Upload
knust
View
2
Download
0
Embed Size (px)
Citation preview
KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY
DEPARTMENT OF ENVIRONMENTAL SCIENCE
VACATION TRAINING (ATTACHMENT) REPORT @
PERSEUS MINING (GHANA) LIMITED
ENVIRONMENTAL DEPARTMENT
1
KOOMSON EDMOND
17TH JUNE, 2013. – 17TH AUGUST, 2013.
CONTENTS
CHAPTER 1
I. CLEARANCE FORM
II. ACKNOWLEDGEMENT
III. LIST OF ABBREVIATIONS
IV. INTRODUCTION
V. ABSTRACT
CHAPTER 2
LABORATORY SECTION
CHAPTER 3
MONITORING SECTION
CHAPTER 4
ENVIRONMENTAL MANAGEMENT SYSTEM
CHAPTER 5
RHABILITATION AND RE-VEGETATION SECTION
CHAPTER 6
COMPLIANCE
2
CHAPTER 1
I. CLEARANCE FORM
STUDENT ------------------------- -----
----------------------
Signature Name/DATE
ENVIRONMENTAL MANAGER ------------------
-----------------------------
SIGNATURE NAME/ DATE
HUMAN RESOURCE MANAGER ----------------------
----------------------------
3
SIGNATURE NAME/DATE
LABORATORY SUPERINTENDENT -----------------------
---------------------------
SIGNATURE NAME/DATE
MONITORING SUPERVISOR ---------------------------
---------------------------
SIGNATURE NAME/DATE
REHABILITATION SUPERVISOR --------------------------
--------------------------
SIGNATURE NAME/DATE
4
COMPLIANCE SUPERVISOR -------------------------
-------------------------
SIGNATURE NAME/DATE
EMS COODINATOR -------------------------------
--------------------------
SIGNATURE NAME/DATE
II. ACKNOWLEDGEMENT
The success of my training was as a result of the support and
cooperation of some staffs that helped me to gain more knowledge
than I expected. I am most grateful to all and I would like to
thank the;
5
Human Resource and the Environmental Manager for first of
all giving me the opportunity to have my training in this
company,
Various Superintendents of the environmental department,
Supervisors of all the various sections of the department,
Environmental officers and the junior staffs of the
department.
I really appreciate all of you for the impartations of knowledge.
I must say that I have learnt a lot about the environment through
this training and it is all your doing. I will always be indebted
to you. Thank you and God bless you.
6
III. LIST OF ABBREVIATION
EPA Environmental Protection Agency
EMP Environmental Management Plan
EMS Environmental Management System
PMGL Perseus Mining Ghana Limited
SOP Standard Operating Procedure
PM10 Particulate Matter 10
TSP Total Suspended Particles
A-F GAP Abenabena Fobinso Gap
FTSF Flotation Tailing Storage Facility
CTSF Cyanide Tailing Storage Facility
WRC Water Resource Commission
MinCOM Mining Commission
AGA AngloGold Ashanti
COC Chain of Custody
7
IV. INTRODUCTION
The first recorded exploration and gold production in the
Ayanfuri area dates back to 1906. More recently, between 1994 and
2001, the Ayanfuri gold mine produced over 300,000oz of gold from
23 shallow oxide open pits and heap leach processing with most of
the production from six granite hosted ore bodies. There were
three principle phases of exploration undertaken at Ayanfuri
since 1988. The first was initial discovery and predevelopment
drilling undertaken by Cluff Mining (“Cluff”). The second was the
exploration of secondary targets to locate additional ore feed
undertaken by Ashanti Goldfields Corporation Limited (“AGC”)
after it acquired Cluff and the third phase was the post mine
closure exploration undertaken by Perseus Mining Limited (PMGL)
during the acquisition from AngloGold Ashanti Limited (“AGA”).
Perseus Mining Ghana Limited (PMGL) is developing the Edikan Gold
Mine, near Ayanfuri in the Central Region of Ghana. It is an open
pit mine and CIL processing plant for the gold-bearing ore. The
treatment plant will process combinations of oxide, transition
and primary ores from the various pits at a nominal capacity of
8
5.5Mtpa. Consequently, these activities will affect the
environment with which the mine interacts. PMGL recognizes the
importance of protecting the integrity and wealth of the
environment for current and future users.
PMGL’s commitment to sound environmental management is set out in
its Environmental Policy including commitments to minimizing and
managing any environmental impacts, maintaining legal compliance
and continual improvement, training and orientation of both
employees and contractors to be competent in their areas of
operation and promote a high sense of responsibility towards
environmental management. PMGL Environmental Policy is supported
by its Environmental Management System (EMS), which is designed
to give full effect to the policy and will operate on the
principles of an international standard for environmental
management systems, ISO14001:2004.
PMGL is wholly owned by Perseus Mining Limited, an Australian
company. Perseus Mining Limited is listed on both the Australian
and Toronto Stock Exchanges. The Perseus Group undertakes gold
exploration in Ghana through Sun Gold Resources Limited (SGRL)
and gold production by Perseus Mining Ghana Limited (PMGL) Edikan
Mine. PMGL has reserves of 2.1 million ounces of gold, plus
1.2Moz of measured and indicated gold resources. Production began
in August 2011 and the plant was commissioned in May 2012.
9
This report gives a brief summary of the activities undertaken by
PMGL’s Environmental Department and also what I studied during my
industrial training (attachment). PMGL is committed to protecting
the environment whilst contributing to the economic development
of the countries in which it operates. All of the Company
stakeholders, including employees, the local communities, and
others have a right to expect the company to take a responsible
and environmentally sustainable approach to their activities. It
is the responsibility of the PMGL Environmental department to
ensure that the environmental policy is obliged in any section of
the company. The environmental department consists of five
sections namely; Environmental Laboratory, Compliance,
Monitoring, EMS, and Rehabilitation and Re-vegetation.
