Exam A

QUESTION 1Which two options are not task attributes for financial task structure?

http://www.gratisexam.com/

A. Task Type

B. Service Type

C. Work Type

D. Chargeable Flag

E. Scheduled Dates

Correct Answer: BDSection: (none)Explanation

Explanation/Reference:Explanation: Incorrect:Not A: Task types assign default attributes to tasks and control how Oracle Projects processes tasks. Task types specify basic task attributes.Not C: Work types represent a classification of work. You use work types to classify both actual and scheduled work.Not E: Oracle Projects uses start and finish dates to control processing, indicate estimated and scheduled duration, and serve as tools to evaluate projectperformance.The start and finish dates at the project level are:Actual: Actual dates when work on the project started and finished. You can use these dates to drive future timecard and earned value functionality.(not E) Scheduled: Scheduled start and finish dates for the project.Target: The expected lifespan of the project.Estimated: A task manager's estimate of when work on the project will be started and finished.Baseline: The baselined schedule

QUESTION 2A new contract project is created for work for a customer by using event-based billing. A decision has been made to give a discount to the customer on a particularinvoice. You want to apply this discount and reduce the invoice without affecting revenue. Which event type should be used to achieve this?

A. Manual

http://www.gratisexam.com/

B. Invoice Reduction

C. Deferred Revenue

D. Automatic

E. Scheduled Payment

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation: Event Type Classification is: Scheduled Payment, Deferred Revenue, Invoice Reduction, Manual, or Automatic (for billing events only)

QUESTION 3In which two circumstances would it be appropriate to deselect the "Interface Revenue to GL" option in System Implementation Options, before you run the Interfaceto GC?

A. During data migration if Revenue is already in General Ledger

B. When Revenue is handled in Accounts Receivable

C. When AutoAccounting is incorrect and the Revenue interfacing to General Ledger needs to be put on hold.

D. When Finance wants to reconcile Unbilled Receivables/Unearned Revenue

E. When Revenue was generated in error for all projects in Released status, and needs to be corrected.

Correct Answer: ABSection: (none)Explanation

Explanation/Reference:Explanation: A: If the revenue amounts are already interfaced to General Ledger (GL) through a different interface, then uncheck the ‘Interface Revenue to GL’ option in theimplementation options and run the ‘Interface Revenue to GL’ process in Oracle projects. This will turn the flags in the revenue records as accepted in GL, though itis not interfaced. Once this is done, revert back the implementation option back to its original state.

QUESTION 4What type of project will a company require to use Organization Forecasting?

A. contract project

B. Administration Project

C. Organization Planning Project

http://www.gratisexam.com/

D. capital project

E. multi-function project

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation: Note:* Compute Forecast Labor RevenueThis process calculates the potential revenue of labor expenditure items based on established bill rates and markups. The expenditure items that the processselects are billable labor expenditure items charged to contract projects that have not yet been processed by the Generate Draft Revenue process. The items do nothave to be approved to be processed for forecast revenue.

QUESTION 5An organization uses Oracle Projects and has fully installed Oracle Human Resources. Which statement does not apply to this scenario?

A. Employees can be entered and maintained in Oracle Projects.

B. Jobs can be set up in Oracle Projects.

C. Organizations can be defined In Oracle Projects.

D. Organization Hierarchies can be defined in Oracle Projects.

E. Worker Assignments can be viewed in Oracle Projects.

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation: Note: * Oracle Projects fully integrates with Oracle Human Resources to keep track of employees and information relevant to them, such as bill rates and mailing address.

QUESTION 6Identify the four different levels where transaction controls are defined.

A. Expenditure Categories

B. Expenditure Organization

C. Employee

D. Project Organization

http://www.gratisexam.com/

E. Expenditure Type

F. Person Type

Correct Answer: ACDESection: (none)Explanation

Explanation/Reference:Explanation: You can configure transaction controls by the following:(A) Expenditure Category(C) Employee (E) Expenditure TypeNon-Labor Resource

QUESTION 7Your client has expressed a desire to produce and summarize invoice lines for Non-Labor transactions by type of expenditure based on high level tasks of theproject. Which invoice formal grouping should he used to achieve this?

A. Top Task, Expenditure Type

B. Top Task, Employee

C. Revenue Category, Expenditure Category, Top Task

D. Top Task, Expenditure Category

E. Top Task, Revenue Category, Expenditure Category, Expenditure Type

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation: Note: * Oracle Projects processes tasks based on their position in the structure. The three distinct positions are:Top Task: A task whose parent is the projectMid Task: A task that is not a top task or a lowest taskLowest Task: A task that is at the bottom of the structure, without any child tasks* You can configure transaction controls by the following:Expenditure Category EmployeeExpenditure Type

http://www.gratisexam.com/

Non-Labor Resource

QUESTION 8Which three types of People Resources does Oracle Projects support?

http://www.gratisexam.com/

A. Team Roles

B. Straight Time

C. Jobs

D. Item

E. Named Person

Correct Answer: ACESection: (none)Explanation

Explanation/Reference:Explanation: Note:* People resources represent named persons or any grouping of named persons (E) by attributes such as job (C), organization, or role (A), whose time (effort) capacity is consumed to complete the project work. Example: Amy Marlin

QUESTION 9Identify three adjustment actions that require submission of Distribute costs program to process the adjustments?

A. Change Comment

B. Release Hold

C. Split

D. Transfer

E. Recalculate Revenue

F. Capitalizable to Non-Capitalizable

Correct Answer: CDF

http://www.gratisexam.com/

Section: (none)Explanation

Explanation/Reference:Explanation: After you have performed the adjustment actions, you need to run the appropriate processes to process the adjustments.The table below notes what processes to run to process each adjustment action.

QUESTION 10A customer has gone into bankruptcy and is unable to pay their bills. This means that the project revenue is now overstated. How can the customer reduce therevenue on the project to accurately reflect the amount of collectable revenue?

