Upload
port
View
0
Download
0
Embed Size (px)
Citation preview
UNIT 512THESIS
Msc HISTORIC BUILDING CONSERVATIONSTUDENT no. 48554111th SEPTEMBER 2014
Restoration, Preservation and the Developmentof Fire Safety Legislation in British Theatres.
Key Words: Theatre, Fire, Restoration, Fire Safety Legislation, New Theatre Royal
i
AUTHOR DECLARATION
UNIT 512/THESIS
RESTORATION, PRESERVATION AND THE DEVELOPMENT OF FIRE SAFETY LEGISLATION IN BRITISH THEATRES
11th SEPTEMBER 2014
I affirm that this Assignment, together with any supporting artefact, is offered for assessment as my original and unaidedwork, except insofar as any advice and/or assistance from any other person in preparing it, and any quotation used from written sources are dully and appropriately acknowledged.
ii
Olivia Mayell
11th September 2014
ACKNOWELEDGEMENTS
I would like to thank my Masters tutor Dr Karen Fielder for her support and constant positivity throughout the year. She
iii
always had the answers and helped me over every obstacle in myway.
With out the New Theatre Royal team I would not have had a paper, or the inspiration and drive for most of the year. I particularly must thank Dom Hart for always being willing to answer every question and offering to share all his knowledge and insights.
ABSTRACT
iv
Although fires in Britain's theatres are less common than theywere in the 19th and early 20th century, they still present the same problem, what does one do with a theatre gutted by fire? This paper researches into the common courses of action after a theatre has been damages by fire and weighs up the advantages and disadvantages of each. It also produces a clearlinear timeline of the development of fire safety legislation in relation to British theatres and links real fire incidents into why some of the legislation was written. Using New Theatre Royal, Southsea, as a case study the paper presents a live restoration and rebuild project.
v
Contents
Authors Declaration ii
Acknowledgments iii
Abstract iv
Contents v
List of Illustrations vi
Introduction 1
Chapter One Restoration and Preservation 5
Restoration 6
Preservation 8
After a Fire 10
Chapter Two Fire Safety Development in British Theatres
16Manual of Safety Requirements in Theatres and Other Places of
Entertainment 19
Post 1940 22
Chapter Three New Theatre Royal 26
The Restoration of the New Theatre Royal 30
Restored and Reinstated 31
Conclusion 39
vi
Bibliography 44
Sources of Illustrations 48
Appendices 49
List of Illustrations
Figure 1 Notre Dame, prior to restoration
Figure 2 Notre Dame, after restoration
Figure 3 Theatre Royal, Norwich, 1930's
Figure 4 Theatre Royal, Norwich, 1935
Figure 5 Volunteers digging out orchestra pit
Figure 6 Current Box Office
Figure 7 Original brass rods on each step
Figure 8 Brass rods now missing from stairs
Figure 9 Orchestra Rail – Edwin Showell & Co Trade Catalogue
[from: theatresearch archive]
Figure 10 NTR three tier auditorium
Figure 11 Matcham box frontages
Figure 12 Pit bar ceiling
Figure 13 Pit bar, Victorian tiles
Figure 14 Briggs' Panic Bar - Advertisement from an Edwin
Showell‟s 1890s Trade Catalogue
[from: theatresearch archive]
vii
Considering the beauty and quiet mystery of our historic
theatres the idea of losing such things to the ravages of a
fire is unthinkable. This was however, once a common
occurrence and although safety regulations have developed to
prevent this from happening so often, a study in 1982 by
Curtains!!! or A New Life for Old Theatres revealed the bleak reality of
our historic theatres. The territory of research that this
paper is looking at overall is British Theatre building,
specifically looking at fire in these buildings and how it
affects its future. Previous research into Britain's theatres
is mostly carried out by The Theatre Trust, who hold archives
on the history of over 1400 theatres in Britain (Theatre
Trust, 2014) and also publish a quarterly magazine discussing
developments, reports and articles.
The aim of this paper is to research two main points,
both surrounding British historic theatres. The first is the
process of what can be done with a theatre that has suffered
fire damage by considering the philosophical approaches to
restoration and preservation and rationalising this in a
practical approach. The second is Britain's fire safety
regulations in relation to theatres. When did legislation
concerning theatres first begin to emerge and what was the
2
reasoning behind the developing legislation? Were these stable
door legislations or did they simply evolve from other
building regulations? A case study will also be researched at
the end of this paper, the New Theatre Royal in Southsea,
Portsmouth. This theatre was recently awarded a Heritage
Lottery Fund grant that is now being used, in conjunction with
funding from the University of Portsmouth, to rebuild a part
of the theatre that burnt down, add a large new addition and
restore the interior of the historic theatre.
This paper hopes to uncover a linear evolution around
theatre legislation and the reasons behind why the regulations
have evolved in the way they have. Although databases such as
Fire.Net have tried to create an overall development of fire
safety in British legislation, there is no specific look at
types of buildings such as theatres or how and why these
regulations came into place. By exploring each major piece of
legislation that relates to theatres, the expectation is to
uncover the relative thinking of those in charge and if
British officials are learning from past events. Although
there is plenty of literature surrounding the original
philosophical reasoning of preservation of buildings, there is
little exploring the beginnings of restoration. There is also
no solid research into what happens to historic theatres after
they have been damaged by fire, possibly because it is now
less likely for an event like this to occur and cause the same
level of damage fires once did. However this research expects
to cover this, while also exploring the advantages and
disadvantages of options such as rebuilding a pastiche, or
3
designing a new theatre. Lastly by choosing a case study that
is currently a live project, the New Theatre Royal, the
research into the projects progress and decisions will be the
first to be written and will allow for further study after the
project's completion. It is a unique project with two strong
but very different elements and while only one, restoration,
will be covered in this paper, the foundations will be laid
for the possibility of further research.
The research for this paper will be gathered through
secondary sources from online databases, such as the Theatre
Trust and Fire.Net but also through printed sources including,
but certainly not limited to; The Seven Lamps of Architecture, Uppark
Restored and Frank Matcham, Theatre Architect. Portsmouth City Councils
Records Office also holds a large amount of information on the
New Theatre Royal, however most research into the case study
will be primary, gathered from site visits over a 6 month
period, interviews and conversations with members of the
Theatre's staff and photographs of the developing project.
The layout of this paper will follow a similar structure
to the one above, beginning with the study into the
philosophical schools of restoration and preservation leading
into what happens after a theatre fire using the theory to
explain the advantages and disadvantages. After this will be
the chapter laying out and exploring Britain's fire safety
legislation and regulations, followed by the case study on
NTR, introducing a brief history of the building, the new
project, what is being restored/reinstated and what is new to
the historic theatre.
4
"Whatever is good in its kinde out to be preserved in respect for antiguity, as well asour present advantage, for destruction can be profitable to none but such as live by
it" -Nicholas Hawksmoor, 17 Feb 1715
Restoration
The origins of restoration of historic buildings came
from the original growing need to preserve. Up until the end
of the eighteenth century there was only one wholly
encapsulating idea to preserve historic buildings, however the
practical way in which this was done began to drift in two
very different directions. By the mid nineteenth century there
7
were two clear and different philosophical schools of thought,
to restore buildings in their most "perfect" form or to
preserve what was inherited from past generations. The most
notable original restorers were the leading church architects
of the 19th century which include Eugène-Emanel Viollet-le-Duc
and Sir George Gilbert Scott (Earl, 1996), both of whom were
criticised as vandals of their time. In their eyes,
preservation was deemed not enough to save many of the
eighteenth century churches, especially in Britain, that had
been left to rot and decay. Preservation here, as in so many
cases, had failed to work and so a more active approach had to
be taken in order to save the buildings from total ruin.
Although restoration is now seen as a more positive thing for
historic buildings than it was in the eighteenth and
nineteenth centuries, care must still be taken as to the
extent of restoration and not to strip the building of its
historical fabric and identity.
As argued by Rowell and Robinson in their study on the
restoration of Uppark " It is difficult to argue that a
twentieth-century copy of an eighteenth-century ceiling is
different in kind from, say, a Victorian renewal of an
eighteenth-century red flock paper. In a slowly evolving and
changing entity..later decoration and restoration work is
surely as much a part of the history of the building as
anything that went before".
Sir George Gilbert Scott and Viollet-le-Duc
8
At its height between 1840 and 1873, over 7,000 churches
had been restored all over the British Isles. Two of the most
prolific architects involved in this surge in restoration, one
in Britain, the other on the continent were Scott (1811-78)
and Viollet-le-Duc (1814-79). Although they were known for
removing later features of notable architecture and
constructing their own, often in the Gothic Revival style the
two spearheaded the campaign for restoration. Troubled and
deeply resented for the best part of a century, without their
determination, restoration may never have become what it is
today, a positive and controlled way of returning the decayed
remnants of our built history back to what it once was.
It is forgotten by Purists that these architects and others
like them were restoring these buildings to prevent total
loss, and the conditions they created then are now seen as the
admirable norm (Earl,1996,p.57).
Ely Cathedral, Cambridgeshire
Due to several rebuilds by medieval craftsmen, problems
in the structure of Ely Cathedral meant that by the Victorian
era much work was needed if the cathedral was to survive. The
repairs and additions made by Scott were extensive, including
huge repairs to the West tower, the moving of the choir stalls
into their current position and the total rebuild of the
Chapel of St.
Catherine near the
west entrance
(Pevsner,1970).
9
Although he repeated the use of stone and lime mortar, Scott
also introduced new materials such as new gilded iron,
Victorian clay tiles and stained glass, something that now
would not be done in a restoration project.
Notre-Dame, Paris
Viollet-le-Duc studied in depth the philosophy behind the
Gothic style rationalising it as a type of skeletal form
designed to bear the weight of tall vaults. He used this
understanding to inform his restoration work of the Gothic
churches in Paris. His Notre Dame project, in 1844, was the
first to see this
applied to his
physical work. His
restoration neither
revived its
twentieth-century
appearance nor
restored the building
back to its original
form. Instead it became a re-imagined form from Viollet-le-
Duc's own head, a form of the building that had never existed
before.
