Upload
vodung
View
214
Download
0
Embed Size (px)
Citation preview
1IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
���������� ����������� ���������� �����������
Phy Vendor’s Perspective
Multi-vendor presentation:Broadcom
Vativ TechnologiesMarvell
2IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
������������� ��������������������� ��������
Primary goal: Define necessary channel requirements formultiple vendors to agree to the feasibility of a 10G phy implementation
1. Compute theoretical capacity on standardized cable channels• Cat 5e, Cat 6, Cat 7 (classes D,E,F)
• Based on unscaled measured data
2. Channel requirements needed for 10G• “Fantasy” Cat 6
3IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
�� �� ������� ����� ������� �� ������� ����� �����
Cat 5e, Cat 6, Cat 7
4IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
�� ���������������� ��������������
• Standard 2 or 4** connector 100m terminated channel
– Differential measurements
– Channels pass cable tester
• Alien crosstalk measured as power sum from 7 cable bundle
. . .
6"
Cable Bundle
6x4 Outer Crosstalkers1x4 Inner Victim
LucentLucent PATCHM AX
3 6 1 2
M odular Jack
M odular Pane l
Cable (245 ft)
Patch Cord (9 ft/5 ft)
Equ ip ment Cord (9 ft/5 ft)
1 2
3 4
Luc entLuc ent PATCHM AX
M odular Pane l
CP Cab le (50 ft) M odular
Jack
3 6 1 2
Patch Cord (5 ft/9 ft)
LucentLucent PATCHM AXLucentLucent PATCHM AX
3 6 1 23 6 1 23 6 1 2
M odular Jack
M odular Pane l
Cable (245 ft)
Patch Cord (9 ft/5 ft)
Equ ip ment Cord (9 ft/5 ft)
1 2
3 4
Luc entLuc ent PATCHM AXLuc entLuc ent PATCHM AX
M odular Pane l
CP Cab le (50 ft) M odular
Jack
3 6 1 23 6 1 23 6 1 2
Patch Cord (5 ft/9 ft)
**Ref: Terry Cobb, Avaya, 2003
5IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� ������� �!���"�!�� ������� �!���"�!�
Insertion Loss
PSNEXT
PSFEXT
Return Loss
• Limit lines extrapolated after 100MHz
6IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� ����������!��� �#� ����������!��� �#
2 Connector PSANEXT 4 Connector* PSANEXT- exceeds proposed limit line
*2 near end connectors only
• Both channels pass Cat 5e cable tester
7IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
����� ��� �"!���"�!�� "#$�!���%!���
����� ��� �"!���"�!�� "#$�!���%!���
• Cable terminated in 100 ohms
• Narrowband interferers have insignificant impact on theoretical capacity
• Broadband noise level below -155 dBm/Hz– Similar results for Cat 6
Hallway LAB Network Closet
8IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� ���� � "���� ���� � "���
• Based on unscaled measured data from 100m - 2 connec tor channel – Background noise –155dBm/Hz
– Not representative of worst case channel
100 200 300 400 500 600 700 800 900 10004.5
5
5.5
6
6.5
7
7.5
8
8.5
9
9.5
One−sided BW (MHz)
Shan
non
Capa
city i
n GB
ps
Capacity with AWGN and ANEXT with 0dB of ANEXT cancellation
Capacity = 9.00 Gbps @ 720MHz
9IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� �&����'�!���"�!�� �&����'�!���"�!�
Insertion Loss
PSNEXT
PSFEXT
Return Loss
10IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� �&�������!��� �#� �&�������!��� �#
Insertion LossLimit Line
ProposedLimit Line fromNov ’02 Tutorial
• 4 Connector channel exceeds proposed ANEXT limit li ne
11IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� �&� � "���� �&� � "���
• Based on unscaled measured data from 100m - 4 connec tor channel – Background noise –155dBm/Hz
100 200 300 400 500 600 700 800 900 10005
5.5
6
6.5
7
7.5
8
8.5
9
9.5
One−sided BW (MHz)
Shan
non
Capa
city
in G
Bps
Capacity with AWGN and ANEXT with 0dB of ANEXT cancellation
Capacity = 9.39Gbps @ 800MHz
12IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� �('�!���"�!�)� �('�!���"�!�)
Insertion Loss
PSNEXT
PSFEXT
Return Loss
* Cable: Siemon Co. Cat 7 TERA Channel
13IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� �( �!���"�!��%�*� �( �!���"�!��%�*
*
*Data supplied by Nexans
14IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� �(� "#$�!���%!���� �(� "#$�!���%!���
• Narrowband interferers suppressed
• Broadband noise level well below –155 dBm/Hz
15IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� �(� � "���� �(� � "���
• Based on unscaled measured data from 100m - 4 connec tor channel– Background noise at –160dBm/Hz– ANEXT = measured Cat 6 reduced by 40 dB
100 200 300 400 500 600 700 800 900 100010
15
20
25
30
35
40
45
50
One−sided BW (MHz)
Shan
non
Capa
city
in G
Bps
Capacity with AWGN and ANEXT with 0dB of ANEXT cancellation
Capacity = 49.36Gbps @ 1000MHz
Using limit lines reduces max capacity to37.71Gbps @ 985MHz
16IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
���!+���,�����$� ����-����������
���!+���,�����$� ����-����������
• Capacity calculations with measured data indicate t hat 10 Gigabit data transmission over 100m Cat 5 or Cat 6 UTP cabl es is not feasible
– Many basic implementation impairments neglected in this simplified analysis
• Actual capacity will be worse
• Alien crosstalk is a fundamental limit– Must be reduced by some means – suggestions are welc ome
– Is disallowing cable bundles, adjacent patch panel locations, or multi-connector
channels an acceptable marketplace solution ?
