30
MICROSOFT PROJECT USER GROUP PRESENTATION DELIVERED BY GERALD LEONARD EVM at the National Archives using MS Project Server

NARA EVM Case Study Presentation For MPA

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: NARA EVM Case Study Presentation For MPA

M I C R O S O F T P R O J E C T U S E R G R O U P P R E S E N T A T I O N

D E L I V E R E D B Y

G E R A L D L E O N A R D

EVM at the National Archives using MS Project Server

Page 2: NARA EVM Case Study Presentation For MPA

National Archives and Records Administration

is a self-governing Federal agency that preserves our nation's history by overseeing the management of all Federal records.

houses the Declaration of Independence, the Constitution of the United States and the Bill of Rights.

has 34 facilities hold about 2.9 million cubic feet of original textual materials.

Page 3: NARA EVM Case Study Presentation For MPA

National Archives and Records Administration

houses: 93,000+ motion picture films 5 million+ maps, charts, and architectural drawings 207,000+ sound and video recordings 18 million + aerial photographs nearly 35 million still pictures and posters electronic records comprising about 4 billion logical

data records

receives sixteen millions requests for records a year

64,000 requests a day 8,000 requests an hour

Page 4: NARA EVM Case Study Presentation For MPA

Mission

The National Archives and Records Administration (NARA) began searching for a Project Management Tool (PROMT) to address the issues with effectively managing its portfolio of IT projects according to the guidelines set forth by the Office of Management and Budget (OMB) and the United States General Accounting Office (GAO).

After reviewing various vendor products the selected team members recommended Microsoft Project Server / Professional 2003 as the solution of choice.

The team also selected wInsight from CS-Solutions as the product of choice to calculate earned value which will fulfill the requirements of an ANSI/EIA 784-A compliant EVMS application. .

Page 5: NARA EVM Case Study Presentation For MPA

PROMT to Support the ERA Program

The Electronic Records Archives (ERA) will be a

comprehensive, systematic, and dynamic means for preserving virtually any kind of electronic record, free from dependence on any specific hardware or software

ERA will authentically preserve and provide access to any kind of electronic record, free from dependence on any specific hardware or software, enabling NARA to carry out its mission into the future.

Page 6: NARA EVM Case Study Presentation For MPA

NARA’s Business Requirements for PROMT

The Project Management tool assists the project team to:

schedule tasks and link task dependencies

assign resources

collect project costs

collaborate on project deliverables (including documents)

manage project risks and issues

report on project accomplishments

communicate with stakeholders

calculate earned value

Page 7: NARA EVM Case Study Presentation For MPA

Value to Management

The Project Management tool assists NARA

track project progress from the desktop

drill into project specifics (tasks, resources, dates, issues, risks and documents)

participate in threaded discussions on deliverables, risks and issues

view documents in the project library

see standard reports on every tracked project

reduce time spent reporting and summarizing project status

view project dependencies (both inter and intra)

determine project priorities

evaluate impact when resources are realigned

Page 8: NARA EVM Case Study Presentation For MPA

Approach

Discovery Determine Current People, Processes and Technologies that

support their existing PMO infrastructure

Planning Develop Process requirements

Develop Technical and configuration requirements

Design Developed solution design based on meeting NARA’s business

requirements

Developed a system that was flexible, reliable and scalable.

Prototype Quickly developed a prototype to demo to Senior Management

so they could see their customized version of the PROMT solution

Page 9: NARA EVM Case Study Presentation For MPA

Approach (cont.)

Pilot Conducted 3 pilots

Each iteration of the pilot included additional functionality and complexity for the team to test.

Transition to Production Worked with the IT organization to documents a robust

and rigors T2P plan and handoff.

Full Implementation

Rollout to the remaining agency New instance of PROMT called PROMT2 that is currently

being rolled out to the rest of the agency.

Training Mentoring and Operational Support

Page 10: NARA EVM Case Study Presentation For MPA

Initial Configuration using Managed Periods

Page 11: NARA EVM Case Study Presentation For MPA

Customized PWA Configurations

Page 12: NARA EVM Case Study Presentation For MPA

Server Configuration

Page 13: NARA EVM Case Study Presentation For MPA

Group Configuration

Page 14: NARA EVM Case Study Presentation For MPA

Timesheet Approvers Group Permissions

Page 15: NARA EVM Case Study Presentation For MPA

PROMT Actual Work Input

Planned Work/Activities

Deliverables (in bold)

Sends to Deliverable Manager for approval

Record actual hours worked

Page 16: NARA EVM Case Study Presentation For MPA

Timesheet Approval in PROMT

Submission of Staff Time

Each entry can be Approved/disapprov

ed In this column.

