Resettlement Monitoring Report Quarterly Report January–March 2014
VIE: Mong Duong 1 Thermal Power Plant
Prepared by Viet Nam Electricity (EVN) GENCO 3 Thermal Power Projects Management Board 1.
EVN GENCO 3 Thermal Power Projects Management Board 1 (TPMB1)
MONG DUONG (2 x 500MW) THERMAL POWER PLANT PROJECT
INTERNAL RESETLEMENT MONITORING QUARTERLY REPORT
Period 1st January to 31st March 2014
Contract No: TPMB1-EVN/ADB-2610L2MFF-Consulting-002
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 2 of 28
Table of Contents
ABBREVIATIONS ................................................................................................................. 3
1. GENERAL INFORMATION OF THE PROJECT ........................................................ 4
1.1. Mong duong Thermal Power Plant Project ........................................................... 4
1.2. The Fresh Water Component .............................................................................. 4
1.3. The Scope of Land Acquisition and Resettlement ................................................ 4
2. DETAILED RESETTLEMENT IMPLEMENTATION PROGRESS .............................. 5
2.1. Information Disclosure and Community Participation ........................................... 5
2.2. Detailed Measurement Survey ............................................................................. 8
2.3. Compensation payment, assistance and resettlement ......................................... 8
2.4. Process of resettlement and site clearance ......................................................... 9
2.5. Restoration of APs’ livelihoods and rehabilitation of APs’ lives .......................... 10
2.6. Assess degree of APs’ satisfaction of compensation and resettlement .............. 10
2.7. Conformity of resettlement implementation progress with civil works progress and next plan ....................................................................................................................... 10
2.8. Issues concerning gender and ethnic minority ................................................... 11
3. PENDING ISSUES ................................................................................................... 11
3.1. Outstanding problems ........................................................................................ 11
3.2. Solutions for pending issues and responsibility of relevant agencies ................. 11
4. CONCLUSIONS AND RECOMMENDATIONS ........................................................ 11
4.1. Conclusions ....................................................................................................... 11
4.2. Recommendations ............................................................................................. 12
APPENDIX .......................................................................................................................... 14
Appendix1 List of the affected Households .................................................................. 14
Appendix 2 Situation of Compensation Payment ........................................................... 22
TABLE
Table 1: Affected Land Area Categorized by Communes til 31/3/2014 ......................................... 5
Table 2 Number of HHs and Persons whose land affected in each Commune til 31/3/2014 ........ 5
Table 3 Summary of consultations undertaken .............................................................................. 7
Table 4 Status of affected household until 31 March, 2014............................................................ 9
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 3 of 28
ABBREVIATIONS
DCARB District compensation, Assistance, and Resettlement Board
DMS Detailed Measurement Survey
EVN Electricity of Viet Nam
FWC Freshwater Component
LFDC Land Fund Development Center
PAP Project Affected Person
PMU Project Management Unit
PPC Provincial People's Committee
RAP Resettlement Action Plan
TPP Thermal Power Plant
TPMB1 Thermal Power Plant Project Management Unit No. 1
TRC Town Resettlement Committee
PC People’s Committee
RC Resettlement Committee
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 4 of 28
1. GENERAL INFORMATION OF THE PROJECT
1.1. Mong duong Thermal Power Plant Project
Mong Duong Thermal Power Plant complex with a total combined capacity of 2’200 MW, is located in the Mong Duong Ward (Cam Pha town, Quang Ninh province). It is situated along Highway 18, 300 km northeast of Hanoi and 18 km from the Center of Cam Pha town. The Project site is located at the mouth of the Mong Duong River and includes one ward (Mong Duong) and one commune (Cam Hai). The objective of building this Plant is to increase the capacity of the thermal electric power source and contribute to the stable supply of electricity throughout the year and especially in the dry season when the hydro plants do not generate much of their maximum capacity
1.2. The Fresh Water Component
The Mong Duong Thermal Generation Plant complex needs a large amount of fresh water from Quarter Four, 2013. It is calculated that, the combined Plant needs 15.000 m3 of fresh water per day. A fresh water supply system therefore must be constructed to serve the project. The system consists of the reservoir, the pumping station, the 10 KV power supply to serve for the pumping station, the water pipe line, and the access road.
Of which, only the Reservoir area and the Water Pineline area relates to land acquisition and resettlement.
1.3. The Scope of Land Acquisition and Resettlement
Based on the detailed design, a total area of 1,849,411.39m2 with 192 households will be permanently affected. Among the permanently affected land, 1,366,399.76m2 is affected by the reservoir in Mong Duong Ward and 483,011.63m2 by the pipe-line and other works (access road, powerhouse, etc) in Cong Hoa Commune and Cam Hai Commune (Cam Pha City). 34% of affected area is productive forest land which is currently used for planting Acacia of 71 households (385 persons) in three communes/wards. FWC will also affect 8000.0m2 of residential land of 37 households (182 persons) in Village 10, Mong Duong Ward. Cong Hoa and Cam Hai communes will not have residential land affected by the FWCt. Area, number of households and persons of affected land are shown detailed in Table 1 and Table 2. Beside, 17,756.5m2 temporary land is also acquired for the Project during construction phase and the compensation was paid for the temporarily affected households.
In the pipeline, DMS also conducted in August to analyze the road widening. According to the original design, pipeline will crossed over on road number 18, thus, the change in in alignment should be done due to the wider road. Because of this change, 3 more households will be affected by this project.