A. Create a revenue write-off event for the uncollectable element and interface to General Ledger.

B. Create a negative funding line and assign to the project thus reducing its revenue.

C. Create a cost adjustment on the project using preapproved batches.

D. Create a credit memo in Oracle Projects and interface to Accounts Receivable.

E. Enter a transaction control against the expenditure types and regenerate the draft invoice.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 11What must be defined to enable a company to use an organization for a straight time expenditure?

A. Define the organization with the Following:1. Add Cost Centre as the Organization type.2. Add an organization classification of HR Organization.3. Add the organization to an organization hierarchy.

B. Define the organization with the Following:1. Add the organization classifications HR Organization and Project Expenditure/Event2. Add the organization to an organization hierarchy3. Add the organization hierarchy to the appropriate Oracle project implementation option setting

C. Define the organization with the following:1. Add the organization classifications Project/Task Owning Organization and Project Expenditure/Event Organization.2. Add the organization to an organization hierarchy.3. Add the organization hierarchy to the appropriate Oracle project implementation option setting.

http://www.gratisexam.com/

D. Define the organization with the following:1. Add the organization classifications Project Expenditure/Event Organization.2. Add the organization to an organization hierarchy.3. Add the organization hierarchy to the appropriate Oracle project implementation option setting.

E. Define the organization with the Following:1. Add the organization classifications HR Organization and Project Expenditure/Event2. Add the organization to an organization hierarchy.3. Define Organization Labor Costing Rules.

Correct Answer: ESection: (none)Explanation

Explanation/Reference:Explanation: Note:* You can set this at the Inventory Organization level in the Project Manufacturing Parameters window, the Costing tabbed region. This allows WIP employeeresources and Project straight time hours to be summarized as Straight Time Expenditure Type Class.* expenditure type classAn additional classification for expenditure types that indicates how Oracle Projects processes the expenditure types. For example, if you run the Distribute LaborCosts process, Oracle Projects will calculate the cost of all expenditure items assigned to the Straight Time expenditure type class. Formerly known as systemlinkage

QUESTION 12A customer has two operating units: US and Ireland. A project that is set in the Ireland operating unit requires the services of employees from the US operating unit.Identify three mandatory steps that must be completed for the employees in the US to enter their time on the project and for costs to be successfully distributed.

A. Set up Internal Billing Implementation options in US and Ireland.

B. Define provider controls in US and receiver controls in Ireland.

C. Set up a new transaction source to receive Intercompany transactions in Ireland.

D. For the project in Ireland, select "Allow Cross Charges to all Operating Units within Legal Entity".

E. For the project in Ireland, set up transaction controls to allow charges from other operating units.

Correct Answer: BCDSection: (none)Explanation

Explanation/Reference:Explanation: B: Provider and Receiver Controls Setup

http://www.gratisexam.com/

For each provider operating unit or receiver operating unit involved in the cross charge, the Provider/Receiver Controls window Provider Controls and ReceiverControls tabs specify:The cross charge method to use to process intercompany cross charges and to override default cross charge method for inter-operating unit cross charges.Attributes required for the provider operating unit to process intercompany billing to each receiver operating unit. This includes the Intercompany Billing Project andInvoice Group.Attributes required for the receiver operating unit to process intercompany billing from each provider operating unit. This includes the supplier site, expenditure typeand expenditure organization.* (C) Intercompany Billing AccountingCompanies choose the intercompany billing method largely due to legal and statutory requirements. When you use this method, Oracle Projects generates physicalinvoices and corresponding accounting entries at legal transfer prices between the internal seller (provider) and buyer (receiver) organizations when they cross alegal entity boundary or operating units.* (D) Overview of Cross Charge When projects share resources within an enterprise, it is common to see those resources shared across organization and country boundaries. Further, projectmanagers may also divide the work into multiple projects for easier execution and management. The legal, statutory, or managerial accounting requirements ofsuch projects often present complex operational control, billing, and accounting challenges.Oracle Projects enables companies to meet these challenges by providing timely information for effective project management. Project managers can easily viewthe current total costs of the project, while customers receive bills as costs are incurred, regardless of who performs the work or where it is performed.Reference: Oracle Project Costing User Guide, Cross Charge

QUESTION 13A project is undertaken for a customer where all labor costs are non-billable, and Non-Labor costs are billable if the accumulated costs incurred are greater than$10k. How can Oracle Projects be implemented to support this?

A. Use transaction controls to restrict billing to Non-Labor elements and to calculate the bill amounts on Non-Labor.

B. Use transaction controls to billing Non-Labor elements, capture the value on the project, and then use the Non-Labor billing extension to calculate when anactivity is billable.

C. Create an agreement and funding for $10k only, and fund only those tasks on a project where you estimate to incur costs of $10k or more.

D. Use the cost-to-cost billing extension to build billing rules to meet the requirement.

E. Use the cost accrual extension.

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 14An organization posts project costs to the balance sheet as they are incurred. Each month they recognize project revenue on each project. Select the option thatensures that costs are credited from the balance sheet and debited to profit and loss as revenue is recognized.

http://www.gratisexam.com/

A. Use events for project revenue and use GL journals to carry out the relevant account postings.

B. Implement a project revenue extension with appropriate event types and AutoAccounting definition.

C. Use miscellaneous transactions to generate revenue with the appropriate AutoAccounting definition.

D. Use preapproved batches with a class type of "Work in Process" to generate revenue with the appropriate AutoAccounting definition.

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 15Company ABC wants to deploy workplan task structures where the lowest tasks represent deliverables. They want to collect costs at a level higher than the lowesttasks for groups of deliverables. Which two task structure relationships are available for them to consider?

