04/18/2023 file:///tt/file_convert/563dba24550346aa9aa30efa/document.xls document.xls
Client Petro-Canada Netherlands B.V. PIPE STRESS CALCULATION
Project P11-b De Ruyter Production Platform Summary Sheet
Doc. No. 144-111-PI-CAL-0062 Rev. R1 System: SK-062
Page 1 of 1
System Description
Line numbers Line numbers cont. Connecting Equipment
6; 8 FW 730 910 A45 12 FW 730 040 A49 Fire Water Pump 730-PS-01B / TP1
12" FW 730 007 A45 12 FW 730 041 A49 Fire Water Pump 730-PS-01A / TP1
12" FW 730 909 A45 4 FW 730 043 A49
6; 8 FW 730 009 A45 10 FW 730 046 A49
12 FW 730 911 A45 10 FW 730 049 A49
12 FW 730 908 A49 6 FW 730 052 A49
12 FW 730 001 A49 6 FW 730 055 A49
12 FW 730 005 A45 6 FW 730 058 A49
12 FW 730 223 A49
12 FW 730 900 A49
Status Note
Design Code B 31.3
System designed for blast Yes
CII Calculation no. - blast case -
CII Calculation no. - design case SK-062A-R1 Calc's included: 063, 081, 082
Process line list Rev. C2
Material specification Rev. C3
Support locations for AFD Yes
Support loads issued AFD Yes
Support detail drawing approved Partly (90% appr'd)
Flexibility approved Yes
Maximum Stresses Expansion Blast
39 (83%) 39 (83%) -
Equipment Nozzle Loads
Tag no. Node no Approved Notes
730-PS-01B / TP1 10 Yes Vendor data
730-PS-01A / TP1 740 Yes Vendor data
Sustained1) Sus+Therm+Occ1)
192 (51%) 2)
1) Allowable Sh*0.5*F2, where F2=0.67 used for all cases. (Sh=142N/mm2.). 2). Allow. for A790-UNS S32760.