The categories of permanently affected lands are as below:
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 5 of 28
Table 1: Affected Land Area Categorized by Communes til 31/3/2014
No Categories of affected land
Reservoir Pipe line
Total (m2) Mong Duong Ward (m2)
Cong Hoa Commune
(m2)
Cam Hai Commune
(m2) Sub-total
(m2)
1 Residential land 8,000.0 - - - 8,000.0
2 Agricultural land 225,309.5 - - - 225,309.5
3 Forest land 305,863.50 195,251.53 129,451.60 324,703.13 630,566.63
4 Aquaculture area 13,872.65 269.00 12,687.80 12,956.80 26,829.45
5 Public land 813,354.16 98,304.20 47,047.50 145,351.70 958,705.86
Total 1,366,399.76 293,824.73 189,186.90 483,011.63 1,849,411.39
(Source: TPMB1, Updated in March 31st, 2014)
Table 2 Number of HHs and Persons whose land affected in each Commune til 31/3/2014
No Categories of affected land
Mong Duong Ward Cong Hoa Commune Cam Hai Commune Total
No. of AHs (HH)
No. of APs
(person)
No. of AHs (HH)
No. of APs
(person)
No. of AHs (HH)
No. of APs
(person)
No. of AHs (HH)
No. of APs
(person)
1 Residential land 37 182 0 0 0 0 37 182
2 Agricultural land 127 508 42 168 23 95 192 768
3 Forest land (for acacia planting)
19 88 35 148 17 69 71 305
4 Aquaculture land 7 41 1 4 1 4 9 49
(Source: TPMB1, Updated in March 31st, 2014)
2. DETAILED RESETTLEMENT IMPLEMENTATION PROGRESS
Detailed on the progress of Resettlement Plan Implementation is in the Appendix 2.1
2.1. Information Disclosure and Community Participation
Information dissemination was conducted by Thermal Power Project Management Unit No.1 (TPMB1) and DCARB of Cam Pha city. Orientation meetings have been conducted since 2009 with relevant parties and affected households. Project information has been delivered to 100% affected households (such as introduction of detailed technical design, scope of impacts on land and asset upon on lands, entitlements for compensation, assistance and resettlement, implementation schedule of land acquisition, compensation, assistance and resettlement and grievance redress mechanism). The documents have also been placed in public places and in the house of village leaders and head of mass-organization
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 6 of 28
11 consultations were conducted by the local authorities from January 1st to March 31st, 2014 and gathered representative of following groups:
Project information disclosure activity was continuously and regularly implemented through the implementation progress. This kind of activity is to enhance local awareness, reduce grievance or complaints from AHs as well as speed up the implementation of the project’s components.
The information disclosure was mainly carried out through: residential meetings, delivery of notices to each household, posting up notice at local government’s offices, delivery of project leaflets and posters, direct meetings with AHs by TPMB1’s, and local authorities.
During the project implementation, the information disclosure activity was implemented mainly in the affected areas to local people and the ones who have complaints, grievance. The disclosed information included; (i) information about the compensation policy and the right of AHs; (ii) information about environmental impacts; (iii) issues arising from the construction execution affecting local people.
Besides, local people were also informed of project compensation implementation arrangements, responsibilities of relevant stakeholders and grievance redressal mechanism and results of grievance redressal as well as newly arising issues during the project implementation.
The results of the consultation show that dissemination of information to local authorities, agencies and organizations, especially local communities where the project has achieved certain results. The public consultation has mobilized the full participation of stakeholders, information about projects, policies and projects that benefit from the project really helped raise awareness for community and contributing to the progress of clearance and construction projects.
The consultation and information dissemination is done in all communes and wards to implement the Project. TPMB1 was in collaboration with the local government has organized a series of meetings, direct dialogue with those remaining claims, the displaced households. The Advocacy, Dissemination and Implementation have been carried out the support policies of Cam Pha City Comittee to speed up the site clearance activities of projects thoroughly. The Project has made sure to get the information to the PAPs fully and as fast as possible.
The Consultation and Information Dissemination has been implemented in accordance with the provisions of ADB, from the municipal level, communes, villages and received basic consensus of the community on the issues : land and resource products affected are compensated. The project has the support appropriate policies for each object affected under the provisions of the Government of Vietnam, The Matrix Rights under the provisions of the projects using ODA Fund. And especially those supporting policy priorities of provinces and cities dedicated to the project.
Both men and women from affected households are encouraged to attend, as well as other interested community members. The list of public meetings for the Fresh Water Component is provided in the following Table.
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 7 of 28
Table 3 Summary of consultations undertaken Ward/commune Time Contents Participants Comments from participants
Mông Dương ward
14/1/2014
Meeting at City PC to solve complaints of people related to site clearance
City PC, LFDC, Ward PC, Resident Area, TPMB1, affected households
The affected household was satisfy with compensation policy
21/2/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money
Cam Pha LFDC, head of Resident Area, TPMB1, affected households
The affected household was satisfy with compensation policy
28/2/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money ;
Cam Pha LFDC, head of Resident Area, TPMB1, affected households
The affected household agreed with compensation policy
14/3/2014 To mobile people to receive compensation money and hand over their land and assets for the Investor
Cam Pha LFDC, head of Resident Area, TPMB1, affected households
The affected household agreed with compensation policy
28/3/2014
To pay compensation, and respond the complaints of people and to mobile people to receive compensation money
Cam Pha LFDC, head of Resident Area, TPMB1, affected households
The affected household agreed with compensation policy
Cộng Hoà commune
14/1/2014
To pay compensation, and respond the complaints of people and to mobile people to receive compensation money
Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households
The affected household agreed with compensation policy
21/2/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money
Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households
The affected household agreed with compensation policy
28/3/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money
Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households
The affected household agreed with compensation policy
Cẩm Hải commune
14/1/2014
To pay compensation, and respond the complaints of people and to mobile people to receive compensation money
Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households
The affected household agreed with compensation policy
21/2/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money
Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households
The affected household agreed with compensation policy
28/3/2014 To pay compensation, and respond the complaints of people and to mobile people to receive compensation money
Cam Pha LFDC, CPC, head of Resident Area, TPMB1, affected households
The affected household agreed with compensation policy
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 8 of 28
Participants of public meetings include all affected households, local authorities, head of mass- organizations and village leaders. The total turns of participants are around 905 people, of whom 407 people are female (accounting for 45%).
Consultations continue to be deployed in the project area through community meetings. 100% of affected households were consulted 3 times or more on the project’ policy of land acquisition, compensation, support, and resettlement.
Affected people have been consulted on the needs of participating in the income restoration program, however, many households are still not aware of the importance of the program, therefore, they are not ready to participate in the program. Propaganda, information disseminating to these households will be continuously performed during the implementation of the income restoration program.
The consultation process has also paid its attention to the needs of women and vulnerable groups such as the poor, single women headed household, elderly or some other policy objects.
Due to the Consultants providing information adequately and transparently on compensation entitlements the complaints of affected people are not considerable in numbers.
2.2. Detailed Measurement Survey
Detailed Measurement Survey was completed before November 10th, 2012. However some added surveys are still continuing due to changes in technical alternatives or some assets outside the project sites but is no longer valid for use left.