The Environmental Laboratory is where samples from surface water
bodies and ground water bodies or portable water in the catchment
communities, observable boreholes, and the process plant effluent
are analyzed. The samples are analyzed after they have been
handed over (COC) by the monitoring section for physical
parameters (PH, Total Dissolved Solids, Conductivity, Dissolved
Oxygen, Turbidity, True Color, Apparent Color, Chlorine and
Alkalinity), nutrients ( nitrate, nitrite, phosphate, etc.),
metals (Pb, Fe, Cu, Ca, Al, Zn, Cd, etc.) and microbiology (E.
coli and Total Coliforms).
The Monitoring Section monitor and do sampling of surface water
bodies and ground water bodies or portable water in the catchment
11
communities, observable boreholes, and the process plant effluent
to be analyzed in the laboratory. The section also monitors dust,
noise blast, and rainfall levels in PMGL concession and in the
catchment communities. The section does this to access whether
the operations of the mine is affecting the environment or not.
The Environmental management system also ensures that all the
requirements of the permit is obliged. This section also develops
training programs (competency and awareness) to assess the
performance of the workers. Internal auditing is also carried out
by this section.
The Compliance sections and the EMS have conflicting duties. The
compliance also ensures that PMGL workers work according to the
requirements of the Permit. Specifically, PMGL’s Environmental
compliance section carries out waste managements on site, annual
environmental monitoring report, and others.
The rehabilitation and re-vegetation section ensures that the
land is restored to its natural structure during and after the
operations of the mine. This section also controls erosion.
All these sections come together to make sure that the
environment is safe for it habitats and the mine operations do
not have negative impact on the environment and the catchment
communities.
12
CHAPTER 2
ENVIRONMENTAL LABORATORY
I started my training at the Environmental Laboratory. The
Environmental Laboratory is where samples from surface water
bodies, ground water bodies, watershed around the mine, and the
process plant effluent are analysed. The samples are analysed
13
after they have been handed over (COC) by the monitoring section
to the laboratory for Physical parameters (PH, Total Dissolved
Solids, Conductivity, Dissolved Oxygen, Turbidity, True Colour,
Apparent Colour, Chlorine and Alkalinity), Nutrients (nitrate,
nitrite, phosphate, etc.), Metals (Pb, Fe, Cu, Ca, Al, Zn, Cd,
etc.) and microbiological analysis (E. coli and Total Coliforms)
to be carried out. However, I was introduced to only the physical
aspect. The laboratory does this analysis to know or determine if
the activities of the mine is having any negative impact on the
environment (flora, fauna, soil, and water) and the neighbouring
communities.
To ensure zero injury and safety at the lab, all laboratory
analysis is done with the right instrument and appropriate
Personal Protective Equipment (PPE). Also, safety is one of the
most important elements in the operation of an analytical
laboratory. PMGL Environmental Laboratory is fully committed to
providing a safe working environment and enforcing procedures
which will ensure the health and safety of each employee. All
laboratory personnel, students on attachment and visitors alike
in the laboratory are entitled to a safe and healthy working
environment. It is to this purpose that all personnel undergo
induction before commencing any work at the laboratory. The
following are some Laboratory Operating Procedures and Personal
Protective Equipment that I was introduced to ensure zero injury
and safety before I commenced working at the laboratory;
14
Personal Protection Equipment (PPE)
I. Safety glasses must be worn when in the laboratory.
II. Gloves must be worn while handling chemicals or samples.
III. Lab coats must be worn when doing any analysis in the lab.
IV. Face shields and goggles must be worn while pouring
concentrated acid.
V. Face shields, goggles, and aprons must be worn during
activities involving vigorous agitation.
VI. UV protective goggles must be worn when using the AAS
equipment.
Laboratory Operating Procedures
I. Materials spilled onto the floors will be cleaned up
immediately using approved disposal protocols.
II. Obstructions from movement will not be allowed in walkways
or working areas that may cause tripping, falling, or any
harm to an individual.
III. Hazard warning signs will be posted at all locations where
there is a potential safety or health hazard.
IV. All personnel will be informed of the hazards in their work
places.
V. Hazardous materials will be handled in containment devices
such as fume hoods or fume absorbers.
15
VI. Laboratory personnel will not store food, eat, drink, or
smoke in the laboratory’s designated work hazard zones.
The following are the detailed Standard Operating Procedures
for the physical aspect of water quality analysis that i
learnt during my duration at the Environmental Laboratory.
However, as part of the SOP, before any analytical work is
commenced at the laboratory, an Environmental Laboratory
Prestart Checklist should always be done. The Prestart
Checklist advices to calibrate all instruments in the
Laboratory before using them. This helps to know that the
Laboratory instruments are safe or accurate to use. It also
teaches on sanitation before starting any analysis. These
are some questions the Prestart Checklist will inquire;
Do all rooms have sufficient light and ventilation?
Are ALL room thoroughly cleaned, waste solutions
emptied into waste container and all glassware at
appropriate places?
Has DO meter been maintained and calibrated? - Write
STD Value. Etc. After meeting all the requirements of
the Prestart Checklist, it should be signed, date
written, and filed.
All these helps the laboratory assistants to arrive at a zero
injury and an accurate work done at the Laboratory.
16
DETERMINATION OF DISSOLVED OXYGEN (DO) AND BIOCHEMICAL
OXYGEN DEMAND (BOD) OF SAMPLES
Dissolved oxygen is the amount of oxygen present in water, or the
number of milligrams of oxygen dissolved in a litre of water. It
is measured in milligram per litre (Mg/L). A good level of
dissolved oxygen is essential for aquatic life. Dissolved oxygen
analyses measures the amount of gaseous oxygen (O2) dissolved in
an aqueous solution. Oxygen gets into water bodies by diffusion
from the atmosphere or surrounding air, aeration (rapid movement
or flow of the water), and by photosynthetic activity of
phytoplankton in the water. Adequate dissolved oxygen is
necessary for good water quality. Deficient DO is caused when the
algae in water uses the available DO for it metabolic activities.
