31
181 Mercer Street Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

181 Mercer Street

Financial Plan Update

Martin S. Dorph

Executive Vice President, Finance and Information Technology

December 8, 2016

Page 2: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

• Summary 3 – 6

• Background (2012 – 2016) 7 – 15

• University Financial Outlook (2017 – 2025) 16 – 19

• Project Update - 181 Mercer 20 – 22

• Current Forecast of Financial Metrics 23 - 28

• Debt & Credit Management 29 – 31

2

Table of Contents

Page 3: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

3

Summary

Page 4: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

History

• The University Space Priorities Working Group, as part of its review of the Core Project,

now referred to as 181 Mercer Street, examined the feasibility of the University’s

financial plan. Data was provided to the USPWG in 2012 and updated the following

year.

• At that time, the project being considered was approximately 670,000 square feet with

a cost of $727 million.

• The information presented included historical and projected operating and capital

budget data, and financial metrics pertaining to the University’s ability to pay for the

project.

• The USPWG Final Report presented the following findings:

o NYU has adopted reasonably conservative and prudent assumptions in its financial planning for capital

construction and that the Working Group’s recommendations for construction on the Coles Site are within

NYU’s current fiscal means. The University need not – and should not – adjust future tuition fees or faculty,

administrative or staff salary assumptions to cover capital costs.

o Building on land the University already owns is less financially costly than building on land that it must first

buy.

• There have been changes to the project since the USPWG report was issued, but the

overall University capital plan has remained consistent with the plan reviewed by the

USPWG.4

Summary

Page 5: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

Current 181 Mercer Finances

• 181 Mercer Street as currently designed and programmed, will be approximately 735,000 square feet with a projected cost of $1,285 million.

• The changes in cost are attributable to the following factors:

o A larger program for the building requiring additional square footage as recommended by the USPWG and as permitted under the City approvals ;

o Based on USPWG recommendations, proportional increase in spaces with higher costs per square foot (e.g., theaters);

o Cost premiums associated with structural support to clear wide span and double height spaces such as theaters, gymnasium, etc.;

o Increase in construction market costs;

o Additional cost escalation due to passage of time.

• The financial plan for 181 Mercer assumes debt issuance of $947 million, fundraising of $300 million, and use of University “working capital” (cash on hand) of $38 million, spread over the next five years.

• To date, $145M has been raised through fundraising efforts.

• The operating budget impact of the project has been incorporated into the University’s Ten Year Financial plan.

5

Summary

Page 6: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

How 181 Mercer Affects the University’s Finances

• In the past five years, the University has outperformed its financial plan and exceeded the projected

financial metrics presented in 2012.

• Our affordability initiatives have resulted in a lower rate of tuition increase and substantial growth in

financial aid, but also lower than anticipated expenses in areas such as debt service, energy, and

general operating supplies and services. Enrollment increased more than projected in 2012 due to

a combination of selected planned growth, higher yield and higher retention

• The University’s capital plan through 2024 – which includes the funding for 181 Mercer- amounts to

$2.76 billion of capital projects, a number consistent with the amount projected in 2012, and also

consistent with the University’s overall rate of capital spending over the past decade.

• In addition to 181 Mercer, the plan includes provisions for new projects such as 370 Jay Street,

additional investments in Tandon School of Engineering, projects supporting science at Washington

Square, and provisions for ongoing capital replacement and improvements on existing facilities.

• Looking forward, the University’s financial plan does not assume or rely on enrollment increases or

additional tuition increases as a funding source for the project.

• The latest projections show that even with the overall higher cost of the project, the

University will generally meet or outperform the financial metrics established in 2012.

(There is a higher debt level and leverage ratio due in large part to increases in the School of

Medicine’s borrowing plans, which is part of the University’s balance sheet. The School of

Medicine’s debt is paid by the School of Medicine).

6

Summary

Page 7: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

7

Background (2012 – 2016)

Page 8: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

• NYU’s financial planning encompasses two budgets: Operating and Capital. They are summarized here:

http://www.nyu.edu/about/news-publications/budget.html

• The University Operating Budget is developed annually, and approved each June by the Board of Trustees.

o We project a Ten Year Financial Plan to assure long-term sustainability of our budget decisions.

o The Operating Budget also undergoes “stress tests” to assure that mitigation strategies are in place in

the event of unforeseen shocks.