As of March 31st, 2014, the discrepancies and omissions in the loss inventory process or other damages arising due to changes in technical alternatives or some assets outside the project sites but is no longer valid for use caused by land acquisition was timely inventory replenishment to ensure the entitlements of the affected people, ensuring compliance RP framework of the project.
Need assessment survey was conducted in July 2013 to design and implement the measures for income and livelihood restoration. Participants chose the vocational training, Acacia’s Cultivating and the breeding’s model. The Income Restoration Program has prepared since December and TPMB1 has sent unofficial updated IRP to ADB for comments before official submission, and ADB sent comments on 27th of January 2014, TPMB1 will responses to ADB comment and send official to ADB in early of April 2014.
In the pipeline, DMS also conducted in August to analyze the road widening. According to the original design, pipeline will crossed over on road number 18, thus, the change in alignment should be done due to the wider road. Because of this change, 3 more households will be affected by this project. It is necessary to assess the impact of these households in next quarterly report
2.3. Compensation payment, assistance and resettlement
As of March 31st, 2013, the total budget of approved compensation, assistance and resettlement is VND 97,405,207,100and VND 96,789,219,900 has been paid for the affected people (including budget for the DCARB), reached 98.8%.
The Progress of Site Clearance of the project was concerned properly, however, due to the unexpected issues happened during the implementation, the schedule of clearance process is carried out slowly in compare with The Resettlement Plan and Resettlement Plan proposed. Compensation payment has implemented for the Pipeline component. Total of unpaid budget is VND 615,987,200, this will be paid for the Reservoir and Pipeline Component before April 30th,
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 9 of 28
2014. This unpaid amount belongs to Resevoir Component. Pipeline Component was completed compensation payment.
In general, The Application Cost for the project was in compliance with the provisions of ADB about the Compensation and Assistance will be based on the principle of replacement cost (market value in normal conditions) at the time of The Compensation Implementation. The TPMB1 has many solutions to make sure that all the displaced Households in the project without having any certificate of Land Use rights or any legal recognition of the acquired land are eligible to receive compensation and resettlement assistance, non-land assets to support the replacement cost of ABD and policies of Vietnam's Law.
Although the compensation paid almost finished, there are some household still complaint on misjudging of their assets. The compensation team of TPMB1 is calculated to add the inventory for those households for next few months
There are total 37 resettled households, concentrated in Reservoir Component and all of them agreed to resettle freely. 12/37 of households returned their fatherland in another province such as Hai Phong, Lang Son, Bac Giang. They are immigrant households those moved to this area during 15 -25 years ago. 25 other households still stay inside the commune but move near to 329 road, and they buy a new land with basic infrastructure for a household and all of them completed construction their resettled houses. These households have already connected to the electricity distribution system because the 35kv electric line completed and put into use in September, 2013 and they also have accessed to potable water supply because they buy their own pumpling machine to collect the water from streams
Table 4 Status of affected household until 31 March, 2014
No Affected Household
situation HHs Remarks House 1 Build a new house 25 2 House is under construction 0 3 HHs has not build new house 0
4 Sell the house and move to other place 12
5 hhs to Hai Phong, 5 hhs to Lang son, and 2 hhs move to other village in Quang ninh province (8 HHs are under construction and 4 HHs have not built yet)
Land 1 Buy a new agriculture land 15 2 Buy a new resident land 25
3 Not buy any kind of land 12 They have their own land or they are too old
Staying/Moving 1 Move to other place 12 2 Staying in Mong Duong ward 25
2.4. Process of resettlement and site clearance
As of March 31st, 2014, the land acquisition and resettlement has achieved good results in general for the Pipeline Component (Cong Hoà and Cam Hai communes). Site clearance rate for
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 10 of 28
Reservoir Component has completed 99.37% (191/192 affected households). And it is going to be completed in the end of April, 2014. Due to delay in payment leading to the site clearance has to be extended the time in comparison with the schedule
As of March 31st, 2014, the site clearance has completed 99.37% (191/192) affected households). And it is going to be completed in the end of April, 2014.
Of total 37 resettlement households, 25 HHs completed their built houses, 8 households are in the process of construction and 4 households returned their father land (in another province). All of 25 resettled built houses have Land Use Right Certificate.
2.5. Restoration of APs’ livelihoods and rehabilitation of APs’ lives
Besides compensation for affected land and property, the project has adopted many policies to support affected households to ensure the progress of relief work as well as the interests of the people and help them to restore stable life
All the affected households who get the payment received full assistances according to project policies such as living stabilization assistance, occupation transmission assistance, and business stabilization assistance.
After the need assessment survey in participating in income restoration programs, an income restoration plan was submitted to ADB in November and have not been approved yet. As soon it is approved by the ADB, income restoration activities will be conducted immediately.
2.6. Assess degree of APs’ satisfaction of compensation and resettlement
The local people in general are satisfied with the result of the lost inventory, compensation price assistance and resettlement policies of the Project.
The PAPs are fully benefiting from the support policies under RP. However, the level of support given is relatively low. Income restoration assistance for severely affected households has supported to will contribute stable income restoration of PAPs life
With the loss of agricultural land household: They are highly appreciated with the counting method, applying the replacement cost and compensation payments. As of Resettlement Monitoring the household who lost some Item during DMS was additional compensation.
As of 31st March, 2013, among 25 complaints letters from 25 affected household relates to misidentify the acquired land and compensation rate. And 24 of them had been solved and there are still 1 households have not been solved yet due to these households do not agree with compensation and support rate, all these households belong to Ward 10 Mong Duong.
2.7. Conformity of resettlement implementation progress with civil works progress and next plan
Compensation and relocation of resettled households have been delayed in comparison with the site clearance and construction progress as well as overall plan of the project. However, the Project tried ensuring the cleared sites for construction.
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 11 of 28
2.8. Issues concerning gender and ethnic minority
The Cam Pha Town Resettlement Committee (TRC) include women representatives from the Mong Duong Ward and Women Union of the Residential Area No.10 to represent the interests of women in the affected households. Capacity-building training were provided to the leaders of the Women's Union, by the social consultant of the TPMB1, to increase their participation in the TRC. The participation of women in leadership and decision making in resettlement planning were guaranteed through equal representation of men and women during the resettlement implementation.
