32
18-1 Two methods of accounting for long-term construction contracts: Percentage-of-completion method. Cost-recovery (zero-profit) method. Long-Term Contracts (Construction)

18-1 Two methods of accounting for long-term construction contracts: Percentage-of-completion method. Cost-recovery (zero-profit) method. Long-Term

Embed Size (px)

Citation preview

Page 1: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-1

Two methods of accounting for long-term construction

contracts:

Percentage-of-completion method.

Cost-recovery (zero-profit) method.

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 2: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-2

Rationale for using percentage-of-completion accounting

is that under most of these contracts, the

Buyer and seller have enforceable rights.

Buyer has the legal right to require specific performance on

the contract.

Seller has the right to require progress payments that

provide evidence of the buyer’s ownership interest.

As a result, a continuous sale occurs as the work

progresses and companies should recognize revenue

according to that progression.

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 3: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-3

Companies must use the percentage-of-completion method

when all of the following conditions exist.

1. Total contract revenue can be measured reliably;

2. It is probable that the economic benefits associated with the

contract will flow to the company;

3. Both the contract costs to complete the contract and the stage

of contract completion at the end of the reporting period can

be measured reliably; and

4. The contract costs attributable to the contract can be clearly

identified and measured reliably so the actual contract costs

incurred can be compared with prior estimates.

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 4: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-4

Companies should use the cost-recovery method when one

of the following conditions applies:

1. When a company cannot meet the conditions for using the

percentage-of-completion method, or

2. When there are inherent hazards in the contract beyond the

normal, recurring business risks.

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 5: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-5

Calculation for Revenue to Be Recognized

LO 3 Apply the percentage-of-completion method for long-term contracts.

Illustration 18-11

Illustration 18-12

Illustration 18-13

Percentage-of-Completion Method

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 6: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-6 LO 3 Apply the percentage-of-completion method for long-term contracts.

Illustration: KC Construction Company has a contract to

construct a €4,500,000 bridge at an estimated cost of

€4,000,000. The contract is to start in July 2010, and the

bridge is to be completed in October 2012. The following data

pertain to the construction period.

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 7: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-7 LO 3 Apply the percentage-of-completion method for long-term contracts.

Illustration: Compute percentage complete.Illustration 18-6

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 8: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-8 LO 3 Apply the percentage-of-completion method for long-term contracts.

Illustration: KC would make the following entries to record

(1) the costs of construction, (2) progress billings, and (3)

collections.Illustration 18-7

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 9: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-9

Percentage-of-Completion, Revenue and Gross Profit, by YearIllustration 18-16

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 10: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-10 LO 3 Apply the percentage-of-completion method for long-term contracts.

Illustration: KC’s entries to recognize revenue and gross

profit each year and to record completion and final approval

of the contract.Illustration 18-17

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 11: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-11 LO 3 Apply the percentage-of-completion method for long-term contracts.

Illustration: Content of Construction in Process Account—

Percentage-of-Completion Method

Illustration 18-18

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 12: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-12 LO 3 Apply the percentage-of-completion method for long-term contracts.

Financial Statement Presentation—Percentage-of-

Completion

Illustration 18-19

Computation of Unbilled Contract Price at 12/31/10

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 13: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-13

Financial Statement—Percentage-of-Completion

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Illustration 18-20

LO 3

Page 14: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-14

Illustration: For the bridge project illustrated on the preceding

pages, Hardhat Construction would report the following revenues and

costs.

Cost-Recovery (Zero-Profit) MethodCost-Recovery (Zero-Profit) Method

LO 4 Apply the cost-recovery method for long-term contracts.

Illustration 18-21

Page 15: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-15

Illustration: Hardhat’s entries to recognize revenue and gross profit

each year and to record completion and final approval of the contract.

Cost-Recovery (Zero-Profit) MethodCost-Recovery (Zero-Profit) Method

LO 4 Apply the cost-recovery method for long-term contracts.

Illustration 18-22

Page 16: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-16

Illustration: Comparison of gross profit recognized under different

methods.

Cost-Recovery (Zero-Profit) MethodCost-Recovery (Zero-Profit) Method

LO 4 Apply the cost-recovery method for long-term contracts.

Illustration 18-23

Page 17: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-17

Financial Statement—Cost-Recovery Method

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Illustration 18-24

LO 4 Apply the cost-recovery method for long-term contracts.

