Upload
art-james
View
227
Download
0
Embed Size (px)
Citation preview
8/9/2019 1011 HPACEngineering Burd
1/7
8/9/2019 1011 HPACEngineering Burd
2/744 HPAC ENGINEERING OCTOBER 2011
DESIGN CRITERIA FOR PRIMARY/SECONDARY AND PRIMARY-LOOP-ONLY SYSTEMS
tion that in real-life conditions, the
relative chilled-water-flow variation
in the plant is changing in direct pro-
portion to the relative plant cooling
load, or W ≈ Q 1:
WFTDRREQ = (CPDCL ÷ CPCLMFC)
× SCSCF (3)
where:
CPDCL = chiller-plant design cool-
ing load in tons
CPCLMFC = chiller-plant cooling
load in tons at the end of mechanical
cooling season or at the load associ-
ated with implementation of various
control strategies (i.e., reset chilled-
water temperature control, etc.)
SCSCF = system control strategy
correction factor, which is equal to
or less than 1. SCSCF equals 1 for
systems that do not utilize reset
chilled-water temperature control at
the chiller plant or variable airflow
rate at terminal units, etc. Otherwise,
As a result, the available chilled-
water-flow turndown ratio (which
represents system water flow con-
trollable range shown in Figure 2) for
the PLOVF system (WFTDRAVLPLOVF)
should be reduced as compared with
WFTDRAVLP/S for the P/S system by
the overall system operational safety
factor (OSOSF) of 0.82 to 0.9. Thus:
WFTDRAVLP/S = WFTDRDEAVL
WFTDRAVLPLOVF = (0.82 to 0.9) ×
WFTDRDEAVL
Required Evaporator Chilled-
Water-Flow Turndown Ratio
Required evaporator chilled-wa-
ter-flow turndown ratio (WFTDRREQ)
is another important parameter while
selecting P/S or PLOVF systems for a
chiller-plant application. WFTDRREQ
for a chilled-water plant can be eval-uated for P/S and PLOVF systems
from the following equation, which
is based on the conservative assump-
determined from Equation 1.
Schematical representation of
comparative available chilled-water
turndown ratios for P/S and PLOVF
systems is shown in Figure 2. Be-
cause of the independent-loops ar-
rangement of the two-loop system
and its unique architecture, the P/S
system is able to utilize all of the
available evaporator chilled-water-
flow turndown ratio. On the otherhand, a PLOVF system, because of
the specifics of its architecture and
rigid dependency of the flows via
the generation and distribution pip-
ing loop system, is able to utilize
less than full available evaporator
chilled-water turndown ratio. Figure
2 outlines suggested parameters, in-
cluding operational safety factors
for F1HL and F1LL, to avoid PLOVF-
system shutdown on high and low
chiller evaporator flows or prema-ture addition or removal of a chiller
and associated ancillary equipment
from the line.
1.1 to 1.05 F1LL
Notes:F1HL—Evaporator allowable high-limit water-flow rate, gpmF1LL—Evaporator allowable low-limit water-flow rate, gpm∆T
DEMAX, ∆T
DEMIN—Maximum or minimum evaporator
design chilled-water temperature, respectively, °F∆T
DEDP—Distribution piping system design temperature
differential, °FWFTDR
AVL P/S, WFTDR
AVL PLOVF—Available chilled-water-flow
turndown ratio for P/S and PLOVF systems, respectivelyOSOSF—Overall system operational safety factor forP/S and PLOVF systems
F1HL F1HL
F1LL F1LL∆TDEMAX
∆TDEMIN
System operationalsafety factor for F1HL
WFTDRAVL P/S
=
1.0 × (F1HL/F1LL) ∆ T D E D P
0.9 to 0.95 F1HL
WFTDRAVL PLOVF
=(0.9 to 0.95) ×
F1HL/(1.1 to 1.05) ×F1LL = (0.82 to 0.9) ×
(F1HL/F1LL)
OSOSF = 0.82 to 0.9
P/S systemwater flow
controllable range
PLOVF systemwater flow
controllable range
System operationalsafety factor for F1LL
OSOSF = 1.0
FIGURE 2. Chiller evaporator comparativeavailable chilled-water turndown ratio
schematical representation for P/S and
PLOVF systems.