• The Capital Budget – looks at the fixed assets (buildings, improvements such as new labs). It is reviewed

and approved annually, but also includes a Ten Year Plan.

o Capital projects are funded from a number of sources: borrowing, fund raising, cash generated from

operations.

o Why borrow: Debt is used to spread the cost of long-term assets over time because fixed assets are

used over time.

o The payments of principal and interest on the debt (“debt service”) is then incorporated into the

operating budget.

• Our goal is to fund the ongoing academic, research and programmatic needs and goals of NYU, while

balancing our ability to cover current expenses with long-term sustainability.

• We use a number of metrics to evaluate that balance.

• Rating agencies (Moody’s and Standard & Poor’s) also independently evaluate our creditworthiness and

financial condition using similar metrics.

8

Background

Page 9: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

Operating Budget 2012 – 2016

There have been some significant developments affecting the University budget since the projections that were made in 2012:

o Tuition and Fee Rate Increases – Since 2013, the rate of undergraduate tuition increase has dropped from 3.9% to 3.5% and

student fees has dropped from 2.8% to 2.0%. Last year, the rate of increase was 2.9%, with no increase in fees, as we moved

forward on the Affordability Initiative.

o Enrollment – Undergraduate enrollment at NYU WSQ increased from 22,280 to 23,435, while graduate and professional

enrollment decreased from 21,631 to 21,410. These numbers compare fiscal 2012 with fiscal 2016 and exclude the Tandon

School of Engineering, which was not part of the SPWG presentation in 2012. The growth in undergraduate enrollment was

due to a combination of selected planned growth, higher yield and higher retention. The decrease in graduate enrollment was

primarily due to declines from peak enrollment in master’s programs.

o Financial Aid – Total financial aid increased from $341 million to $488 million, while undergraduate financial aid alone grew by

$182 million to $269 million.

o Energy – 7.5% decline in University’s energy budget between 2012 and 2016 due to conservation measures, re-estimations of

energy price inflation, and savings from full operation of the co-generation plant.

o Debt Service – Continuous savings due to actual long-term interest rates consistently below the University’s financial plan

assumption of 6% interest.

o Tandon School of Engineering – Starting in 2014, (with the first full year being 2015), the NYU Polytechnic Institute

successfully merged into the University and became the Tandon School of Engineering, bringing with it savings in

administrative and auxiliary operations from the merger.

o Portal Campuses – Enrollment at NYU Abu Dhabi grew from 447 to 1,048, the first commencement took place in Spring 2013

with a graduating class of 140 students from 49 countries. The new campus opened at Saadyiat Island in 2014. The inaugural

class of 300 freshmen enrolled at NYU Shanghai in 2013, and the new permanent campus opened in August 2014. The Portal

Campuses have operated on a break even basis – they have added revenues and expenses to the University budget but have

not impaired the WSQ budget

9

Background

Page 10: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

Operating Budget 2012 – 2016

• With those changes, the University has consistently been able to generate a

positive operating margin (the excess of revenues over expenses) in its Operating

Budget.

• In fact, the University has outperformed its budget by about $450 million over the

past five years.

• The positive operating margin is used to fund a portion of capital projects as well

as provide school-based operating reserves.

Background

10

(estimated)

Page 11: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

11

Background

Capital Budget 2012 – 2016

• The University has undertaken $1.9 billion in capital projects over the past five years

• The total capital spend over the past ten years was $3.9 billion.

878

96 80

840

Capital Expenditures2012 - 2016*(dollars in millions)

Academic

Student Housing and Student Services

Faculty Housing

Campus Infrastructure, Administration,and Other

$1,894

Page 12: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

Capital Budget 2012 – 2016

Significant projects undertaken in the past five years include:

Academic

• 370 Jay Street, Brooklyn Mixed-Use Academic Building (2013-2016): $185M

• 20 Cooper Square Mixed-Use Academic Building (2013-2016): $14M

• 433 First Ave for the Colleges of Dentistry and Nursing and Bio-Engineering (2012-2016): $147M

• 60 5th Avenue (formerly Forbes Building) for the Marron Institute, Center for Data Science, and Courant Computer Science Department

(2014-2016): $59M

• The Media and Games Network at 2 MetroTech Center, Brooklyn (2013-2016): $16M

• FAS Physics at 726 Broadway (2012-2016): $84M

• FAS Science Projects at Silver and Meyer (2012-2016): $30M

• Tandon School of Engineering Projects (2012-2016): $51M

• Miscellaneous Academic (2012-2016): $238M

Student Housing and Student Services

• 383 Lafayette Student Services Building (2012-2016): $49M

• 404 Lafayette for Athletics (2015-2016): $16M

• Miscellaneous Student Housing and Student Services (2012-2016): $41M

Faculty Housing

• Faculty Housing Renovations and Investments: $80M

Campus Infrastructure, Administration, and Other

• 383 Lafayette Building Purchase (2014): $17M

• 404 Lafayette Building Purchase and Stabilization Renovations (2015-2016): $171M