Preservation
The popularity of Architectural preservation began
officially in the eighteenth century as a response to the
10
Figure 2 Notre Dame, after restoration
Figure 1 Notre Dame, prior to restoration
growing modernism movement. The leading art critic of the
nineteenth century John Ruskin, first stood up and voiced his
opinion on what he saw as mindless and irreversible
destruction, however it was not until William Morris formed
the SPAB that the preservation school of thought began to make
its mark.
The Seven Lamps of Architecture
One of the first pieces of literature written concerning
the negative effect of restoration was by Ruskin in 1849.
Widely considered the father of anti restoration Ruskin firmly
believed that to restore was to destroy, buildings were not
something to be repaired but to be cared for, thus first
introducing the idea of "stewardship" or "trusteeship". Ruskin
conveys the idea that buildings partly belong to those who
built it and partly to every generation to come, and so we are
to care for them until the time comes to part with them. The
passing down or passing on of a building is something to be
honoured and treasured, the next generation has the same right
to a building that we have had and therefore we must pass them
on in the condition that we were given them.
"For indeed, the greatest glory of a building is not in
its stones, nor in its gold. Its glory is in its Age...we feel
in the walls that have long been washed by the passing waves
of humanity....the decline and birth of dynasties, and the
changing of the face of the earth.." (Ruskin, 1849,p.243.) He
poetically describes the way in which buildings stand over us,
11
watching and withstanding, only to be changed by humanity
naturally and over a lengthy period of time. Ruskin describes
at length the idea of memories being attached to buildings,
that they hold the echoes of the past. By changing the fabric
of the building so that it could no longer be recognisable to
those who first experienced it, then those memories must
surely disappear with the material, a brick or door in a
Victorian house can look the same when replaced but it does
not experience what its predecessor did. Within this same
chapter Ruskin lays out his opinion on restoration, "It means
the total destruction which a building can suffer: a
destruction out of which no remnants can be gathered.."
(Ruskin,1849.p.252) a blunt and clear statement that resonates
with many others throughout history. Later he explains this
opinion "that spirit which is given only by the hand and eye
of the workman, never can be recalled" (Ruskin,1849,p.253)
meaning that when new work is done on a building to "restore"
it a new spirit is imprinted on to the building but the old is
lost. Although his opinion is brutal it is not without
reasoning when he goes on to explain his belief that copying
architecture is utterly impossible. To copy a historic wall
that has experienced many centuries of wear resulting in a
loss of depth or colour is counterproductive, either one
copies the wall but attempts to restore, in which case this is
a speculation on what was once there, or one copies exactly
what is there now and in that case what has been achieved, why
is the copy better than the original?
12
SPAB
The Society for the Protection of Ancient Buildings
(SPAB) is an organisation that since its conception in 1877
has been against the destructive restoration of historic
buildings. Set up by William Morris and other members of the
Pre-Raphaelite brotherhood in the wake of a deep concern that
the historic fabric of buildings was being scraped away by the
overzealous attempts of architects to restore them
(SPAB,2009). The SPAB manifesto, as with the Seven Lamps of
Architecture, does not dance around the subject of restoration
but pounces upon it and rips it apart labelling it "a feeble
and lifeless forgery". This importance of the document goes
beyond the contents but to its physical form. This was the
first time the basic ideals that guide modern conservation
principles had been set down. The modern day society still
adheres to these beliefs with their principal concern being
the nature of restoration and repair works because of the
potentially damaging effect they can have. They encourage the
mending of historic fabric and state on their website that
"Old buildings cannot be preserved by making them new."
The problem with SPAB teachings arise when studying
a building that has reached beyond the point of simple repair
work and the theory of preservation will no longer save it. If
we are to comply with their guidelines then these buildings
will be lost, as to interfere with their fate would go against
the manifesto. But what of the importance of these buildings,
they could be the last of their kind and therefore hugely
13
significant on a national scale, or important historically on
a local scale, how does one justify the loss of said buildings
simply because of an idea not to interfere.
After a Fire
There are three main options available to those who wish
to rebuild a theatre after it has been destroyed by fire,
although thankfully this is a much rarer occurrence than it
once was. The decision of which course of action to take is
greatly influenced by how damaged the building has been and
how much of the original is left. For the chosen case study
New Theatre Royal, which is studied in greater depth in
chapter three, much time had passed since the fire which
destroyed all of its backstage, so a modern part rebuild and
internal restoration plan was the obvious choice for this
Grade II listed theatre. Complete new build
The most likely result
for a theatre that has caught
fire has sadly always been
either total destruction or a
gutted shell of what once was.
For these theatres and the
people involved in their care
and stewardship, the decision is often a complete modern
rebuild, to reflect the current times and not to try and
14
Figure 3 Theatre Royal, Norwich. 1930's
replace what ha s been lost. An example of this was the fire
in the Theatre Royal in Norwich in 1934, which gutted the
entrie building and left it structurally unsafe, unable to be
saved. The decision was made to completely rebuild the theatre
as a new faience-front, Art Deco style building,(fig.4) a
architectural style that was at the height of popularity
during the 1930's.
The benefits of a complete modern
rebuild are down to the opportunity in
internally redesign, be that a more
spacious theatre with a more
agreeable, open feel, or the chance to
employ the most modern theatre
technology. Compare trying to add this
new technology in to an existing
historical theatre, where there are
many restrictions on modifications due
to grade listings. Having the opportunity to create this all
from new, down to lighting and sound is extremely beneficial,
both financially and in the prospected life of the theatre. As
well as internally, the external appearance of the theatre is
just as important in a modern design, owing to its influence
in its local context. The original context or streetscape may
have totally changed around the theatre and so a new build has
the ability to be designed to fit more comfortably into its
new and current surroundings.
On the other hand the negatives of a modern rebuild
revolve around the loss and impact on the public who knew and
15
Figure 4 Theatre Royal,
used the old theatre. Although the original fabric will have
already been lost in the fire, the visual aspects of losing
the theatre if it is not to be rebuilt in the same fashion
have a lasting impact on the retelling of the past. The
history of the building that once stood can be retold to a
certain degree but there is something lasting about seeing
what one is learning about in order to fully understand it. If
said theatre was the last of its kind, a greater sense of loss
will be associated with it compared to a twentieth century
terraced house burning down. Historic buildings, including
theatres, are irreplaceable pieces of history that are not
repeated or mass produced. Statistics presented by TheatreSearch
state that a 1982 survey showed 85% of the 1000 Theatre
Royals, Grands, Alhambras and Empires had been destroyed or
irretrievably altered and only a tenth are still in use as
theatres. Another shock statistic to discourage the idea of
complete demolition from TheatreSearch is the number of remaining
listed theatres; only ten Grade I listed theatres and just 44
remaining of Grade II* listed description.
(TheatreSearch,2011. Mackintosh & Sell, 1982)
Partial Rebuild
In several cases in the history of British theatres some
have managed to escape only partly damaged, mostly thanks to
the efficiency of the fire protection in place and the quick
thinking of the theatres staff. Examples of these included New
Theatre Royal, Southsea and Theatre Royal, Drury Lane, both of
16
which had fires which started backstage and fire safety
curtains that dropped, saving the rest of the theatre from any
damage.
The advantages of partially rebuilding a theatre depend
upon the part of the theatre being rebuilt. In most cases
theatre fires start backstage, in which case there is
potential for modern, technical improvements. As with a
complete modern rebuild, a huge advantage of rebuilding this
particular section of a theatre is the chance to improve the
technical performance that can be achieved on stage by
enlarging fly towers, lifts and mechanisms and creating a much
more spacious backstage that will positively impact on the
performance of the building. Building upon this point the
potential of added space, depending on the amount of
surrounding land, can lead to increases in profits due to
interests of bigger shows and theatre companies. In fact the
SPAB at one time (now deleted) added a note to their manifesto
in 1924 in favour of this type of modern addition explaining
that "A modest addition is not opposed to the principles of
the Society provided....that the new work is in the natural
manner of today, subordinate to the old and not a reproduction
of any past style."
However the disadvantages of rebuilding part of a theatre
are many and concentrate mainly on difficulty with design and
harmony. Firstly a historic theatre is likely to be listed
which throws into light how much can be done to the building;
the argument to build additional space onto a historic
building must be a sturdy and persuasive one. The design of
17
this added piece of architecture splits those concerned into
two camps, a stark modern contrast so as to show the time
difference between the old and new, which could try so hard to
differ from the original that the harmony of the finished
building could turn into a competition between old and new. On
the side a subtle design just different enough to acknowledge
the distinction which could threaten to be so successful that
the lines between old and new are blurred and disturb any
historical record of the theatre. As explained "..no matter
how carefully designed and executed, must to some degree
interfere with the appreciation of the thing preserved."(Earl,
1996,p.113)
Rebuild/Restore
The most famous of theatres in British history was, and
thanks to a twenty-three year long project, still is the Globe
Theatre. Its reconstruction began in 1993 and can only be
described as painstakingly accurate. After three and a half
years of construction the Globe was finished, arguably the
most important and successful theatre reconstruction project
ever completed. This type of project is extreme and requires
complete faith and dedication to the original theatre. As well
as complete rebuilds, internal rebuilds and/or restorations
are also commonly necessary when confronted with a theatre
that has been gutted internally. The Savoy Theatre in London
is an example of this as in 1990 while restoring the theatre
the inside was completely gutted by a fire. Thankfully the
18
original drawings survived and an accurate restoration was
completed in three years.
There are several advantages to rebuilding and/or
restoring a theatre back to its original appearance. The
theoretical approach behind restoration is to bring a building
back to its former, more desirable state (Earl, 1996). This is
certainly true in public buildings such as theatres as the
memories of those who know it are much easier to recollect in
a theatre; that appears the same, once this is gone those
memories fade and distort without something to anchor them to.