Notes and symbols: 1 and 2 — Series chiller-evaporator arrangement bypass pipes3 — Chiller-plant decoupling pipe
4 — P/S- or PLOVF-system primary-loop pump
5 — P/S-system secondary-loop pump
6 — Chiller-evaporator arrangement A and B have equal cooling loads
7 — For the specifics of control system arrangements, see1
W — Chiller-plant cumulative relative water-flow rate via chillers’ evaporators
WCPGS
, WCPDS
— Chiller-plant water flow rate via generation and distribution systems, respectively
TINT
— Intermediate chilled-water temperature between chillers 1 and 2
— Additional electrical valves for series chiller-evaporator control arrangements
VFD — Variable-speed pumps control arrangement1
Relative parameters are shown overlined
VFD
VFD
VFD
VFD
Load
Load
Chiller #1
Chiller #1 Chiller #2
Chiller #2
B. Series chillers evaporation arrangement
A. Parallel chillers evaporation arrangementW
CPGSW
CPDS
WCPGS
WCPDS
Distribution SystemGeneration system
Distribution SystemGeneration system
W/2
W/2
W W
W
W
4
2
1
4 5
5
3
3
TINT
FIGURE 1. Examples of a parallel chillers evaporators arrangement and a series chiller
evaporator arrangement.
8/9/2019 1011 HPACEngineering Burd
3/7
SCSCF should be assumed to be less
than 1.
Reset Temperature Control and
Required Chiller-Plant Chilled-
Water Turndown Ratio
Figure 3 is illustrative of the impact
of the reset chilled-water-tempera-
ture control strategy. This is analyzed
for the cooling coil (which is assumed
to be maintained at ideal clean heat-
exchanger-surface conditions) with a
design load of 28.5 tons.1 The air-han-
dling units are operating with con-
stant airflow; we assumed a minimum
mechanical cooling load of 2.9 tons.
The upper graph shows four op-
tional control strategies related to
chilled-water supply temperature.
Option 1 is associated with constant
relative chilled-water temperature T1
= 1 (T1 = 40°F) over the system’s en-
tire operational hours. (Note: relative
parameters are shown overlined.)
Option 2 resets relative chilled-water
temperature from T1 = 40ºF (T1 = 1)
at design conditions with relative
cooling load Q = 1 to T1 = 47.5ºF (T1 =
1.19) at Q = 0.1.
Options 3 and 4 are a combination
of options 1 and 2. Option 3 main-
tains design chilled-water tempera-
ture of 40°F (T1 = 1) until Q is reduced
to 0.52. After that, it gradually resets
relative chilled-water temperature to
47.5°F (T1 = 1.19) at Q = 0.1. Option
4 maintains relative design chilled-
water temperature of 40°F (T1 = 1)
until Q is reduced to 0.29 and after
that gradually resets relative chilled-water temperature to 47.5°F (T1 =
1.19) at Q = 0.1.
The graph in the middle of Figure
3 depicts relative temperature-dif-
ferential variations associated with
control strategies shown in the upper
graph. The relative temperature dif-
ferential (∆T) increases for Option 1
from ∆T = 1 at Q = 1 to ∆T = 1.25 (or
by a factor of 1.25) when the relative
cooling load, Q, decreases from the
design value of 1 to 0.1; ∆T decreasesfor options 2, 3, and 4, respectively,
from 1 at design load Q = 1 to 0.2 at Q
= 0.1 or by the factor of 5.
The bottom graph in Figure 3
shows relative chilled-water-flow-
rate (W) variation as a function of the
relative cooling load Q. Under the
Option 1 chilled-water-temperature
control strategy, W reduces from 1
to 0.08 when Q is lowered from 1 at
design conditions to 0.1, respectively.
At the same time, options 2, 3, and 4experience reduction of W from 1 at
design conditions to 0.5 at the end of
the mechanical cooling season.
