Upload
nasapmc
View
13.500
Download
0
Tags:
Embed Size (px)
Citation preview
©Humphreys & Associates, Inc. 1979-2009
3111 N. Tustin Avenue, Suite 250Orange, CA 92865
(714) 685-1730 (Phone)(714) 685-1734 (Fax)
Email: [email protected]://www.humphreys-assoc.com
No portion of this material covered by the copyrights hereon may be duplicated, reproduced, distributed, or copied in any form, or by any means - graphic, electronic, or mechanical, including photocopying, recording, taping, printing, or information and retrieval systems without written permission of Humphreys & Associates, Inc.
The following material is copyrighted by Humphreys & Associates, Inc. 1979 – 2008.Portions of the following material are also copyrighted by Arthur Andersen & Co. 1980 - 1981.
All rights reserved.
Humphreys & Associates, Inc.
©Humphreys & Associates, Inc. 1979-2009
Presented byGary Humphreys
ofHUMPHREYS & ASSOCIATES, INC.
Daytona Beach, FLFebruary 24-25, 2009
Establishing A Performance Measurement Baseline
(PMB)
©Humphreys & Associates, Inc. 1979-2009
The Earned Value Process
• Identify short tasks
• Schedule each task
• Assign a budget to each task
• Measure progress of the tasks
0046
©Humphreys & Associates, Inc. 1979-2009
Work Definition
WBS DICTIONARY
Work Breakdown Structure
0091
WBS Index
©Humphreys & Associates, Inc. 1979-2009
Electronics system
Prime mission equipment Training
Program management
Hardware Software System integration
Equipment Facilities System engineering
Project .management
Statement of work
Paragraph 2.0
Paragraph 3.0
Paragraph 4.0
Paragraph 2.1
Paragraph 2.2
Paragraph 3.2
Paragraph 4.1
Paragraph 4.2
Paragraph 2.1.1
Paragraph 2.1.2
Paragraph 3.1.1
Paragraph 3.1.2
Paragraph 3.2.1
Paragraph 3.2.2
Paragraph 4.1.1
Paragraph 4.1.2
Paragraph 4.2.1
Paragraph 4.2.2
Paragraph 3.1
5452
Statement Of Work (SOW)/
WBS Matrix
©Humphreys & Associates, Inc. 1979-2009 0093
Work Breakdown Structure Dictionary
Documents the scope of each element
Is a valuable communication tool
Identifies closely related items that are not included
Serves as a framework for understandingchanges in scope
©Humphreys & Associates, Inc. 1979-2009 0106
Responsibility Assignment Matrix and Control Account Structure
Account
Control Account
StatorAssembly
RotorAssembly
CaseAssembly
FanAssembly
Full ScaleFan Rig
MinorFan Rig
Fan Compressor Turbine
Engine Training
ContractContract Work Breakdown Structure
Man
ufac
turi
ng
Des
ign
Com
pany
Tes
t
Dual SpoolCompressor Rig
Eng
inee
ring
Work Packages
Planning Packages
Mechanical Design
Analytical Design
Drafting and Checking
Control Account
Control Account
Control Account
Control Account
Control Account
©Humphreys & Associates, Inc. 1979-2009
Organization Structure Considerations
WorkloadExpertiseAvailability of contractorsScope of workEconomic environment
0101
©Humphreys & Associates, Inc. 1979-2009
Control AccountA tool established by or for the owner to monitor the cost and schedule performance of a managerially significant element of the work.
0104
©Humphreys & Associates, Inc. 1979-2009 1336
Assure development of an achievable initial project planDocument assumptions, original scope, and planProvide basis for meaningful analysis and trending
Why Have A Schedule Baseline?