Another reason is due to the value and importance of the
theatre, the complete loss of any historical theatre is
irreversible, architecturally, historically and socially .
Lastly rebuilding or restoring a theatre using its original
materials requires the skills of craftsmen, these are now few
and far between and so the importance of supporting them is
invaluable, if these building traditions are to continue. A
report published by English Heritage in 2005, estimated that
the built heritage workforce would have to rise by 3,420 in
the following 12 months to almost 90,000. The lessening
interest in this field of construction is an area that must be
addressed, by working on local buildings, interest in learning
about these skills may begin to rise.
Based upon a Puritanism belief any such attempt to
rebuild a historic building would be a "pastiche" or a "fake".
The belief that "If something is damaged or destroyed, they
consider that it should not be repaired or copied, but swept
away" (Rowell&Robinson, 1996,p.37) is shared by many and to
19
oppose this could create strong feelings that may cause
problems for a rebuild project. Another problem that groups
such as SPAB use as an argument against such a project is the
evidence of what once was. Following the total loss of a
building, evidence for reconstruction may be very hard to come
by, many theatres store the history of the building including
plans in the theatre itself. After destruction any attempt to
rebuild the theatre is seen as speculation on what was once
there, the argument being if one cannot rebuild it exactly,
then why rebuild at all.
When faced with a damaged historic theatre the decision
as to which philosophical school of thought is most suitable
appears overwhelming and impossible. The draw of preservation
is its clear: arguments by famous architects and the creation
of a society with the once sole purpose of preventing the
destruction of restoration. Although it was once the more
widely accepted school of thought this may well have changed
in more recent years. The rapid decay in our historic built
environment has meant that the efforts of just preservation
are often no longer enough. Historic buildings damaged by
events such as fires are sometimes the last remaining example
of an architect's work or style of architecture and therefore
the loss of such a building is hard to justify. Hence
restoration is becoming a more common and therefore more
developed way of caring for a historic building.
The likelihood of a destructive fire within our historic
theatres is thankfully becoming a much rarer event, however
20
the decision on what will happen to the building after this is
still as complex, if not more so. The public attachment to
buildings such as these means that by demolishing the remains
of a theatre, one could be faced with public anger. Therefore
the options available must be carefully weighed up,
considering the advantages and disadvantages previously
discussed. Unfortunately decisions such as these are never
simple and the financial benefits of a decision such as this
normally over rule any other factors. As the famous Greek
tragedian Sophocles wrote in his tragedy Antigone, "Surely
there never was so evil a thing as money, which maketh cities
into ruinous heaps, and banisheth men from their houses, and
turneth their thoughts from good unto evil."
21
Chapter TwoFire Safety Development in British Theatres
"Man is the only creature that dares to light a fire and live with it. The reason? Because he alone has learn to put it out." Henry Jack Vandyke Jr
22
The development of fire safety in Britain is complex and
was slow to progress into what it is today. The threat of fire
in theatres was present from the early 19th century when the
use of naked gas flames was introduced into all British
theatres. The use of gas lighting in theatres had become a
potent sign of technological advances; however it was not
without its dangers. From the beginning of the 1800's to the
mid 1900's a number of major fires caused the deaths of over
1000 people. Called for by a Select Committee in 1886, Captain
Shaw of the London Fire Brigade listed fifty fires in London's
Theatres that had occurred in the previous thirty-three years
as well as twenty-six in the provinces (Booth,1995). These
fires resulted in "stable door" legislation as a result of
public enquiries and a home office investigation.
The first step taken in the prevention of fires in
theatres was after the old Drury Lane Theatre was demolished
to make way for a more modern design that incorporated new
fire prevention innovations. The most essential of these was
the introduction of the iron safety curtain, which later
became mandatory in all large theatres in Britain, and a large
water tank incorporated into the ceiling of the auditorium.
Despite these innovations the theatre caught fire in 1809,
23
caused it is believed, by the gas lighting, which was the
cause of almost all theatre fires until electric lighting was
introduced (Wright, 2007). Although fire resistant scenery
was introduced along with these, the curtain and upholstery
were extremely flammable and onstage lighting was positioned
too close to most stage curtains.
The Exeter Theatre Royal fire in 1887 is the most studied
and worst theatre fire in British history due to the death of
186 people. It was the second theatre fire that caused
considerable change within the legislation to protect
audiences and theatres. It brought to light the lack of safe
routes out of theatres in case of a fire and also the
overcrowding that often occurred in stalls of theatres. Over
capacity in theatres was a danger in its self but paired with
a lack of emergency exit routes proved fatal. In the stalls of
the Theatre Royal the exits were located at the back of the
theatre, those seated in the front rows became trapped between
the fire and a mass of people trying to escape. Most of the
dead were seated on the upper gallery where there was but a
single exit (Anderson, 2002) and panic caused many of the
audience members to throw themselves out of the windows onto
the street below. This accident led to a report which aided
in the passage of Section 36 of the Public Health Acts
Amendment Act of 1890 which outlines that "Every building
which, after the adoption of this part of this Act in any
urban district, is used as a place of public resort, shall, to
the satisfaction of the urban authority, be substantially
constructed and supplied with ample, safe, and convenient
24
means of ingress and egress for the use of the public, regard
being had to the purposes for which such building is intended
to be used, and to the number of persons likely to be
assembled at any one time therein". This was a positive
development in the fire safety of British theatres; it was the
first acknowledgement that fire exits were imperative to
saving lives in the event of a fire and was the first
government act that required London and other urban Theatres
to have means of escape that met a certain standard. These
standards were however set very low and separate councils were
not required to comply. A separate bill introduced to allow
county councils the power to engage inspectors and insist on
fire escapes and fire alarms was not passed, seeming to
suggest that the main focus was inner cities, and theatres in
other areas of the country were not seen as at risk or as
important.
In 1905 London County Council was given powers to
facilitate means of escape through the London Buildings Act
(Amendment) Act. This built upon a previous act from 1894;
however it now laid out what was accepted as "proper means of
escape". Two problems immediately arise from reading through
the act its self, the first was the act made it very clear
that it was for London only. It is correct that theatre fires
at the time were far more common in London than anywhere else
in the country but it is not to say that they did not occur in
any other city. In fact those fires during the 19th century
and early 20th century that led to deaths or complete
destruction of buildings were located in cities outside of the
25
capital. The second problem of the 1905 act was that it was to
be enforced upon "new buildings" which was defined within the
act as a building that was started after the commencement of
the act on the 1st January. Therefore any building already
standing or one which had began to be constructed before the
act commenced did not have to conform to this act, no means of
escape was necessary. The act did include a new schedule of
fire-resisting materials which was the first time a list of
this kind was available.
A fire in 1911 dictated the evacuation time in all public
buildings including offices, right up until modern day. This
fire was at the Empire Palace Theatre in Edinburgh. The French
illusionist, The Great Lafayette was halfway through his
performance when a lamp at the back of the stage caught fire
and set the whole stage alight. During this time it was
traditional for the orchestra to play the National Anthem
during breaks between performances. On realising that they
were in danger, the audience made a rush for the doors but the
threat of a stampede was believed to have been prevented by
the playing of the National Anthem by the orchestra. By the
time they had finished playing, which was 2.5 minutes, the
whole audience of about 3000 had been safely evacuated from
the building (Stollard,1991). On studying the fire precautions
that the theatre had in place it was a coincidence that
playing the National Anthem allowed the safe escape and not
that it kept the audience calm. The Empire Palace Theatre had
been built with ample exits from the building that were
designed to allow full escape in three minutes (Fernandez,
26
2011). The theatre was also equipped with a mandatory fire
safety curtain, which was lowered as soon as the outbreak of
the fire was discovered, however it jammed. The employees of
the theatre had been trained by the London fire department and
practised monthly fire drills, 10 years previously this would
never have been done. Through this training they knew to use
the fire extinguishing equipment and water to put out the
flames on the curtain. Altogether, this had so far been the
most competent reaction to a fire in a theatre that had ever
occurred and the quick reactions and well planned fire exits
had no doubt saved the lives of the audience members.
Manual of Safety Requirements in Theatres and Other Places of
Entertainment
As a result of several very public theatre fires in
Britain, the Home Office introduced its "Manual of Safety
requirements in theatres and other places of public
entertainment" in 1934. This manual was split up into sections
that focused on objects/areas within a theatre and places of
public entertainment that required special attention when it
came to fire prevention. The introduction states that
"although in some of the larger towns considerable attention
has been given...other areas where...public performances are
given in buildings which do not afford the necessary
protection against fire"(p.1) As mentioned before, the London
Buildings Act (Amendment) Act had really only influenced
theatres in London and here it was recognised that other
27
cities were not up to similar standards. From the beginning,
the manual highlights nine fires that directly influenced the
creation of the document and that every precaution advised is
a direct result of lessons learnt by one of the following
disasters: -Ring Theatre Vienna where 620-850 people died (1881)
-Exeter fire where 186 people died (1887)
-Paris Charity Bazaar where 124 died (1897)
-The Iroquois Theatre Chicago where 566 people died (1903)
-The Empire Palace Theatre Edinburgh (1911)
-The Grand Assembly Rooms Leeds (1923);
-Drumcollogher Co Limerick where 50 people died out of a total
of 150 (1926)
-The Glen Cinema Paisley where 70 children were suffocated and
crushed (1929)
-Coventry (1931)
Each of the fires in which people died led to either
experiments that increased the knowledge of fire safety areas
(Vienna, value of roof vents and different types of safety
curtains) or resulted in complete legislation overhauls
(Exeter, Iroquios, Paisley and Paris). Those fires that
actually resulted in no deaths were mentioned because the home
office believed that thanks to "the steadiness and courage of
the audience, aided in many cases by praiseworthy action on
the part of management and staff"(p.4) the prevention of any
loss of life was worth mentioning. This can be analysed as
28
Z x Floor Area in Square feetA= E x B x C x D
either an increase in training and education on how to prevent
fires, how to fight them (Empire Palace and Grand Assembly) or
the understanding that everyone would escape unhurt if they
just remained calm and left the building one at a time (Empire
Palace and Coventry).