Thus, Figure 3 indicates that the
reset chilled-water temperature con-
trol has a pronounced impact on
WFTDRREQ in the chiller plant. The
unchanged magnitude of chilled-
water temperature T1 = 40°F for the
considered conditions (Option 1)
leads to the reduction of the relative
chilled-water flow from 1 to 0.08 (re-sulting in WFTDRREQ = 12.5), while
Q fluctuates from 1 to 0.1. Option 2
would result in W variation from 1 to
OCTOBER 2011 HPAC ENGINEERING 45
DESIGN CRITERIA FOR PRIMARY/SECONDARY AND PRIMARY-LOOP-ONLY SYSTEMS
Relative cooling load, Q
1.20
1.15
1.10
1.05
1.00
0.95
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
1.2
1.0
0.8
0.6
0.4
0.2
0.0
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
Option 1
Option 2
Option 3
Option 4
Option 1
Option 2
Option 3
Option 4
Relative cooling load, Q
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
Relative cooling load, Q
R e l a t i v e c h i l l e d - w a t e r
t e m p e r a t u r e d i f f e r e
n t i a l , ∆ T
R e l a t i v e c h i l l e d - w a t e r
fl o w r a t e ,
W
R e l a t i v e s u p p l y
c h i l l e d - w a t e r t e m p
e r a t u r e ,
T 1
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1
Notes: Supply chilled water temperature at design relative cooling load Q = 1 is assumed to be 40°FOption 1: Constant chilled-water temperature maintained at its design level VFTDR
REQ = 12.5
Option 2: Linear reset chilled-water temperature control from design conditionsto 0.1 relative cooling load (WFTDR
REQ = 2)
Option 3: Reset chilled-water temperature control at 0.52 relative cooling load and below (WFTDRREQ
= 2.1)
Option 4: Reset chilled-water temperature control at 0.29 relative cooling load and below (WFTDRREQ = 4.2)
Option 1
Option 2
Option 3
Option 4
FIGURE 3. Relative chilled-water-plant parameters at various cooling loads and supply
chilled-water temperature control strategies.
8/9/2019 1011 HPACEngineering Burd
4/7
PARKER BOILER’S NEW 205 SERIES TC CONDENSING BOILERS!
PARKER BOILER CO
5930 Bandini Blvd,
Los Angeles, CA 90040
Ph. (323)727-9800
Fax (323) 722-2848
www.parkerboiler.com [email protected]
NEVER A COMPROMISE FOR QUALITY OR SAFETY
DESIGN
TOLERANCE
ASME
H
0.5 (WFTDRREQ = 2).
Under Option 3, the magnitude of
W is reduced from 1 to 0.47 (WFT-
DRREQ = 2.1) at Q = 0.52 and then W
increases to 0.5 (WFTDRREQ = 2) at Q
= 0.1. Finally, under Option 4, W is re-
duced from W = 1 to W = 0.24 (WFT-
DRREQ = 4.2) and then W increases to
W = 0.5 (WFTDRREQ = 2). The higher
magnitude of WFTDRREQ should be
selected between the two turndown
ratio values that relate to options 3
and 4 to establish the resulting value
of WFTDRREQ for the system.
Chiller-Water-Plant Required
Number of Chillers
The number of chillers sharing the
plant load at a given chiller’s load
safety factor should be selected for
both P/S and PLOVF systems with
the purpose of making WFTDRAVL
equal or higher than WFTDRREQ to
eliminate water flow via the decou-
pling pipe and to optimize chiller-
plant electrical energy use.
The required number of chillers
for the plant optimal operation can
be calculated from the following
equation:
NREQ = (WFTDRREQ ÷ WFTDRAVL) ×
CPLSF (4)
where:
WFTDRAVL = available chilled-wa-
ter turndown ratio for a chiller plant
with P/S and PLOVF systems
WFTDRREQ = required chilled-wa-
ter turndown ratio for a chiller plant
with P/S and PLOVF systems
CPLSF = chiller-plant load safety
factor
If the installed number of chill-
ers in the plant (NI) is less than NREQ,
then WFTDRRE Q is greater than
WFTDRAVLP/S & PLOVF and the applica-
tion of the P/S system will be ben-
eficial from the energy-conservation
point of view as compared with a
PLOVF system. If NI is greater than or
equal to NREQ, then WFTDRREQ is less
than or equal to WFTDRAVLP/S & PLOVF,
and both P/S and PLOVF systems are
equally energy-efficient.
Chilled-Water Plants With Parallel
and Series Chiller Evaporators
Schematical representations of the
chiller plant with a parallel and series
connection of the chillers’ evapora-
tors and P/S and PLOVF systems are
shown in Figure 1.