The population of the commune mostly affected by the project, Ward No. 10, is inhabited predominantly by members of the two ethnic minorities living in this area, Dao and Tay, while in the area affected by the pipeline, the majority is Kinh. The community consultation, project information disclosure for all PAPs, including ethnic minorities have been conducted in the project during the project implementation by TPMB1, People Committee of Mong duong, and the Communes in the project regions. Seriously the Asian Development Bank has provided affected households in the vulnerable group including minorities with a certain amount to support their life and livelihood development in compliance with the updated RP and legal framework
3. PENDING ISSUES
3.1. Outstanding problems
1 households have not gotten the compensation because they do not agree with compensation and support rate, all these households belong to Ward 10 Mong Duong.
The income restoration programs have not been approved yet, therefore, it could not be conducted according to the time schedule.
Finding out information of 12 resettled households whom moved to other provinces is very difficult.
3.2. Solutions for pending issues and responsibility of relevant agencies
TPMB1 is cooperating with the Land Fund Development Center, City PPC, leaders of the villages and other stakeholders to mobilize 2remaining households to get compensation and to hand over the sites for the contractors and add compensation based on the project policies for all missing land and assets. In the case of households still not accept, the project will implement the compulsory execution according to the Vietnam Laws and ADB framework.
Contact with ADB to ask for approval progress the income restoration program and then conduct income restoration activities as soon as possible.
Keep trying to contact with local authorities in the provinces that 12 resettled households move to and find out about their residence and livelihood after resettlement.
4. CONCLUSIONS AND RECOMMENDATIONS
4.1. Conclusions
The Resettlement Policy has been implemented in a satisfactory way by TPMB1 that ensuring meeting the objectives of the project. The problems happened in the implementation has been solved in time by exchange and collaborate solution by stakeholders.
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 12 of 28
Implementing the activities on compensation, assistance and resettlement were delayed in comparison with the approved resettlement plan. Progress on compensation and resettlement implementation until March 31th, 2014 is 99.37%. The compensation payment completed 99.37% of total of anticipated compensation budget. The remaining budget is anticipated to be paid for the APs within April 2014.
The policy priorities of the City support has been consulted dissemination to affected households and communities, contributing relatively satisfactorily in resolving the complaints and questions which still remain.
The asset inventory of affected HHs and relocation cost calculation has been performed in an open and public way by TPMB1 and local Compensation and Support Board. Asset inventory participants include all affected households and representatives of the MRB, local authorities, representatives of the local Compensation and Support Board
Replacement cost was applied for all types of properties, land affected by the project. The Compensation Payment has to comply with the procedures. Compliance has paid compensation directly to affected household at the communal office and before the construction of at least 01 month.
Granting land use right certificates (both resident land and production land) for relocated households in Mong Duong is being submitted to CPC for approval, other land area have not been implemented
The dissemination of information about the project in general and the policy on Compensation, support and Resettlement has been coordinated between TPMB1 and stakeholders with efforts. Most of interviewees said that they had received information about the project as well as the compensation policy of the implementing agencies. Information dissemination, community consultation have witnessed the cooperation of DCARBs of Cam Pha city along with Mong Duong ward in the project region and have basically conducted as per the regulated process resulting in the certain efficiency.
Gender equity and ethnic minority activities have been effectively integrated into the project activities
The income restoration programs have not been approved by ADB yet and therefore, income restoration plan would be delay in comparison to the time schedule.
The resolve questions and complaints feedback of the affected household have concerned by TPMB1, local governments and related stakeholders. 23 per 25 households who raise their grievances have been satisfactorily resolved and 2households not yet because these households do not agree with compensation and support rate.
4.2. Recommendations
The PC of Quang Ninh province, and DCARBs of Cam Pha city should pay its special attention and put emphasis on households that have to move to another place and/or those are severely affected on their income source. The PC should approve, make decisions and create favorable conditions for remaining households to move to the new place as well as the activities to restore income of the affected households.
TPMB1 should closely cooperate with the PC of Quang Ninh province, Cam Pha city, and DCARBs of city to support and create favorable conditions of compensation funds, to help the locality to resolve shortcomings related to land acquisition and resettlement in an effective and timely manner to ensure the planned implementation of the project
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 13 of 28
Quickly complete the granting of land use right-certificates for resettled households and prevent the encroachment problem of agricultural and forestry land which has been handed over to hamlet community
Income restoration activities should be conducted as soon as possible. The Income Restoration Program should have the production model transformation which could use more female workers or have the priority policy for single women, or the affected households lead by women.
It is necessary to enhance the participation of women in community activities and their ideas sharing in meeting leaded by women union. Training course on gender equity should be held at all the communes for both men and women to increase the society on women’s equity.
The gender issue has not been properly concerned: In the next phase, the project should provide specific policy priorities to support the women in employment or health protection measures when women loss their agriculture land, so far loss of productive land. We propose the TPMB1 indicate the Data about women in Monthly Resettlement Monitoring Report.
The dissemination of information about the project operation need to continue to support information to the community and policies as well as their interests in the Project. TPMB1 and stakeholders should collaborate more in solving problems which could be arised in the Process of Resettlement and Income Restoration of affected household in particular and the other affected households in general.
