17
PPP The Aviation Sector In Nigeria Revives

Ppp final project (artifact)

Embed Size (px)

Citation preview

  1. 1. PPP The Aviation Sector In Nigeria Revives
  2. 2. Domestic terminal of Muritala Muhammed Airport, Lagos Nigeria TYPE OF PPP CONCESSION: BUILD, OPERATE AND TRANSFER (BOT)
  3. 3. The project was to design, construct and operate a new domestic terminal and ancillary facilities as a result of the destruction of the domestic terminal by fire in 2000. The new terminal, Murtala Muhammed Airport Two (MMA2), has a land area of 20,000m2 and comprises a terminal building, a multi-storey car park, and an apron.
  4. 4. The PPP procurement in Nigeria is regulated by the following legislations The Infrastructure Concession Regulatory Commission (ICRC) Act 2005 The Public Procurement Act 2007 . Legal Framework
  5. 5. Value for money analysis The VFM method adopted was simply comparing the estimated cost of implementing the PPP under Public Procurement with that of the private sector
  6. 6. In 2003, the Federal Ministry of Aviation advertised for bids for the project, and after an evaluation process, Royal Sanderton Ventures Limited emerged as the preferred bidder, while Bi Courtney Limited was the reserved bidder. Royal Sanderton was awarded the contract. Six months into the implementation phase, there was no significant construction activities on ground, the government decided to revoke the contract signed with Sanderton. After necessary negotiations, the contract was awarded to Bi Courtney, the reserved bidder. The contract duration was initially for 12 years, and subsequently extended to 36 years through an addendum signed between the Federal Airports Authority of Nigeria (FAAN) and Bi Courtney. Bid Preparation
  7. 7. Allocation of Risks The plan completely transferred all development and operating risks to Bi Courtney Ltd . The federal Government was to provide security at the airport terminal Bi Courtney was given the guarantee of first right of consideration, if FAAN and the federal government elect to build a new domestic terminal in Lagos state
  8. 8. PROCUREMENT AGENCY: Federal Airport Authority of Nigeria BIDDERS: Royal Sandeson Ventures Ltd. Bi- Courtney Ltd. SELECTED BIDDER: Bi- Courtney Limited DURATION OF CONTRACT: 36 years ESTIMATED COST OF PROJECT: US 200M
  9. 9. The Project was Part-financed by a Consortium of six banks: Oceanic Bank International Plc, Zenith Bank Plc, GT Bank Plc, First Bank Plc, First City Monument Bank Plc and Access Bank Plc to the tune of $150m,in addition to equity of the owner/proprietor.
  10. 10. The concessionaire regains his investment through charges for the services provided in the terminal: Payment by airlines for terminal services Payment for car park services Payment for advertisement in the terminal Payment by shops and restaurants Payment Mechanism
  11. 11. MMA2 was the first major BOT infrastructure project to be completed by a Nigerian company without ext ernal finance The project had been successfully completed The project boasts of the first and the largest Multi storey car pack in Lagos The terminal also boasts of a fully equipped clinic that is open to all terminal users, and handles over 50 flights daily
  12. 12. There was initial paucity of fund had ,the company had to start construction without a long-term financing agreement in place. In March 2007 secured a US$150m part-financing from a consortium of six banks for the completion of MMA2 Some airlines were reluctant to move from the international terminal. FAAN reopened the old terminal General Aviation Terminal (GAT) for some airlines because the apron at MMA2 was not able to accommodate the growth in domestic services; There were disputes by the parties and claims of breach of contractual right
  13. 13. The importance of having an agreed financial model and long term financing in place at the outset of the project; The initial bidding process also points to the importance of managing politicians expectations and setting realistic goals regarding timelines; Revoking a contract and re-awarding it to a different company not only delayed the project but also triggered doubts in private participants minds about whether such changes were spurred by political rather than economic issues;
  14. 14. The difficulty of enforcing contractual agreements (e.g. while the contract has a clause assuring that all scheduled domestic flights in and out of FAANs airports in Lagos shall operate from the new terminal during the concession period, FAAN continues to operate the old domestic terminal, Any conflict of interest faced by the Government puts significant pressures on the ability of the private sponsor to recover its investments and thus placed the financial viability of the project at risk.
  15. 15. ICRC PPP Toolkit Invest On line . Com Airport technology .com World Bank PPIAF Reference Guide Bi Courtney Aviation Services Ltd http://www.mma2.com.ng/about Framework Note PPP Nigeria www.tremolet.com Legal Framework of PPP Nigeria www.dejure.up.ac.za/. References