A. Define the structures as Fully Shared.

B. Utilize Task-based mapping structures.

C. Define a separate branch of task hierarchy for deliverables.

D. Define a separate branch of task hierarchy for cost collection.

E. Define the structures as Partially shared.

Correct Answer: BCSection: (none)Explanation

Explanation/Reference:Explanation: Note:* You can set up two types of project structures in Oracle Projects:/ Workplan structures consist of tasks that help project managers and team members plan, track, and deliver projects on time. / Financial structures consist of tasks that help project managers and financial administrators track billing, costs, budgets, and other financial information forindividual projects.* If you enable both a workplan structure and a financial structure for your project or project template, you can decide whether or not they are integrated, and if so, towhat degree. You do this by choosing one of the following options on the Structures setup page:/ Shared Structures: Enables you to generate a financial structure with a task hierarchy that is fully shared by the workplan structure task hierarchy. Workplan andfinancial structures are fully shared by default./ Partially Shared Structures: Enables you to generate a financial structure that is partially shared by the workplan structure hierarchy./ Non-Shared: Task-Based Mapping: Enables you to map individual workplan structure tasks to individual financial structure tasks./ Non-Shared: No Mapping: Choose this if you do not want to integrate your project workplan and financial structures in any way.

http://www.gratisexam.com/

QUESTION 16A US-based company is providing resources to a UK subsidiary and has implemented Oracle Projects intercompany billing solutions. How would the US companycreate the Accounts Payable invoice in the UK operating unit?

http://www.gratisexam.com/

A. when the draft intercompany invoice is approved in the us Projects ledger

B. when the draft intercompany revenue is approved in the US Projects ledger

C. Invoice automatically created as part of the PRC: Tieback Invoices from Receivables in the US Project ledger

D. when the draft intercompany invoice is released in the US Projects Ledger

E. on creation of the Intercompany revenue in the US General Ledger

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation: The provider operating unit runs the process PRC: Tieback Invoices from Receivables, which automatically creates corresponding intercompany invoice supplierinvoices ready to be interfaced to Oracle Payables in the receiver operating unit.Note:See step 6 below.Intercompany Billing Processing FlowIntercompany billing processing requires the following steps:1. The provider operating unit enters or imports cross charge transactions.2. The provider operating unit distributes costs of the cross charges, which are identified as cross charge transactions by the cost distribution processes. Thedistribution of the costs is independent of revenue generation and are distributed even if revenue has not been generated.The provider operating unit also imports project-related supplier costs from Oracle Purchasing and Oracle Payables and project-related expense report costs fromOracle Payables.3. The provider operating unit runs the process PRC: Generate Intercompany Invoices for a Single Project, or the process PRC: Generate Intercompany Invoices fora Range of Projects, to generate draft intercompany invoices with the associated intercompany receivable and revenue accounts, and the transfer price.4. The provider operating unit reviews, approves, and releases the intercompany invoices.5. The provider operating unit interfaces the approved intercompany invoices to Oracle Receivables. You can include the following activities in this process:o Accounting for invoice roundingo Creation of receivable invoices including sales tax6. The provider operating unit runs the process PRC: Tieback Invoices from Receivables, which automatically creates corresponding intercompany invoice supplier

http://www.gratisexam.com/

invoices ready to be interfaced to Oracle Payables in the receiver operating unit.Use Oracle Receivables to print the invoice as well as to create accounting for Oracle Subledger Accounting.7. If cost reclassification is enabled, the provider operating unit performs the following processing steps:a. Runs the process PRC: Generate Cross Charge Accounting Events to generate accounting events for the provider cost reclassifications.b. Runs the process PRC: Create Accounting to create accounting entries for the provider cost reclassification accounting events in Oracle Subledger Accounting.When you run the process in final mode, you can optionally choose to transfer the accounting to Oracle General Ledger. If you select this option, the createaccounting process initiates Journal Import in Oracle General Ledger. The receiver operating unit imports the intercompany supplier invoices into Oracle Payables. This import process calculates recoverable and non-recoverable taxamounts. Upon review and approval in Oracle Payables, the receiver operating unit runs the process Create Accounting to create subledger accounting entries forthe supplier invoices in Oracle Subledger Accounting. When you run the process in final mode, you can optionally choose to transfer the accounting to OracleGeneral Ledger. The receiver operating unit interfaces the supplier invoice to Oracle Projects, which pulls in the non-recoverable tax amounts as additional project costs. (Optional) You can require the receiver operating unit to run additional customized processes to create additional accounting entries in Oracle Subledger AcReference: Oracle Project Costing User Guide, Cross Charge

QUESTION 17You have defined a Non-Labor resource "Mini Truck" with an expenditure type "Vehicle" that has a rate of $100. This resource is attached to three Non-Laborresource organizations: "Construction-East," "Construction-West," and "Construction-Central."How do you set up a rate of $150 for usage charges when the "Mini Truck" owned by "Construction-Central" is charged to a project?

A. In the Project setup, enter a rate of $150 for "Construction-Central" in the organization overrides.

B. In the Non-Labor resources setup, select the "Construction-Central" organization and enter a rate of $150.

C. Create a new rate schedule with a rate of $150 for "Mini Truck" and attach it to the project.

D. Create a new rate schedule with a rate of $150 for "Mini Truck" and attach it to "Construction-Central."

E. Write custom code in Non-Labor cost override extension.

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 18A project is enabled for Burdening by setting up a burden schedule at the project type level. A Miscellaneous expenditure Item Is charged to the project with a rawcost of $100 and expenditure type "Overhead." The "Overheads" expenditure type is excluded from all cost bases in the burden structure. What happens when the"PRC: Distribute usage and Miscellaneous Costs" program is run for this project?

A. The program errors with the message "Missing Expenditure type."

B. The program completes successfully; Raw Cost = $100, Burden Cost= $0, Total Burdened cost = $100.

http://www.gratisexam.com/

C. The program completes successfully; Raw Cost = $100, Burden Cost= $100, Total Burdened cost = $100.

D. The program completes successfully; Raw Cost = $100, Burden Cost= $0, Total Burdened cost = $0.

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation: Note: * Distribute Usage and Miscellaneous CostsThe process computes the costs and determines the default GL account to which to post the cost for expenditure items with the following expenditure type classes:UsagesBurden TransactionsMiscellaneous TransactionsInventory and WIP transactions not already costed or accounted

QUESTION 19A customer wants to make a new classification mandatory on all their new projects. Select the three options that could help them accomplish this.