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 14 of 28
APPENDIX
Appendix1 List of the affected Households
Cộng Hòa commune
No Name of household head Ethnic
Family member
Job situation of the hhs members Primary Income
Secondary Income
Male Female
Under 18
years old
Above 18
years old
Under 18
years old
Above 18
years old
Employment Unemployment
1 Bàng Phương Hùng Kinh 2 1 2 3 Worker Forestry planting
2 Bế Văn Mít Tày 1 1 1 1 2 Forestry planting Trader
3 Bế Văn Viện Tày 1 1 2 1 2 Farmer Forestry planting
4 Bùi Hữu Đài Kinh 2 1 1 2 Farmer Forestry planting
5 Bùi Hữu Luân Kinh 2 1 1 3 Farmer Forestry planting
6 Bùi Đức Chinh Kinh 1 1 Trader Forestry planting
7 Đào Xuân Tuy Kinh 1 1 3 1 Trader Forestry planting
8 Đỗ Thành Minh Kinh 1 1 Worker Trader
9 Đỗ Thị Bảy Kinh 1 3 1 Farmer Worker
10 Hà Thị Thuỷ Tày 3 1 1 Farmer Forestry planting
11 Hà Văn Chung Kinh 1 1 1 1 1 Farmer Forestry planting
12 Hà Văn Lường Tày 1 1 Forestry planting
13 Hà Văn Lưu Kinh 1 Forestry planting
14 Hà Văn Mùi Kinh 2 1 1 2 Trader Forestry planting
15 Hà Văn Năm Kinh 1 1 2 Farmer Forestry Planting
16 Hà Văn Tần Kinh 1 3 4 Farmer Forestry Planting
17 Hà Văn Thuỵ Kinh 1 3 2 3 Farmer Forestry Planting
18 Hoàng Minh Thắng Kinh 1 1 Soldier Trader
19 Hoàng Thị Minh Tày 1 1 1 1 2 Forestry planting
Forestry Planting
20 Hoàng Văn Toàn Tày 3 2 5 Farmer Forestry Planting
21 Lại Văn Tòng Kinh 3 1 4 Worker Forestry Planting
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 15 of 28
No Name of household head Ethnic
Family member
Job situation of the hhs members Primary Income
Secondary Income
Male Female
Under 18
years old
Above 18
years old
Under 18
years old
Above 18
years old
Employment Unemployment
22 Mã Văn Sáng Tày 1 2 1 1 3 Farmer Forestry Planting
23 Ngô Thị Vân Kinh 1 1 3 4 Trader Forestry Planting
24 Nguyễn Đức Nhuần Kinh 3 2 5 Trader Forestry Planting
25 Nguyễn Đức Thành Kinh 1 1 Worker Forestry Planting
26 Nguyễn Đức Tốt Kinh 1 1 Soldier Forestry Planting
27 Nguyễn Hữu Nhuyên Kinh 2 3 5 Farmer
Forestry Planting
28 Nguyễn Ngọc Hiến Kinh 1 1 Soldier Forestry Planting
29 Nguyễn Thị Thuỷ Kinh 1 2 2 2 Forestry planting
Forestry Planting
30 Nguyễn Thị Tình Kinh 1 1 1 1 2 Trader Forestry Planting
31 Nguyễn Văn Huế Kinh 1 1 Soldier Forestry Planting
32 Nguyễn Văn Phượng Kinh 2 2 4 Farmer Forestry Planting
33 Nguyễn Văn Thành Kinh 1 2 1 2 Farmer Forestry Planting
34 Nguyễn Văn Tới Kinh 1 1 Soldier Forestry Planting
35 Nông Văn Lan Tày 2 1 1 3 Forestry planting
Forestry Planting
36 Phạm Nam Hương Kinh 1 1 Soldier Forestry Planting
37 Phan Thị Nhật Kinh 1 1 1 1 2 Trader Forestry Planting
38 Tô Văn Nà Sán Dìu 1 1 1 2 3
Forestry planting
Forestry Planting
39 Bùi Quốc Duy Kinh 1 1 3 4 Trader Forestry Planting
40 Hà Mạnh Hùng Tày 1 2 1 1 3 Farmer Forestry Planting
41 Trần Thị Châu Kinh 1 1 Farmer Forestry Planting
42 Cong Hoa Commitee
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 16 of 28
Cam hai:
No Name of household head Ethnic
Family member Job situation of the hhs members Primary
Income Secondary
Income Male Female
Under 18
years old
Above 18
years old
Under 18
years old
Above 18 years
old Employment Unemployment
1 Bùi Văn Tay Kinh 3 1 2 Forestry Planting
2 Đào Xuân Quang Kinh 1 1 2 2 Forestry Planting
3 Hà Văn Dương Kinh 1 1 Trader
4 Hà Văn Tình Kinh 1 1 Worker Forestry planting
5 Hoàng Văn Ngọc Kinh 1 1 1 1 2 Farmer Forestry planting
6 Lê Đức Tính Kinh 1 Trader
7 Lưu Đức Oanh Kinh 1 1 1 1 2 Worker Forestry planting
8 Đỗ Văn Lỳ Kinh 2 1 1 3 Forestry Planting
9 Mai Thị Việt Kinh 1 1 2 1 3 Worker
10 Hoàng Văn Ngọc Kinh 1 1 1 1 2 Farmer Forestry planting
11 Nguyễn Văn Việt Kinh 1 1 Farmer
12 Nguyễn Văn Tần Kinh 3 2 5 Farmer Forestry
planting
13 Nông Thị Vấn Tày 1 Trader
14 Phạm Bá Quyết Kinh 1 1 2 Worker
15 Phạm Thị Gái Kinh 2 2 3 2 Aquaculture Forestry
planting
16 Trần Thị Thúy Nga Kinh 3 1 3 Worker Forestry
planting
17 Phạm Thị Thu Ánh Kinh 1 1 2 Worker Forestry
planting
18 Trương Thị Dịu Kinh 1 1 1 2 Worker
19 Trương Văn Trò Kinh 2 1 Aquaculture
20 Trần Thị Bùng Kinh 1 1 1 1 Aquaculture
Forestry planting
21 Trần Thị Châu Kinh 1 1 Trader
22 Từ Minh Ngọc
Sán Dìu 1 2 1 2 Farmer
Forestry planting
23 Hoàng Văn Nghiên Kinh 1 1 1 1 2 Aquaculture Forestry planting
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 17 of 28
No10.ward
No Name of household head Ethnic
Sexual Job situation of the hhs
members Primary income
Secondary income
Male Female
Under 18
years old
Above 18
years old
Under 18
years old
Above 18
years old