Although proper means of escape had been touched upon
before in the London Buildings Act (Amendment) Act they had
never been set out in such terms until the manual. Due to the
lessons learned from the Exeter Theatre Fire the manual set
out a formula to calculate the total width of exits required
from each portion of a building. The value of each can be
found in Appendix A
A theatre could have all the fire exits that were required of
it, but as proved by the fire in the Paris Bazaar and the
Iroquois Theatre, without proper signage, these escape routes
would be invisible in the panic of fire. By using fire exits,
audiences can be trained to use all exits not just the main
entrance, as by using just the main route all calculations as
to the time of clearing become useless. On a purely
psychological level one cannot over estimate the importance of
well located fire exits to keep an audience feeling secure and
calm in the event of a fire.
The Manual introduced the importance of the route of
escape for the first time. This highlighted the danger of
29
moveable seats and stated that all seats should be fixed to
the ground with no less than 12 inches between the rows.
Gangways were noted as an important part of the route of
escape and so the width was set down as a minimum of 44
inches, although this was to be for new builds only, which
begins to bring into question the safety of the existing
buildings and why these strict new guidelines were not the
same. As a result of a fire in Laurier Palace Theatre,
Montreal in 1927 and the death of 80 people the width of
escape routes had to be the same the entire way including
corridors and stairways. The final and arguably most important
part to these escape route were the fire doors, which up until
the report was written had no standard codes or requirements.
The escape doors in the case of Iroquois were locked from the
outside and could not be opened from the inside, a point which
is made clear in the report could not happen again. Many
designers and builders had begun to design fire doors with
ways of opening them from the inside quickly.
The second important section within this manual was "Part
V" p.40, on fire prevention including the fire curtains,
drenchers and roof vents, all features that became mandatory
for larger theatres. After the fire in Vienna, experiments
began on different types and grades of fire safety curtains,
depending on the size and age of the theatre. The most common
at the time that are described within the report were rigid
one, two and three piece curtains. The grade of the curtain
required depended upon which class the theatre was given and
this class depended on the seating capacity and overall size
30
of the auditorium. (Appendix B) As well as specification on
the type of curtain and the material it should be made from,
the manual also included that there must be no scenery
obstructions such as at Iroquois, where an on stage spotlight
blocked the dropping of the safety curtain. Finally there
could not be any delay between the discovery of a fire and the
dropping of the curtain, something that today seems
unthinkable however, in several cases in the 1900's the delay
of the fire curtain being dropped led to disasters such as in
Exeter. The value of drenches over these safety curtains was
seen as immeasurable, with evidence from the Empire Palace
theatre when the staff wetted the curtain themselves to save
the audience. Modern theatres are not required to have
drenchers with their safety curtains as the quality of modern
day fire safety curtains is much greater than their Victorian
counter parts, thanks greatly to the early developments in
Vienna. In modern day health and safety, particular attention
is paid to smoke inhalation as several studies, including one
by John R. Hall, Jr, written in 2011 in which he states "As of
1999 and later years, the smoke inhalation to burns ratio has
been about 2-to-1", show that smoke inhalation is more likely
to be a cause of death. Although this was not so much the case
in the 1900's as poorly chosen building materials and fire
exits caused more deaths by burns, a large number of the
deaths in Exeter were caused by people choking to death in the
gallery because of the smoke. As with the safety curtains the
types of roof vent that the report deemed necessary were split
into categories depending on the capacity. (Appendix C)
31
The 1934 manual was the largest and most detailed that
had ever been written and fire safety regulations today take
many of their major points from it. By studying the most
devastating fires, those responsible for the new legislation
could learn from the mistakes made and the most common factors
that led to deaths in these theatres. This manual does not
however attempt to talk about the structural issues that led
to many theatre fires such as building materials and the
prevention of a building collapsing due to fire damage.
Post 1940
The safety of the structure of theatres was first
reviewed by a joint committee of the building research board
and the fire offices committee (FOC) in 1946 when they
released their first report, 8 years after they were first
established. Following this report the Joint Fire Research
Organisation was established, this was a specially formed
group who became responsible for the research into all aspects
of fire prevention (BRE, 2014). For the first time a
professional research board had been set up with the equipment
and resources to methodically reassess how the building
structures of the time were performing. Although the JFRO was
later amalgamated into the Building Research Establishment the
organisation was the first to test and consciously seek to
improve building materials in a bid to ensure better fire
resistance in buildings.
32
Until 1961, every local authority in the country had the
legal right to create building bylaws, resulting in over 1400
unregulated bylaws across the country before the Public Health
Act of 1961. This act first introduced the idea of one set of
building regulations that would cover the entire country, a
more straightforward way of regulating safety in buildings in
the whole country and a huge step forward in the safety in
theatres.
In addition to one set of building regulations introduced
to the whole country, the Fire Precautions Act 1971 set out
additional legislation to regulate every authority and every
building within those authorities. One of these that hugely
impacted British theatres was one that would become standard
in public buildings today, the Fire Certificate. As set out in
the Act this certificate was, and still is, issued under the
act by the fire authority and section 1 (2) (c) "Use for
purposes of entertainment, recreation or instruction or for
purposes of any club, society or association ;" outlined that
theatres were one of the public buildings that required this
certificate. Each building had to submit details of the use of
the building, plans of each floor of said building and what
the fire authority would have been most interested in, the
building's means of escape in case of fire and the warning
system the building had in place. Fire inspectors were also
granted maximum powers for the first time after having been
rejected several years previous. Inspectors now "may do
anything necessary for the purpose of carrying out this
33
Act...namely to enter any such premises...and to inspect the
whole.."
Fire safety regulations have been instrumental in
increasing the safety within British Theatres. Destructive
fires such as those in the eighteenth and nineteenth century
are no longer a common occurrence as they once were. The sad
but true reality is that without fires such as at Exeter,
Iroquois, Vienna or Empire Palace, the painstakingly detailed
regulations in place today may not have existed. It is only by
experiencing and learning from these tragedies that officials
could collect vital information from consequent investigations
that led to stable door legislation. The Theatre Royal fire in
Exeter led to a complete over haul of the then existing
regulations in London and many other provincial cities and the
creation of the Section 36 of the Public Health Acts
Amendment Act of 1890. The most instrumental and detailed
legislation to be published on fire regulations in British
theatres was the Manual of Safety Requirements in Theatres and
Other Places of Entertainment which took into account nine
incidents involving fires in four theatres and two cinemas
around the world. Each fire informed officials of certain weak
aspects such as fire exits, signage and fire fighting
equipment that were then investigated and the minimal
requirements specified. This highly detailed and specific
report still influences all modern regulations and is
invaluable in the improvement of public safety and fire
prevention in Britain's theatres.
34
Chapter ThreeNew Theatre Royal
"Les longs souvenirs font les grands peuples." - Montalambart, c 1830
Long memories make great people.
37
The New Theatre Royal has a complex history of
redevelopment, destruction and controversy. The site was
originally Landport hall, used as a racquet court before being
bought by Mr Henry Rutley in 1854. Rutley also purchased Swan
Tavern (The White Swan) and used the two venues as music halls
until he applied for a license to covert the hall into a
theatre two years later. The license was granted on the
condition that the adjoining door between the two was blocked
up ( Stephen, 2011, p. 6) and on the 29th of September 1856
the Theatre Royal opened. The theatre changed hands after
Rutley died in 1874 being run temporarily by Portsmouth and
Southsea Assembly rooms and Theatres Limited until Mr John
Waters Boughton bought the theatre and surrounding land.
There is no doubt that this change of hands and subsequent
land purchase made a positive and long lasting impact on the
fate of the Theatre. The historical link to the land behind
the Theatre and The White Swan has meant that project
architects Penoyre & Prasad have been able to make full use of
the empty land on Exchange Road.
38
On the 19th May 1884, two years after his purchase,
Boughton employed C.J.Phipps to expand and remodel the entire
Theatre. By rebuilding the new theatre within the shell of the
old Phipps was able to finish this project in 3 months,
reducing the financial impact on the Theatre. He created three
balconies, with three boxes on either side of the stage, one
at each level as well as two additional boxes and the rear of
the dress circle (first balcony) (Theatres Trust,
2013).Boughton continued to buy up land and in 1900 employed
Frank Matcham to enlarge the Theatre. There is no doubt that
this decision was in direct consequence of the growing
popularity of the Theatre and his recent success allowed
Matcham to make a number of large alterations as well as the
enlarged auditorium, including the large projecting enclosed
iron and glass balcony on Phipps' original façade. The largest
alteration inside was the auditorium its self, with the stage
being absorbed back into the ground floor seating and the
addition of Matcham's steel cantilever balconies. This
innovation in Theatre construction was one of Matcham's
greatest achievements, eradicating the need for structural
columns that often hindered the view of the audience.
By 1932 the decline of the Theatre and the introduction
and popularity of the cinema forced the NTR into becoming a
cinema with a projector and screen added to the auditorium. In
1948 it became a theatre again showing mainly Variety shows
before being closed for the first time. Hector Ross repertory
company occupied the building for a couple of years before
being closed again only to be reopened as a bingo hall. This
39
turbulent time for the Theatre reflects the uncertain times of
British theatre with many in London such as the Alhanbra in
Leister Square and The Empire Palace Theatre, Portsmouth. The
NTR can be said to have reached the end of its "natural life"
(Earl, 2001). The natural flow of the Theatre would have been
to either stay as a theatre or close permanently having served
the purpose for which it was built. However by forcing extra
life into the building, using it for activities that it was
not designed for, the Theatre suffered damage not only to its
fabric but to its reputation as well.
