15
1 MICE Tracking Detectors Malcolm Ellis NFMCC Meeting 12 th March 2006

1 MICE Tracking Detectors Malcolm Ellis NFMCC Meeting 12 th March 2006

Embed Size (px)

Citation preview

1

MICE Tracking Detectors

Malcolm Ellis

NFMCC Meeting 12th March 2006

2

Tracker Status• KEK test beam data analysis

ongoing– Light yield observed in cosmic ray test

at Fermilab– Results from Osaka and Fermilab

analyses of KEK test beam data– Plans

• Tracker construction plans– Procurement– Mechanical design– Quality Assurance

• Read out system– Cryogenic system– Front end electronics

• Software

3

Light Yield observed at Fermilab

2500 ppmExpectation

10.6 p.e.

4

Four Station Prototype

v

x

w

xv

x

w v

x

w

BACD

v

x

w

xv

x

w v

x

wv

x

wv

x

w

xv

xv

x

w

x

w v

x

wv

x

w

BACD

New

5000XB

MixtureXC

5000WC

5000XA

5000WD

5000VA

3500WB

2500VB

2500VD

2500XD

3HF (ppm)VIEWSTATION

5000XB

MixtureXC

5000WC

5000XA

5000WD

5000VA

3500WB

2500VB

2500VD

2500XD

3HF (ppm)VIEWSTATION

5

Osaka Analysis

• Original stations:– Light yield ~20% less than expectations

• New (fourth) station:– Light yield ~40% less than original

station• Based on V views of stations B and D

– Consistent results from FNAL analysis

4.8(5000)8.7(5000)8.3(3500)-W view

5.0(2500)-8.2(2500)7.8(5000)V view

4.1(2500)8.4(mix)7.2(5000)8.3(5000)X view

st Dst Cst Bst Anpe(3HF ppm)

4.8(5000)8.7(5000)8.3(3500)-W view

5.0(2500)-8.2(2500)7.8(5000)V view

4.1(2500)8.4(mix)7.2(5000)8.3(5000)X view

st Dst Cst Bst Anpe(3HF ppm)

H. SakamotoA. Horikoshi

6

Damaged Mirrors?• FNAL mirror reflectivity set up:

• Batches of fibre tested from ALL stations– New (fourth) station AND original stations– Results ALL consistent with 80% reflectivity– No evidence for poor mirroring on new station

7

Damaged fibres?• No evidence of dependence of light yield on

position along fibre …– … but, need to sort out decoding problem– Also indicates

mirror ‘OK’

– Channel-to-channel response awaits finaldecoding

8

Connectors!

Patch Panel Connector set 104

Loss of light due to fibre/ area misalignment =22.59%

Due too the fact that the fibres have a cladding approx 12% of diameter the

actual loss is

25.5%

9

Light Loss summary• Light Yield ~20% lower than expected in

original three stations– Possibly due to decoding problems (biasing

event selection to include noise on pedestal)• Fourth station shows further reduction

– Between 25% and 40% of that in the original three stations depending on the analysis

• Connector hole misalignments– Old and new station connectors lose

approximately 15%– Patch panel connectors lose an additional 20%

• Analysis ongoing in both groups• Investigation of the hardware continuing• QA technique development as part of

investigation• Plan to build a fifth station to test

construction technique and QA procedure before construction of final trackers.

10

Procurement• Scintillating and clear fibre

ordered from Kuraray• 4 Sumitomo cryocoolers ordered:

– Water-cooled, indoor compressors– 20m high pressure helium hoses– Delivery soon

• Parts for four 2-cassette VLPC cryostats ordered at FNAL

11

Mechanical design• Preparing for D&S review in April• Aiming to complete fifth station

(check of final design, construction and QA techniques) by July.

• Full production to begin in July.

12

Quality Assurance• Scanning stage used to position a UV

LED over fibre plane.• LED excites 3HF in one fibre and CCD

cameras image the fibre and mirror:– Measure light output – Check for bundling or connector threading

errors– Measure transmission through mirror

606+/-5

215+/-5

Spot smaller than a fibre

Intense central area

13

Cryogenic System• Reliable operation at FNAL and KEK• Design updated (thermal link)

– Cryostat package out for bid– Move to fabrication shortly.

• Demonstrated temperature stability with the cryostat tilted by 25 degrees:

14

Front End Electronics• AFEIIt pre-production boards have

arrived and are under test• TripT testing is progressing

– Current first pass yield is 80%– More than enough chips for D0 +

MICE + spares for both experiments.

• Still a lot of critical work required on firmware for AFEIIt use in MICE:– Plans being developed by T. Hart (IIT)– Possible support from RAL (Engineers

visiting on 20th and 21st March)– Test stand being setup at FNAL (IIT

group) and RAL

15

Software• Simulation studies:

– Station spacing – RF Background and front end

electronics effect on pattern recognition

• Reconstruction:– Currently in the process of a major

upgrade of G4MICE– Working towards improved tracker

reconstruction, PID.

• KEK data analysis– Being performed in G4MICE– Algorithms being developed for light

loss study and QA process are being incorporated into G4MICE.