Save updates the master schedule

Page 17: NARA EVM Case Study Presentation For MPA

PMO Earned Value Reports

Output from PROMT to Project Connect is exported to Excel spreadsheets and provided to PMO management for review and analysis

Currently done at WBS Level 3 (data is automatically rolled up to the summary levels by Project Connect) for the work packages

Page 18: NARA EVM Case Study Presentation For MPA

Input to EV Reports

Steps Description of Activity Responsibility

Collect status of each lowest level task (Physical %

Complete) for the specified time period from

deliverable owner

Project Control

Enter status data into MS Project File (PMO IMS) Project Control

Load statused end of period MS Project file onto the

desktop computer that has Project Connect,

2/Insight Administrator and CS Glue installed

Project Control

Open the MS Project File.

Note the Project Control Toolbar and follow step by

step directions below

Project Control

Page 19: NARA EVM Case Study Presentation For MPA

Project Connect Setup

Set the Period End Dates to match the defined end of period status date that will

be used with each MS Project file:

a.Select the X12 button on the Project Connect Toolbar.

b.Select the Periods button.

Page 20: NARA EVM Case Study Presentation For MPA

Project Connect Setup (Cont).

•Select a Month in the End Dates and the Day that ends the period in the calendar.

•When finished select Save which will generate a Template File that can be used for any project. For

consistent calculations the MS Project Status Date and the Project Connect Period End Date must

match.

Page 21: NARA EVM Case Study Presentation For MPA

Master Schedule (MS Project) w/ Project Connect Application

Clicking on EVM button will initiate BCWP calculation.

Project Connect Adds Calc BCWP

Data column automatically X12 Transfer File button

Earned value method has been determined For each task. 5 = Physical % Complete EVM not needed for

summary elements

Physical % Complete entered For those tasks With EVM = 5.

Page 22: NARA EVM Case Study Presentation For MPA

Sample Project Information Statistics

WBS NAME BCWP BCWS ACWP BAC CPI SPI EAC VAC TCPI

1 Electronic Records Archives (ERA) Program 8,448,757.70 9,329,437.34 7,688,031.13 11,784,003.98 1.10 0.91 $11,039,327.09 $744,676.88 0.81

1.01 Program Management (ERA PMO) 4,009,651.86 4,376,980.30 3,023,481.76 5,399,230.25 1.33 0.92 $4,167,285.90 $1,231,944.35 0.58

1.01.01 Plans (ERA PMO) 52,729.40 114,106.20 60,773.67 168,182.15 0.87 0.46 $348,727.82 ($180,545.67) 1.07

1.01.02 Program Control (ERA PMO) 758,025.22 979,869.02 750,522.44 1,450,148.85 1.01 0.77 $1,636,347.74 ($186,198.89) 0.99

1.01.03 Management and Administration (ERA

PMO) 574,625.63 574,625.63 599,856.39 666,667.57 0.96 1.00 $695,939.72 ($29,272.15) 1.38

1.01.04 Program Management Training (ERA PMO) 221,030.65 221,030.66 151,546.50 236,755.86 1.46 1.00 $162,328.26 $74,427.60 0.18

1.01.05 Procurement Management (ERA PMO) 44,323.47 44,507.87 31,202.12 57,986.05 1.42 1.00 $40,860.09 $17,125.96 0.51

1.01.06 Risk Management (ERA PMO) 199,337.77 199,337.76 97,668.07 234,247.10 2.04 1.00 $114,772.34 $119,474.76 0.26

1.01.07 Quality Management (ERA PMO) 27,139.89 77,949.64 13,273.71 81,200.05 2.04 0.35 $89,213.19 ($8,013.14) 0.80

1.01.08 Steering Committee Meetings 3,339.00 3,339.00 980.68 3,339.00 3.40 1.00 $980.68 $2,358.32 0.00

1.01.09 ERA PMO Configuration Management 53,803.86 80,521.09 33,237.74 95,191.86 1.62 0.67 $71,501.59 $23,690.27 0.67

1.01.10 Communications (ERA PMO) 562,325.18 568,162.20 316,143.27 670,637.41 1.78 0.99 $377,669.27 $292,968.14 0.31

1.01.11 Records Management (ERA PMO) 25,313.96 25,313.96 9,661.10 27,741.21 2.62 1.00 $10,587.46 $17,153.75 0.13

1.01.12 Oversight Support for FY 2005 (ERA PMO) 27,576.58 27,576.58 12,379.39 30,203.14 2.23 1.00 $13,558.47 $16,644.67 0.15