A consequence of the NTR being empty and without purpose
for the years before 1972 meant that several threatening
planning applications were submitted between 1963 and 1970,
all of which proposed the demolition of the Theatre. The
first, in 1963 was submitted in April by a development company
that wished to demolish the entire building and redevelop the
site as a dance hall, new theatre and a large block of flats
(Planning Portal, 2014). The second application came in 1966
and was the closest to being granted with just 5 votes to 3.
This was submitted by a London development company, Norman
Bruce Ltd (p.159, CMP,2011) As well as the demolition of NTR
it also included the complete demolition of the White Swan. A
ten story hotel was proposed along with 36 car parking spaces,
and was greeted with a lot of support from locals. They argued
the need for a large hotel in the area to attract business and
also pointed out that the NTR could only be used for stage
performances when permission was granted from the owner of the
Kings Theatre. The third planning application that could have
40
affected the future of NTR was submitted in 1969 and detailed
the erection of a block comprising of offices with flats,
however this too was rejected along with the last application
in 1970 that included of the demolition of the whole site.
In 1972 disaster struck the Theatre. It is believed that
children broke into the building and set off fireworks
backstage, causing the fly tower, stage and all of backstage
to catch fire (Offord, 1995). The historically significant
auditorium was only saved because the safety curtain,
redesigned after the Manual for Safety Requirements and Other Places of
Entertainment made it mandatory, fell protecting it from the
blaze that destroyed everything behind it. Compared to other
theatre fires such as the Theatre Royal in Covent Garden or
The Empire Palace Theatre in Edinburgh, both of which were
completely destroyed, the damage to NTR could hardly be called
monumental. In fact square footage wise it was only a fraction
of the Theatre, never the less the anti "Theatre Royalists"
used this to their advantage arguing that the most expensive
part of the Theatre had been lost. Following the fire the
Theatre was boarded up, however the interior was subject to
vandalism, much of the plaster work was smashed as were the
stained glass windows on the first floor bar. A direct
reaction of this was the formation of The New Theatre Royal
Trustees (Portsmouth) Ltd (Arts Council, 2014) and in 1980
enough funds were raised to buy the freehold (Theatres Trust,
2013). This purchase was significant to the future of the
Theatre; it saved the building from the possibility of
demolition by the council or a change of use which would have
41
been permanent and irreversible. However it has meant that the
Theatre is run as a charity, with no private funding except
from donations from the public and the money made from ticket
sales. If the Theatre had been bought by a private company or
individual then it could have been rebuilt much sooner and the
link now being formed with Portsmouth University would have
been unlikely.
Once the Trust had secured
purchase of the Theatre work
began on clearing the debris left
by the fire. The route taken by
the Trust was initially
conservation, with a great deal
of damage in the auditorium it
became the number one priority
for the Trust and the volunteers to quickly begin to conserve
what still remained intact in the Theatre. A lack of funding
resulted in any restoration work of plaster work and soft
furnishings left until money was raised. One of the first
courses of action was to dig out the orchestra pit (fig.5) to
allow for the temporary thrust stage to be put in place. The
history of the building tells us that the Theatre could not
have survived vacant any longer than it already had been, as
the threat of demolition was still high, so by repairing the
auditorium as quickly as possible the Trust could begin
earning money and in turn repairing more of the building.
Consequently in 1984 the plasterwork in the auditorium was
42
Figure 5 Volunteers digging out orchestra pit
also repaired as much as possible with anything removed that
was beyond saving. A year later offices for the Trust were set
up in the Upper Dress Circle bar, the reduced capacity (320)
meant that the bar space that remained on the Dress Circle and
Stall levels allowed for a comfortable amount of space for the
audience to use during the performances. In 1995 Roderick Ham
was employed and introduced a phased scheme of repairs to the
NTR. The focus of these repairs was the restoration of the
iron balcony and major work to the auditorium. Modern work to
the inside of the Theatre has proven to be less than
satisfactory with a new Box Office counter(fig.6) added in
2008 now top of the Theatres list to be removed and
potentially repositioned. The
location is untrue to the
original and the design is
proving too small for the
capacity they hope to achieve
after the new build and re-
opening.
In 2012 the Theatre was
granted a Heritage Lottery Grant of £939,900 to fund their
exciting project of expanding the current Theatre with a
modern extension. Design by Penoyre & Prasad, this new
addition is in collaboration with the University of Portsmouth
with part of the extension being used by the University's
drama department. The Anthony Minghella Creative Learning
Space will be a "unique creative learning space"(New Theatre
Royal [NTR], 2013). Caroline Sharman, the Theatre's Director,
43
Figure 6 Current Box Office
wishes to create a "made in Portsmouth" stamp as there is"an
urge to engage in detail with the working practices and
creative priorities of theatre makers." (Tompkins,Todd, 2007)
For the Theatre a new state of the art fly tower and back of
house facilities have been incorporated into the new design,
elements that have been missing from the Theatre since 1972
and have limited the Theatres capability to their own
productions.
The Restoration of New Theatre Royal
NTR has a unique history of evolution that tells the
story of Victorian theatre Architecture. The Conservation
Management Plan supplied by TheatreSearch in 2011 lays
emphasis on this fact and highlights the importance of layers
within the architecture. The scars on the building made by
unnecessary alterations, actions and events are a part of the
Theatres history and form an essential part of its identity.
Thus the direction that has been chosen by the Theatre and
encouraged by relevant authorities is one of a light touch to
preserve, conserve and celebrate all that the Theatre is.
The relative sensitivity analysis completed in the CMP
makes clear that there is little in the building of low
interest and the "whole building is highly sensitive to
change" (CMP, p.88, 2011). Set out in three colour categories,
red, purple and green as expected the entire outer shell of
the Theatre is highlighted in red along with many of the
internal walls also in either red or purple. The exception
44
being stud walls that are in place within the auditorium such
as the rear stalls wall and the temporary stage. The two most
important sections for understanding the plan for the
restoration of the Theatre are the Heritage Opportunity
Assessment followed by the Conservation and Restoration Key
Priorities. The first of these, the Heritage Opportunity
Assessment, details the history of the area and its
significance to the Theatre with an example being the
Exterior: Main Elevation described as the oldest part of the
building largely untouched from Phipps, with a "roof line that
tells an important story about the building's evolution" (CMP,
p.95, 2011). The opportunities that these areas present are
then briefly outlined with space for any additional comments.
The Conservation and Restoration Key Priorities table splits
the areas down even further and also prioritises these as
either high, medium or low with the Narrative bullet pointing
what will happen with each of these areas.
Restored and Reinstated
The fire in 1972 and the subsequent abandonment of the
building for a short time after this caused irreversible
damage to many of the unique features of the Theatre. A main
objective set out by the conservation management plan is the
restoration of the features that survive today and to
reinstate as much as possible that which was vandalised after
1972. An important outline set out in the management plan is
that "full, pure restoration would deprive the building of its
45
own life story" (p.103, C.M.P, 2011). In many cases the purist
approach can be the direction that should be taken in order to
save the historical fabric of a building, when that building
has gone through only one phase of development and therefore
only has one period of time that it can be restored back to.
However in the case of NTR the building has seen over 200
years of alterations, some such as Matcham's were positive as
it allowed the building to expand and included important
safety additions. On the other hand additions such as stud
walls and the "floating" stage were necessary at the time, but
if left in place would have a negative impact on not only the
historic fabric but the aesthetics of the Theatre. SPAB states
that "every change, whatever history it destroyed, left
history in the gap, and was alive with the spirit of the deeds
done midst its fashioning"(SPAB, 1877). Taken from the 1877
manifesto, it strengthens the decision made by NTR not to
strip back all of the additions made to Theatre.
Brassware
The brassware in the NTR was a
significant addition by Matcham when he
altered the Theatre in 1900 (CMP,
2011), it is one of the signature
features that he used in all of his
theatres but unfortunately most of it
has now been removed from NTR along
with the electric light fittings.
46
The Conservation Management Plan highlights several
areas where Matcham's brassware should be reinstated the first
of which being the external doors. These were remodelled in
1900, but are now missing the brass
handles, push-plates and crash-bars
that would have originally all been in
place.(CMP,2011) As an element of the
main external façade the replacement of
this brassware is of high priority for
the Theatre.
Matcham's main staircase up to the
dress circle once featured original
brass stair rods on each step over the
original carpets.(fig.7) It can be assumed that along with the
other brass fittings that were once
present in the Theatre, the stair rods
were taken in 1966 when the Theatre was looted and vandalised
while it was vacant.
As with the main external doors,
all internal doors also contained brass
fittings and fixtures designed by
Matcham and these too have been removed.
Matcham's brassware was supplied by
Edwin Showell & Co. whose trade
catalogue has survived and some of these
missing fittings can now be reproduced and used in restoration
projects such as this.
47
Figure 7 Original brass rodson each step
Figure 8 Brass rods now missing from stairs
Figure 9 Orchestra Rail
Finally the orchestra pit rail, which although has been
classed as a low priority for the NTR's restoration, the
patterns for re-casting are available from the Edwin & Showell
& Co. catalogue (fig.9) and therefore could be reinstated. It
is important to keep consistency with restoration projects
such as this and if brassware is being reinstated in other
locations around the building such as the doors and the main
staircase then the orchestra pit should also be included. The
rail as a physical element is also significant as it creates a
dividing element between the orchestra and the front row
stalls. (CMP, 2011)
Electric Light Fittings
The Conservation Management Plan highlights the
importance of the original light fittings, all of which have
been replaced since they were designed and installed by
Matcham. Particular emphasis has been put on reinstating these
in the main foyer as these "form essential elements of
Matcham's atmospheric foyer entrances." (p.113,CMP,2011) The
priority level for reinstating these original light fittings
has been listed as medium, along with the other locations that
lighting has been mentioned as important, including the main
staircase, stalls and the auditorium ceiling. The original
location and principles of Matcham's house lighting is
currently unknown to the Theatre, however it is hoped that
after more research they can be reinstated into the auditorium
along with the introduction of LED technology.