©Humphreys & Associates, Inc. 1979-2009
Schedule Integration “Schedules Must Tier”
Total Program Level• Customer• Senior management• Program Office
Intermediate Level• Customer• Program Office• Functional management• Control Account Managers
Detail Program Level• Program Office• Functional management• Control account Managers
Item 1 2 3 4 5 6 7Control Account 14Control Account 15Control Account 16Control Account 17Control Account 18
Control Account 16 WP No. 1WP No. 2WP No. 3WP No. 4WP No. 5
0151
Contract/ProgramSchedule
Major eventor FunctionalOrganization
MilestoneSchedule
Control Account and
Work PackageSchedules
Start Stop
©Humphreys & Associates, Inc. 1979-2009 0622
Target Price
Performance Measurement
Baseline
Target Profit
Budget Base
Management Reserve
Control Account Budgets
Summary Level
Planning Packages
For Known Effort
Withheld For
Unknowns
UndistributedBudget
©Humphreys & Associates, Inc. 1979-2009
Planning And Budgeting:Establishing The Performance
Measurement Baseline
Identify management reserves
Allocate resources to scheduled tasks
Identify performance measurement methods
Time-phase the resources (budget plan)0621
©Humphreys & Associates, Inc. 1979-2009
Provide A Time-Phased Budget
0146
$
$
$ $ $
For each WBS element
©Humphreys & Associates, Inc. 1979-2009
By Providing A Time-PhasedBudget for Each Control Account
0147
Task
1
2
3
Total
Schedule Resources
$
$
$
$
$
$
$
$
Control Account
©Humphreys & Associates, Inc. 1979-2009
Elements Of The Base And Baseline
0157
Distributed Budget(Control Account)
Distributed Budget(Control Account)
DiscreteWork Packages
DiscreteWork Packages
ApportionedEffort
ApportionedEffort
Level ofEffort
Level ofEffort
PlanningPackagesPlanningPackages
©Humphreys & Associates, Inc. 1979-2009
Three Classifications Of Work Measurement
1 . Discrete effort2 . Apportioned effort3 . Level Of Effort (LOE)
0165
©Humphreys & Associates, Inc. 1979-2009
It represents units of work at levels where work is performed
It is clearly distinguished from all other Work Packages
It is assignable to a single organizational element and Control Account
It has scheduled start and completion dates and, as applicable, interim milestones all of which are representative of physical accomplishment
Work Packages
0168
©Humphreys & Associates, Inc. 1979-2009
Work Packages
0169
It has a budget or assigned value expressed in terms of dollars, hours or other measurable units
It’s duration is limited to a relatively short span of time or it is subdivided by discrete milestones to facilitate the objective measurement of work performed
It is integrated with detailed engineering, manufacturing, or other schedules
©Humphreys & Associates, Inc. 1979-2009
Discrete WorkMeasurement Techniques
Incremental milestones50/50 method0/100 methodEquivalent unitsUnits completePercent complete
0174
©Humphreys & Associates, Inc. 1979-2009
Incremental Milestone---Planning
1 42 3
Milestone
1234
Totals
Budget
3001,2001,200
6003,300
0175
©Humphreys & Associates, Inc. 1979-2009
Incremental Milestone---Status
43
Milestone
1234
Totals
Budget
3001,2001,200
6003,300
0176
Earned Value
3001,200
00
1,500
©Humphreys & Associates, Inc. 1979-2009
Month January February March April Total
1,500 2,000 2,200 1,000 6,700
$150,000 $200,000 $220,000 $100,000 $670,000
Budget Feet
Budget @ $100 per foot
Units Complete---Planning
0184
©Humphreys & Associates, Inc. 1979-2009
Units Complete---Status
Month January February March April Total
BudgetFeet
1,500 2,000 2,200 1,000 6,700
Budget@ $100per foot
$150,000 $200,000 $220,000 $100,000 $670,000
QuantityInstalled 1,000 2,000 2,000 1,700 6,700
$100,000 $200,000 $200,000 $170,000 $670,000
0185
Earned @ $100 per foot
©Humphreys & Associates, Inc. 1979-2009
Percent CompleteMonth January February March April
Budget 150 185 250 200
Date
BAC785
3 25
Status of work depends upon individual evaluationof work accomplished
0186
©Humphreys & Associates, Inc. 1979-2009
Typical Work Activities For Planning Classification
Design drawingsTest specificationsMaterial parts listComponent testFabrication operationPrinted circuit card design
0170
DISCRETE EFFORT
©Humphreys & Associates, Inc. 1979-2009
Example Of Apportioned EffortInspection estimated as 10% of related
production Control Account
ProductionControlAccount
200500100
800
InspectionControlAccount
205010
80
ProductionControlAccount
150450150
750
InspectionControlAccount
154515
75
JuneJulyAug
Total
Budget Earned
0193
©Humphreys & Associates, Inc. 1979-2009 1309
The Major Resource Questions
Is the project achievable within the time and resource constraints?
Is the project being planned to use resources efficiently?