1.01.13 Program Management Tools (ERA PMO) 516,422.12 516,981.56 159,758.91 581,470.02 3.23 1.00 $179,903.74 $401,566.27 0.15

Page 23: NARA EVM Case Study Presentation For MPA

Sample EVMS Performance Indices

0

0.2

0.4

0.6

0.8

1

1.2

1.4

SPI CPI TCPI

SPI 0.51576 0.52326 0.5659 0.56673 0.66468 0.69503 0.84323 0.82301 0.9056 0.88114 0.90628 0.94626 0.94021 0.94084 0.94158 0.94535 0.9461 0.97689

CPI 0.7829 0.7633 0.85293 0.93039 1.11618 1.17588 1.1713 1.12081 1.09895 1.10372 1.04246 0.98029 0.99599 1.00804 1.01693 1.03082 1.04923 1.0646

TCPI 1.01618 1.03889 1.03395 1.02081 0.95325 0.90705 0.86203 0.89027 0.82229 0.76483 0.84445 1.16573 1.00438 0.99035 0.97745 0.95441 0.92064 0.88206

Sep 03 Oct 03 Nov 03 Dec 03 Jan 04 Feb 04 Mar 04 Apr 04 May-04 Jun-04 Jul-04 Aug-04 Sep-04 Oct-04 Nov-04 Dec-04 Jan-05 Feb-05

SPI = Schedule Performance Index

CPI = Cost Performance Index

TCPI = To Complete Performance Index

Page 24: NARA EVM Case Study Presentation For MPA

Scheduling

Project Control Staff integrates:

Remaining Work

% Complete

Network Logic, and

Other Factors that impact Earned Value data.

Staff develops realistic assessment of remaining work on unfinished activities/deliverables

Integrated Master Schedule Data ported to Project Connect for earned value calculations.

Page 25: NARA EVM Case Study Presentation For MPA

Requirements for Earned Value Management (EVM) Reporting

EVM data to be delivered to PMO monthly Vendor EVM data must be delivered in one of the following two

formats. ANSI X12 839 EDI format

wInsight compatible XML format Other reporting standards:

DI-MGMT 81468, Contract Funds Status Report (CFSR) approved October 19, 1995

DI-MGMT-81466, Cost Performance Report, approved October 19, 1995

Developer initiated baseline or EV reporting changes bound by contract stipulations

Developer must use physical, not duration-based, percent complete Developer Performance Measurement Baseline (PMB) to cover entire

technical scope of contracted work, include realistic schedules integrated with appropriate level and mix of resources

Page 26: NARA EVM Case Study Presentation For MPA

Requirements for Earned Value Management (EVM) Reporting

Written variance analyses will be provided for +/- $25,000 current cost and schedule variances, +/-$50,000 cumulative cost and schedule variances, and +/-$125,000 variances at completion.

All negative BCWS, BCWP or ACWP will be explained. PMO will use EIA 748-A, EIA Standard-Earned Value Management

Systems, January 2002, to validate data from Developer’s PMB.

Page 27: NARA EVM Case Study Presentation For MPA

Program Performance Reporting

Completed: Assessing PROMT, wInsight and Project Connect tools for data accuracy,

consistency and relevance Implementing procedures for resolving excessive variances

Government review of Contractors’ CDRLs Integrate NHE EVMS data with the contractors’ performance during

SA&D phase Current: (Systems Analysis and Design Phase) Performance Reporting

Data analyzed monthly, compiled quarterly Vendor Reporting Requirements defined in Contract Coordinate CDRLs’ feedback with CORs and QA

Out years (Increments) Performance Reporting wInsight is used by both developmental contractors Developing Increment 1 Integrated Schedule for ERA Program Office Working with DCMA and DCAA to support audits and baseline reviews Improving the WBS Reporting Structure

Page 28: NARA EVM Case Study Presentation For MPA

Integrated EVMS Analysis

Program Critical Events

SA&D Progress

EVMS Summary Analysis Integrate the Budget Financial System with EVMS

Integrate contractors’ EVMS XML data files with internal NHE EVMS Data

Review monthly and provide a consolidated report quarterly

Page 29: NARA EVM Case Study Presentation For MPA

Sample EVMS Data

EVMS Cumulative Data

through FY05

$0

$2,000,000

$4,000,000

$6,000,000

$8,000,000

$10,000,000

$12,000,000

$14,000,000

$16,000,000

$18,000,000

Sep 0

3

Nov 03

Jan

04

Mar

04

May

-04

Jul-0

4

Sep-0

4

Nov-04

Jan-

05

BCWS

BCWP

ACWP