Employment Unemployment
1 Bàn Văn Năm Dao 1 1 1 2 Farmer
2 Bùi Quang Chiến Kinh 1 3 1 2 Farmer
3 Bùi Quang Chính Kinh 1 Farmer
4 Bùi Quang Cường Kinh 1 1 1 1 Farmer
5 Đàm Văn Ắm Tày 1 2 1 2 Farmer
6 Đặng A Sắt Dao 1 1 2 2 Farmer
7 Đặng A Ửng Dao 3 1 3 2 Worker
8 Đặng Phúc Tiến Dao 2 1 1 3 Farmer
9 Đặng Thị Loan Kinh 1 1 3 Worker
10 Đặng Văn Ba Dao 2 1 3 2 2 Worker
11 Đặng Văn Nguyên Dao 1 1 2 1 1 Worker
12 Đặng Văn Tư Dao 3 1 2 1 5 Farmer
13 Đặng Xuân Ba Dao 1 1 1 1 Farmer
14 Đặng Xuân Cường Dao 2 1 1 1 2 Farmer
15 Đặng Xuân Lương Dao 1 1 1 2 Farmer
16 Đặng Xuân Minh Dao 1 3 Farmer
17 Đào Đức Thọ Kinh 1 1 1 2 Farmer
18 Đào Văn Chuỳ Kinh 1 1 1 2 Worker
19 Đỗ Thị Hồng Kinh 2 1 1 Retirement
20 Đỗ Văn Biên Kinh 1 1 1 1 1 Farmer
21 Hà Văn Hầu Tày 1 1 1 3 1 Forestry planting
22 Hồ Quay Phương Dao 1 1 1 1 2 2 Farmer
23 Hồ Văn Đức Dao 2 1 2 1 2 Farmer
24 Hồ Văn Phúc Dao 1 1 1 1 Worker
25 Hồ Văn Thanh 1 2 2 1 7 Worker
26 Hoàng Thị Bé Tày 1 1 1 2 Farmer
27 Hoàng Thị Kim Dao 2 1 2 1 2 Farmer
28 Hoàng Thị Liên Tày 1 3 2 2 Forestry planting
29 Hoàng Văn Anh Kinh 1 1 1 Forestry planting
30 Hoàng Văn Khoa Tày, Dao 1 1 1 1 1 Farmer
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 18 of 28
No Name of household head Ethnic
Sexual Job situation of the hhs
members Primary income
Secondary income
Male Female
Under 18
years old
Above 18
years old
Under 18
years old
Above 18
years old
Employment Unemployment
31 Hoàng Xuân Đoàn Tày 1 1 1 1 Forestry planting
32 La Văn Bộ Tày 2 1 1 1 Forestry planting
33 La Văn Huấn Tày 1 2 Farmer
34 Lê Văn Nam Kinh 1 2 2 2 Farmer
35 Lê Văn Nhất Kinh 1 2 3 2 Worker
36 Loan Văn Phổ Tày 1 Forestry planting
37 Loan Văn Quang Tày 2 1 Forestry planting
38 Loan Văn Tô Tày 1 1 Worker
39 Loan Văn Tường Tày, Nùng 1 2 2 Worker
40 Loan Văn Việt Tày 1 2 Forestry planting
41 Lộc Văn Vương Tày, Kinh 2 1 1
Forestry planting
42 Lục Văn Hùng Tày 1 1 Forestry planting
43 Lương Văn Cò Tày 1 1 Forestry planting
44 Lương Văn Yên Tày, Dao 1 1
Forestry planting
45 Lý Minh Trọng Dao 1 1 1 Farmer
46 Lý Minh Tuấn Dao 1 1 Farmer
47 Lý Thị Hai Dao 2 2 Farmer
48 Lý Thị Tư Dao 1 Farmer
49 Lý Văn Hai Dao 2 1 2 1 Farmer
50 Lý Văn Năm Dao 2 1 2 1 2 Forestry planting
51 Lý Văn Phúc Dao 2 1 2 Forestry planting
52 Lý Văn Sáu Dao 2 1 2 1 Farmer Forestry planting
53 Lý Văn Tư Dao 2 2 1 1 2 Farmer Forestry planting
54 Lý Văn Việt Dao 2 2 1 1 Farmer Forestry planting
55 Lý Xuân Cảnh Dao 3 1 1 1 Farmer Forestry planting
56 Lý Xuân Minh Dao 2 1 3 1 1 Farmer Forestry planting
57 Lý Xuân Thắng (Lý Xuân Hồng) Dao 1 1 2 1 3
Forestry planting
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 19 of 28
No Name of household head Ethnic
Sexual Job situation of the hhs
members Primary income
Secondary income
Male Female
Under 18
years old
Above 18
years old
Under 18
years old
Above 18
years old
Employment Unemployment
58 Ngọc Văn Bẩy Tày 1 1 1 1 2 Forestry planting
59 Ngọc Văn Chiều Tày 4 1 1 Forestry planting
60 Ngọc Văn Miêu Tày 1 1 1 1 Farmer Forestry planting
61 Nguyễn Bảo Long Kinh, Dao 1 1 1 1 Farmer
Forestry planting
62 Nguyễn Đức Thức Kinh 1 1 2 1 Farmer Forestry planting
63 Nguyễn Như Đạo Kinh 2 1 1 2 Retirement Forestry planting
64 Nguyễn Quốc Đệ Kinh 1 1 2 1 Retirement Forestry planting
65 Nguyễn Sỹ Nam Kinh 1 Worker
66 Nguyễn Thanh Cảnh Tày 1
Forestry planting
67 Nguyễn Thị Hoa Kinh 2 2 Forestry planting
68 Nguyễn Thị Linh Kinh 1 1 2 Forestry planting
69 Nguyễn Văn Long Kinh 1 1 1 1 1 Worker
70 Nguyễn Văn Luân Kinh 1 1 Farmer
71 Nguyễn Văn Nức Kinh 1 2 Farmer
72 Nguyễn Văn Sỹ Kinh, Tày 1 2 1 Farmer
73 Nguyễn Văn Tá Tày 1 1 1 1 2 Farmer
74 Nguyễn Văn Thanh Kinh 1 1 1 1 1 Worker
75 Nguyễn Văn Thụy Kinh 1 2 1 2 1 Worker
76 Nguyễn Xuân Qúy (Qúy Ngà) Kinh 1 1 1 1 Trader
77 Nông Quốc Khánh Tày 2 4 1 Worker
78 Nông Văn Toản Tày 1 Forestry planting
79 Phạm Huy Cường Kinh 1 1 Forestry planting
80 Phạm Thị Giang Kinh 1 1 Forestry planting
81 Phoòng Cắm Công Dao 1 1 Forestry planting
82 Phoòng Cắm Tắc Dao 2 1 1 1 Forestry planting
83 Phoòng Cắm Thành Dao 1 1 1 1 1
Forestry planting
84 Phoòng Đình Huy Dao 1 2 1 1 Farmer
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 20 of 28
No Name of household head Ethnic
Sexual Job situation of the hhs
members Primary income
Secondary income
Male Female
Under 18
years old
Above 18
years old
Under 18
years old
Above 18
years old
Employment Unemployment
85 Phoòng Đình Phú Dao 1 2 Farmer
86 Phoòng Đình Thống Dao 3 1 1 1 Farmer
87 Phoòng Đình Vinh Dao 1 2 1 2 1 Forestry planting Worker