A. Define the classification as Mandatory in the Classification configuration.

B. Define the classification as Mandatory in the Project Type configuration.

C. Define the classification category to allow one code only.

D. Define project status controls to disallow project status changes where classification category codes are missing.

E. Define the classification as Required on the appropriate project templates in the Quick Entry screen.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation: Note:* You define project classifications to group your projects according to categories you define. A project classification includes a class category and a class code. Thecategory is a broad subject within which you can classify projects. The code is a specific value of the category. * (see step 3 below) Defining class categories and class codes To define class categories and class codes:1. Navigate to the Class Categories and Codes window.2. Enter a unique Class Category name and a Description.3. Specify whether the class category is mandatory for every project you define.

http://www.gratisexam.com/

Enable if all projects must have a code assigned to this class category. Do not enable if this class category is optional. If you do not enable this option, you cannotuse this class category in your AutoAccounting rules.4. Specify whether you want to use the class category in your AutoAccounting rules.Suggestion: For each project, you can use only one code with one class category for use with AutoAccounting rules. If an AutoAccounting category already existswithin a particular date range, assign an end date to the existing AutoAccounting category and then create a new one.5. Specify whether you want to allow entry of only one class code with this class category for a project.Note: Defining multiple class codes for one category for a project may affect reporting by class category; defining multiple class codes may cause your numbers tobe included more than once.6. Enter the Name, Description, and Effective Dates for each class code.7. Save your work.Reference: Project Classifications (Class Categories and Class Codes)

QUESTION 20An employee has entered eight hours of billable time on a project. You want only three hours to be billable and five hours to be nonbillable. What is the adjustmentaction that should be applied on this expenditure item?

A. Transfer the item.

B. Change the billable status.

C. Split the item.

D. Apply billing hold.

E. Change quantity.

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation: You can split an item into two items so that you can process the two resulting split items differently.For example, you may have an item for 10 hours, of which you want 6 hours to be billable and 4 hours to be non-billable. You would split the item of 10 hours intotwo items of 6 hours and 4 hours, marking the 6 hours to be billable and 4 hours to be non-billable.The resulting split items are charged to the same project and task as the original item.Reference: Types of Expenditure Item Adjustments

QUESTION 21Identify three transactions for which Oracle Project Costing enforces budgetary controls.

A. project-related purchase requisitions and purchase orders entered in Oracle Purchasing

B. expense reports entered In Oracle iExpenses

C. supplier invoices entered in Oracle Payables

http://www.gratisexam.com/

D. contingent worker purchase orders entered in Oracle Purchasing

E. employee timecards entered in Oracle Time and Labor

Correct Answer: ACDSection: (none)Explanation

Explanation/Reference:Explanation: Note: * Enable Budgetary Controls and Encumbrance AccountingTo use budgetary controls, you must implement budgetary control and encumbrance accounting for the ledger in Oracle General Ledger and enable encumbranceaccounting in Oracle Payables or Oracle Purchasing. Encumbrance accounting automatically creates encumbrances for requisitions, purchase orders, and invoices.* PSA: Budgetary Control Report TemplateThis profile option can be set at the site, application, responsibility, and user levels. You must select Budgetary Control Results Template as the value for this profileoption to enable users to view funds check results from Oracle Purchasing and Oracle Payables after a funds check.Reference: Oracle Projects Implementation Guide, Implementing Oracle Project Management

QUESTION 22You have imported Labor transactions into Oracle Projects from Oracle Time and Labor by running the "PRC: Transaction Import" program. What is the correctsequence to run the concurrent programs listed below to transfer the cost and accounting entries of these transactions to General Ledger?1. PRC: Distribute Labor Cost2.PRC: Transfer Journal Entries to GL3.PRC: Create Accounting (with the Transfer to GL option set to "No")4.PRC: Interface Labor Costs to GL5.PRC: Generate Cost Accounting Events6.PRC: Distribute and Interface tabor costs to GL

A. 1, 3, 6

B. 1, 5, 3, 4

C. 1, 5, 3, 2

D. 1, 2

E. 3, 6

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

http://www.gratisexam.com/

The following activities take place as part of the expenditures process flow for labor costs:1. Run the process PRC: Distribute Labor Costs. This process calculates the raw and burden cost components for labor cost expenditure items. It also usesAutoAccounting to determine the default debit account for each expenditure item.2. Run the process PRC: Generate Cost Accounting Events. This process uses AutoAccounting to determine the default credit account for each expenditure item. Italso generates accounting events for distributed transactions. You can optionally select Labor Cost as the process category to limit the process to labor costs.3. Run the process PRC: Create Accounting. This process creates subledger journal entries for eligible accounting events. You can run the process in either draft orfinal mode. You can optionally select Labor Cost as the process category to limit the process to labor cost accounting events. Optionally, the process can postjournal entries in Oracle General Ledger.If you define your own detailed accounting rules in Oracle Subledger Accounting, then Oracle Subledger Accounting overwrites default accounts, or individualsegments of accounts, that Oracle Projects derives using AutoAccounting.4. Run the process PRC: Transfer Journal Entries to GL. When you run the process PRC: Create Accounting, if you select No for the parameter Transfer to GL,then you run the process PRC: Transfer Journal Entries to GL to transfer the final subledger journal entries from Oracle Subledger Accounting to Oracle GeneralLedger. You can optionally select Labor Cost as the process category to limit the process to labor cost accounting events. Optionally, the process can post journalentries in Oracle General Ledger.5. Run Journal Import in Oracle General Ledger. (optional) This process brings the final accounting entries from Oracle Subledger Accounting into Oracle GeneralLedger.Reference: Oracle Projects Fundamentals, Expenditures Process Flow Example: Labor Cost

QUESTION 23Your organization has configured employee rate schedules. Which three schedules can utilize employee rate schedules when delivering a project?