Chilled-water systems with par-
allel chiller-evaporator connections
(Figure 1A) are common. The chiller’s
plant load and the relative water-flow
rate is equally (W ÷ 2) shared by a
number of chillers on line until it is
reduced to a single chiller. The paral-
lel chiller arrangement is relatively
46 HPAC ENGINEERING OCTOBER 2011
Circle 177
DESIGN CRITERIA FOR PRIMARY/SECONDARY AND PRIMARY-LOOP-ONLY SYSTEMS
8/9/2019 1011 HPACEngineering Burd
5/7OCTOBER 2011 HPAC ENGINEERING 47
DESIGN CRITERIA FOR PRIMARY/SECONDARY AND PRIMARY-LOOP-ONLY SYSTEMS
the entire mechanical cooling season.
We considered four control strat-
egy options outlined earlier in Figure
3. The conditions shown in Table 1 for
a P/S system under Option 1 (without
chilled-water reset temperature con-
trol) will require the installation of
nine 67-ton chillers. The same option
for a PLOVF system will require the
unit cooling-coil parameters will not
change. Each table also includes two
values of OSOSF for PLOVF system
that are either 0.9 (Option 1A) or 0.82
(Option 1B). Required number of chill-
ers is calculated utilizing Equation 4 to
satisfy the conditions under which a
chiller plant will not have water flow-
ing through the decoupling pipe for
simple in operation and maintenance.
Chilled-water systems with series
chiller-evaporator connections are
mostly utilized in custom-made appli-
cations. The same series connection
is equally applicable for a P/S and
PLOVF system and variable-speed
pump control. The series-chillers ar-
rangement (assuming that identical
chillers to be employed in both series
and parallel arrangements) requires
a substantial increase of the pressure
drop via the evaporator (because of
a twofold W increase in relative wa-
ter flow via a chiller at design con-
ditions). In this instance, the design
pressure drop will be approximately
eight times higher in a series ar-
rangement (Figure 1B) than in a par-
allel arrangement (Figure 1A).
The series arrangement is less
dependable in operation and will
require employment of additional
electrically operated control valves
to remove/add a chiller from/to the
line to adjust the load or to isolate
a failed chiller (Figure 1B). The se-
ries arrangement will make the reset
chilled-water temperature control
more challenging to implement, even
for a P/S system because of the in-
troduction of the additional variable
parameter (TINT in Figure 1B) repre-
senting the temperature of chilled
water leaving Chiller 1 and entering
Chiller 2.
When the identical and equal
number of chillers with similar
load-sharing strategy is utilized, the
chilled-water turndown ratio will bethe same for both parallel and series
chillers’ evaporator arrangements.
Specifying Chillers
Tables 1 and 2 demonstrate com-
parative chiller-plant analysis of the
required number of chillers for P/S
and PLOVF systems. The data in these
tables are related to two sets of values
for distribution-piping-system design
temperature differential: ∆TDEDP =
15°F (Table 1) and ∆TDEDP = 10°F (Table2). For the purpose of analysis of the
∆TDEDP impact on required number
of chillers, we assumed that terminal-
TABLE 1. Comparative chiller-plant turndown ratios and required number of chillers for
P/S and PLOVF systems (∆ T DEDP = 15°F).
Parameter
P/SOption 1
PLOVFOption 1A
PLOVFOption 1B
P/SOption 2
P/SOption 3
P/SOption 4
Overall system operationalsafety factor, OSOSF
1 0.90 0.82 1 1 1
WFTDRREQ 12.5 12.5 12.5 2 2.1 4.2WFTDRAVL. DES 1.5 1.3 1.2 1.5 1.5 1.5
Required number ofchillers, NREQ
8.4 9.3 10.2 1.3 1.4 2.8
Installed number ofchillers, NI
9 10 11 2 2 3
Required individual chillersdesign load, tons
67 60 55 300 300 200
Notes:1. Chiller plant design cooling load, tons: 6002. Installed chiller plant cooling load capacity, tons: 6003. Assumed chiller-plant load safety factor: 14. Assumed maximum chiller evaporator design chilled-water temperature differential
(∆TDEMAX) = 22.4 °F
5. Assumed distribution piping system design temperature differential (∆TDEDP) = 15 °F6. Control options 1, 2, 3 and 4 are in reference to Figure 37. AHUs serviced by the chiller plant are assumed to be operating with constant-air-flow control
arrangement8. Reset chilled water temperature control is assumed to be applicable only for P/S system1
TABLE 2. Comparative chiller-plant turndown ratios and required number of chillers for
P/S and PLOVF systems (∆ T DEDP = 10°F).