48
Soft Furnishings
The reinstatement of the soft furnishings within the
Theatre are categorised as a high priority in the Conservation
Management Plan as, like the brassware, the soft furnishings
are a key detail that Matcham and Phipps both used to tie
together the interior of their Theatres. Phipps' soft
furnishing detail is described well in The Stage 1884, the
seating and curtains are described as crimson and the seating
on the Dress circle as maroon. Matcham's interior was the
opposite, cream, light terracotta and gold with the soft
furnishing in copper. Although a colour scheme has not been
decided yet, it is advisable for the Theatre to keep a
consistency to their restoration and conservation process,
therefore as the auditorium is being restored to Matcham's
design the colour scheme should be of that time as well.
Plaster
NTR has only some of the original
plaster that survives as most was
vandalised and destroyed after 1972.
The fibrous plaster work that is still
completely intact is located on the
front of the three tiers(fig.10), the
dress circle was altered by Matcham
and so dates to 1900 while the Upper
circle and Gods survive from
Phipps. The four boxes
(fig.11) also have decorated
49
Figure 10 NTR three tier auditorium
Figure 11 Matcham box frontages
plaster frontages, however these were damaged when they were
removed to allow the temporary stage to be installed, so have
been sent to Hayles and Howe, the plaster restoration company
that began the original repair of the plaster in the 1980's.
The fronts of the tiers are extremely important to the Theatre
as they are almost completely intact and are another element
of the Theatre that tells the story of its evolution and
adaptations.
Pit Bar
The Pit Bar located at basement level is an area of the
Theatre that has already begun to be restored. The room was
once the bar for those seated in the stalls, however it has
been decided that because of the tight size of the space its
future use will be as an over spill space from the new stalls
bar.
A vast amount of damage has been
done to this area of the Theatre,
mostly caused sometime between the
1920's and 1950's. The original room
was decorated with tiles but at a
later date these were painted over
gold. In addition wooden boards with
Art Deco paintings were screwed on to
the walls, causing damage to the
Victorian tiling. Furthermore the old
wiring and construction steels have
caused considerable damage to the
50
Figure 12 Pit bar ceiling
Figure 13 Pit bar, Victoriantiles
ceiling, meaning that the room had become unsafe. The
restoration progress began in January starting with the old
wiring being stripped from the room and the Art Deco boards
carefully being unscrewed from the walls. The ceiling render
has been completely removed in order to do this, leaving the
concrete bare.(fig.12) The Victorian tiles are the main focus
of the room as although some have been damaged by the screws,
the rest remain largely intact and the cleaning process is
well on its way to restoring their original colour.(fig.13)
The room still has a long way to go before it is finished and
has been delayed several times due to complications arising in
other areas of the Theatre.
Required Modern Additions
The Theatre will have to have many new additions in the
areas of Health and Safety, Access and Technology as the
standards of the old Theatre were well below what are now
legal requirements. Most of these additions are located in the
auditorium, the new rear stalls ramp that allows for
wheelchair access to the stalls bar and toilets has already
been built on the left of the stalls and modern radiators have
been added to the dress circle and upper circle.
Conversations with health and safety consultants and the local
council have highlighted the need for more ventilation into
the auditorium during shows. The area that has been settled
on, although no work has yet to begin, is through the North
East stalls entrance. A large hole would have to be punched
through the wall above the second set of doors in this
51
entrance corridor; however the lack of current structural
plans of the building could complicate this seemingly simple
alteration. It is unknown as to what complications, if any,
weakening this wall could do structurally to this part of the
Theatre, however what is clear is the loss of historic fabric
that the required new ventilation system will cause. Other
modern additions that are needed to bring the Theatre up to
today's standards for the public's comfort are modern kitchen
facilities in the dress circle bar and upgraded toilet
facilities throughout the Theatre. The kitchen area has
already had many alterations over several years and a modern
upgrade from the current 1970's style kitchen can only
described as positive.
Due to the importance of the New Theatre Royal not only
locally but on a national scale, the decisions made on the
restoration and conservation have had to comply with the
outlines set out by the Heritage
Lottery and the Conservation Management
Plan. In fact the Theatre is described
in The Theatres Trust Guide to British
Theatres 1750-1950 as of "special
note". (Earl & Sell, 2000) The
decision making process has been
created using all available authorities
including, but not limited to,
Portsmouth City Council, English
Heritage(Appendix F) and the Heritage
52
Figure 14 Brigg's Panic-bar
Lottery Fund. The main point set out in the plan that will
require the most consideration is the decision to "reverse
poor and unhelpful or insensitive interventions" (CMP, p.100,
2011) as to some extent this could be a personal opinion and
the process must be monitored carefully to avoid this.
An important part of any theatre is the interior
decoration; the details are all carefully designed to create
an atmosphere that is crucial to the visitors experience and
this is the reason why the Theatre has chosen to reinstate all
lost elements that can be such as the plaster work, soft
furnishings, brassware and sculptures. Another reason behind
some of the restoration decisions is the availability to
recreate what has been lost; examples of this are the main
facade exterior doors. These were remodelled by Matcham and so
the original design by Phipps has been lost, leading to the
decision to restore these to 1900. Matcham's doors are
described by many as a key element of his theatres, in fact
Matcham's chief engineer Robert Briggs was a patentee of an
emergency escape panic-bar (fig.14) that Matcham specified for
all of his theatres. These bars were made by Edwin Showell &
Son under the name Briggs' Patent Panic Bar, and the design of
these has been recorded by the manufacturer and is therefore
available for the Theatre to reinstate.
53
Conclusion
This thesis has researched into the philosophical schools
of thought concerning restoration and preservation along with
a more in-depth study of the development of fire safety
regulations concerning British theatres and the advantages and
disadvantages of three specific options one can take after a 56
theatre has suffered a fire concluding with a case study on
the New Theatre Royal, Portsmouth. A clear linear study has
been produced of the historical developments and influences
concerning British regulations for fire safety noting the
particular importance of the Manual of Safety Requirements in
Theatres and Other Places of Entertainment and its influence
in modern day legislation. A case study on the New Theatre
Royal in Portsmouth has also been included in this thesis to
enable the further study on a selected "after fire" option for
a theatre. By studying the progression of a current rebuild
and restoration project, along with the factors and history
that influenced the project, one can further understand the
advantages and disadvantages of this chosen path in real time.
The two philosophical schools of thought studied briefly
in the thesis are the split that appeared in the care of
historical buildings at the end of the eighteenth century
enabling the development of Restoration and Preservation as
two separate approaches. The abundance of writing in favour of
Preservation such as that of Ruskin and the manifesto of SPAB
meant that researching this school of thought through
secondary research was relatively informative. However the
lack of written material in favour of Restoration at the time
of the split meant that several architectural projects were
the only method of researching the beginnings of Restoration.
The main sections of this thesis concentrate on how to
ensure a theatre can continue working after a serious fire,
57
the development of fire regulations and the New Theatre Royal
as a case study.
Researching through secondary material, several theatres
that had suffered damage through fires informed the three main
options available for theatres after fires. However due to the
success of British fire regulations recent theatre fires are
far less common and therefore a detailed description of
projects involving theatres in the more common early twentieth
century proved more elusive.
The decision of how to reinstate a theatre after damage
depends almost completely on the extent of said damage, a
theatre totally gutted has no hope of a simple partial rebuild
and is more likely to survive after a large restoration or
rebuild project depending upon how much of the historic
structure and internal fabric remains. The advantages of a new
build over either of the other options brought to light
through research are intertwined with the reasoning behind any
other modern development; the introduction of beneficial new
technology. The disadvantages of a new build are heavily
weighed down by public sympathy for the lost historic building
and the loss of historic fabric. The reality is that historic
theatres cannot be underestimated in their importance. In
comparison to this, a partial rebuild is seen as a far less
drastic form of action, however does rely on the extent of the
damage to be fairly minimal or at least have a fair amount of
complete original fabric and structure intact. It builds upon
the idea of new technology, but depends on the original
location of the fire and therefore which section is rebuilt.
58
On the other hand the design of a partial rebuild is
scrutinised far more as it is seen as a delicate balancing
act; too much like the original building and the lines between
old and new could blur, but too new and modern and the old
could be overwhelmed. Lastly the third option, rebuild/and
restore and the value of the original historic theatre, which
according to the statistics from TheatreSearch is so great we
cannot afford to lose anymore. However the evidence or
information needed for total reconstruction may not be
available as is the case for many historic buildings, so any
attempt to recreate what once was is seen as speculation on
the original.
The research into the development of British fire safety
regulations involved reading through published legislation and
communications with the Theatre Trust based in London, some
original legislation has since been amended meaning the
original publications were hard and in some cases impossible
to find.
The first introduction of fire fighting equipment within
a British theatre was Drury Lane's Theatre Royal, a safety
curtain and water tank, which led to safety curtains being
mandatory in all large theatres however a preventative method
wasn't introduced until after the Theatre Royal fire in
Exeter. This led to Section 36 of the Public Health Acts
Amendment Act of 1890 and the inclusion of "Every building
which..is used as a place of public resort, shall, to the
satisfaction of the urban authority, be substantially
constructed and supplied with ample, safe, and convenient
59
means of ingress and egress for the use of the public ". This
is the first acknowledgment that fire exits had been
previously missing and that they were instrumental in the
prevention of loss of life in the case of a fire. Following
this the London Buildings Act (Amendment Act) of 1905 gave LCC
powers to enforce the need for means of escape, however for
the mean time this was a power limited to London and did not
extend to the rest of the country until the Manual of Safety
Requirements in Theatres and Other Places of Entertainment in
1934. This manual reflected upon nine specific fires; Ring
Theatre in Vienna, Theatre Royal Exeter, Paris Charity Bazaar,
The Iroquois Theatre Chicago, The Empire Palace Theatre
Edinburgh, The Grand Assembly Rooms Leeds, Drumcollogher Co
Limerick, The Glen Cinema and Coventry. From each fire lessons
were learnt, understood and then reinforced within sections of
the manual based around fire exits and fire prevention. The
manual covered all internal concerns but did not begin to
cover how the structure of a building could be affected by a
fire; this was first investigated and later reported on by a
joint committee of the building research board and the fire
offices committee (FOC) in 1946. The Public Health Act of 196
first introduced the idea of one set of building regulations
that would cover the entire country making it impossible for
theatres to avoid the 1934 manual. In 1971 fire inspectors
were granted powers to enter any theatre at anytime with the
intent to issue or cancel fire safety certificates.