This leads to the extinction of the animals in the aquatic
habitat.
To determine the dissolved oxygen and BOD of samples, the
following equipment is needed;
Temperature Controlled Incubator
BOD Bottles with glass stoppers
BODTrak Apparatus
Tissue paper
Disposable hand gloves
Extech DO Meter Model DO700
Dissolved Oxygen Electrode
Distilled Water
17
The following are the procedures for determining dissolved oxygen
and BOD;
Put on PPE before commencing.
Calibrate the DO metre at 8.00Mg/L. The stirrer should
always be in distilled water after calibration.
Samples should be poured into a well labelled BOD bottles
and covered with their glass stoppers respectively.
PMGL method of determining BOD is to measure the DO of each
sample for five days. The first day DO value minus the fifth
day value gives the BOD. But in all the five days, the
samples are kept in a temperature controlled incubator.
The first day reading is the dissolved oxygen.
DETERMINATION OF pH OF SAMPLES.
pH is a measure of the acidity or basicity of an aqueous
solution. Solutions with a pH less than 7 are said to be acidic
and solutions with a pH greater than 7 are basic or alkaline.
Pure water has a pH very close to 7. The pH scale is traceable to
a set of standard solutions whose pH is established by
international certified body. Primary pH standard values are
determined using a concentration cell with transference, by
measuring the potential difference between a hydrogen electrode
and a standard electrode such as the silver chloride electrode.
Measurement of pH for aqueous solutions can be done with a glass
electrode and a pH meter, or using indicators.
18
pH is determined using a pH metre. At PMGL, the metre is
calibrated after the appropriate mode has been selected using
known buffer solutions before samples are read. The buffers used
are 4.00, 7.00, and 10.01. The deviation should not be less or
greater than 0.02. The following equipment’s are needed in
determining pH.
1. pH metre with a probe
2. distilled water in a beaker
3. Tissue paper
The procedures for determining pH are as follows;
1. All standards and samples must be at room temperature.
2. The instruments must first be calibrated using the
calibration standards of the pH buffers.
3. The standards are first read before the samples.
4. Each sample must be shaked before taking its reading.
5. The pH probe is inserted into the bottle containing the
sample.
6. The pH recorded after stabilization, and then the probe is
inserted into a beaker of distilled water for rinsing.
NB: PPE’s must be worn.
DETERMINATION OF CONDUCTIVITY AND TOTAL DISSOLVED SOLIDS (TDS)
19
Conductivity is the ability of water to carry an electrical
current. Absolutely pure water is a poor conductor of
electricity. Water shows significant conductivity when dissolved
salts are present. Over most ranges, the amount of conductivity
is directly proportional to the amount of salts dissolved in the
water. The conductivity of water is measured in micro Siemen.
The amount of mineral and salt impurities dissolved in the water
is called total dissolved solids (TDS). TDS is measured in parts
per million. TDS tell how many units of impurities there are for
one million units of water. For example, drinking water should be
less than 500 ppm, water for agriculture should be less than 1200
ppm, and high tech manufactures often require impurity-free
water. One way to measure impurities in water is to measure the
electric conductivity of water. Half of conductivity is TDS.
To determine conductivity and TDS, the following equipment is
needed;
1. Conductivity metre
2. Beaker containing distilled water
3. Conductivity Standard solution
The following are the procedures for determining conductivity and
TDS;
1. The appropriate PPE’s must be worn.
2. The conductivity metre is switched on, appropriate mode
selected, and then calibrated with a standard solution.
20
During my time at the laboratory, standard 1413 were always
used for calibration.
3. The metre probe is inserted into the sample bottle for
reading. The metre is allowed to stabilise and the value
recorded.
4. The probe is rinsed with distilled water and placed in a
beaker containing distilled water.
5. Since half of conductivity is TDS, after getting
conductivity value, the mode of the metre is changed to ppm
and the value that will be displayed is TDS.
NB: Standards readings are taken before samples.
DETERMINATION OF TURBIDITY OF SAMPLES
Turbidity is the haziness or cloudiness of water. The measurement
of turbidity is a key test of water quality. It is the measure of
the degree to which the water loses its transparency due to the
presence of suspended particulates. The more total suspended
solids in the water, the murkier it seems and the higher the
turbidity. Phytoplankton, sediments from erosion, algae growth,
etc. causes turbidity in water bodies. Turbidity is measured in
NTU: (Nephelometric Turbidity Units). The instrument used for
measuring is called nephelometer or turbidimeter, which measures
the intensity of light scattered at 90 degrees as a beam of light
passes through a water sample. The turbidity of drinking water
should not be more than 5NTU.
21
The following are equipment and reagents needed;
Turbidity sample bottles (cells)
Distilled water
Turbidimeter
Tissue paper
Reference calibration standards
Calibration of the turbidimeter must be done before samples are
measured. Calibration is done with five turbidity standards (S0,
S2, S3, S4, and S5).
The appropriate PPE’s must be worn.
Take the first standard (S0) by the cap and clean with
silicone oil to remove all spot.
Press CAL and place the S0 into the instrument cell
compartment, cover it, and then press ENTER. The instrument
display counts down from 60 to 0, and then makes a
measurement (20NTU).
This is repeated for the four other standards. At the end of
the last standard reading, press CAL to calibrate. If it
reads to 4000NTU or closer to it, the meter is accurate to
read samples; else calibration has to be repeated.
Procedures for reading samples are;
Take the readings of the first three samples; this time
round, after wiping it with silicone oil and placing it into
22
the cell compartment, press enter. Record the displayed
value.
After that, in addition to the samples reading, distilled
water also has to be read as a check for blank.
Shake sample gently and pour about 30ml into the turbidity
cell.
The water spot and finger print is wiped whilst holding the
cap. Finger print can add to the value.
The sample cell is placed into the cell compartment and
instrument covered.