Parameter
P/SOption 1
PLOVFOption 1A
PLOVFOption 1B
P/SOption 2
P/SOption 3
P/SOption 4
Overall system operationalsafety factor, OSOSF
1 0.90 0.82 1 1 1
WFTDRREQ 12.5 12.5 12.5 2 2.1 4.2
WFTDRAVL. DES 2.2 2.0 1.8 2.2 2.2 2.2
Required number of
chillers, NREQ5.6 6.2 6.8 0.9 0.9 1.9
Installed number ofchillers, NI
6 7 7 1 1 2
Required individual chillersdesign load, tons
100 86 86 600 600 300
Notes:1. Chiller-plant design cooling load, tons: 6002. Installed chiller-plant cooling-load capacity, tons: 6003. Assumed chiller-plant load safety factor: 14. Assumed maximum chiller evaporator design chilled water temperature differential
(∆TDEMAX) = 22.4 °F5. Assumed distribution piping system design temperature differential (∆TDEDP) = 10 °F6. Control options 1, 2, 3 and 4 are in reference to Figure 37. AHUs serviced by the chiller plant are assumed to be operating with constant-air-flow control
arrangement
8. Reset chilled water temperature control is assumed to be applicable only for P/S system1
8/9/2019 1011 HPACEngineering Burd
6/7
TM
Introducing Atherion. In mythology, the name refers to the clean air
only the gods could breathe. In reality, it’s the way Modine brings thefresh air from outside into your workplace.
Designed to provide significant outdoor air ventilation to any space.
15-30 ton commercial packaged ventilation system with optional energy recovery
Meets latest ASHRAE 90.1 and 62.1 standards for efficiency, green buildingand indoor air quality
Best-in-class MERV 16 filtration
Higher IAQ with up to 100% outside air ventilation
Industry-leading high efficiency gas heating option withConservicore™ Technology
Integrates Modine’s PF™ microchannel condenser technology
The latest in cooling technology with factory-installed
microprocessor controlsR A I S E Y O U R C O M F O R T L E V E L
MODINE MANUFACTURING COMPANY | 1-800-828-HEAT | WWW.MODINEHVAC.COM
For more information, call 1-800-828-HEAT or visit www.MODINEHVAC.com.
STEP INSIDE FOR A BREATH OF FRESH AIR.
48 HPAC ENGINEERING OCTOBER 2011
installation of either 10 60-ton chill-
ers (Option 1A) or 11 55-ton chillers
(Option 1B). Thus, the PLOVF system
will utilize a higher number of chill-
ers to satisfy given conditions.
Table 1 further indicates that the
number of installed chillers (NI) for a
P/S system under Option 2 (assuming
continual reset water-temperature
control through the entire cooling
season) could be reduced to two 300-
ton chillers. The number of installed
chillers (NI) under options 3 and 4
(assuming reset water-temperature
control during off-design conditions)
for a P/S system could be reduced to
two 300-ton chillers or three 200-ton
chillers, respectively.
Table 2 shows the number of chill-
ers required for the system with
∆TDEDP = 10ºF could be reduced by
the factor of 1.5 compared with the
system with ∆TDEDP = 15ºF because
of the higher WFTDRAVL value cal-
culated from Equation 1. Still, the
number required for a P/S system
under options 2, 3, and 4 remains
substantially lower than for a PLOVF
system.
In a real-life situation, it is unlikely
(perhaps, with the exception of mod-
ular chillers) that the number of chill-
ers would be increased to nine or 10
(Table 1) or to six or seven (Table 2)
for a chiller plant with P/S and PLOVF
systems because of the additional
cost associated with the multiple
chillers and their ancillary equipment
(cooling towers, condenser pumps,
controls, etc.). Because of that, two
300-ton chillers are most likely to be
installed for the considered plant.