A. Job rate schedules

B. Planning schedules

C. Cost rate schedules

D. Bill rate schedules

E. Resource class rate schedules

Correct Answer: BCDSection: (none)Explanation

Explanation/Reference:Explanation: You can use rates to calculate amounts for costing, billing, and workplan and financial planning. Oracle Projects determines rates from a combination of rateschedules and rate overrides. You can define the following four types of rate schedules in Oracle Projects:* Employee: Use this type of rate schedule to define standard hourly rates or percentage markups by employee. You can use employee rate schedules as planningschedules (B), cost rate schedules (C) , and bill rate schedules (D).* Job: Use this type of rate schedule to define standard hourly rates by job title. When you enter a job-based rate schedule, you enter a job group to indicate whichjobs are used to determine rates. You can use job schedules as planning rate schedules, cost rate schedules, and bill rate schedules.* Resource Class : Use this type of rate schedule to define planning rates by resource class, or as a combination of resource class and organization.* Nonlabor: Use this type of rate schedule to define rates or percentage markups by nonlabor expenditure type or a combination of nonlabor expenditure type and

http://www.gratisexam.com/

nonlabor resource. You can use nonlabor rate schedules as planning rate schedules, cost rate schedules, and bill rate schedules.Reference: Rate Schedule

QUESTION 24The Profile option "PA: Cross Project User-Update" is set to "Yes" for a Projects module user. Which two statements apply?

A. The use must be named as a Key Member on a project to be able to see Summary Labor Costs.

B. The user will be able to update projects across all Operating Units.

C. The user will be able to update only the projects belonging to the same Operating Unit to which the user belongs.

D. The user view Summary Labor Costs for all projects.

E. The user must also have Organization Authority for all Operating Units to update all projects.

Correct Answer: BESection: (none)Explanation

Explanation/Reference:Explanation: PA: Cross Project User - Update: Enables users to update all project information. This applies only to the operating units the responsibility has access to through theMO: Operating Unit profile option or the MO: Security Profile profile option.Note: Users whose responsibilities are associated with a cross business group access security profile can view and update project and resource information acrossall business groups in your enterprise.Reference: Oracle Projects Fundamentals, Responsibility-Based Security

QUESTION 25Which three Project foundation setups are shared across Operating Units in a multi-organization setup?

http://www.gratisexam.com/

A. Project Classifications categories

B. Project Types

C. Project Templates

D. Project numbers

E. Expenditure Types

http://www.gratisexam.com/

Correct Answer: ABESection: (none)Explanation

Explanation/Reference:Explanation: A: Project Classifications (Class Categories and Class Codes)You define project classifications to group your projects according to categories you define. A project classification includes a class category and a class code. Thecategory is a broad subject within which you can classify projects. The code is a specific value of the category.B: In a multi-organization environment, you must set up project types for each operating unit. It is possible to have the same project type names in multiple operatingunits. However, each project type has it own attributes to control project processing by operating unit.E: In a multi-organization environment, expenditure types are set up once and are shared across all operating units.Reference: Oracle Projects Implementation Guide, Implementing Oracle Project Costing

QUESTION 26Which three statements are correct about defining a cost budget for a project?

A. You can enter budget amount at the project level, the top task level, or the lowest task level.

B. You can enter budget amount only at the lowest task level.

C. You can enter budget amount for a combination of lowest task and a labor resource.

D. You can enter budget amount only at the top task level.

E. You can enter budget amount for a combination of lowest task and a Non-Labor resource.

F. You cannot enter budget amount for a combination of lowest task and a Non-Labor resource.

Correct Answer: ACFSection: (none)Explanation

Explanation/Reference:Explanation: A: You can budget at the project, top task, or lowest task level.Note:* When you create budgets and forecasts that do not use budgetary control and budget integration features, you can choose to enter budget and forecast amountsat any level of the financial structure by selecting one of the following lowest level planning level options:ProjectTop TaskLowest TaskWhen you choose the Lowest Task option, you can enter amounts at all levels of the financial structure including top tasks, middle-level tasks, and lowest tasks.You can also enter amounts at multiple task levels within the same branch of the financial structure. Oracle Projects treats the amounts that you enter at each tasklevel as incremental amounts that roll up into the total amounts for the project.

http://www.gratisexam.com/

QUESTION 27A customer is using Oracle Payables and Oracle Projects. The customer has two suppliers set up with names X and Y, respectively. Supplier Y has been mergedwith Supplier X. The Supplier Merge Program is run from the Supplier Merge option in Oracle Payables and you have chosen to merge all transactions. What willhappen to the supplier references on transactions related to Supplier Y that are already interfaced to Oracle Projects?

A. The Supplier Merge Program does not impact any supplier transactions that are already interfaced to Oracle Projects.

B. The Supplier Merge Program completes with error, the merge is not possible because transactions related to Supplier Y are already interfaced to OracleProjects.

C. The supplier references to Supplier Y will be modified to Supplier X for all transactions existing in Oracle Projects.

D. The transactions related to Supplier X and Y will be deleted from Oracle Projects.

E. The transactions related to Supplier Y will be deleted from Oracle Projects.

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation: Note:* When you merge supplier information you have different options. You can choose to merge both invoices and purchase orders. If you choose to merge invoices,then you can merge all invoices or just unpaid invoices. When you choose to merge all invoices, any associated payments are merged as well.* Supplier MergeYou can merge suppliers in Oracle Payables to maintain your supplier records. This functionality enables you to merge duplicate suppliers into a single,consolidated supplier. You can use it to merge transactions within the same supplier from one supplier site to a different supplier site. You can also choose to mergeall transactions for a supplier into a new supplier, or you can choose to merge only unpaid invoices.The supplier merge program in Oracle Payables updates the supplier references on related transactions in Oracle Projects.

QUESTION 28You are setting up an AutoAccounting rule and trying to use "Class Code" as the parameter for that rule. Which setup must exist in order to use "Class Code" asone of the parameters?

A. Enable AutoAccounting for one Class Code of a Class Category.

B. Enable AutoAccounting for all the Class Codes of a Class Category.

C. Enable AutoAccounting for the Class Category.

D. Enable AutoAccounting for both Class Category and Class Code.

Correct Answer: ASection: (none)Explanation

http://www.gratisexam.com/

Explanation/Reference:Explanation: * AutoAccounting Parameter: Class CodeAutoAccounting class code on the project.Note: Since you can define many project classification categories, the Class Code parameter always corresponds to the one classification category that youspecified as the AutoAccounting classification category.Reference: Oracle Projects Implementation Guide

QUESTION 29A company has multi-currency projects and tasks. What is the hierarchy in which the currency attributes are allocated to a transaction?