©Humphreys & Associates, Inc. 1979-2009TIME
BUDGET
CONTRACTTARGET COST
(CTC)
CONTRACTTARGET
PRICE (CTP)REQUIRED FUNDINGPROFILE *
0119
Funds vs. Budget
DOLLARS
©Humphreys & Associates, Inc. 1979-2009 0154
Funds vs. ACWP + ETC
TIME
ACTUALS
REVISED FUNDINGFORECAST
CURRENTAUTHORIZED
FUNDING
TIME NOW EAC
ETC
EARNEDVALUE
BUDGET
DOLLARS
©Humphreys & Associates, Inc. 1979-2009 8126
Funding Profiles vs. Performance Trend Lines
TIME
EARNEDVALUE
TIME NOW
ETC
BUDGET
ACTUALS
FUNDINGPROFILE
EAC
DOLLARS
©Humphreys & Associates, Inc. 1979-2009
Rolling Wave Planning
0200
A M J J A S O N D J F M A M J J A S O N D J F M A M J
Control Account Time Phased Plan
9 Months All Future Periods
WP No. 1
WP No. 2
WP No. 3Planning Package(s)
Remaining Budget, Schedule& WorkScopeTime Now
©Humphreys & Associates, Inc. 1979-2009
Rolling Wave Planning
0201
A M J J A S O N D J F M A M J J A S O N D J F M A M J
Control Account Time Phased Plan
All Future Periods
WP No. 1
WP No. 2
WP No. 3
Planning Package(s)Remaining Budget, Schedule
& WorkScope
3Months
Time Now
WP No. 4
3Months
6Months
©Humphreys & Associates, Inc. 1979-2009
Detailed Planning Becomes Budget When Formally Authorized
0159
Control AccountAuthorization
Contract
©Humphreys & Associates, Inc. 1979-2009
Work Authorization And Release
WBS orientationTraceability/hierarchyResponsibility assignmentScope of workScheduleBudgetCharge number
0160
©Humphreys & Associates, Inc. 1979-2009 0161
CONTROL ACCOUNT WORK AUTHORIZATION Revision Number: OriginalIssue Date: 2/1/year 1
Control account number: 1.4.2 Title: System test plan/procedures Responsible organization: 4000
Program name: Mor Ded Contract. number 1234-5678
Schedule (baseline): Start CompletionOriginal: 02/09/Year 1 09/04/Year 1
Revised: __________ __________
Elements Of CostAmount authorized
Prior authorization Current authorization Total BudgetDirect labor hours..............……Contract help hours...........…...
Total hours...............Direct labor $..........................Contract help $........................ Material $.................................Subcontract $...........................Other direct costs $................
Total $...................... - 0 -
- 0 -- 0 -
- 0 -
$ $$
864864
864864
10627
10627
10627
10627
Work statement (including applicable reference documents) (Indicate schedule dates for each item, unless noted above)
Update test plans & procedures to reflect changes in test equipment, simulation equipment. System design and testing methods.(In accordance with Contract Data Requirements List items ADOB & ADOC).
SAMPLESAMPLE(continue on reverse side)
Release authority Performance commitmentName Date Name. Date
Page 1 of ___
©Humphreys & Associates, Inc. 1979-2009
Subsystem Integration
0120
Organization Level
Scheduling Budgeting
Technical Description/
Work Authorization
Performance Measurement
Program DivisionContract
(milestone) Contract ContractContract
Performance Report (CPR)
Reporting Program Manager
Program Master
Schedule
WAD & Budget Data
Sales Order
Control Account
Responsible/Performing
Manager
Intermediate Schedule &
CAP
Work Authorization
Document (WAD)
Functional Performance Report (FPR)
Work Package
Performing Employee
Control Account
Plan (CAP)
CAM Performance
Report
WBS Level
Contract Performance Report (CPR)
Control Account
Plan (CAP)
WAD & Budget Data
Control Account
Plan (CAP)
©Humphreys & Associates, Inc. 1979-2009
Summarize Costs
$ $ $
$$$ $
$ $ORGANIZATION
WBS
0217
©Humphreys & Associates, Inc. 1979-2009
Plan Ahead For Orderly Data Collection
Identify needed dataDetermine level of detailDetermine source of each data itemDefine data identification codesDesign formsDesign and write proceduresTrain personnel
0218
©Humphreys & Associates, Inc. 1979-2009
Change control andthe Performance
Measurement Baseline
0329
©Humphreys & Associates, Inc. 1979-2009
Effect Of Changes
0330
$ Changes
New Baseline
Original Baseline
New BudgetAt
Completion
Original BudgetAt
Completion
Time
©Humphreys & Associates, Inc. 1979-2009
120
120
-
-
-
-
45
30
30
105
120
120
45
30
30
225
10
10
5
-
-
15
110
110
40
30
30
210
10
10
-
-
-
10120
Date DescriptionContractTargetCost (CTC)
AuthorizedUnpriced
Work(AUW)
CBB ManagementReserve PMB Undistributed
BudgetDistributed
Budget
1/14
1/31
2/5
2/15
2/23
2/28
ABC Contract
January Summary
Contract Change No. 001P.O. Letter-AdditionalManagement Reports
February Summary
P.O. Letter-Motor Redesign
0338
Budget Baseline Log
-
100
100
40
30
30
200
©Humphreys & Associates, Inc. 1979-2009
AvoidChanges to budgets of completed work
Transfer of work without budget or budget without work
Reopening completed tasks
0335
©Humphreys & Associates, Inc. 1979-2009
1. Organization & Start up
2. Assessment
3. Design
4. Documentation
5. Training
6. Implementation
7. Review & Validation
Q 1 Q 2 Q 3 Q 4
0351
Implementation Schedule
©Humphreys & Associates, Inc. 1979-2009
$ $
TIME
CONTRACT TARGET COST
ReportingCutoffDate
Thank you for your participation0567
The End of InstructionEAC
BAC
BCWS
BCWP
ACWP