

Page 26: Gonzales.matthew

26

The Tools (data sets)

Standard ‘global files’ should be in place prior to developing the Performance Measurement Baseline (PMB)

The Tool Function

Resource Breakdown Structure - Resource structure from line organization or IPTs(RBS) - Standard resource classifications

- Standard direct rates

Indirect Rate Structure - Standard/approved forward pricing rates/factors- Appropriate burdening scenarios (overhead/g&a)

Organization Breakdown Structure - Line Management Structure or IPTs(OBS) - Skill centers and service centers

Accounting Calendar - Common monthly calendar for Account System and Cost Control Module

[email protected]

Page 27: Gonzales.matthew

27

‘I skate to where the puck is going to be, not where it is.’

Wayne Gretzky

[email protected]

Page 28: Gonzales.matthew

28

Where is the puck going?

What to expect

[email protected]

Page 29: Gonzales.matthew

29

NPR 7120.5d Business Requirements

[email protected]

Page 30: Gonzales.matthew

30

Business Products for Phase A

Phase A

Preliminary Project Plan • Cost and schedule controls

Phase A Work Agreements

Preliminary Integrated Baseline• NASA Standard WBS (to WBS Level 3)• WBS Dictionary• Integrated Master Schedule• Life cycle cost estimate

• Preliminary life-cycle cost estimates includes reserves• Workforce estimate

Phase B Work Agreements

[email protected]

Page 31: Gonzales.matthew

31

NPR 7120.5d Business Requirements

[email protected]

Page 32: Gonzales.matthew

32

Business Products for Phase BPhase B

Final and approved Project Plan• Cost and schedule controls

Integrated Baseline Reviews for all contractors with life cycle cost greater than $20M

• Includes Prime contractors second tier subcontractors

Phase C Work Agreements

Final Integrated Baseline• NASA Standard WBS to Control Account/Work Package• WBS Dictionary to Control Accounts• Integrated Master Schedule

• Includes Tier 1 Master Schedule• End-to-end integrated Critical Path Network

• Life cycle cost estimate• Preliminary life-cycle cost estimates includes reserves

• Workforce estimate

[email protected]

Page 33: Gonzales.matthew

33

Implementation 15 Month Timeline

KDP-CPhase B Phase C

Transitioning from Phase B to Phase CThe first year of Phase C

Qtr 1 Qtr 2 Qtr 3 Qtr 4Qtr -1

• Project PDR

• Integrated Baseline Reviews of contractors

• Adjustments to final integrated baseline

• Prepare Phase CD Work Agreements

• Establish budget logs

• Data and process normalization period

• Begin monthly cadence Incorporate ACWP Incorporate BCWP

• Process and review for anomalies

• Generate CPR Format 1

• Run through three monthly cycles

• Make corrections as required

• Commence customer reporting

• Analyze performance trends (CPI SPI)

• Commence ETC maintenance

• Review variances

• Exercise cost and schedule change control process

• Variance Analysis Reporting

• Analyze performance trends (CPI SPI)

• Estimate to Complete (ETC) maintenance

• Budget to Complete (BTC) Maintenance

• Reserve utilization and attrition analysis

• VAR Correction Actions Tracking

• Analyze performance trends (CPI SPI)

• Comprehensive annual EAC

• Variance at Complete analysis

• Reserve utilization and attrition analysis

[email protected]

Page 34: Gonzales.matthew

34

0

20000

40000

60000

80000

100000

120000

140000

160000

180000

JUN

FY

06

JUL

FY

06

AU

G F

Y06

SE

P F

Y06

OC

T F

Y07

NO

V F

Y07

DE

C F

Y07

JAN

FY

07

FE

B F

Y07

MA

R F

Y07

AP

R F

Y07

MA

Y F

Y07

JUN

FY

07

JUL

FY

07

AU

G F

Y07

SE

P F

Y07

OC

T F

Y08

NO

V F

Y08

DE

C F

Y08

JAN

FY

08

FE

B F

Y08

MA

R F

Y08

AP

R F

Y08

MA

Y F

Y08

JUN

FY

08

JUL

FY

08

AU

G F

Y08

SE

P F

Y08

OC

T F

Y09

NO

V F

Y09

DE

C F

Y09

Budgeted Cost of Work Sheduled

Budgeted Cost of Work Performed

Actual Cost of Work Performed

0

20000

40000

60000

JUNFY06

JULFY06

AUGFY06

SEPFY06

OCTFY07

NOVFY07

Total ProjectEarned Value Performance Trends

Page 35: Gonzales.matthew

35

0.60

0.87

0.91

0.55

0.60

0.65

0.70

0.75

0.80

0.85

0.90

0.95

1.00

1.05

Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07

Cost PerformanceIndex (CPI)Performance Trend

CPI Goal at ProjectReplan

CPI Goal at 100% ofReserve Consumption

Total ProjectEarned Value Performance Trends

SPI TRACKING - STARTING JU '06lY

0.82

0.940.96

0.50

0.60

0.70

0.80

0.90

1.00

1.10

Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07

SchedulePerformance Index(SPI) PerformanceTrend

SPI Goal at ProjectReplan

Cost Performance Index (CPI)

Schedule Performance Index (SPI)

$224M

$253M

$233M IEAC

Page 36: Gonzales.matthew

36

‘Efforts and courage are not enough without purpose and direction’

John F. Kennedy

[email protected]