88 Phoòng Tắc Qúy Dao 1 2 1 3 1 Forestry planting Worker
89 Phoòng Tài Múi Dao 1 1 Forestry planting
90 Phoòng Thị Mai Dao, Kinh 1 1 1 1 Farmer
91 Phoòng Văn Sinh Dao 3 1 1 2 1 Farmer Forestry planting
92 Phoòng Văn Tư Dao 2 2 1 Farmer Forestry planting
93 Phùn A Hải Dao 1 1 1 Farmer
94 Phùn A Phúc Dao 1 1 3 1 1 Forestry planting
95 Phùn A Sơn Dao 1 3 Forestry planting
96 Phùn Văn Tư (Phoòng Thị Mai) Dao 1 1 1 1 Farmer
97 Tạ Hữu Hợi Kinh 1 1 1 1 Farmer Worker
98 Triệu Chăn Thống Dao 1 1 1 1 Trader Worker
99 Triệu Kim Tề Dao 5 4 1 Forestry planting Worker
100 Triệu Quý Bình Dao 2 1 1 Forestry planting Worker
101 Triệu Quý Dếnh Dao 2 1 2 1 Forestry planting
102 Triệu Quý Quân Dao 3 2 1 1 2 Forestry planting
103 Triệu Qúy Sáng Dao 3 1 4 1 1 Worker
104 Triệu Xuân Lợi Dao, Chiêm 1 1 4 Worker
105 Vi Văn Đăng Tày, kinh 1 1 1 1 Farmer
Forestry planting
106 Vi Xuân Lộc Tày 1 1 3 1 Farmer Forestry planting
107 Vũ Văn Tơn Kinh 1 1 Trader Forestry planting
108 Phùn Thị Minh Dao 1 1 2 1 Aquaculture
109 Vi Thị Hồng Tày 1 3 2 Farmer
110 Vi Thị Huệ Tày 1 3 Farmer
111 Vi Văn Muội Tày 1 3 Farmer Forestry planting
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 21 of 28
No Name of household head Ethnic
Sexual Job situation of the hhs
members Primary income
Secondary income
Male Female
Under 18
years old
Above 18
years old
Under 18
years old
Above 18
years old
Employment Unemployment
112 Triệu Quang Sáu Farmer Forestry planting
113 Vi Văn Đăng Tày, kinh 1 1 1 1
Forestry planting
114 Vi Xuân Lộc Tày 1 1 3 1 Forestry planting Trader
115 Vũ Văn Tơn Kinh 1 1 Forestry planting
116 Đỗ Thị Hồng Kinh 2 1 Trader
117 Đỗ Văn Biên Kinh 1 1 1 Trader
118 Triệu Chăn Thống Dao 1 1 1 1 Worker
119 Lý Văn Việt Dao 2 2 1 1 Farmer Forestry planting
120 Triệu Kim Tề Dao 5 4 1 Farmer
121 Lã Văn Nàng Dao 1 1 3 1 Farmer
122 Vi Thị Liều Tày 1 1 1 1 Farmer Forestry planting
123 Phùng Văn Tơn Dao 2 2 1 1 Farmer Forestry planting
124 Phạm Thị Luyến Kinh 1 1 1 Trader
125 Đong Mo High School
126 Mong duong Committee
127 Dong Mo Medecine Center
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 22 of 28
Appendix 2 Situation of Compensation Payment
Appendix 2.1: Situation of Compensation Payment until 31/3/2014
No Component
Date of project information dissemination
Detailed Measurement Survey Making compensation plan Verify and approve the
compensation plan Situation of Compensation
payment Situation of Site
Clearance Contract
award
Starting date
Finishing date
Starting date
Finishing date Starting date Finishing
date Submitting
date Approval Starting date
Finishing date
Starting date
Finishing date
1 Pineline 24/8/11 31/12/12 10/10/11 10/11/12 13/11/11 15/11/12 12/11/12 13/11/12 24/12/12 Continue 14/1/13 Continue 6/12/13
Cộng Hòa 24/8/11 31/12/12 10/10/11 10/11/12 13/11/11 15/11/12 12/11/12 13/11/12 24/12/12 Continue
14/1/13 Continue
6/12/13
Cẩm Hải 24/8/11 31/12/12 10/10/11 10/11/12 13/11/11 15/11/12 12/11/12 13/11/12 24/12/12 Continue
14/1/13 Continue
6/12/13
2 Resevoir 24/8/11 31/11/13 10/10/11 31/11/13 13/11/11 31/11/13 12/11/12 31/11/13 24/12/12 Continue
14/1/13 Continue
5/4/14
Mông Dương 24/8/11 31/11/13 10/10/11 31/11/13 13/11/11 31/11/13 12/11/12 31/11/13 24/12/12 Continue
31/3/14 Continue 5/4/14
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 23 of 28
Appendix 2.2: Number of Affected Households until 31/3/2014
No Component
Long term affected households Total Affected HHs (both long term and short
term Affected HHs No. Of Severe HHs
No. Of None-severe HHs
Affected Business
HHs
HHs with Vulnerable People
Total
Lost from 10% or more of
agricultural land
Number of resettled
HHs Poor HHs
Ethic Minorities
HHs
Single Woman
headed HHs
Social Policy HHs
1 Pineline 53 53 0 12 0 5 5 1 7 65
Cộng Hòa 36 36 0 6 0 3 4 0 5 42
Cẩm Hải 17 17 0 6 0 2 1 1 2 23
2 Resevoir 101 101 37 26 0 6 93 7 3 127
Mông Dương 101 101 37 26 0 6 93 7 3 127
Total 154 154 37 38 0 11 98 8 10 192
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 24 of 28
Appendix 2.3: Area of the acquired land until 31/3/2014
No. Components/ Packages
Permanently Acquired Land Area (m2) Temporarily Acquired Land Area (m2)
Agricultural Land
Residential Land
Aquacultural Area Forest Land Other Land Total Forest Land Other Land Total
1 Pineline 0.0 0.0 12,956.80 324,703.13 145,351.70 483011.63 11460.7 6295.8 17756.5
Cộng Hòa 0.0 0.0 269.00 195,251.53 98,304.20 293824.73 0.0 1667.0 1667.0
Cẩm Hải 0.0 0.0 12,687.80 129,451.60 47,047.50 189186.90 11460.7 4628.8 16089.5