The research into the case study, New Theatre Royal, was
largely primary research, collected over months of site
60
visits, photographs and interviews with the Theatres Director
and Operations Manager. The history of the theatre was
researched using material located in the Theatres archives,
the Portsmouth Records Office and informative online
databases; including that of the Theatres Trust.
The New Theatre Royal owes thanks to many of these
regulations as it would not have survived without the
mandatory safety curtain that prevented the destruction of
anything more than backstage during its fire in 1972. The fire
affected the section of the Theatre containing the majority of
its performance technology. As discussed in the first chapter
of this thesis this allows for the potential of either a
modern or pastiche partial rebuild with the newest available
technology for stage performances included. The decision made
by the NTR trust was a modern partial rebuild with a very
large extension including new facilities for the use of
University of Portsmouth, an investor in the project. This
thesis concentrates on the restoration of the NTR as it is
just as large a project, if not larger than the partial
rebuild. This is also the part of the project that the NTR
staff are most involved in themselves, the restoration and
reinstatement of what the Heritage Statement and Conservation
Statement deemed necessary for a sympathetic and authentic
restoration project. These include but may not be limited to;
brassware, electric light fittings, soft furnishings, plaster
and the pit bar.
61
The possibility of future research is definitely
available and it can be taken in several directions depending
upon which point from this thesis is taken forwards. The case
study of New Theatre Royal was hindered at the time because
the project has yet to be finished, however once it is a
completed a more in depth study on the project as a whole
would be beneficial because of the complex history of the
Theatre and the extremely ambitious and unique project they
have embarked on. This thesis has only mentioned the modern
partial rebuild by Penoyre & Prasad because of the slow
progression of the project, however much could be researched
into with this part of the project such as the design
influence and its impact on the historic theatre.
Research into British fire safety legislation and its
impact on Britain's theatres is another area that can be
expanded on. The Manual of safety requirements in theatres and
other places of entertainment is an extremely lengthy report
that is still influencing legislation today, the positives and
negatives of this could be researched as well as the potential
for further study into any other regulations or legislation
and the effect on historic theatres.
62
Aldous,T.(2002) Frank Matcham, Theatre Builder. History Today. London,United Kingdom: History Today Ltd
Anderson,D. (2002). The Exeter Theatre Fire. London: Entertainment Technology Press Ltd
Booth,M.(1995). Theatre in the Victorian Age. Cambridge: Cambridge Univeristy Press.
Burman,P.(1995). A Question of Ethics. The Conservation and Repair of Ecclesiastical Buildings. Retrieved from http://www.buildingconservation.com/articles/ethics/conservation_ethics.htm
Carson,L (1884) The Stage Guide 1884. London: The Stage
Carson, L. (1900) The Stage Guide 1900. London: The Stage
County Recreation Department (1976) The Theatre Royal An examination of its potential for restoration and development as a city and regional arts facility. Hampshire, United Kingdom
Earl,J. (1996). Building Conservation Philosophy. Dorset: Donhead Publishing.
64
Earl, John & Sell, Michael, (200), The Theatres Trust Guide to British Theatres 1750-1950. London: A&C Black.
Fernandez, B (2011).The Festival Theatre, Edinburgh.Retrieved from Arthur Lloyd's music hall and theatre history database: http://www.arthurlloyd.co.uk/Edinburgh/Festival.htm
Fressoz,J.(2007). The Gas Lighting Controversy: Technological Risk, Expertise, and Regulation in Nineteenth-Century Paris and London. Journal of Urban History, 33. 729-755. http://dx.doi.org/ 10.1177/0096144207301418
Garrett,D. (2011).The New Theatre Royal, Guildhall Walk, Portsmouth. Retrieved from Arthur Lloyd's music hall and theatre history database: http://www.arthurlloyd.co.uk/PortsmouthTheatres.htm
Glasgow School of Art fire: Iconic library destroyed.(2014) Retrieved from BBCNews Website: http://www.bbc.co.uk/news/uk-scotland-glasgow-west-27556659
Hall, Jr.(2011). Fatal Effects of Fire. NFPA, index no. 1598
History of Fire Safety.(2009) Retrieved from FireNet database: http://www.fire.org.uk/history-of-fire-safety.html
Mackintosh, Iain & Sell, Michael, (1982), Curtains!!! or A New Life ForOld Theatres. Eastbourne:John Offord,
National Heritage Training Group. (2005). Traditional Building Craft Skills. English Heritage database: http://www.english-heritage.org.uk/content/imported-docs/p-t/craftskillsreport.pdf
New Theatre Royal, Portsmouth.(2013). Retrieved from http://www.takeonebuilding.org.uk/buildings/new-theatre-royal-portsmouth
New Theatre Royal (Portsmouth),(2011) Retrieved from the Theatres Trust Theatres Database : http://www.theatrestrust.org.uk/resources/theatres/show/983-new-theatre-royal-portsmouth
65
Offord,J (1995). New Theatre Royal Portsmouth. A short appreciation. Portsmouth, United Kingdom: Tabarts Productions
Our History. (2014). Retrieved from the BRE Database: http://www.bre.co.uk/page.jsp?id=1712
Pevsner, N.(1970) The Buildings of England: Cambridgeshire. (2nd ed.) Harmondsworth: Penguin.
Portsmouth City Council Planning Portal.(2014) Retrieved from the Portsmouth City Council Database : http://publicaccess.portsmouth.gov.uk/online-applications/
Rowell,C, Robinson,J.(1996). Uppark Restored. London: National Trust Enterprises Limited
Stephen, L. (2011). Heritage Statement: New Theatre Royal, Guildhall Walk, Portsmouth.(11/0153) M:\HC\Projects\Projects 101-200\11.0153 - New Theatre Royal, Portsmouth\Reports\2011.08.30_Heritage Assessment_NTR_Final.docx
Stollard, P.(1999). Fire From First Principles: A Design Guide to InternationalBuilding Fire Safety. (3rd ed) London: E & Fn Spon.
Strike,J. (1994). Architecture in Conservation Managing Development at Historic Sites. London: Routledge.
Theatres and Halls in Portsmouth, England.(2013) Retrieved from http://www.arthurlloyd.co.uk /PortsmouthTheatres.htm#royal
Theatresearch, (2011). The New Theatre Royal, A Conservation Management Plan. North Yorkshire: Theatresearch
Theatresearch, (2011). The New Theatre Royal, A Conservation Statement. North Yorkshire: Theatresearch
The New Theatre Royal Trustees (Portsmouth) Ltd. Retrieved from the Arts Council Database: http://www.artscouncil.org.uk/funding/browse-regularly-funded-organisations/npo/new-theatre-royal-trustees-portsmouth-ltd/?minimal=true
66
Tompkins,S. Todd,A (2007) The Unfinished Theatre. Architectural Review. Issue No.1325.Northampton, United Kingdom: EMAP Publishing Limited
Walker,B.(1980) Frank Matcham. Belfast: Blackstaff Press
Williamson,K.(2010). Development and Design of Heritage Sensitive Site: Strategies for Listed Buildings and Conservation Areas. Oxon: Routledge.
Wright,P. (2007). Iron Curtain: From Stage to Cold War. New York: OxfordUniversity Press Inc.
University of Portsmouth New Theatre Royal.(2012). Retrieved from Penoyre & Prasad database : http://www.penoyreprasad.com/projects/university-of-portsmouth-new-theatre-royal/
67
Sources of Illustrations
Figure 1 Notre Dame, prior to restoration [Retrieved September2nd 2014: http://fr.academic.ru/dic.nsf/frwiki/568062]Figure 2 Notre Dame, after restoration [Retrieved September 2nd 2014:
http://www.saber.es/web/biblioteca/libros/catedral-de-leon-historia-y- restauracion/html/fotos/f016.htm]Figure 3 Theatre Royal, Norwich, 1930's [Retireved September 2nd 2014: https://secure.theatreroyalnorwich.co.uk/Online/default.asp?doWork::WScont
68
ent::loadArticle=Load&BOparam::WScontent::loadArticle::article_id=F1DCA31 C-5488-47B3-9480-99AF0226DD18]Figure 4 Theatre Royal, Norwich, 1935 [Retrieved September 2nd 2014
https://secure.theatreroyalnorwich.co.uk/Online/default.asp?doWork::WScont
ent::loadArticle=Load&BOparam::WScontent::loadArticle::article_id=F1DCA31 C-5488-47B3-9480-99AF0226DD18]Figure 5 Volunteers digging out orchestra pit [from: New Theatre Royal archive]Figure 6 Current Box Office [Authors own]Figure 7 Original brass rods on each step [Authors own]Figure 8 Brass rods now missing from stairs [Authors own]Figure 9 Orchestra Rail – Edwin Showell & Co Trade Catalogue [from: theatresearch archive]Figure 10 NTR three tier auditorium [Authors own]Figure 11 Matcham box frontages [Authors own]Figure 12 Pit bar ceiling [Authors own]Figure 13 Pit bar, Victorian tiles [Authors own]Figure 14 Briggs' Panic Bar - Advertisement from an Edwin Showell‟s 1890s Trade Catalogue[from: theatresearch archive]
69
where:-A = a number of units of exits widths requiredone unit is 22 inches.Exits should be in multiples of this width, with no exit less than two units of this width.