Press enter and record the displayed value.
Do same for all samples and the distilled water.
After each reading, the turbidity cell must be rinsed with
distilled water.
NB: Put on the appropriate PPE.
DETERMINATION OF TOTAL SUSPENDED SOLIDS (TSS) IN WATER SAMPLES
TSS includes all particles suspended in water which will not pass
through a filter. As levels of TSS increase, a water body begins
to lose its ability to support a diversity of aquatic life.
Suspended solids absorb heat from sunlight, which increases the
water temperature and decreases dissolved oxygen (warmer water
holds less oxygen than cooler water). To determine the TSS, the
sample must be filtered and residue dried to get the suspended
particles
23
Equipment needed is;
Measuring cylinder (500ml)
Filter paper
An oven
Petri dish
Filtering apparatus
Desiccator and sample tray
The following are the procedures;
Put on the appropriate PPE.
Filter papers are labelled according to the labels on
samples and weighed at room temperature. SWITCH OFF air
condition during this time to prevent the filter paper from
moistening. The filter paper is weighed and recorded as l1.
The sample is shaken and 100ml is poured into the filtering
apparatus setup.
After filtering, remove the filter paper gently on a tray.
Rinse the filtering apparatus with distilled water.
The filter paper on tray is placed in an oven to dry.
After drying, leave it to cool for some time and weigh
again. Record the reading as l2.
The suspended solids are calculated as;
L2-L1 / V×1000
Where;
L1------------ initial weight
24
L2----------- final weight
V------------- Volume of sample taken in ml.
This is repeated for all samples.
DETERMINATION OF TRUE AND APPARENT COLOUR IN WATER SAMPLES
Apparent colour is the colour of the whole water sample, and
consists of colour from both dissolved and suspended components.
True colour is measured after filtering the water sample through
0.45um filter paper to remove all suspended components.
Equipment needed;
Distilled water
Filter membrane
Filtration setup
Sample cells
Procedure;
The spectrophometer is switched on and the test is selected.
To calibrate, an empty cell is inserted and press zero on
the screen.
25
For apparent colour, fill the sample cell with 10ml of the
sample and wipe it to get rid of all finger print. But for
true colour, the sample must be filtered.
The first value that appears is recorded. Before analysing
samples, distilled water must be analysed first.
NB: When under measuring range is displayed on the screen, zero
is recorded as the value. All PPE must be worn.
DETERMINATION OF TOTAL ALKALINITY IN WATER SAMPLES
Alkalinity is the measure of the capacity of water or any
solution to neutralize or ‘buffer’ acids. The measure of acid-
neutralizing capacity is important in figuring out how ‘buffered’
the water is against sudden changes in pH. Alkalinity is caused
by the presence of carbonates, bicarbonates, hydroxides and other
dissolved salts. It is important to drinking water food and
aquatic life. This is determined by titration with a standard
solution of a strong mineral acid to an end point of about pH 4.3
using a pH meter.
Equipment;
0.001M HCL
100ml beaker
Distilled water
Tissue paper
100ml volumetric flask
26
pH meter
burette
Firstly, calibration is done with distilled water. The procedure
is as follows;
The appropriate PPEs must be worn
A 0.001M HCL is prepared.
The HCL is transferred into the burette.
25ml of each sample is pipetted into different beakers
The initial volume of the HCL in the burette is recorded as
initial volume (V1)
The HCL is titrated against the sample. As the HCL is
gradually drained into the sample in the beaker, the
solution is stirred gradually with the pH probe.
When the pH meter reading reaches 4.3, the final reading is
recorded (V2)
The initial reading is subtracted from the final reading to
get the alkalinity value.
The sample is discarded and the beaker and probe are
rinsed.
This is repeated for all samples.
DETERMINATION OF CHORIDE IN SAMPLES
Almost all natural waters contain chloride ions. Its
concentration varies considerably according to the mineral
27
content of the soil in any given area. In small amounts they are
not significant. In large concentrations they present problems.
In large concentrations above 250mg/l, water becomes unpleasant
to drink. Chloride is commonly found in streams and wastewater.
It may get into surface water from several sources including
wastewater from industries, agricultural runoff and others. The
equipment and reagent used to determine chloride are;
0.0O96Mol/dm3 silver nitrate solution
Distilled water
Measuring cylinder
Burette setup
5% K2Cr2O7 incubator
Beaker
10ml pipette
Distilled water is first tested as blank before the sample
analyses is being carried out.
The procedures Include;
10ml of the sample is measured into a beaker.
2 drops of the potassium dichromate is added to the sample.
The prepared silver nitrate is transferred into the burette.
The initial volume (V1) of the burette is recorded.
During titration, if the colour of the sample turns from
yellow to orange, the final volume (V2) is recorded.
The difference in volume gives the amount of chloride in the
sample.
28
The same is repeated for all other samples.
NB: PPE is needed before starting the analysis.
These are the physical aspects of water quality analysis I learnt
at the environmental laboratory.
CHAPTER 3
MONITORING SECTION
According to section 4.4.3 (a) (b) of the EPA permit for the
operation of the mine, PMGL is obliged to undertake periodic
monitoring of the environment within her concession and the
adjoining lands and submit environmental monitoring returns
monthly. It is for this purpose that this section monitor water,
dust, noise, blast and acid rock drainage (ARD) in the entire
environment within and around PMGL concession and the
29
neighbouring communities to know how the operations of the mine
is affecting the environment.