• Capital Replacement (2012-2016): $274M

• Cogen Utility for Superblocks (2016): $20M

• Information Technology (2012-2016): $135M 12

Background

Page 13: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

Financial Metrics: Historic Performance

• In 2012, The USPWG was presented with the financial metrics used to set budget goals for the University.

• We analyzed the following metrics over the historic period 2013-2016 to compare projected performance with actual

results. Across several metrics, the University has out-performed the Financial Plan.

o Operating Margin: Excess of annual operating revenues over annual operating expenses (WSQ only). This is

the annual cash flow generated from University operations before use for capital projects, or deposits to reserve

accounts. The University has outperformed projections by an average of $48 million per year.

o Cash and Unrestricted Investments: Working Capital plus unrestricted long term investments as of August 31 of

each year. Long- term investments do not include donor-designated endowment but do include “quasi-

endowment”, i.e., funds invested long term but not restricted. (WSQ only). Cash and unrestricted investments

are approximately $150 million greater than projected.

o Debt Service: Annual Principal and Interest Payments (WSQ only). Debt Service is now about $24 million

below projection – even as the amount of debt has grown as projected, interest rates have remained

lower than assumed in our planning.

o Debt Service as a % of Annual Operating Budget (WSQ only). This metric is currently well below projection

due to lower rates.

o Capital Expenditures: (WSQ only). Capital expenditures are slightly below projection as some projects have

lagged in timing of construction.

o Debt: Long-Term Debt Outstanding. School of Medicine debt is included in this metric, as it is part of the

University balance sheet. The amount of debt outstanding is $465 million higher than projected, because

long term debt for pending capital expenditures planned in FY16-18 was accelerated into a larger issue in

FY16 to take advantage of low interest rates.

o Leverage: Ratio of Expendable Financial Resources to Debt (with expendable financial resources defined as

unrestricted and temporarily restricted net assets less plant). Again, School of Medicine debt is included in the

calculation of this metric. The earlier issuance of debt creating a lower EFR to Debt ratio than expected.13

Background

Page 14: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

14

Background

73 53 59

101

161

104 107

146

-

50

100

150

200

250

FY13 FY14 FY15 FY16

do

llars

in m

illio

ns

Operating Margin (WSQ Only)

November 2012 Projection Actual Activity

1,655 1,777 1,627

1,909

1,861 2,040 2,129 2,056

-

500

1,000

1,500

2,000

2,500

3,000

FY13 FY14 FY15 FY16

do

llars

in m

illio

ns

Cash and Unrestricted Investments (WSQ Only)

November 2012 Projection Actual Activity

Note: FY16 Actuals are preliminary (audit not yet final).

Note: FY16 Actuals are preliminary (audit not yet final).Note: FY16 Actuals are preliminary (audit not yet final).

Note: FY16 Actuals are preliminary (audit not yet final).

141 161

183 177

133 146 138 153

-

50

100

150

200

250

300

350

FY13 FY14 FY15 FY16

do

llars

in m

illio

ns

Annual Debt Service (WSQ Only)

November 2012 Projection Actual Activity

5.8% 6.2% 6.6% 6.1%

5.1% 5.3% 4.7% 5.1%

0.0%

2.0%

4.0%

6.0%

8.0%

10.0%

12.0%

14.0%

FY13 FY14 FY15 FY16

% o

f O

per

ati

ng

Exp

ense

s

Annual Debt Service as a % of Operating Expenses (WSQ Only)

November 2012 Projection Actual Activity

Page 15: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

15

Background

327

322

517

402

335

266

486

441

-

100

200

300

400

500

600

700

FY13 FY14 FY15 FY16

do

llars

in m

illio

ns

Capital Expenditures (WSQ Only)

November 2012 Projection Actual Activity

Note: FY16 Actuals are preliminary (audit not yet final).

Note: FY16 Actuals are preliminary (audit not yet final).

Note: FY16 Actuals are preliminary (audit not yet final).

.

.

