Upload
antonio-pearson
View
214
Download
0
Tags:
Embed Size (px)
Citation preview
1
BPA Fish and Wildlife DivisionUsing Pisces Data to Analyze Wildlife Management Costs
December 2006
Portland, Oregon
2
Introduction
• Tom Karier asked BPA to provide an analysis of the costs associated with the operations and maintenance (O&M) of wildlife projects.
• This presentation will discuss our efforts to date to meet Dr. Karier’s request.
• This was initially an informal exercise designed to provide information to support the FY07 – FY09 selection process.
3
Layers of Data
WE WE
WE
ProjectFrom BES and Pisces
ContractFrom BES and
Pisces
WE WE
WE
ContractFrom BES and
Pisces
Work Elements are only found in Piscesand provide the basis for most of what is
new and useful about reporting out ofPisces
4
WE HubThe Work Element
is the hub.
Work Element“Install Fish Screen”
Budget/ActualsAn estimate of how much
the work element willcost.
ScheduleWhen the work will
occur.
Target SpeciesIdentification of thebenefiting species.
ImplementationStrategy
Identification of the BiOpor NWPA strategy the
work supports.
MetricsObjective measurements
of what the workaccomplished.
Today
Today
Today Tomorrow
Today
Today
$
LocationThe on-the-ground
location of where thework will occur.
N
S
EW BiOp ?
Much of a contract’s pertinent informationis organized by the work element.
Currently in Pisces.
Not yet in Pisces.
Legend
NWPA?
5
WE Budget Estimates
• WE Budgets are estimates provided by the contractor. They are not based on invoiced actuals, but rather the contractors professional opinion. Pisces provides some guidance on what to include in these estimates but is not overly prescriptive.
• Planned WE Budgets are the contractors’ best estimates of the costs associated with a given WE at the time of SOW development.
• Updated WE Budgets are the contractors’ best estimates of the costs associated with a given WE at the time the work is completed.
6
WE Duration
8/06 9/066/064/06
1/06 2/06
1/06 2/06 3/06 4/06 5/06 6/06
12/1/2005 6/30/2006
11/05 12/05 1/06 2/06 3/06 4/06
10/1/2005 4/30/2006
4/06 5/06 6/06 7/06 8/06 9/06
3/1/2006 9/30/2006
WE A Spending Plan
WE B Spending Plan
WE C Spending Plan
Figure 1: Issued Contract and BPA Internal “Contract” Spending Plan
Contract or BPA Internal Spending Plan
$1,000
$5,000
$20,000
The Contract or BPA Internal SpendingPlan is built from the work elements. Theshape of the spending plan comes from
the the work element budgets anddurations.
$26,000
$143 $143 $143 $143 $143 $143 $143
$714 $714 $714 $714 $714 $714 $714
$2857 $2857 $2857 $2857 $2857 $2857 $2857
11/05
$143 $143 $857
10/1/2005
12/05
$857 $857 $3714 $3714 $3571 $3571 $2857 $2857 $2857
9/30/2006
7
Project Performance Period
$15333
2/0712/06
Contract 1
Figure 3: Project Spending Plan
8/06 9/066/064/06
1/06 2/06
$26,000
11/05
$143 $143 $857
10/1/2005
12/05
$857 $857 $3714 $3714 $3571 $3571 $2857 $2857 $2857
9/30/2006
Contract 2
Contract 3(BPA Internal)
10/06
$40,000
8/06
7/1/2006 2/28/2007
$3000 $3000 $5000 $5000 $7000 $7000 $5000 $5000
10/1/2005 2/28/2007
2/06 3/06 4/06 5/06 6/06 7/06 8/06 9/06 10/06 11/06 12/06
1/1/2006 12/30/2006
$100,000
$8333 $8333 $8333 $8333 $8333 $8333 $8333 $8333 $8333 $8333 $8333 $8333
Project I $13190 $16190 $13333 $5000 $5000$15333$13190$857 $9190 $12047 $11904 $11904$12047$9190$143 $143
For this project, the FY06 CouncilRecommendation would be $166,000. Based onthe spending plans to the right, the actual amountof spending in FY06 is predicted to be ~$107,500.
If this were an ongoing project, Contract B andBPA Internal “Contract” C would likely have somework from the FY05 Council Recommendation that
occurs in FY06. Depending on the timing andbudget of that work, the predicted spending may
or may not be close to $166,000.
The project spending plan is the sum of itscontract and BPA Internal “Contract” spending
plans. It’s shape comes from their shape.
11/05 12/05 1/06 2/06 3/06 4/06 5/06 6/06 7/06 8/06 9/06 10/06 11/06 12/06 1/07 2/07
8
Discussions/conclusions
• This analysis is not intended to provide a definitive answer to any specific management question.
• There is substantial variation amongst wildlife projects with respect to:– Wildlife management costs/acre and– The distribution of funding amongst the work categories
• Additional analysis is required to determine the source of the variation.
• There is currently overlap between the habitat enhancement and habitat O&M work categories. Work elements in their current form are focused on what the work is and not why we are doing the work.
9
Next Steps
• Optimize Wildlife Enhancement and O&M Work Elements – Improve our ability to differentiate between
management phases – Review work element classifications
• Which are enhancement? Which are O&M?
– Better identify all of the costs associated with each phase
• Redistribute foundational work element budget estimates
10
Next Steps
• Incorporate Wildlife Data into Pisces– HU/Crediting Information– Acquisition Level Data
• Categorize acquisitions and projects– Use structured data from Pisces (WE
information, metrics) to compare “like to like”