A. Project, Task

B. Implementation Options, Project, Task

C. Task, Project, Implementation Options

D. Task, Implementation Options, Project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation: Note:Setting up Multi-Currency TransactionsTo set up your system to process multi-currency transactions, perform the following steps:* Implementation OptionsUse the Currency Implementation Options to control the default values for currency attributes at the operating unit level. Oracle Projects uses the currency attributesto calculate currency exchange rates. See: Currency Implementation Options.* CurrencyFor each project for which you want to process multi-currency transactions, set up the Currency options in the project and task options window. This option enablesyou to enter default currency attributes for a project. See: Currency, Oracle Projects Fundamentals.* Cross ChargeYou can use the Cross Charge Options to specify whether the project can accept charges from other operating units. See: Cross Charge Setup, Oracle ProjectsFundamentals.* Task Currency and Cross Charge Options* You can use the Task Currency and Cross Charge Options to override the costing currency conversion attributes and cross charge options in a lowest task. See:Currency, Oracle Projects Fundamentals and Cross Charge Setup, Oracle Projects Fundamentals.* Transaction Entry and Transaction ImportDuring Transaction Entry and Transaction Import, you can override the project and task currency attributes. See: Entering Expenditures, Oracle Project Billing UserGuide and Currency Conversion Attributes for Imported Transactions, Oracle Projects APIs, Client Extensions, and Open Interfaces Reference.Reference: Oracle Projects Implementation Guide

http://www.gratisexam.com/

QUESTION 30Identity three transactions that can be entered as a pre-approved expenditure batch:

A. Burden

B. Supplier Invoices

C. Usages

D. Expense Reports

E. Miscellaneous

Correct Answer: ADESection: (none)Explanation

Explanation/Reference:Explanation: Pre-approved expenditures are timecards, expense reports (D), usage logs, miscellaneous transactions (E), burden transactions (A), inventory transactions, andwork in process transactions usually completed on paper and approved by a supervisor. You enter pre-approved expenditures into Oracle Projects in batch mode,generally on a weekly basis. After you enter the batches into the system, you submit them for review and then release them for cost distribution.Reference: Pre-Approved Expenditures

QUESTION 31An organization has agreed to bill rates based on a person's job, which are updated annually. The rates are recorded on a default bill rate schedule that is attachedto each project. An employee has and HR assignment job of Consultant. However, the employee is temporarily working on a project as a Project Manager. What isthe correct way to ensure that the employee's time is billed correctly?

http://www.gratisexam.com/

A. Amend the employee's HR assignment to Project Manager.

B. Add the employee as a separate line to the default bill rate schedule.

C. Use the transaction control functionality at the project level.

D. Use the assignment override at the project level.

E. Use the employee bill rate override at the project level.

Correct Answer: D

http://www.gratisexam.com/

Section: (none)Explanation

Explanation/Reference:Explanation: Job Assignment OverridesYou can override both an employee's job assignment and an employee's billing title for this project or lowest level task.When you override an employee's job assignment, the new job assignment determines bill rates for the employee's billing on this project or lowest task (if this taskuses job bill rates). You can choose any active job in the Oracle Applications database.When you override an employee's primary billing title, the new billing title appears on future invoices for this employee's billing (if this project's labor invoice formatdisplays an employee billing title).Any job assignment override you enter for this project or lowest task takes precedence over any project job assignment override.

QUESTION 32Your company has set up the burdening functionality to capture the overheads incurred on all projects. They have decided to store these overhead costs as aseparate expenditure item on the same project and also charge it to a separate expense account. Which step would you perform to set up the required expenseaccount?

A. Set up the account at the expenditure type defined for the Burden transaction.

B. Set up the Total Burdened Cost Credit AutoAccounting function.

C. Set up the Burden Cost Account AutoAccounting function.

D. Set up the Burden Cost Clearing Account AutoAccounting function.

E. Set up the account at the expenditure category defined for the Burden transaction.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation: Storing Burden Costs as a Separate Expenditure Item on the Same ProjectYou can choose to hold the burden cost components as a separate expenditure item on the same project. The expenditure items storing the burden costcomponents are identified with a different expenditure type that is classified by the expenditure type class Burden Transaction.Reference: Oracle Project Costing User Guide

QUESTION 33Which types of rate schedules should be defined to allow rates to be used to generate financial plans?

A. Job Labor Rates ScheduleNon Labor Rate Schedule

http://www.gratisexam.com/

B. Resource Class SchedulePlanning Rate ScheduleLabor Rates Schedule

C. Resource Class ScheduleLabor Rates ScheduleNon Labor Rate Schedule

D. Resource Class SchedulePlanning Rate ScheduleNon Labor Rates Schedule

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation: Defining Rate SchedulesYou can define four types of rate schedules. The following table lists the four types of rate schedules and indicates how you can use each rate schedule type inOracle Projects. Note:* If you select the option to use planning rates, then you can choose the cost and revenue rate schedules to use to generate amounts. If you do not select the optionto use planning rates, then Oracle Projects automatically chooses the rate schedules that are used to calculate actual cost and revenue (bill) amounts.* You must specify rate schedules for resource class. When Oracle Projects is unable to determine the actual or planning rates to apply in a calculation, OracleProjects automatically applies rates from the default rate schedules you specify for resource class.Reference: Oracle Projects Fundamentals

QUESTION 34Identify the correct setup to Integrate Project costing with Oracle Inventory.

A. 1. In Oracle Inventory, enable Project Cost Collection for each organization.2. In Oracle Projects, define an expenditure type with class "Inventory."3. Define the project related transaction source in Oracle Inventory.

B. 1. Set up Oracle Project Manufacturing.2. In Oracle Projects, define an expenditure type with class "Inventory."3. Define the project-related transaction source in Oracle Inventory.