BLAST MONITORING
As stated vividly in the Section 5.1.2(C) and 5.2 of the Permit,
PMGL is obliged to monitor ground vibration and overpressure
during every blast period. Where limits are above acceptable
levels or EPA standards (117dBLs for ground vibrations and 2mm/s
for overpressure or air blast), the company is required to take
corrective actions to mitigate it. Blasting is done only during
the day (between 12:20hrs and 17:3hrs daily) when conditions are
suitable. Inhabitants or communities close to the pits are
informed of the blast times through the use of sign boards in
these communities. Blast is carried out at Abenabena pit, Fobinso
pit, and A-F Gap pit. At PMGL, blast monitoring is divided into
two, with monitoring done in Abenabena and Fobinso. These are the
two communities closer to the pits. The blast monitoring device
used is called Geosonic (SSU 5500). During blast, we were adviced
by our supervisors to put on our PPE and also ensure that all
safety precautions are observed.
Blast monitoring is done to ensure that Ground vibration (peak
particle velocity) and air blast or overpressure levels (PSPL)
resulting from PMGL’s blasting operations meet PMGL internal
standards and accepted international standards for protection of
property and human health.
30
The following are the procedures to monitor blast;
a) Transport Geosonic (SSU 5500) to the monitoring location in
the protective case
b) Remove the geophone, microphone and accessories from the
case
c) Geophone: attach spikes to geophone. Press geophone firmly
into ground with the arrow opposite the cable toward
vibration source while ensuring that the bubble level is at
the Centre. Connect cable to instrument.
d) Microphone: attach spike to mast, insert in mounting block
and press spike into the ground. Clip microphone into mast
and install windscreen. Point toward source and connect
cable to instrument.
e) Monitoring personnel will be informed about two minutes to
the blast.
f) At this time, there should be no movement until the blast is
over. This is because; the values can be affected or
altered.
g) After the blast, the data is recorded and sent to the
office.
NOISE MONITORING
In the section 5.1.2 (a) (c) of the permit, it is required that
PMGL addresses potential significant impacts of noise. As long as
31
the company continues to operate, noise pollution would be
generated. Noise pollution to some extent has great impact on the
living organisms in the environment. In view of this, noise
monitoring is done in the two main catchment communities (Fobinso
and Abenabena). Noise monitoring is done both day and night. The
equipment for monitoring is calibrated according to the
manufacturer’s specifications. In the day, it is monitored from
7:00am to 9:45pm and at night, from 10:00pm to 6:50am. The
monitoring equipment (Casella CEL-63x series) is calibrated to
monitor noise for one month. At the end of every month, data is
retrieved.
DUST MONITORING
Dust monitoring is completed in accordance with regulatory
requirements and in response to external complaints to determine
the impact of PMGL’s operations on the surrounding environment
and communities. PMGL’s Environmental Management Plan on Air
Quality management to suppress dust generation is as follows;
The use of water tankers to water haul and access roads to
the mine and all catchment communities.
32
Mounting of regular speed checks and slow down signs along
all access roads to the mine and neighboring communities for
vehicles to minimize dust in populated areas and in these
communities.
Monitoring of Total Suspended Particles (TSP) and
Particulate Matter (PM10) in the catchment communities.
PMGL has put all these measures in place to ensure that dust
generated from their operations do not have impact on the fauna
and flora in the environment.
The size of Total Suspended Particles (TSP) and Particulate
Matter (PM10) largely determines the extent of environmental and
health damage caused. Particulate Matter consists of airborne
particles in solid or liquid form and has the ability to reach
the lower regions of the respiratory tract when inhaled. The
Minivol Air sampler is used to monitor dust (TSP and PM10).
Weighed Filter papers are inserted into the filter holder of the
machine to monitor dust in the catchment communities. After 24
hours, filter papers are removed and weighed again. The
difference in the initial and final reading gives the value of
TSP and PM10.
WATER QUALITY MONITORING
Water sampling is carried out on site and in all the catchment
communities. It is done weekly and monthly. The various sampling
33
locations include surface water bodies, ground water or portable
water, observable boreholes, and processing plant effluents. The
under listed items are checked/prepared prior to leaving the
office to undertake the sampling exercise;
Bucket (for ground water sampling)
Cooler box
Adequate number of ice packs for cooler box
Adequate quantity of preserved/sterilize bottles
On-site measuring instrument
Flow meter (where applicable)
Sampling data recording sheet, field note book, pen, pencil
Appropriate PPE in place (Hand gloves, gum boots, goggles,
hard hat etc.)
Wash bottle filled with distilled water
Tissue paper
Cleaning/sterilizing agents (methylated spirits)
Keys to all monitoring boreholes
Generator with adequate fuel in fuel tank
Submersible pump(s), 2” and/or 3”, with all hose/pipes, etc.
Regulator for submersible pumps
Water depth indicator for sampling of boreholes
Location list
WEEKLY WATER SAMPLING
34
Weekly water sampling is carried out from Monday to Thursday of
every week in a month. So the number of weeks in a month
determines the number of times weekly samples will be taken.
During weekly sampling, samples are taken from streams or surface
water in or around all catchment communities, plant effluent, and
portable bore holes in catchment communities or ground water.
Before portable boreholes are sampled, the tap is sterilized with
methylated spirit or by heating prior to turning tap on. Surface
water samples are taken in the middle of the stream not on the
banks. Sample bottles are only opened when the samples are about
to be taken. With the sample bottle oriented in the upstream
direction (against flow of stream), a reasonable quantity of
water (about 1/3 full) is obtained and the sample bottle is
rinsed three times with stream water before the actual sample is
taken. Sampling surface films are avoided as they contaminate the
sample. All surface water are labeled using PMGL as the
initials. Ground water is labeled with GPMGL as initials. After
that the number of the sampling point, then the date of sampling.
This gives a unique identity to each sample. When taking samples,
the bottle should be filled leaving no room for air. Samples are
kept in cool box after sampling.
The picture below is a weekly water sampling at Nkotimso.
35
MONTHLY WATER SAMPLING
Monthly samples are taken at the first week of every month.
Actually, monthly sampling represents week one sampling of every
month. Because this sampling is of great concern to EPA, sampling
points for all surface water bodies have been divided into
Control, Compliance, and Surveillance points.