2,449 2,486 2,861

2,826 2,176 2,266 2,449

3,272

-

1,000

2,000

3,000

4,000

5,000

FY13 FY14 FY15 FY16

do

llars

in m

illio

ns

Outstanding Long-Term Debt (WSQ + SOM)

November 2012 Projection Actual Activity

0.47x 0.48x 0.38x

0.40x

0.50x

0.67x 0.58x

0.26x

0.00x

0.20x

0.40x

0.60x

0.80x

FY13 FY14 FY15 FY16

EFR

/Dir

ect

Deb

t

Expendable Financial Resources to Direct Debt (WSQ + SOM)

November 2012 Projection Actual Activity

Page 16: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

16

University Financial Outlook

(2017 – 2025)

Page 17: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

The University’s current Ten Year Financial Plan is based on the following Operating

Budget assumptions:

o UG Enrollment Growth at Washington Square: Slight reduction following “over

enrollment” compared to plan in 2016.

o Graduate and Professional Enrollment Growth: essentially flat

o UG Tuition: Moderation of rate of increase compared to recent history

o UG Room and Board: Moderation of rate of increase compared to recent history

o UG Financial Aid: Rate of increase as needed to maintain discount rate

o Graduate Tuition: Rate of increase consistent with recent history

o Philanthropy: Consistent with recent history

o Annual Merit Increases (Salaries): Maintain competitive market position

o Energy: Overall, lower, with rate of increase lower than recent history

o General Inflation in Other Than Non-personnel Costs: 2.5% per year after FY18

o Some savings and adjustments due to affordability initiatives (no affordability

initiative funds used to fund 181 Mercer)

17

Outlook

Page 18: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

18

Outlook

.

The University’s Capital Plan projects $2.76 billion of spending, including the

181 Mercer Street project. ($3.9 billion was spent over the past ten years)

1,135

508

244

869

Projected Capital Expenditures2017 - 2024(dollars in millions)

Academic

Student Housing and Student Services

Faculty Housing

Campus Infrastructure, Administration,and Other

$2,756

Page 19: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

19

Outlook

Following is a list of the major capital projects planned for the next ten years. .

Academic

370 Jay Street Mixed-Use Academic Building (2017-2018): $219M

404 Lafayette for the College of Global Public Health (2017-2019): $50M

FAS Physics at 726 Broadway (2017): $29M

FAS Science Projects at Meyer (2017-2019): $63M

Tandon School of Engineering Projects (2017-2020): $107M

Miscellaneous Academic (2017-2025): $53M

Student Housing and Student Services

Miscellaneous Student Housing and Student Services: $20M

Faculty Housing

Faculty Housing Renovations and Investments: $103M

Campus Infrastructure, Administration, and Other

Capital Replacement (2017-2025): $648M

Cogen Utility for Superblocks (2017-2018): $40M

Information Technology (2017-2025): $94M

Miscellaneous Campus Infrastructure, Administration and Other (2017-2021): $39M

181 Mercer (Mixed Use Project): $1,285M

Page 20: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

20

Project Update – 181 Mercer

Page 21: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

21

181 Mercer

561

198

132

259

135

Capital Uses - 181 Mercer(dollars in millions)

Academic

Student Housing

Faculty Housing

Athletics

Other

$1,285

300

947

38

Capital Sources - 181 Mercer(dollars in millions)

Fundraising

Long-Term Debt

University Working Capital

$1,285

• 181 Mercer Street as currently designed and programmed, will be approximately 735,000 square feet

with a projected cost of $1,285 million.

• The changes in cost are attributable to the following factors

o Increase in square footage as permitted under the City approvals

o Based on USPWG recommendations, proportional increase in spaces with higher costs per

square foot (e.g., theaters)

o Cost premiums associated with structural support to clear wide span and double height spaces

such as theaters, gymnasium, etc.

o Increase in construction market costs

o Additional cost escalation due to passage of time

Page 22: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

22

181 Mercer

Annual Operating Revenues

Student Housing Revenue (~475 beds @ 97% occupancy) 8$

Faculty Housing Rents 11$

Total Annual Operating Revenues 19$

Annual Operating Expenses

Building Operating Expenses 14$

Debt Service 69$

Total Annual Operating Expenses 83$

Net Operating Surplus/(Deficit) (64)$

• 181 Mercer Street is projected to incur an annual “carrying cost” of $64 million

per year.

• The annual carrying cost has been incorporated into the University’s Ten Year

Financial Plan.

• The assumed interest rate on the debt is 6.0%. At current interest rates,

annual cost could be reduced by up to $12 million per year.