In existing buildings:-Doors 40 to 55 inches wide count as 2 units 56 to 75 inches wide count as 3 units 76 to 100 inches wide count as 4 units 101 to 125 inches wide count as 5 units
B = Construction of Buildings:"Class A" Buildings B=6"Class B" Buildings B=5"Class C " Buildings B=3
C= Arrangements and Protection of Stairs
For places not more than 21 inches above or below ground levelc=6stairs from places on a single floor not more than 5 feet above or below ground level c =5enclosed stairs from circle or gallery or stairs leading down to vestibule or direct to open air c=4stairs from circle or gallery unprotected and coming down into main floor of building ( Note- in such cases the exits from ground floor must be of sufficient width to handle persons from circle or gallery) c=3
D= Exposure HazardPlaces of public assembly will usually be rated as medium hazard This factor for high hazard is provided to cover a situation where exposure hazard may be serious (see list of risks below)high hazard d=1medium hazard d=2
proximity to premises of the following classes shall be held to constitute a high hazard: -
72
Accumulator makersAeroplane store and manufactures Artificial flowersArtificial Leatherbedding manufacturers brush makingcabinet making candle makingcardboard box makingcelluloidcellulose sprayingchemical workersconfectioners ( (manufacturing)cork. cotton wool.cotton clothingcotton waste. chemicalsdruggist (wholesale and manufacturing)dry cleaningfeathersfilm storage and handlingfireworksflanneletteflour and grist millgarageshay and straw dealershemp flax and juteIndian rubber making and treatinginsulating. material manufacturinglinoleum manufacturingmunitions makers and storesoil and colour merchantsoil and petrol stores (unless with underground tanks)oil refineriespaper bagspaper worksrag and waste dealerrag sortingrepositories( furniture) sawmillsships chandlersshoddystationers (manufacturing)
73
stablesstraw goodstoy shopsupholstererswood working
E= factor dependant upon height of floor above or below groundlevel
each circle, balcony or tier to be considered separately. if height or depth is intermediate take nearest figure when height is precisely between two values, take the lower value of the factor. hieght above ground level is to be taken as mean height of a circle, gallery, etc.
where height is 80 feet " E =260 70 =280 60 =310 50 =340 40 =370 30 =400 20 =440 10 =470
At ground level =500where depth = 5 =470
10 =440 15 =370 20 =340
Z= class of user of building:user for closely seated audience Z=50user as dance hall, restaurant, etc Z =30
74
Appendix B - Table showing different grades of safety curtains and which class of building they should be used in.
76
Taken from the Manual of Safety Requirements in Theatres and other places of entertainment.
Appendix C - Table showing different types of roof vents and which class of building they should be used in.
77
Appendix D - English Heritage Listing Description of New Theatre Royal
Building Details: Building Name: THEATRE ROYAL Parish: PORTSMOUTH
79
District: PORTSMOUTH County: HAMPSHIRE Postcode: PO1 2DD Details: LBS Number: 474695 Grade: II* Date Listed: 30/10/1969 Date Delisted: NGR: SU6400200048 Listing Text: PORTSMOUTH SU6300 GUILDHALL WALK, Landport 774-1/8/270 (West side)30/10/69 Theatre Royal (Formerly Listed as: LANDPORT COMMERCIAL ROAD Theatre Royal)
GV II*
Theatre, formerly hall. Built as Landport Hall 1854, convertedto theatre 1856, substantially rebuilt 1884 by CJ Phipps, reconstructed 1900 by Frank Matcham, restoration work in progress from 1980. Grey and red brick in English bond, stone dressings and iron balcony. Welsh slated hipped roof. EXTERIOR: 3-storey facade with attic at centre. 5 bays. Acrossfront is a projecting 2-storey iron and glass shelter with curved ends, arcaded with 5 fretted round-arched openings, flanking paired and enriched iron Corinthian columns, basket arched opening at each end, moulded iron cornice. On first floor are 5 paired windows each with two 2-leaf fixed casements set under round iron arch with centre dividing column and flanking paired pilasters, ornate patterned aprons. On left and right return and to each of the recessed flanking curved wings is a similar round-headed casement with fretted iron balustraded balcony; band cornice and similar balustrade over with splayed rooflight over centre 3 bays. Ground floor facade is faced in black marble and has six 2-leaf entrance doors with fanlight; each leaf has 2 moulded lower panels, 2 oval middle panels and glazed upper panel. Plasterwork above imposts has decorated panels. First floor has rusticated stone quoin strips, moulded band then fluted stone Corinthian pilasters to quoins and flanking the centre 3 bays to second floor. On each side of iron
80
rooflight, high level first floor is a 2-leaf casement set under flat stone arch with flanking paired pilasters, moulded band, moulded stone head panel and second floor sillband between pilasters. Second floor has five 2-leaf 6-pane casements each with stone architrave and pediment. Entablature and moulded stoneeaves cornice. Centre 3 bays have facing stone dentilled pedimentwith relief carvings within tympanum and at centre is a half round fixed attic casement with moulded stone architrave and keystone. INTERIOR: decoration of 1900 is intact and unaltered with nautical theme having seafaring emblems such as ships prows between the boxes, Dolphin's anchors and mermaids, life belts andshells on the dress circle with military emblems on the upper circle. (Balfour A: Portsmouth: London: 1070-: 67; Lloyd DW: Buildings ofPortsmouth and its Environs: Portsmouth: 1974-: 109, 110, 111; The Buildings of England: Pevsner N & Lloyd DW: Hampshire and theIsle of Wight: Harmondsworth: 1967-: 460). Listing NGR: SU6401300094
81
General Assessment:
In the 1840s a building called the Landport Hall was convertedfrom aracquets court attached to the Swan Tavern. In 1854, Henry Rutley, acircus proprietor, took over the tavern and applied for a licence to convertthe hall into a theatre, which opened in Sept 1856. Rutley died in 1874,and Boughton, who acquired the theatre in 1882, purchased adjoining land,
83
commissioning C J Phipps to build a larger theatre. This had threebalconies, and three boxes, one at each level, on either side as well as twoboxes at the rear of the first tier. Continuing to buy up land, Boughtondecided to enlarge the auditorium and improve the stage facilities,engaging Frank Matcham, with whom he had worked at the PrincesTheatre.Phipps' restrained but handsome pedimented classical façade of1884survived this reconstruction. Matcham did, however, make an additionwhich completely tranformed the appearance of the theatre - a projectingenclosed balcony of enriched iron and glass, supported by an arcade ofslender coupled colonnettes.Matcham built a new stage 19.8m (65ft) deep and enlarged Phipps'auditorium by absorbing part of the old stage 10.66m (35ft) deep within it,and building a range of four bow-fronted boxes on each side between thethe ends of the balconies and the new proscenium, which was 9.14m (30ft)wide. He also partly reconstructed the balconies themselves, althoughmaking use of Phipps' supporting iron columns.The lyre-shaped first balcony of six rows is pure Matcham and iscantilevered out from a line of columns which rise up to support the frontsof the two Phippsian horseshoe balconies above. The sides of the upperbalconies were altered to improve sightlines. The overall decorations (byDe Jong) are of an incredible richness. The boxes are framed by giantpolygonal columns and each upper box has an arched canopy which bellies
84
forward with a scrolled top above an oval panel. Linking the capitals of thecolumns on each side is a wide semi-circular arch, originally framing abust. The proscenium is flanked by niches, originally with statues.Surmounting the opening is a large flared painted panel with trumpetingTritons in plasterwork at its base.The whole is held together by a scheme of extremely detailed plasterworkwith a predominently nautical theme. The first tier panels aredecoratedwith naval symbols - mermaids, dolphins, anchors and shells. The secondtier honours the army; laurel wreathed lions spouting forth electric globeswhile between are draped guidons and colours. The third has continuousdeeply moulded Rococo acanthus motifs which gently emphasise itsearlier form. Most of the panel painting was lost in a thoroughlyinsensitive 1948 redecoration, although there does survive theexcellentlarge panel over the proscenium showing Thespis and boys at play.In 1959 the theatre became a bingo hall. In 1971 an application for listedbuilding consent to demolish was refused. The stage was destroyed by firein 1972 (children playing with fireworks; fortunately the firebrigadelowered the iron curtain) and the building was closed. Furthervandalismof the interior followed.Following this, members of the Theatre Royal Society worked atweekends to protect the building from decay and vandalism. TheNewTheatre Royal Trustees (Portsmouth) Ltd was formed and in 1980sufficient funds were raised to buy the freehold.
85
Despite the Trust's worthy efforts, the recovery of this superb theatreproceeded at an agonizingly slow pace. A phased scheme by Rod Ham ledto the restoration of the façade, improvements to front of house spaces,major repairs in the auditorium and the laying of the foundations for acompletely new dressing room and administration wing, but the rebuildingof the stage house is still awaited.The sightlines from the balconies are very good and allowed a forestage tobe built forward of the proscenium, enabling the splendid auditorium tofunction as a most exciting setting for drama. The comparatively largevolume, which does not detract at all from the intimacy of thetheatre, andthe unusual sloping angle of the ceiling, suggests a superb acoustic foropera and musical theatre, as well as for speech.Even in its incomplete form, the public face of the theatre was in excellentcondition and the building used for occasional performances (and regularlyas a shoppers' cafe rendezvous!), bringing confidence back to a part of theCity which had formerly seemed doomed to decay.Forty years since the fire, plans for the new stage house are finallyunderway, with reopening anticipated in 2013/14. With a potential capacityof 1,500 and an ability to arrange programming to complement that of theKing's, Southsea, the complete re-opening of this theatre is greatlyanticipated across the City, region and beyond.
86