This is equivalent of the condi-
tions when NI is less than NREQ and
WFTDRREQ is greater than WFT-
DRAVL for both P/S and PLOVF sys-
tems. Under these scenarios, a P/S
system will provide lower annual
electrical energy usage for the chiller
plant compared with a PLOVF sys-
tem. As an additional benefit, a P/S
system will reduce the number of
times a system swtiches
from two-
chiller to single-chiller operation and vice versa by about 10 percent to 18
percent, compared to a PLOVF sys-
tem with an OSOSF of 0.9 or 0.82,
respectively.
Summary
This investigation specifies design
criteria and required conditions at
which P/S and PLOVF systems will
have no energy wasteful chilled-wa-
ter flow via the decoupling pipe of
the chiller plants with parallel andseries chiller-evaporator arrange-
ments and essentially operate as sin-
gle-loop systems. As long as both P/SCircle 178
DESIGN CRITERIA FOR PRIMARY/SECONDARY AND PRIMARY-LOOP-ONLY SYSTEMS
8/9/2019 1011 HPACEngineering Burd
7/7
InfraMation 2011The Leading Infrared Camera Users Conference!
Bally’s in Las Vegas | November 9 - 11
Share your passion for thermalimaging and discover innovationsin Building Thermography. Visitwww.inframation.org to learn moreand register today.
DiscoverHiddenProblems Before They Take aChilling Turn
Prevent energy costs and HPAC fi xes fromskyrocketing, and warm your customers’ hearts.Spot signs of trouble early with the help of anaffordable FLIR i-Series thermal imaging camera.
NASDAQ: FLIR
The thermal images shown are for illustrative purposes only, and may not have been taken by the camera series depicted.
Visi t www.fl ir.com/hpac-i to explore how
i-Series can help you keep away the chill.
Or call 866.477.3687 today.
Quality – Innovation – Trust
i-Series
Point-and-Shoot Simplicity
Starting Under $1,200
OCTOBER 2011 HPAC ENGINEERING 49
and PLOVF systems operate in this
mode (assuming both systems have
the same major parameters, identi-
cal chiller and evaporator arrange-
ments, equal design chilled-water-
pump horsepower, overall flow, head
pressure, variable-frequency-drive
controls, etc.), their annual electrical
energy use will be optimal and equal.
The other findings of the article are
as follows:
• Satisfying the above conditions
requires a larger number of chillers
with a lower design cooling capacity
as compared with current engineer-
ing practice for both P/S and PLOVF
systems and may call for the employ-
ment of modular chillers.
• The procedure of selecting and
specifying available and required
chilled-water turndown ratio for the
evaporators of a chiller plant with
P/S or PLOVF systems is presented
to optimize electrical energy use.
• The number of chillers for P/S
or PLOVF systems is selected based
on the optimal distribution-piping-
system temperature differential
and chiller-plant load safety factor
to match the required and available
magnitudes of the chilled-water turn-
down ratio.
• A P/S system requires a lower
number of chillers in a chiller plant
compared with a PLOVF system
because of the higher controllable
range of water-flow rate for P/S sys-
tem and the ability to realize a reset
chilled-water-temperature control
strategy.• A PLOVF system compared with
a P/S system—assuming both sys-
tems have an equal number of chill-
ers and chiller capacities—will need
more frequent changes in the num-
ber of operating chillers and their as-
sociated ancillary equipment over the
cooling season because of the lower
available magnitude of chilled-water
turndown ratio.
• The similar procedures and de-
sign criteria are equally applicable forthe selection of available and required
magnitudes of a hot water boiler-plant
turndown ratio, as well as a number
of boilers in the central boiler plant
with P/S or PLOVF systems.
References
1) Burd, A., & Burd, G. (2010, De-
cember). Primary/secondary-loop vs.
primary-loop-only systems. HPAC
Engineering , pp. 36-45. Available at
http://bit.ly/Burd_1210
Did you find this art icle useful? Send
comments and suggestions to Senior
Editor Ron Rajecki at ron.rajecki@
penton.com.
Circle 179
DESIGN CRITERIA FOR PRIMARY/SECONDARY AND PRIMARY-LOOP-ONLY SYSTEMS