Page 23: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

23

Current Forecast of Financial Metrics

Page 24: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

Current Forecast of Financial Metrics

24

• The March, 2014 Final Report of the University Space Priorities Working Group

concluded that the replacement building at 181 Mercer Street could be

“accommodated within the University’s capital spending framework” and “unless

there are unexpected or unforeseen developments, the proposed Capital Spending

and Financing Plan is unlikely to impair the financial status of NYU.”

• The following pages compare the metrics as projected in 2012 to both the historical

results for the years 2012 -2016, and as projected through 2024. (Note the

projections made in 2012 ended in 2021).

• The forecasted financial metrics show that the University generally meets or

exceeds the metrics originally projected in 2012.o Annual operating margin and unrestricted cash and investments continue to exceed

projections and trend upward. The University has historically generated an operating

margin approximately $50 million greater than planned.

o Total debt outstanding exceeds the 2012 projection due to increased School of Medicine

debt plans, plus the increase in borrowing that is driven by the increase in the cost of 181

Mercer.

o The Expendable Financial Resources to Debt ratio falls below the 2012 metrics due to that

increased borrowing.

o Annual debt service projects higher as a result of increased borrowing (but debt service as

a % of the University operating budget remains roughly consistent with the projections).

Page 25: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

Current Forecast of Financial Metrics

25

Note: FY16 Actuals are estimated.

Note: FY16 Actuals are estimated.

73 53 59

101 84

105 131

159

207

161

104 107

146

93 120

166 194

185

220

255 278

-

50

100

150

200

250

300

FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24

do

llars

in m

illio

ns

Operating Margin (WSQ Only)

November 2012 Projection Actual Activity Forecast

Actuals Forecast

1,655 1,777 1,627

1,909 1,615

1,790 1,716 1,770 1,889

1,861 2,040 2,129 2,056

1,879 1,885 1,946 2,120 2,081

2,352 2,547

2,865

-

500

1,000

1,500

2,000

2,500

3,000

FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24

do

llars

in m

illio

ns

Cash and Unrestricted Investments (WSQ Only)

November 2012 Projection Actual Activity Forecast

Actuals Forecast

NYU has historically generated an operating margin

approximately $50 million per year greater than planned.

This expected outperformance is not included in this

projection. Interest rate on new debt is projected at 6%

although current rates are in the 4% to 4.5% range.

Page 26: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

2,449 2,486 2,861

2,826 3,305 3,255 3,247 3,193 3,137

2,176 2,266 2,449

3,272 3,456 3,603 3,992 3,972

4,644 4,615 4,482 4,442

-

1,000

2,000

3,000

4,000

5,000

FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24

do

llars

in m

illio

ns

Outstanding Long-Term Debt (WSQ + SOM)

November 2012 Projection Actual Activity Forecast

Actuals Forecast

Current Forecast of Financial Metrics

26

Note: FY16 Actuals are estimated.

Note: FY16 Actuals are estimated.

Increase in debt is primarily driven by School of Medicine plan for $700 million in

additional debt that has been approved since the Nov. 2012 projection by FY21 ,

and increase in borrowing to support 181 Mercer project.

327

322

517

402 445

225

102 107 111

335

266

486

441

527

665

575

443

183 113 120 130

-

100

200

300

400

500

600

700

FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24

do

llars

in m

illio

ns

Capital Expenditures (WSQ Only)

November 2012 Projection Actual Activity Forecast

Actuals Forecast

Page 27: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

Current Forecast of Financial Metrics

27Note: FY16 Actuals are estimated.

Note: FY16 Actuals are estimated.

141 161

183 177

235 235 240 240

243

133 146 138 153 153

210 216 224

282 287 287 294

-

50

100

150

200

250

300

350

FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24

do

llars

in m

illio

ns

Annual Debt Service (WSQ Only)

November 2012 Projection Actual Activity Forecast

Actuals Forecast

5.8% 6.2% 6.6% 6.1%7.7% 7.4% 7.3% 7.0%

7.0%5.1% 5.3% 4.7% 5.1% 4.7%

6.3% 6.2% 6.2%

7.5% 7.3% 7.2% 7.1%

0.0%

2.0%

4.0%

6.0%

8.0%

10.0%

12.0%

14.0%

FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24

% o

f O

per

ati

ng

Exp

ense

s

Annual Debt Service as a % of Operating Expenses (WSQ Only)

November 2012 Projection Actual Activity Forecast

Actuals Forecast

Debt service on debt issued in 2017 and later is projected at an

interest rate of 6.0% -significantly higher than current rates.

