Page 1: 1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009

1 BROOKHAVEN SCIENCE ASSOCIATES

CHILLED WATER & COMPR. AIR PIPING

Thomas F. Joos, P.E.Lead Civil/Structural Engineer

CFAC Review November 9-10, 2009

Page 2: 1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009

2 BROOKHAVEN SCIENCE ASSOCIATES

Outline

• Overview (Scope/Cost)• Technical Progress• Schedule• Issues & Risks• Look Ahead• Conclusions

Page 3: 1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009

3 BROOKHAVEN SCIENCE ASSOCIATES

Overview

• Scope (WBS 1.05.03.04)• New 24” diameter Central Chilled Water (CCW) Supply, 24” diameter CCW Return

& 4” diameter Compressed Air (CA) piping• New piping extends between the existing CCW/CA mains on Rochester Street to a

point at the edge of the NSLS-II Ring Building Construction site• Total distance of approximately 1,100 feet (each)• Includes all excavation/backfill, valves, appurtenances and connections to existing

CCW and CA mains.

• Cost• Contract amount = $1.436M

• Pre-bid estimate = $1.008M

Page 4: 1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009

4 BROOKHAVEN SCIENCE ASSOCIATES

CCW Piping Plan

North

B-0452

Upton

Gas Station

Existing CCW/CA Mains

(Rochester Street)

CCW Piping Plan – Part 1

Page 5: 1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009

5 BROOKHAVEN SCIENCE ASSOCIATES

CCW Piping Plan

North Existing Drainage

Swale & Culverts

Interface with Ring

Building Piping

Intersection Rowland St.

& Groves StreetCCW Piping Plan – Part 2

Page 6: 1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009

6 BROOKHAVEN SCIENCE ASSOCIATES

Technical progress

• Contract Awarded 08/27/09

• Notice to proceed Issued 09/28/09

• Review of Contractor Submittals Ongoing– (Facilitates ordering of long lead items)

• Ordering of Materials Ongoing– (Ductile Iron Pipe, etc.)

• Obtained Work Permit/Digging Permit 10/14/09

• Contractors Schedule into Project Master 10/26/09

Page 7: 1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009

7 BROOKHAVEN SCIENCE ASSOCIATES

Schedule

Page 8: 1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009

8 BROOKHAVEN SCIENCE ASSOCIATES

Issues & Risks

• Crossing Rochester Street• Work starts with making taps to existing mains• Traffic Control (constricted due to other road closures)• Ability to close up road(s) prior to winter weather

• Trenching Rowland Street• Minimize interference with F&O operations• Ability to close up road(s) prior to winter weather

• Crossing Drainage Swale• Must cross swale to make interface with RB contractor installed piping• Weather dependent

Page 9: 1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009

9 BROOKHAVEN SCIENCE ASSOCIATES

Look Ahead

• Considering delaying start of construction to Spring ‘10• Likely schedule would be start 3/15, complete by 6/15• Minimizes risks of having to work through winter weather• Takes advantage of available float in overall project schedule• CCW piping can be completed as late as December 2010 without

adversely affecting other project activities (Pentant 1 turnover Feb. ‘11)

• Would need to consider coordination with Ring Building Contractor installed CCW piping details (availability of blank flanges, etc.)

Page 10: 1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009

10 BROOKHAVEN SCIENCE ASSOCIATES

Conclusions

• Contract awarded & firm price established

• Material ordering in progress

• Looking to proceed in a manner that reduces project risks

• Even with rescheduling, projected construction schedule will have CCW piping available to NSLS-II site well in advance of required date (Pentant 1 turnover), Feb. 2011. (approximately 1yr. of float)