1
Phase
Implementation and Test Plan
Making your implementation planFirst Steps
Consider your use case diagram and your prioritization of use cases from your design document (checked against provided list)
Use the prioritization (and provided list) to decide the priority or priorities of each use case
Modify your use case diagram to show your priorities.
Janice Regan, 2008 2
Janice Regan, 2008 3
LMS partial use case diagram Order based on importance of each use case as
expressed by the user/client
Calculate overdue fee
Library staff
Generate overdue letter ….
browseResource
reserveResourcemanageResource
checkInResource
checkOutResource
resourcepatron
managePatron
Overdue form letter
Phase 4
Phase 1
Phase 2
Phase 3
Consider your time constraints, Decide which phases will be completed for each presentation date
Iteration 1 Client Demonstration (July 21)
20 minutes, prepare your system before meeting
Iteration 2 Client Demonstration (July 30 )
20 minutes, prepare your system before meeting
User Acceptance Test (Aug. 5-7)
60 minutes, install from code during meeting
Janice Regan, 2008 4
Making your implementation planNext schedule each phase
Consider your time constraints,
Consider dates, July 21, July 30, Aug 5-7
You will be told which phases to present at each meeting,
Leave time to be sure you have fully tested the components for a phase before the meeting.
You may develop more than is needed for the presentation meeting (particularly the first two meetings) before the meeting but present only what is promised)
The system you present should be stable, it is better to miss a deadline on one promised feature than to present an unstable system.
Janice Regan, 2008 5
Making your implementation planConsiderations in scheduling
Divide you group into implementation phase subgroups
Divide into pairs (or a single or triple if you have an odd number of members)
Decide which use cases / classes will be developed by each pair in each phase of development.
Decide how much time to allow for each part of the implementation process, for each of the use cases / classes or groups of use cases /classes (within the duration of each phase)
Janice Regan, 2008 6
Making a schedule: First steps
Important parts of implementation Create implementation test plan Create unit test plan Implement Code inspection Unit testing Integration test plan Integration into system Integration testing Create System test plan System testing User acceptance testing (UAT for your project)
Janice Regan, 2008 7
Janice Regan, 2008 8
For each group of units
Overview of Implementation phase
Create Class Skeletons
Define Implementation Plan (+ determine subphases)
Define Coding Standards
For each unit
ImplementMethods in class/es
Code review
Unit test
Create integration Test plan
Create unitTest plans Release unit
for integration
IntegrationTesting
System Testing
Create systemTest plan
Janice Regan, 2008 9
Planning using Gantt chart The Gantt chart in the next slide illustrates the
following items that you should include in a project schedule GANTT chart
Milestones: Due dates of deliverables Dates of important meetings (UAT, Client Meeting …)
Phases Start and end date of each phase
Tasks (sub phases, activities) Start and end date of each task Tasks on critical path highlighted
Janice Regan, 2008 10
Project Schedule – An Example
MICROSOFT PROJECT CAN BE USED TO MAKE A GANTT CHART
Janice Regan, 2008 11
On your Gantt chart also include The Gantt chart in the next slide illustrates the
following additional items that should be included in a project schedule GANTT chart
Tasks (activities)
Names of resources (team members) responsible for each task
Percentage of available time of resource on each task (when a resource is assigned to more than 1 task at a time)
Dependencies between tasks (does task A need to be finished before task B starts)
Janice Regan, 2008 12
Project Schedule – Another Example
Janice Regan, 2008 13
Updates to your Gantt chart At the end of each phase of the project
the Gantt chart should be updated to reflect the details of the next phase.
Some tasks may be unfinished and need to be added to the next phase
Some tasks may be finished early and need to be moved back from the next phase
Janice Regan, 2008 14
LMS partial use case diagram Order based on importance of each use case as
expressed by the user/client
Calculate overdue fee
Library staff
Generate overdue letter ….
browseResource
reserveResourcemanageResource
checkInResource
checkOutResource
resourcepatron
managePatron
Overdue form letter
Phase 4
Phase 1
Phase 2
Phase 3
Janice Regan, 2008 15
LMS Example: Make the test plan for first phase (or group of phases) Implement the use cases or parts of use cases in the first
phase (or group of phases) Each pairs use cases/classes may be consider a unit
Complete code reviews of the written code, code should be reviewed by a different pair (not the pair that wrote it)
Unit test the code (run and test) Once each unit is unit tested, integrate all units into build 1
(the build containing all use cases or parts of used cases in the first phase)
Build 1 can be tested (integration testing) by performing the checkInResource use case (function) and the checkOutResource use cases
Build 1 may be presented to the client
Janice Regan, 2008 16
LMS partial use case diagram Order based on importance of each use case as
expressed by the user/client
Calculate overdue fee
Library staff
Generate overdue letter ….
browseResource
reserveResourcemanageResource
checkInResource
checkOutResource
resourcepatron
managePatron
Overdue form letter
Phase 4
Phase 1
Phase 2
Phase 3
Janice Regan, 2008 17
LMS Example: Phase 2 You need to consider if the parts of the classes
being implemented in phase 2 are substantially independent of those implemented in phase 1
CASE A: If they are substantially different You can produce build 2 by integrating all units developed
during phase 2. Build 2 can be developed at the same time as build 1. When build 1 and build 2 have been individually
integration tested they can be integrated together into build 3 and integration tested.
Janice Regan, 2008 18
LMS Example: Thread phase 2 Make the test plan for 2nd phase (or 2nd group of phases) Implement the use cases or parts of use cases in the 2nd
phase (or 2nd group of phases) Each pairs use cases/classes may be consider a unit
Complete code reviews of the written code, code should be reviewed by a different pair (not the pair that wrote it)
Unit test the code (run and test) Once each unit is unit tested, integrate all units into build 2
(the build containing all use cases or parts of used cases in the 2nd phase or 2nd group of phases)
Build 2 can be tested (integration testing) by performing the manageResource use case (function)
Build 2 can be presented to the client
Janice Regan, 2008 19
LMS Example: Alternate approach You need to consider if the parts of the classes
being implemented in thread 2 are substantially independent of those implemented in thread 1
CASE B: If they have many interdependent components It may be more efficient to modify build 1 by sequentially
integrating the partial classes (units) produced in thread 2 into build 1.
When all units for thread two have been integrated you have produced build 2.
Janice Regan, 2008 20
LMS Example: Phase 2 For this case use cases in phase 2 are strongly related
(coupled) to the use cases in phase 1 Many parts of phase 2 use or depend on code developed in
phase 1 The phase 1 code will be used as a basis for developing the
phase 2 code Therefore development of phase 2 follows development of
phase 1, they cannot be developed simultaneously Make the test plan for 2nd phase (or 2nd group of phases) Implement the use cases or parts of use cases in the 2nd
phase (or 2nd group of phases) Each pairs use cases/classes may be consider a unit Units are added to phase 1 code after unit testing
Janice Regan, 2008 21
LMS Example: Phase 2
Complete code reviews of the written code Again code should be reviewed by another pair before testing begins
Unit test the code (run and test) Once each unit is unit tested, integrate all units (one unit at
a time) into build 1 Intermediate builds (1.1, 1.2 …) are produced each time a
new unit is integrated into the previous intermediate build. Integration testing is done at each step
Build 2 can be tested (system testing) by performing the manageResource use case (function) the checkInResource use case (function) and the checkOutResource use cases
Build 2 can be presented to the client