C. 1. In Oracle Inventory, enable Project Cost Collection for each organization.2. In Oracle Projects, define an expenditure type with class "Inventory."3. Define the project-related transaction type in Oracle Inventory.

D. 1. Oracle Project Manufacturing must be set up. 2. In Oracle Inventory, enable Project Cost Collection for each organization.

http://www.gratisexam.com/

3. Define the project-related transaction source in Oracle Inventory

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation: * Integrating Projects with Inventory without Project ManufacturingYou can implement Inventory to Projects integration so that you can issue from inventory to projects without installing Project Manufacturing. To implement thisintegration, follow these steps:1. Enable Project Cost Collection. In the Organization Parameters window in Oracle Inventory, enable the Project Cost Collection Enabled box. See Defining CostingInformation,Oracle Inventory User's Guide.2. Create a Project-Enabled Transaction Type. 3. Set the INV: Project Miscellaneous Transaction Expenditure Type Profile Option. In Oracle Inventory, set the value of this profile option to User Entered. With thissetting, You must enter expenditure types for project miscellaneous transactions.4. Create an Inventory Expenditure Type. In Oracle Projects, create an expenditure type with the transaction type class Inventory. * Oracle Inventory IntegrationThe following steps are required for Oracle Inventory integration:1. Install and implement Oracle Inventory2. Define project-related transaction types in Oracle InventoryReference: Oracle Projects Implementation Guide

QUESTION 35A company requires advance payments for their contract projects. How would they ensure that for specific types of work they always have an advance payment?

A. Create a specific agreement type and use the advance receipts required extension to ensure that these agreements require advance payments.

B. Set the customer profile in Accounts Receivable to require advance payments.

C. Create a transaction control for specific agreement types to ensure that advance payments are received.

D. Enter a negative agreement value and funded amount.

E. Fund the projects with a dummy agreement.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation: Note:* You can set up an agreement to require advance payments by selecting the Advance required on the agreement. You can also use the Advance Required client

http://www.gratisexam.com/

extension to determine which agreements require advance payments. On these agreements, you can enter funding only up to the amount of advance payments.The ability to change the Advance Required agreement option is controlled by function security.* Agreements with Advance PaymentsYou can require advance payments on an agreement and record advance payments as they are made. When you generate draft invoices for projects that arefunded by the agreement, the advance balance that is displayed on the funding summary is reduced. You then interface the invoice to Receivables. The AutoInvoiceprocess in Oracle Receivables reduces the balance on the advance.

QUESTION 36Your company wants to define all its equipments as Non-Labor resources to track the cost incurred on the usage of these equipments, when defining theequipment. When defining the equipment as a Non-Labor resource in the system, you need to assign an expenditure type to it. What kind of expenditure type to it.What kind of expenditure type can be assigned to a Non-Labor resource?

A. expenditure type defined with Expenditure Type Class as Work in Process

B. expenditure type defined with Expenditure Type Class as Burden transactions

C. expenditure type defined with Expenditure Type Class as Supplier Invoices

D. expenditure type defined with Expenditure Type Class as Miscellaneous Transactions

E. expenditure type defined with Expenditure Type Class as Usages

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation: Oracle Projects uses the following expenditure type classes to process non-labor project costs:* Usages - Asset usage costs are interfaced to Oracle General Ledger.* Supplier Invoices - Oracle Payables supplier invoices are interfaced from Oracle Payables to Oracle Projects.* Miscellaneous Transaction - Miscellaneous Transactions are used to track miscellaneous project costs. This expenditure type class is similar to usages. Thedifference is that, for miscellaneous transactions expenditure items, you are not required to specify a non-labor resource or a non-labor resource organization, asyou are for usage expenditure items. Miscellaneous transactions may be used for the following costs:Fixed assets depreciationAllocationsInterest charges* Burden Transaction - Burden transactions track burden costs that are calculated in an external system or calculated as separate, summarized transactions. Thesecosts are created as a separate expenditure item that has a burdened cost amount, but has a quantity and raw cost value of zero. Burden transactions areinterfaced to Oracle General Ledger. As with any other transaction in Oracle Projects, you can adjust and capitalize burden transactions, or accrue revenue orgenerate invoices for these transactions.* Work In Process - This expenditure type class is used for Project Manufacturing WIP transactions that are interfaced from Manufacturing to Oracle Projects. Youcan also use this expenditure type class when you import other manufacturing costs via Transaction Import or when you enter transactions via pre-approved batchentry.Reference: Expenditure Type Classes

http://www.gratisexam.com/

QUESTION 37A customer needs to enable all employees to enter timecards through the web against projects and tasks. What needs to be implemented to allow time to berecorded in Projects?

A. Project CostingOracle Time and LaborHuman Resources

B. Oracle Time and LaborPayrollPurchasing

C. Project CostingProject ManufacturingHuman Resources

D. Projects Resource ManagementOracle Time and LaborHuman Resources

E. Project CostingOracle Time and LaborHuman ResourcesPayroll

Correct Answer: ESection: (none)Explanation

Explanation/Reference:Explanation: Note:* Payroll* Time & Labor.There are many reports within Oracle Time & Labor to gather data about timecards entered through self-service and to gather data about timecards that you havetransferred to the professional forms timecard window.Reference: Oracle Time and Labor Implementation and User Guide

QUESTION 38A customer has provided a purchase order for $100k. The customer issues an additional $20k to the original purchase order. How would you invoice the totalamount of $120k on only one invoice as per the terms of the contract?

A. Create a separate agreement and funding for $20k.

B. Update the existing agreement value to $120k and add an additional funding line against the project for $20k.

http://www.gratisexam.com/

C. Update the cost budget to $l20k.

D. Create a manual invoice in Accounts Receivable for the additional value.

E. Update any existing transactions to allow billing to the new amount.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 39The Finance Director is concerned that some of his or her project revenue may be overstated. What it should be reviewed to understand the revenue position oneach project?