• Capacity calculations with measured data indicate 1 0 Gigabit data transmission over 100m Cat 7 may be possible
– Further investigation with actual line codes and mo re accurate models warranted
17IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
�� ����.�/���������0!����
�� ����.�/���������0!����
Fantasy Cat 6
18IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
1���������$ ��%�*���"1���������$ ��%�*���"
• 10GBASE-T may be possible on newly specified improved UTP cable with sufficiently low alien cros s talk
– “Fantasy Cat 6”
• ANEXT is only one part of the overall noise budget– ANEXT must be sufficiently small to permit realizable levels for other
impairments
• ADC quantization noise and sample clock jitter are t he next largest impairments
– Residual NEXT/FEXT/echo/ISI, round off noise, transmit distortion, adaptation noise, background noise, etc. also contribute
19IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
�1�.�/����������1�.�/���������
• Assuming a cable with sufficiently low ANEXT, analog-to-digital conversion is the next dominant noise source
– Determined by the resolution and timing jitter of th e ADC
– Reduces noise budget available for ANEXT
• Assume:– Quantization noise is AWGN
– Background noise is AWGN
– ANEXT is the only other uncancelled noise source
– 416 MHz baseband PAM
20IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
�$���%.� �"�� ��!�� �$���%.� �"�� ��!��
• Slicer symbol SNR* = the average PAM-modulated symbo l SNR to achieve SER=10-12
• PAM10 SNR* = 32.21 dB
• MMSE−DFE SNRMMSE = exp{�ln(1+SNR(f))df/B} −1 and the corresponding channel capacity C= �log2(1+SNR(f))df
– Channel SNR(f) is determined by insertion loss, ali en crosstalk, quantization noise (Vpp=2V) and background noise (-155dBm/Hz)
– Target SNRMMSE=SNR*−coding gain+design margin
– Coding gain = 6dB (TCM),
– Design margin should cover the impact of all real-w orld system defects, including:
ü <6dB coding gainü Clock jitterü Uncancelled echo/NEXT/FEXT/ISI
ü Analog non-linearitiesü Analog noiseü Arithmetic noiseü “Other” – system margin
21IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� � "�������������� � "�������������
12
9
6
12
9
6
Design Margin
(dB)
Limit lineMeasured data
NANA21.130.738.21
19.540.819.523.535.21
17.829.117.818.932.21
11
NANANANA38.21
NANANANA35.21
NANA17.824.132.21
10
Channel Capacity (Gbps)
ANEXT reduction
(dB)
Channel Capacity (Gbps)
ANEXT reduction
(dB)
Target SNRMMSE
(dB)
ADC ENOB (bits)
22IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
� �� ��� �&� � "���� �� ��� �&� � "���
• Based on unscaled measured data from 100m- 4 connect or Cat 6 channel with
– 30dB ANEXT reduction– −155dBm/Hz background noise
100 200 300 400 500 600 700 800 900 10005
10
15
20
25
30
One−sided BW (MHz)
Shan
non
Capa
city
in G
Bps
Capacity with AWGN and ANEXT with 30dB of ANEXT cancellation
Capacity = 28.80 Gbps @ 800MHz
23IEEE 802.3 – 10GBT Study Group Interim Meeting
Portsmouth, NH – May 21-22, 2003
�!�"����!���!�"����!��
• 10GBASE-T is not feasible over a large portion of e xisting Cat 5e and Cat 6 cable plants
– ANEXT is the fundamental limit
• A new cable matching Cat 6 performance with suffici ently reducedANEXT could support 10GBASE-T
– 30-35dB ANEXT reduction necessary
– Requires characterization beyond current 250MHz Cat 6 spec
– ENOB > 10 bits for PAM10
• Existing standard Class F cable could support 10GBA SE-T– No further characterization necessary
– ENOB >10 bits for PAM10
• Once the appropriate channel medium is selected, a coded modulation scheme needs to be chosen to optimize pe rformance