Page 18: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-18

2010 2011 2012 Contract price €675,000 €675,000 €675,000 Cost incurred current year 150,000 287,400 170,100 Estimated cost to complete in future years 450,000 170,100 0 Billings to customer current year 135,000 360,000 180,000 Cash receipts f rom customer Current year 112,500 262,500 300,000

A) Prepare the journal entries for 2010, 2011, and 2012. A) Prepare the journal entries for 2010, 2011, and 2012.

LO 3 Apply the percentage-of-completion method for long-term contracts.

Illustration:

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Casper Construction Co.

Page 19: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-19 LO 3 Apply the percentage-of-completion method for long-term contracts.

2010 2011 2012

Costs incurred to date € 150,000 € 437,400 € 607,500

Estimated cost to complete 450,000 170,100

Est. total contract costs 600,000 607,500 607,500

Est. percentage complete 25.0% 72.0% 100.0%

Contract price 675,000 675,000 675,000

Revenue recognizable 168,750 486,000 675,000

Rev. recognized prior year (168,750) (486,000)

Rev. recognized currently 168,750 317,250 189,000

Costs incurred currently (150,000) (287,400) (170,100)

Gross profi t recognized € 18,750 € 29,850 € 18,900

Illustration:

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 20: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-20 LO 3 Apply the percentage-of-completion method for long-term contracts.

Construction in progress 150,000 287,400 170,100 Cash 150,000 287,400 170,100

Accounts receivable 135,000 360,000 180,000 Billings on contract 135,000 360,000 180,000

Cash 112,500 262,500 300,000 Accounts receivable 112,500 262,500 300,000

Construction in progress 18,750 29,850 18,900 Construction expense 150,000 287,400 170,100

Construction revenue 168,750 317,250 189,000

Billings on contract 675,000 Construction in progress 675,000

20122010 2011

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Illustration:

Page 21: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-21 LO 3 Apply the percentage-of-completion method for long-term contracts.

Income Statement 2010 2011 2012

Revenue on contracts 168,750$ 317,250$ 189,000$

Cost of construction 150,000 287,400 170,100 Gross profit 18,750 29,850 18,900

Balance Sheet (12/31)Current assets:

Accounts receivable 22,500 120,000 - Cost & profits > billings 33,750

Current liabilities:Billings > cost & profits 9,000

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Illustration:

Page 22: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-22

Companies recognize revenue only to the extent of costs

incurred that are expected to be recoverable.

Only after all costs are incurred is gross profit recognized.

LO 4 Apply the cost-recovery method for long-term contracts.

Cost-Recovery Method

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 23: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-23

Cost-Recovery MethodCost-Recovery Method

Illustration:

Construction in progress 150,000 287,400 170,100 Cash 150,000 287,400 170,100

Accounts receivable 135,000 360,000 180,000 Billings on contract 135,000 360,000 180,000

Cash 112,500 262,500 300,000 Accounts receivable 112,500 262,500 300,000

Construction in progress 67,500 Construction expense 150,000 287,400 170,100

Construction revenue 150,000 287,400 237,600

Billings on contract 675,000 Construction in progress 675,000

20122010 2011

LO 4 Apply the cost-recovery method for long-term contracts.

Page 24: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-24

Illustration:

Income Statement 2010 2011 2012

Revenue on contracts € 0 € 0 € 675,000

Cost of construction - - 607,500 Gross profit - - 67,500

Balance Sheet (12/31)Current assets:

Accounts receivable 22,500 120,000 - Cost & profits > billings 15,000

Current liabilities:Billings > cost & profits 57,600

Cost-Recovery MethodCost-Recovery Method

LO 4 Apply the cost-recovery method for long-term contracts.

Page 25: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-25 LO 5 Identify the proper accounting for losses on long-term contracts.

Loss in the Current Period on a Profitable Contract

► Percentage-of-completion method only, the estimated

cost increase requires a current-period adjustment of

gross profit recognized in prior periods.

Loss on an Unprofitable Contract

► Under both percentage-of-completion and completed-

contract methods, the company must recognize in the

current period the entire expected contract loss.

Long-Term Contract Losses

Long-Term Contracts (Construction)Long-Term Contracts (Construction)

Page 26: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-26

Illustration: Loss in Current Period

Long-Term Contract LossesLong-Term Contract Losses

LO 5 Identify the proper accounting for losses on long-term contracts.

