Upload
gabriella-francine-gaines
View
213
Download
0
Embed Size (px)
Citation preview
• 10 miles on I-80 from Robb Dr. to Vista Blvd.
• Reconstruction through congested downtown
• Installation of new 10-mile ITS system
• Preserved Operational Capacity
I-80 DB Location & Scope
• Accelerate Schedule • Innovation–Pavement– Traffic Operations –Public Outreach
I-80 DBWhy Design Build?
• Fixed Scope; Lump Sum Price Centers• Evaluation Criteria – 50% Price– 40% Technical– 10% Schedule
• Pre-Proposal for Pavement Design• $50K/day early completion incentive
I-80 DBProcurement Strategy
I-80 DB Schedule
• Construction began 3 months after NEPA approval
• Impacts of Early Completion Incentive
• At-Risk Early Start • Completed construction 6
months ahead of original DB schedule
I-80 DB Risk Transfer
• Subsurface Conditions• 3rd Party Coordination• Utility Relocation• Public Outreach
• 67 Different ATC’s – 10 Used• Maintenance of Traffic • Auxiliary Lanes• Ramp Meters
I-80 DB Innovation
I-80 DB Lessons Learned
• Aesthetic Concepts/Design– Develop concepts in advance – More prescriptive specs
• Soft Subgrade Conditions– Risk is difficult to transfer– Communicate during procurement
• Conditional ATC’s– Competing interests – Impacts to acceleration
West MesquiteLocation & Scope
• Downtown Mesquite, NV• Replace Diamond Interchange with
Roundabouts at Ramp Terminals • Replace Bridges on I-15
• Speed of Delivery• Opportunity for Innovation• Reduce Impacts to I-15
West MesquiteWhy Design Build?
• Fixed Scope & Variable Price• Evaluation Criteria – 60% Price– 30% Technical– 10% Schedule
• Limit the lane closures on I-15
West MesquiteProcurement Strategy
• Construction began 1 month after NEPA approval
• Completed construction 6 months ahead of engineer’s estimated schedule
• 3 months ahead of other Proposers
West Mesquite Schedule
West Mesquite Innovation• 30 Different ATC’s – 4 Used
• Accelerated Bridge Construction (ABC) Bridge slide – limited disruption to I-15
West Mesquite Lessons Learned
• Specifications for Innovation Hollow Nail Walls
• Bridge Deck Quality Remediation requirements
• Innovation & Small DB Projects Bridge Slide great example
• 15 miles of I-15 - South of Las Vegas
• Installation of a new ITS system
• Integration with RTC’s Freeway and Arterial System of Transportation (FAST)
I-15 ITS Location & Scope
• Innovation– Technology Expertise
• Immediate Need– Minimize traffic impacts
I-15 ITSWhy Design Build?
• Fixed Scope; Lump Sum Price
• Evaluation Criteria – 65% Technical– 35% Price
• $5k per day early completion incentive
I-15 ITS Procurement Strategy
I-15 ITS Schedule
• Construction began 1 month after NEPA approval
• System was operational 9 months ahead of Bid-Build scenario
I-15 ITS Lessons Learned
• Keeping up with Technology Resources with experience
• Evaluating new products Aligning vendor spec’s/products
• Warranties Consistency among projects