22
Electricity Supply to Africa and Developing Economies: Challenges and Opportunities Johan Smith TNEI Africa Paper Number 1.05 Session Number 1 15 November 2017 Model validation for accurate representation of renewable power plant technologies in developing utilities to free up capacity

1.05 Model validation for accurate representation of ......Model Aggregation • Incorporating entire RPP models with complete collector networks into a large electrical network –unpractical

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Johan SmithTNEI Africa

    Paper Number 1.05

    Session Number 1

    15 November 2017

    Model validation for accurate

    representation of renewable power

    plant technologies in developing

    utilities to free up capacity

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Agenda

    • Introduction• Problem Statement• Case Study

    – Steady state study– Dynamic capacity simulation

    • Model Validation Examples– Full inverter coupled technologies– Synchronous generator technologies

    • Model Aggregation• Conclusions

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Introduction

    • Abundance of renewable resources in Africa• Grid integration study is required to investigate

    sufficient grid capacity

    – Steady state study– Dynamic study

    • Steady state load flow studies are the first and sometimes the only factor taking into

    consideration – equipment loading and voltage

    violations

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Introduction (contd…)

    • Dynamic studies require the existing and new generation, as well as the existing T&D network

    to be accurately represented

    • Safety margins needs to be introduced when integrating renewable generation:

    – Capacity can be remaining– False capacity which places the network at risk

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Problem Statement

    • Using non-validated simulation models to determine network capacity can produce

    unreliable results, which could lead to under- or

    over-utilisation of the existing network

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Case Study – Existing study case network

    • Existing study case network63% OHL loading for

    existing network

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Case Study – Steady state simulation

    • Renewable plant connected to base case

    100% OHL loading with

    new 116MW RPP

    Theoretical spare capacity = 115MW

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Study Case – Dynamic capacity simulation

    • Network subjected to fault at 132 kV busbar

    Dynamic spare

    capacity = 45MW

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Study Case – Input data errors

    • Network with additional 45 MW is used and the inertia time constant of the generators are

    changed to represent a 10% error in input data

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Model Validation – Inverter technologies

    Full inverter coupled technologies:

    • Model validation focus– Active and reactive current injection for system

    events and control modes

    • Accurate plant measurements are required to validate RMS and EMT models

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Model Validation – Inverter technologies (contd…)

    • Reactive power control – measured vs. simulated (RMS model)

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Model Validation – Inverter technologies (contd…)

    • Open Loop Reactive Power Validation for +2% Voltage Reference Change (RMS Model)

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Model Validation – Inverter technologies (contd…)

    • Open Loop Reactive Power Validation for Tap Change Operation with Fixed Voltage Reference

    (1p.u.) and 4% Droop (RMS Model)

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Model Validation – Inverter technologies (contd…)

    • EMT model – system event required for RPP to go into grid support mode thus injecting or

    absorbing reactive current

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Model Validation – Synchronous technologies

    • Data requirements:– Sampling rate: 5µs (20kHz)

    • Lower resolution acceptable (1-10ms) for RMS models

    – Measured quantities:• Field voltage• Field current• Terminal voltage• Active and reactive power

    – Validation focus• Accurate representation of generator which includes AVR,

    governor and PSS

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Model Validation – Synchronous technologies

    • Typical tests:– AVR:

    • Open circuit test• Closed circuit test• Limiter tests

    – Governor:• Generator test: open circuit saturation curve, power

    rejection test

    • Governor test: high and low frequency excursion test, load ramp rate test.

    – Power System Stabiliser (PSS): • white noise test

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Model Validation – Synchronous technologies

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Model Validation – Synchronous technologies

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Model Aggregation

    • Incorporating entire RPP models with complete collector networks into a large electrical network – unpractical and cumbersome

    • Model aggregation required by utilities and forms part of overall validation process

    • During major network disturbance it is possible for a portion of the generators to experience voltages beyond protection limits – not possible to capture these as the aggregated model represents the “average” generator in the RPP

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Model Aggregation (contd…)

    • After aggregation, the model is compared to the full validated model

    • Simulation study to compare reactive current contribution at the POC

    – Aggregate model is sufficient for studying impact on larger electrical network

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Conclusions

    • Case presented highlight the need for using validated models for representing generation to calculate remaining capacity

    • Validation process was described for both inverter and synchronous generator technologies

    • To validate simulation models – simulation results are compared to site measurements

    • Model aggregation is integral part of model validation – provides accurate model to represent RPP in larger power system study

  • Electricity Supply to Africa and Developing Economies: Challenges and Opportunities

    Conclusions (contd…)

    • Dynamic and steady state simulations are required in order to determine available capacity

    • Model validation ensures the accurate model representation of renewable technologies in

    order to determine the “safe” available capacity