2 Resevoir 225,309.5 8,000.0 13,872.65 305,863.50 813,354.16 1366399.76 0.0 0.0 0.0
Mông Dương 225,309.5 8,000 13,872.65 305,863.50 813,354.16 1366399.76 0.0 0.0 0.0
Total 225,309.5 8,000.0 26,829.45 630,566.63 958,705.86 1849411.39 11460.7 6295.8 17756.5
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 25 of 28
Appendix 2.4: Housing and other assets affected until 31/3/2014
No. Components/ Packages
Affected Housing Area
(m2)
Affected Shop Area (m2)
Affected Factory Area
(m2)
Affected Rice and crops area
(m2)
Affected Tree (tree)
Affect Objects/ Architect Works
Relocated Graves
(pcs) Affected Other Assets
1 Pipeline 2,004.8 0.0 288.0 528.0 73,512.0
Appendix 2. 4.1
Appendix 2. 4.1
Cộng Hòa 1,198.0 0.0 288.0 310.0 46,232
Cẩm Hải 806.8 0.0 0.0 218.0 27,280
2 Resevoir 2,813.0 0.0 0.0 169,765.0 99,893
Mông Dương 2,813 0.0 0.0 169,765.0 96,791
Total 4,817.8 0.0 288.0 170,293.0 173,405.0 0.0 -
Appendix 2.4.1: Affected Other Assets until 31/3/2014
No. Components/ Packages Toilet Kitchen Bathroom Well Barns Cement roof Fence Water Tank Electric Line
(m2) (m2)/ (m2) (pcs) (m2) (m2) (m2) (m3) (m)
1 Pineline 16.92 144.27 2.79 1.00 329.20 130.56 8.40 372.76 4490.00
Cộng Hòa 0.00 10.63 2.79 1.00 35.60 0.00 0.00 50.19 1695.00
Cẩm Hải 16.92 133.64 0.00 0.00 293.60 130.56 8.40 322.57 2795.00
2 Resevoir 89.36 419.86 87.20 8.00 1,758.30 127.80 32.60 851.60 18537.70
Mông Dương 89.36 419.86 87.20 8.00 1758.30 127.80 32.60 851.60 18537.70
Total 106.28 564.13 89.99 9.00 2087.50 258.36 41.00 1224.36 23027.70
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 26 of 28
Appendix 2. 5: Situation of Compensation Payment until 31/3/2014
No Component
Compensation Cost (VND) Paid and None-paid yet (VND) Situation of Compensation Situation of Site Clearance
Total of cost estimation approved
by 31/3/2014
Total of cost according to the
compensation plan Paid until 31/3/2014 None-paid No. of HHs received
compensation
No. of HHs none-received
compensation
No. of HHs handed over the
sites
No. of HHs have not been handed
over the sites
1 Pineline 17,074,100,200 17,074,100,200 17,074,100,200 0 65 0 65 0
Cộng Hòa 7,670,930,200 7,670,930,200 7,670,930,200 0 40 0 42 0
Cẩm Hải 7,365,028,400 7,365,028,400 7,365,028,400 0 20 0 23 0
Pipeline (addition Recovery) 2,038,141,600 2,038,141,600 2,038,141,600 0 5 0 0
2 Resevoir 80,401,106,900 80,401,106,900 79,715,119,700 615,987,200 126 1 127 1
Mông Dương 80,401,106,900 80,401,106,900 79,715,119,700 615,987,200 126 1 127 1
Total 97,405,207,100 97,405,207,100 96,789,219,900 615,987,200 191 1 191 1
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 27 of 28
Appendix 2.6: Situation of Compensation Payment until 31/3/2014
Components/ Packages
Communal Level District Level Compensation Committee Provincial PMU Provincial Level Court
No.
of
Com
plai
ned
HH
S
No.
of H
Hs
are
satis
fact
orily
re
solv
ed
No.
of
Com
plai
ned
HH
S
No.
of H
Hs
are
satis
fact
orily
re
solv
ed
No.
of C
ompl
aine
d H
HS
No.
of H
Hs
are
satis
fact
orily
re
solv
ed
No.
of C
ompl
aine
d H
HS
No.
of H
Hs
are
satis
fact
orily
re
solv
ed
No.
of C
ompl
aine
d H
HS
No.
of H
Hs
are
satis
fact
orily
re
solv
ed
No.
of
Com
plai
ned
HH
S
No.
of H
Hs
are
satis
fact
orily
re
solv
ed
Resevoir 17 14 0 0 0 0 0 0 0 0 0 0
Pipeline 8 8 0 0 0 0 0 0 0 0 0 0
Total 25 23 0 0 0 0 0 0 0 0 0 0
1st Quarterly Internal Resettlement Monitoring Report 2014 Mong Duong (2 x 500MW) Thermal Power Plant Project
Page 28 of 28
Appendix 2.7: Progress on compensation and resettlement implementation till 31/3/2014
Component Pipeline Component Resevoir
Component
Cộng Hòa Cẩm Hải Mông Dương
Activities on compensation and resettlement Complete situation Complete situation Complete situation
Information Dissemination and Community Participation 100.0% 100.0% 100.0%
Detailed Measure Survey (DMS) 100.0% 100.0% 100.0%
Setting Compensation Plan 100.0% 100.0% 100.0% Consulting and Counseling with the APs on compensation plan 100.0% 100.0% 100.0%
Update the RP and approve by ADB 100.0% 100.0% 100.0% Finalized the compensation plan and submit for approval 100.0% 100.0% 100.0%
Verify and approve the compensation plan 100.0% 100.0% 100.0% Consultate the APs on the approved compensation plan (to the agricultural land) 100.0% 100.0% 100.0%
Compensation Payment 100.0% 100.0% 99.37%
Resettlement and Site Clearance 100.0% 100.0% 99.37%
Independent Monitoring and Reporting 100.0% 100.0% 99.37%
Compensation Progress by component 100.0% 100.0% 99.37%
Compensation Progress of the Project 100.0% 100.0% 99.37%