A. the Project Status Inquiry to review the project's margin figures

B. the expenditure inquiry to understand the project's revenue position against the invoice position

C. the Project Summary unbilled receivables and unearned revenue report, which will identify all unearned revenue

D. the revenue review form to inquire on the amount of revenue raised and invoices raised on a project

E. the invoice review form to inquire on the amount of revenue raised and invoices raised on project

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation: Summarize Unbilled Receivables / Unearned Revenue BalancesThe summarize unbilled receivables/unearned revenue balances process creates summary data required for running the UBR and UER reports. The processcreates summary balances for draft revenue and draft invoices in Oracle Projects. The process summarizes amounts for draft revenues for which the process PRC:Generate Revenue Accounting Events has successfully generated events. The process summarizes amounts for draft invoices that have been transferred,imported, and successfully tied back to Oracle Receivables.The unbilled receivables and unearned revenue transactions are summarized by project, by account segment, cost center, and GL period, deriving the summaryamounts used in the reports.

QUESTION 40After receiving supplier costs from the Oracle Payables Supplier Invoices transaction source vow customer wants to perform adjustments in Oracle Projects.Which three setups should exist?

A. AutoAccounting for Supplier Cost Credit Account

http://www.gratisexam.com/

B. Transaction Source enabled for Adjustments

C. Default Supplier Cost Credit Account under project implementation options

D. Project/Task level Transaction Controls

E. AutoAccounting for Supplier Invoice Cost Account

Correct Answer: BCESection: (none)Explanation

Explanation/Reference:Explanation: C: If you enable the Allow Adjustments option for a predefined transaction source for supplier costs, you must complete at least one of the following setup steps:/ (C) Specify the default supplier cost credit account for supplier cost adjustments in Oracle Projects implementation options for each operating unit./ Define a rule in Oracle Subledger Accounting to determine the supplier cost credit account.This setup is required for the process PRC: Create Accounting to successfully create accounting for supplier cost adjustments. Oracle Projects displays a messageasking you to validate the setup each time that you enable the Allow Adjustments option for a predefined transaction source for supplier costs. (B)E: You can adjust the supplier cost expenditure items in Oracle Projects to transfer or split the items. Oracle Projects processes these supplier invoice adjustmentsusing the Supplier Invoice Cost Account AutoAccounting function.Reference: Oracle Projects Implementation Guide, Implementing Oracle Project Costing

QUESTION 41Which project class type can include revenue budgets?

A. Capital

B. Indirect

C. Contract

D. Capital and Indirect

E. Capital and Contract

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation: Note:* Allow Revenue Budget Entry. Indicates if you allow entry of revenue budget types. You may choose to not allow entry of revenue budgets for indirect or capitalprojects. You must enter a revenue budget for a contract project before it can accrue revenue and be billed.

QUESTION 42

http://www.gratisexam.com/

Which statement is true about the use of the calendar assigned to a project?

A. It is the default calendar assigned to resource requirements for the project.

B. It is the default calendar for the automatic generation of cost forecasts in Financial Plans.

C. It is the default calendar used for determining accounting periods.

D. It is used in the determination of currency exchange rates.

E. It is used by date-dependent system workflows.

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation: When you implement Oracle Projects, you can select the calendar used to maintain PA periods.PA Period TypeSpecify a Period Type, which is used to copy Project Accounting Periods from the calendar associated with the ledger. If you copy PA Periods from GL, OracleProjects copies all of the periods of this Period Type to set up the PA Periods.In a multiple organization environment, the PA Period Type is specified for each operating unit.Reference: Oracle Projects Implementation Guide, Implementation Options

QUESTION 43A project manager would like to find out how much event revenue was accrued against a project up to and including a specific date. Where would this informationbe available?

A. Events form within Project Status Inquiry

B. Accrued revenue within Expenditure Inquiry Form

C. Revenue Review Form

D. Review Project Funding Form

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation: Project Status InquiryYou can quickly and easily review the current status of a project, and then drill down for a more detailed review of the project and its tasks. It enables you to searchfor a project using search criteria. You can review project, task, and resource summary amounts, and actual and commitment amounts using a different resourcelist.

http://www.gratisexam.com/

Oracle Projects maintains various levels of project summary amounts for cost, commitment, revenue, and budget amounts by project, task, and resource. You canreview project summary amounts to quickly determine the status of a project, such as reviewing the current and original budgeted amounts and compare them toactual and commitment amounts. You can drill down to see summary amounts for the resources of the project or the selected task. You can select a resource list bywhich you want to view actuals and budgets. In addition, you can export project status inquiry data into an Excel spreadsheet for further analysis.

QUESTION 44An organization has specific departments that manage capital projects. How would you ensure that only these departments own capital projects?

A. Use the transaction control Functionality at the project level.

B. Use the settings in "Additional Details" of the Project/Task owning organization classification.

C. Remove the asset definition options from the templates used by departments that are not managing capital projects.

D. Use the Project/Task owning organization hierarchy in the implementation options.

E. Set up a separate organization hierarchy for the departments that are managing capital projects.

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation: 1. If you enable the Project Task Owning Organization classification, you must also specify the additional organization information for the classification as follows:a. Place your cursor on the Project Task Owning Organization classification.b. Select the Others button.c. In the Additional Organization Information window, place your cursor in the Project Type Class Information field.d. In the Project Type Class Information window, enter information for the following fields:? Allow Entry Of Indirect Projects: Select Yes from if you want this organization to own indirect projects.? Allow Entry of Capital Projects: Select Yes from if you want this organization to own capital projects.? Allow Entry of Contract Projects: You must select Yes.Note: You must select Yes, even though you cannot create contract projects in Oracle Grants Accounting. Oracle Grants Accounting uses contract projects toprocess revenue and invoices for awards. Oracle Grants Accounting uses an underlying award project to process revenue and invoices. The award project is acontract class project.e. In the Project Type Class Information window, select the OK button.f. In the Additional Organization Information window, select the OK button.g. In the Forms dialog box that asks you if you want to save the changes you have made, select the Yes button to save your work.Reference: Oracle Grants Accounting User Guide, Entering Organization Classifications