2010 2011 2012 Contract price €675,000 €675,000 €675,000 Cost incurred current year 150,000 287,400 215,436 Estimated cost to complete in future years 450,000 215,436 0 Billings to customer current year 135,000 360,000 180,000 Cash receipts f rom customer Current year 112,500 262,500 300,000

b) Prepare the journal entries for 2010, 2011, and 2012 assuming the estimated cost to complete at the end of 2011 was €215,436 instead of €170,100.

b) Prepare the journal entries for 2010, 2011, and 2012 assuming the estimated cost to complete at the end of 2011 was €215,436 instead of €170,100.

Casper Construction Co.

Page 27: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-27

2010 2011 2012

Costs incurred to date € 150,000 € 437,400 € 652,836

Estimated cost to complete 450,000 215,436

Est. total contract costs 600,000 652,836 652,836

Est. percentage complete 25.0% 67.0% 100.0%

Contract price 675,000 675,000 675,000

Revenue recognizable 168,750 452,250 675,000

Rev. recognized prior year (168,750) (452,250)

Rev. recognized currently 168,750 283,500 222,750

Costs incurred currently (150,000) (287,400) (215,436)

Gross profi t recognized € 18,750 (€ 3,900) € 7,314

Long-Term Contract LossesLong-Term Contract Losses

LO 5 Identify the proper accounting for losses on long-term contracts.

Illustration: Loss in Current Period

Page 28: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-28

Construction in progress 18,750 7,314 Construction expense 150,000 215,436

Construction revenue 168,750 222,750

Construction in progress 3,900 Construction expense 287,400

Construction revenue 283,500

20122010 2011

Long-Term Contract LossesLong-Term Contract Losses

LO 5 Identify the proper accounting for losses on long-term contracts.

Illustration: Loss in Current Period

Page 29: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-29

Illustration: Loss on Unprofitable Contract

Long-Term Contract LossesLong-Term Contract Losses

LO 5 Identify the proper accounting for losses on long-term contracts.

2010 2011 2012 Contract price €675,000 €675,000 €675,000 Cost incurred current year 150,000 287,400 246,038 Estimated cost to complete in future years 450,000 246,038 0 Billings to customer current year 135,000 360,000 180,000 Cash receipts f rom customer Current year 112,500 262,500 300,000

c) Prepare the journal entries for 2010, 2011, and 2012 assuming the estimated cost to complete at the end of 2011 was € 246,038 instead of € 170,100.

c) Prepare the journal entries for 2010, 2011, and 2012 assuming the estimated cost to complete at the end of 2011 was € 246,038 instead of € 170,100.

Casper Construction Co.

Page 30: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-30

2010 2011 2012

Costs incurred to date € 150,000 € 437,400 € 683,438

Estimated cost to complete 450,000 246,038

Est. total contract costs 600,000 683,438 683,438

Est. percentage complete 25.0% 64.0% 100.0%

Contract price 675,000 675,000 675,000

Revenue recognizable 168,750 432,000 675,000

Rev. recognized prior year (168,750) (432,000)

Rev. recognized currently 168,750 263,250 243,000

Costs incurred currently (150,000) (290,438) (243,000)

Gross profi t recognized € 18,750 (€ 27,188) € 0

Long-Term Contract LossesLong-Term Contract Losses

LO 5

$675,000 – 683,438 = (8,438) cumulative loss Plug

Illustration: Loss on Unprofitable Contract

Page 31: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-31

Construction in progress 18,750 - Construction expense 150,000 243,000

Construction revenue 168,750 243,000

Construction in progress 27,188 Construction expense 290,438

Construction revenue 263,250

20122010 2011

Long-Term Contract LossesLong-Term Contract Losses

LO 5 Identify the proper accounting for losses on long-term contracts.

Illustration: Loss on Unprofitable Contract

Page 32: 18-1 Two methods of accounting for long-term construction contracts:  Percentage-of-completion method.  Cost-recovery (zero-profit) method. Long-Term

18-32

Loss on construction contract 8,438

Construction in progress 8,438

Construction expense 287,400

Construction revenue 287,400

2010 2011

Long-Term Contract LossesLong-Term Contract Losses

LO 5 Identify the proper accounting for losses on long-term contracts.

For the Cost-Recovery method, companies would recognize the

following loss:

Illustration: Loss on Unprofitable Contract