Control points are the source or closer to the source of the
stream or river. These points are not in the operational area of
the mine. As a result the activities of the mine do not have any
impact on these points. Therefore parameters like DO, pH,
conductivity, TDS, and other physical parameters are expected to
be standard. If parameters are not standard, then there might be
36
illegal mining operations going on or chemicals used by some
farmers around that area is causing that.
Compliance points are on the concession or the operational area
of the mine. So the mine has full control over these points. The
activities of the mine are definitely affecting these points.
Because the mine has full control over them, it makes sure that
parameters like DO, pH, conductivity, TDS, and other physical
parameters are not above the standards of EPA. They are also
called discharge points, because from there, the water flows into
the external environment. Once the river or stream flows from
these points, it’s directly get into the external environment.
It’s to this purpose that both EPA and PMGL are interested in the
quality of these sampling points so that the external environment
is not disturbed.
Surveillance points are also not in the operational area of the
mine but their quality is dependent on the compliance points.
This is because the water flows from the compliance point before
it gets to the surveillance points. When parameters or water
quality at compliance points are right and that of surveillance
is not, then there is an assumption that is as a result of the
use of chemicals by farmers around these points or the operations
of illegal mine (galamsey).
Observable boreholes, ground water or portable water, surface
water, processing plant effluent are sampled monthly. The
observable boreholes are purged at least 24 hours before
37
sampling. This is to get fresh water for analyses. Boreholes
levels are taken before and after purging. This is done to know
the difference in rise fall of the water table at that particular
point. Samples are taken and labeled as done in the weekly
sampling. In monthly sampling, observables boreholes are labeled
as OPMGL plus sample point number and date of sampling. After
sampling samples are stored in cool box and sent to the Lab.
CHAPTER FOUR
ENVIRONMENTAL MANAGEMENT SYSTEM (EMS)
Environmental management system (EMS) refers to the management of
an organization's environmental programs in a comprehensive,
systematic, planned and documented manner. It includes the
organizational structure, planning and resources for developing,
implementing and maintaining policy for environmental protection.
More formally, EMS is a system and database which integrates
procedures and processes for training of personnel, monitoring,
summarizing, and reporting of specialized environmental
performance information to internal and external stakeholders of
a company. The goals of EMS are to increase compliance to the
38
Permit requirement to arrive at zero injury. However, PMGL’s EMS
is typically backboned by an International Organization of
Standards (ISO14001) which helps to understand the EMS process
and improve the Environmental Management Plan (EMP) of the
company (PMGL) and also develop an Environmental Policy to guide
all workers and contractors.
The following are the operations PMGL’s EMS undertakes to ensure
that the requirement of ISO14001 and the Permit are complied by
all workers and contractors in discharging their duties;
Conducting inspections and audits at all working places or
departments (both mother company and contractors) to ensure
that the requirement of the permit is met or the right
standard operating procedures are followed in view of
protecting the environment.
Develop or come out with Environmental Management Programs
to educate all workers on working procedures and test their
competency.
Ensure that all Environmental Management Programs and
Environmental Management Plans are reviewed regularly.
39
DEVELOPMENT OF ENVIRONMENTAL MANAGEMENT PROGRAMMES
As required in the section 5.3 of the Permit, PMGL is obliged
to carry out Health, Safety and Environmental Training for all
employees. Records for attendance and tests on the training
are kept. The training sections include;
1. Environmental Awareness and Induction of new and annual
leave employees: Before an employee start to work, he or she
has to be trained on Health and Safety Policy, Job
Assessment, PPE usage, fire prevention and control. Likewise
is done for all permanent employees who resume from their
annual leave.
Environmental Awareness is not an individual concern but it
is a social movement regarding concerns for environmental
conservations and improvement of the health of the
environment. Having concern for the world or environment
around you is what we call environmental awareness. In view
of this, PMGL’s EMS train it employees on awareness programs
like The overall policies structure, and direction of the
company, The meaning and significance of PMGL’s
Environmental Policy, The importance of conformance with
PMGL’s environmental policy and with procedures (the EMS),
the danger of non-conformity to the environmental policy,
oil management procedures, air and water quality
40
managements, top- soil conservation, waste management and
others.
2. Environmental competency: At PMGL, all people who carry out
work onsite, or on behalf of the mine, receives appropriate
training and it is ensured that they are competent to
perform their tasks. This training is done to ensure the
effective performance of an individual’s responsibilities.
That is to know the quality of being adequately or well
qualified physically and intellectually. Examples of the
competency programs are waste management procedures (both
hazardous and domestic), used battery storage and disposal,
fuel and oil management, bush clearing and topsoil
management and others.
All these training programs are done;
To ensure that best safety practices are observed.
To create awareness of environmental risk associated
with hazardous waste.
To welcome all attendees to PMGL Mine Site.
To introduce participants to PMGL company and its
activities.
To outline expectation in terms of health, safety,
environmental, social and security performance.
To recognize the responsibilities of all personnel on
site.
41
CONDUCTION OF INSPECTIONS AT VARIOUS WORK PLACES
External auditors from EPA and sometimes Minerals Commission come
to PMGL site to conduct inspections to assess the performance of
the PMGL’S EMS, including activities of contractors and workers
whether work is done according to the requirement of the Permit
or not. Moreover, inspections are carried out to identify non
conformity and the required corrective actions, and assess need
for additional staff development and retraining.
Also, internal auditing is done to assess the performance and
competency of the workers in various departments. It is done to
also ensure that the requirement of the permit and ISO14001 is
adhered to. The EMS Section (EMS Coordinator) including the
Environmental Manager other environmental officers carry out this
internal audit. In case of any non-conformity, corrective and
preventive actions identified during the internal audit will be
prescribed. Below are some of the requirements or checklists of
internal auditors at PMGL during internal auditing;
Battery Storage Area
Well ventilated storage area.
“no naked light within 20m sign” posted.
Batteries stored upright and in single level only, not
stacked on top of each other.
Cell caps installed on batteries.
