TW@ESI1st January 2017
Hope all of you had a good time off and Happy New Year to all!
The following is a record of what was done during the last working week/s and a forecast of the first week in 2017.....
A General Note before we start-•Welcome back to all those who where overseas in Poland and wish the Fenechs a good continuing vacation down under in Aussie Land- well done to Nicky who finished the Sydney Hobart race aboard Breakthrough •Welcome to the group Donaghan- Jerico is still pending to accept the invitation to join the group•On Wednesday 3rd Jan 2017, a part time student , Patrick Brejza will be joining the TRIDIUM/HSDK software development section.
Projects and deadlines• 16_007_LeMeridien_BMS_upgrade- We have started working on
phase 1 panels – phase 1 which has to be completed by Feb 2017- next steps are– We need to order the JACES and Field devices – Prepare the Software for the phase one panels– Once materials are here, design sketches are available and software is
available we will do change over.Early next year we should do the change over for the roof panels with the
programmed logic and some basic graphics only• 14_069- Q019 AS410 – We are proceeding with works here in
conjunction with Gruppo Sett in Italy• 16_025_DeLaRue_OFX- Design is ready, materials have been
ordered and training by overseas specialists will be on 16/1/17• 14_069- Q021_TF4- Panel is on site and installed- still issues to be
resolved with regards to the FOC terminations
Projects and deadlines• 16_041_RSM_Zebbug_Security-. We need to complete all works by End
of January 2017- All materials have been ordered and we need to start thinking of Panel building, programming , Testing and commissioning
• 16_051_Baxter_AHU_Controls- Many thanks to all who pushed and pulled to complete what we could complete. All IO devices have been installed and tested, we could not test the closed loop due to problems on the air balancing activities by others- In our first week in we must complete what we can to put this project to sleep and complete
• 16_058_Methode- Another fast tack project Jace Based AHU control system here – we will kick it off in this week – Target is to finish it by end of February 2017- we have started ordering the long lead items here – the plan is to start Panel design ASAP and start panel build on 3 or 4th week of Jan 2017.
• 15_023_FM panels- We have a new 2 panels for FM environmental (D5M-110) ... The delivery date is not know – design is completed
Projects and deadlines• 16_015_RSM- this lighting control project is to be completed in the first weeks
when we get back in we need to really keep a good eye on what is happening on site by the main contractor- we must ensure the wiring and terminations are done properly- as soon as the main contractor collects the field devices we must ensure he tests the DALI loops and then we can commission and program
• 15_011- Sliema apartments – We have done some terminations and panel build is completed too.
• 16_023_GGY- we have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform
• 14_083_Intercontinental – We have commissioned the system with snags - we will return to site when snags are done by others- we also have to deliver the pool panel
• 15_038_new_HA_Ovt and 15_026_Apap Residence are two home automation projects scheduled for Q1 2017 – we have built all panels for these projects and we are awaiting others to complete their installation
• 12_027- Parliament –We are finalizing the documentation and eventually need to integrate ProWatch.
Projects and deadlines• 13_031_CCA- still issues with values on ILPS and we also have to execute
some new works at CCA (new cameras, pagers)• 12_043_Life Sciences – we have nearly completed all items here- some
small snags are pending to close off• 13_075_Bosch_ProWatch_Genetec_Interface - The Bosch HSDK interface
is well advanced and we have documented and we should shortly be expecting to go overseas to commission
• 13_070- SCM Lagoona Plant room We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue
• 12_025- The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
• 14_081_Siggiewi School- there are some snags pending here due to louvres
DesignLast week• Meridien – Briefed DSH & Shridar on Panel Sketches, on site (MCPM2 &
MCPM1)• Methode SMT – released MF Parts for quote (still chasing quote)• OTM – completed SAS-000980• FM Env – Draughted new Panel Design for D5M-110 submitted to client• Sliema Graham Apartments – As Built update of DDC PanelsNext Week:• Methode SMT – release long-lead items from MF (after receipt of
quote)• Methode SMT – Points List, P&IDs, Panel Design• De la Rue – from Client drawing, convert to our Panel Drawing standard• RSM Security – Draught Intruder Panels & DAC Panels after receipt of
sketches from CCI, SAI
InstallationThis past week: • Continue with works at Mosta workshop• Continue with works at Baxter• Water meter readings at Lifesciences• Fix camera and other works at CCA villaNext week:• Works at Sliema apartments• Works at Life sciences• Continue with works at Mosta workshop
Panel Build
Well done to the efforts done to catch up – we are still in slight delay
• We need to fit in Le Meridien panel change overs on site• RSM security panels (DAC/Intruder)• 16_058_Methode- 3rd or 4th week of Jan 2017
Mater DeiWeek 48
Yearly Field devices checks, IR images & coordinated tests Nov--D07-CC1, D07-CC2, B01-CC1, BP1-CC1, B02-CC1, BP2-CC1, B03-CC1
Quarterly panel checks Nov -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1,
D02-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3, D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2, D12-CC1
Weekly update of antivirus on all BMS stations
ReactiveHandling of reactive work orders
Others• Participating in weekly fire drills• Tackling software work orders • New Angiography Project• Training of new team member• Integration of Samoc into Master
Sales and Business DevelopmentWe are working on quotes for a Sterling
Chemicals Line 2 PLC system, S5 PLC upgrade for Kordin Grain terminals , lighting control systems in Qatar.
Birthday wishes go to
Romina Buttigieg- 5th JanJohn Galea- 7th Jan
Team ESI
• I would like you take the opportunity and spend 15-30 minutes reflecting on 2016 and listing what went good for you on your job and what went bad... List your achievements and disappointments and set your major objectives for 2017!! Anyone wishing to share this exercise .. Please do so!!