15
Olivier Brunner, on behalf of RF/MK. RF/MK: 2013 in a nutshell

Installation: equipment, waveguides, water cooling, local cabling Upgrade of LEP equipment Contract follow up: new klystrons, spare circulators

Embed Size (px)

Citation preview

Page 1: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Olivier Brunner, on behalf of RF/MK.

RF/MK: 2013 in a nutshell

Page 2: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Installation: equipment, waveguides, water cooling, local cabling Upgrade of LEP equipment Contract follow up: new klystrons, spare circulators Reliability is a key issue here: RFQ commissioning, phase adjustment

Linac 4 – HPRF system installation and commissioning

Page 3: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

• WR 2300, L = 1500 mm, r1=70mm, r2 = 40mm • VSWR ≈ 1.2 [depth 0 -> 100 mm]• S11 ≤ -30 dB [depth 0 -> 90 mm]• Range: ≈ max 60˚

Developments

phase adjustment / phase tuners graphic user interfaces (GUI)

Page 4: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

D. Glenat

System performed very well: Did not limit the evolution of peak or integrated luminosityBetter performance than in 2011

Some “weaknesses” have been identified

To do list• 8 klystrons replaced (new boilers + age profile)• HV bunkers equipped with new air cooling systems• New klystron heating system• Oil tests and reconditioning• HV cable repair campaign• Thyratron replacement• DCCT and tetrode replacement R&D in progress• Maintenance• …

LHC RF System Operation (ACS)

Page 5: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

o Very simple circuito No cooling (±10W)o 90 litters oil volume

o Sophisticate circuito Water/oil Cooling o 350 litters oil volumeo Limited lifetime

0

0.5

1

1.5

2

2.5

0 20 40 60

Sp

ark

ch

arge

(m

C)

VOLTAGE (kV)

Thyratrons & Solid State thyristors

Thyratron n°1914

Thyratron n°2827

Switch n°4 A5 triggerMA2622A

Switch n°1 trigger MA2622A

Solid State device has better performances than the thyratron Validated during 2012 running period In series production

Solid state crowbars (“fast protection system”)

Page 6: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Zone with welding defect

Klystron filament glitches responsible for frequent RF trips during operation Procedure validated to re-weld the connectors without damaging the insulation material Campaign in LHC will soon be launched

Repair of the high voltage connectors

Page 7: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Zone with welding defect

Equipment used in LHC are no longer produced by industry Development of a FPGA based electronic located in HV modulator Evaluation tests in progress

Digital measurement system for the klystron modulators

Page 8: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Zone with welding defect

Photo-diodeamplifier

Waveguideport

Detectorview angle

Interlock

Waveguidesystem

Optional external logic

Presented at the BE-KT day, June 3rd 2013 Agreement between CERN and an external company (Microstep-MIS- Slovak Rep.) to

transfer the knowledge

A new generation of Arc Detectors for the HPRF systems

Page 9: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Sample Testing with the Quadrupole Resonator

Research Highlight: Slow cooling across Tc

mitigates flux trapping in bulk niobium and reduces its residual losses.

High resolution measurements of the surface resistance

• Testing of models for SRF loss mechanisms• Studies of new materials and niobium treatments

SRF research

Page 10: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Zone with welding defect CTF3 operation (11 S Band and 1 L Band power sources) Thirteen PETS tanks installed and commissioned Full beam transport to end-of-line spectrometer Power produced (70 MW/PETS): fully consistent with expectations Max power produced: 720 MW (12 PETS) Max deceleration: ≈ 36%

CTF3 & CTF3 Test Beam Line (TBL)

TBL line in CLEX

Beam deceleration, measured in spectrometer and compared with expectations

Page 11: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Zone with welding defect

Contract (almost) placed with industry for 1 GHz high efficiency klystron Gun Sub-harmonic buncher Beam dynamics

Drive beam front end developments

Page 12: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Zone with welding defect Xbox1 reliably working for most of the year Two structures successfully tested Test bed for:

LLRF systems Conditioning and breakdown detection algorithm Diagnostic tool development

Xbox1: 12 GHz high gradient breakdown tests

Test Stand produces reliable results comparable to KEK

Page 13: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Zone with welding defect

Xbox2: Second X-band test bench in bld 150 Modulator installed Klystron in validation tests at SLAC Commissioning: Spring ‘14

Preparation of Xbox2

Page 14: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Zone with welding defect

Based on high repetition, low power klystrons Contract for klystron&modulators placed in August (Toshiba) Integration work has started

Next generation of x-band facility: Xbox3

Page 15: Installation: equipment, waveguides, water cooling, local cabling  Upgrade of LEP equipment  Contract follow up: new klystrons, spare circulators

Zone with welding defect

Cavities shipped to: Pakistan, London, Edinburgh, Madrid, Rome, Berlin, Poland, Norway, Hungary,

Denmark, Cern,...

LEP Copper cavities – a new life!

CERN, Bld 182 London Science Museum