Storage area not overloaded with batteries.
42
Used batteries disposed of to authorized vendor only.
Storage area separated from storage areas for
chemicals, oil and fuel.
Battery acid drums clearly marked.
Fire extinguishers in place, up to date inspection
record, proper type.
Fuel Tanks
Tank in bunded area with volume of 110% of largest
tank.
“No Naked Light Within 20m” sign posted.
Fuel tank filling instruction signs posted.
Fire extinguisher of proper type present nearby with up
to date inspection record.
Spillage within bund cleaned.
Sump clean.
Oil trap cleaned daily (if applicable).
Valve to oil trap kept closed and locked (if
applicable).
Absorbent/cleaning materials available.
Tank clean and free of spillage on top.
MSDS for materials being stored nearby.
Supervisor’s and worker’s understanding of proper
storage, maintenance and cleanup procedures.
43
Mechanical/Electrical Workshops
MSDS sheets available nearby for all oil/fuel/chemical
products in use.
Absorbent materials available for spill/leak clean up.
Adequate number of uncontaminated waste barrels in
place, properly marked, covered with lid if open to
rain, and emptied regularly.
Proper separation of contaminated and uncontaminated
waste.
Concrete collection sumps clean and free of spillage.
Working areas bunded or trenched to capture spillage
and rainwater runoff.
Working areas connected to oil separator.
Oil Separator cleaned daily, free of contaminants.
Contaminated Materials List posted in widely visible
locations.
Emergency response procedures posted in widely visible
locations.
In addition to these and other checklists, pictures of any
unlawful or non-conformance works are taken. After the
inspection, the internal audit team will initiate an inspection
Report which points out the non-conformity and it Corrective
Action. The report is sent to the Department Heads who were
affected to know the effect of the non-conformity and correct it.
44
A non-conformity form will come in when the heads of departments
do not work on the corrective actions of the auditors.
EXAMPLE OF HOW INSPECTION REPORTS ARE DONE
Above is a non-conformance pictures taken at AMS during an
inspection on 7th August, 2013. Improper way of storing used
batteries. No fire extinguishers, overloaded storage, no posted
signs like “no naked light within 20m”.
Recommendation;
It should be orderly arranged without overloading them.
Fire extinguishers should be there.
Batteries stored upright and in single level only, not
stacked on top of each other.
45
A B
Above are pictures taken at AMS (B) and Total (B) during an
internal audit on 7th August, 2013.
A is disorderly arranged. It is arranged to the edge of the wall
of the bunded area. In case of spill, the hydrocarbon will
directly get into the environment. The drums can easily fall to
cause spillages.
Recommendation;
It should be orderly arranged.
It should be arranged 1m away from the wall of the
bunded area. This is to prevent any fuel from getting
onto the bare soil in case there is a spill.
46
Although B is arranged above the bare ground but is not in a
bunded area. In case of any spillage, the oil will easily get
into the soil.
Recommendation;
It should be in a bunded area.
In addition, one other thing I learnt at EMS is a disturbance
form. It is a form that is filled when anyone want to disturb or
destroy any land for a particular purpose. I studied that a land
is disturbed as and when needed for a particular purpose. But
before the disturbance, the individual carrying out the
disturbance has to fill a disturbance form at the EMS section.
The map and size of the land to be disturbed should be attached
to the form and signed by the Environmental Manager after the
individual has filled his or her part. The form is filed at EMS
section for future records.
In conclusion, PMGL‘s EMS ensures that all the requirements in
the Permit are adhered to in all workplaces of the company. They
also preach on how to prevent disturbances and control
environmental aspects to any part (air, soil water, flora, and
fauna) of the environment. They also make sure that all employees
are well trained and competent to discharge their duties through
induction, awareness, and competency programs
47
CHAPTER FIVE
THE REHABILITATION AND RE-VEGETATION SECTION
As required in the Section 5.1.13 of the Permit, PMGL is obliged
to address issues of rehabilitation during and after it
operations. To meet this requirement, the company is required to
develop and maintain a post closure land-use plan for the sites,
48
rehabilitate areas that are no longer required for the operations
of the mine, ensure that the mine closure meets legal
requirement, undertake rehabilitation practices that protect the
environment and public health, and monitor and manage
rehabilitated areas until the vegetation is self-sustaining and
reclamation objectives achieved.
In addition, in the Section 4.8 of the Permit, PMGL is also
required to restrict vegetation clearance to areas required for
operational activities, strip, stockpile appropriately and label
topsoil for future rehabilitation. This means that disturbing of
land is done as and when needed for an operation. The use of land
clearing Permit is to limit vegetation clearing on the mine site.
Topsoil is often the most important factor in the rehabilitation
process. At PMGL, the topsoil of all disturbed lands have been
stripped, stockpiled, and labeled according to where it was
stripped. The topsoil stockpiles are been used for rehabilitation
works. To prevent the topsoil stockpile from adverse weather
conditions or drying up, erosion and to loose it soil nutrient,
pueraria seeds is spread on them to make it moisturise and rich.
Pueraria also fix nitrogen into the soil.
Before a site is vegetated, re-sloping of deposited waste rock is
done to obtain the required slopes indicated in the plan. Design
of waste rock dumps is done using flat slope angles (20-30
degrees) to reduce erosion. The final land form must be
hydrologically compatible with the surrounding area. 20-30
49
degrees slope angles are used at PMGL. After that, Dumping and
spreading of oxide materials on the compacted waste rocks is
done. Topsoil is taken from a nearby stockpile and spread over
the oxide material. Oxide that is non-economical for milling will
be considered and environmental resource for capping of waste
dumps. The oxide material will be deposited on the rock and
spread to a suitable thickness based on the final land use
planned for the area. Oxide floors and compacted oxide should be
deeply ripped to ease the development of roots in the final
cover. Wherever possible, handling of oxide materials and topsoil
shall be planned for the favourable weather condition to reduce
over compaction and dust generation. All these earthworks would
be done by the mining department and supervised by the
environment department or rehabilitation officer.
Right after earthworks, rehabilitation starts. At PMGL, it starts
with grassing. This involves establishing an initial vegetative
cover to control soil erosion, which is usually planned to take
advantage of the early rains of the wet season. Re-vegetation is
initially done with species that will contribute most to the
stability and utilization of the ecosystem or farming system that
will be developed in the area. Initial Stabilization of slopes
may include Planting of Vetiver, Guinea, Brachiara and Citronella
grasses across the slope to serve as an erosion control
structures.
50
When the grasses has established, seedlings of plants (viable)
nursed at the rehabilitation nursery are transplanted.
Transplanting is done with planting charts of 70% local trees and
30% exotic trees in the rainy season. The exotic ones fix
nitrogen into the soil. Examples of plants transplanted are;
Local:
• Khaya ivorensis (mahogany)
• Picnantus angulensis (otie)
• Ceiba pentandra (onyina)
• Magnifera indica (mango), etc.
Exotic:
• Piper nigrum (pepper corn)
• Cedrela odorata (cedrela)
• Milletia milletia (milletia)
• Samanea samani (rain tree/monkey pod), etc.
Below are the pictures of the rehabilitation section nursery.
51
Maintenance of the rehabilitated areas is a basic requirement for
achieving productivity and the progression to the final ecosystem
of farming system. The following maintenance practices are
carried out;
• Regular weeding to rid farms of weeds and rodents;
• Tending to prevent competition for nutrients between weeds
and the plants;
• Application of fertilizer;
• Promptly repairing areas showing signs of erosion; and
• Period spraying and pruning of plants.
In conclusion, the rehabilitation section is obliged to ensure
that the land is restored to its natural structure after and
during the mine operations.
52
CHAPTER SIX
THE COMPLIANCE SECTION
Compliance can be defined as either a state of being in
accordance with established guidelines, specifications, or
legislation. Environmental compliance is the process of adhering
to environmental regulations in effect, environmental policies,
and requirements of Permits. In addition, environmental
compliance means conforming to environmental laws, regulations,
standards and other requirements.
The aim of the Environmental compliance section at PMGL is to
ensure that all employees or workers discharge their
responsibilities according to the requirement of the Permits
(EPA, MinCOM, WRC, and others) and the environmental policies.
In the section 3.7 and 4.2 of the EPA Permit, PMGL can apply for
the renewal of their permit. Renewal of permit is done when the
existing one is about outdating. If the company wants to make
changes in its environmental monitoring point locations or
changes in pit and waste dump designs, the company has to notify
53
EPA of such changes, seek approval before implementation. This is
one of the duties of the Compliance section.
Below are some of the activities carried out in this section;
Timely submission of compliance reports to MinCOM, EPA and
WRC.
Waste segregation and management across site.
Dust suppression across site and catchment communities.
Update of standard operating procedures and policies.
Incident investigation and corrective actions.
Follow on community complains.
DUST SUPRESSION ACROSS SITE AND CATCHMENT COMMUNITIES
PMGL’s Environmental Management Plan on Air Quality management to
suppress dust generation is as follows;
The use of water tankers to water haul and access roads
to the mine and all catchment communities.
Mounting of regular speed checks and slow down signs
along all access roads to the mine and neighboring
communities for vehicles to minimize dust in populated
areas and in these communities.
Monitoring of Total Suspended Particles (TSP) and
Particulate Matter (PM10) in the catchment communities.
54
PMGL has put all these measures in place to ensure that dust
generated from their operations do not have impact on the fauna
and flora, air, and water in the environment.
WASTE SEGREGATION AND MANAGEMENT ACROSS SITE
In the section 5.2 of the EPA permit, PMGL is obliged to
segregate it solid waste generated onsite before disposing. It is
to this purpose that the company has placed separate waste bins
(domestic waste bin, hazardous waste bin, and plastic waste bins)
at vantage points. Inspections are also conducted to determine
when these bins require replacement. Non-hazardous wastes are
disposed in a land fill site constructed on site. In the same
vein, hazardous wastes are also disposed of in a HDPE and clay
lined land fill. All the landfill sites on site are inspected by
the compliance section regularly to ensure that they are properly
maintained.
For the effective compliance of waste management procedures on
site, employees are trained about that during induction or
awareness training periods. In the training sections, all
personnel, including contractors are taught on how waste are
placed into the allocated containers clearly marked on site.
Also, workers are trained for management of on-site landfill and
management of all new recruits on waste management plan during
induction.
55
FOLLOW ON COMMUNITY COMPLAINS
If catchment communities complain that the operations of the mine
are adversely affecting their environment, it is the
responsibility of the Compliance section to investigate the
issue. For instance, when a community complain that their source
of drinking water is being polluted, this section would have to
investigate whether the mine is causing that or not. With this
complain, certain parameters like TDS, TSS, DO, BOD, and others
of that water body will be analyzed. The results will be compared
with the current monthly or weekly water analysis of that water
body. If the mining is causing that, corrective actions will be
taken. All these investigations are done because some illegal
mining (galamsey) operations cause or chemicals used by farmers
around that water body can cause that. This is done for all other
complains.
On the whole this section ensures that all the requirements of
the Permits are obliged by all and sundry in the company.
56
REFERENCES
I. SOP’s of all the sections in PMGL’s Environmental
Department.
II. www.chesapeakebay.net/discovery/bayecosystem/dissolvedoxygen
III. www.lenntech.com/turbidity.htm
IV. www.state.ky.us/nrepc/water/wcpdo.htm
V. www.lenntech.com/why_the_oxygen_dissolved_is_important.htm
VI. www.ret.gov.au/resources/Documents/LPSDP/BPEMRehab.pdf
VII. www.en.wikipedia.org/wiki/Environmental_compliance
VIII. www.praxiom.com/iso-14001-definitions.htm
57