Page 28: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

0.47x 0.48x

0.38x

0.40x 0.31x

0.35x 0.38x 0.41x 0.46x

0.50x

0.67x 0.58x

0.26x 0.19x

0.15x 0.15x 0.21x 0.23x

0.29x 0.36x

0.45x

0.00x

0.10x

0.20x

0.30x

0.40x

0.50x

0.60x

0.70x

0.80x

FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24

EFR

/Dir

ect

Deb

t

Expendable Financial Resources to Direct Debt (WSQ + SOM)

November 2012 Projection Actual Activity Forecast

Actuals Forecast

Current Forecast of Financial Metrics

28

Note: FY16 Actuals are estimated.

Reduction in EFR to Direct Debt is primarily driven by School of Medicine plan for $700

million in additional debt that has been approved since the Nov. 2012 projection by FY21 ,

and increase in borrowing to support 181 Mercer project.

Page 29: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

29

Debt & Credit Management

Page 30: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

Measuring & Monitoring NYU’s Debt Capacity

30

• NYU’s ability to pay its debt service is evaluated by both internal and external third parties at regular intervals. The

University and its School of Medicine (the “obligated group”) maintain a credit rating that is separate from the credit

rating of NYU Hospital, which is a separate entity. While NYU’s financials are consolidated annually to include both

the Hospital and the University, neither entity is legally obligated for the debt of the other.

• Annually, Moody’s and S&P assess NYU’s credit worthiness and assign a credit rating to NYU’s debt. This credit

rating is used by investors to assess risk relative to NYU’s ability to pay debt service on its obligations. NYU’s last

annual credit review was completed in May, 2016. Moody's and S&P both affirmed NYU's credit rating, at Aa3

(positive outlook) and AA- (stable outlook), respectively. NYU has maintained these ratings since the first rating was

assigned in 2009.

• Moody’s holistic review of NYU’s credit strengths and weaknesses is summarized as follows:

• Credit Strengths:

• Relatively rapid transformation to a globally competitive, research-intensive university, with a presence in

more than 40 countries

• Large size and scope of operations…provides diversity and economies of scale

• Substantial amount of highly marketable real estate holdings in New York City

• Strong clinical demand contributing to robust hospital operating performance

• Significantly improved monitoring and oversight capacity for this large and complex organization

• Credit Challenges:

• Very high leverage, including operating leases and a modest pension liability

• Exposure to the profitability of clinical care from an A3 rated organization

• Moderate liquidity for such a large and complex organization, mitigated by modest potential calls and

committed bank lines

• Complexity of business lines and diverse locations highlight the importance of coordinated oversight and

skilled management

Page 31: 181 Mercer Street Financial Plan Update - NYU · 2016-12-08 · Financial Plan Update Martin S. Dorph Executive Vice President, Finance and Information Technology December 8, 2016

Measuring & Monitoring NYU’s Debt Capacity

31

• In their most recent rating reports, both firms commented on NYU's exceptional enterprise profile and robust and continuing

student demand. Some notable excerpts from the reports include:

o "We believe that NYU will be able to easily absorb the additional debt at the current rating level. We expect they will

issue additional debt in the next two to three years to fund the Mercer Street expansion, which we believe they will

also be able to absorb at the current rating level.“ (S&P)

o "The university has robust strategic planning and a track record of execution and monitoring of strategies.” (Moody’s)

o "NYU's investments in the recently consolidated engineering school, formerly NYU Poly, combined with New York

City's initiatives to expand applied science, engineering, and technology transfer will drive strong positive

momentum.“(Moody’s)

• The University continues to utilize conservative planning assumptions and analyses.

o In addition to external evaluation, the Finance Committee of NYU’s Board of Trustees reviews NYU’s financial

performance and projections at least twice a year, and have reviewed the metrics shown in this presentation.

University leadership also provides “stress tests” demonstrating our capacity to manage through unexpected financial

shocks.

o Since FY09, NYU’s cash and long term investments have grown by 47%. After eliminating permanently restricted

investments in NYU’s endowment, the growth in cash and unrestricted investments is 33% over the same time

period. Thus, as the University has increased its debt portfolio, it has also increased its financial reserves.

o The University’s Operating Budget continues to show an upward trend in operating margin, and has demonstrated

consistent outperformance – the actual operating margin has exceeded the budgeted margin by over $50 million per

year.

o NYU’s existing debt portfolio is composed of fixed rate, amortizing debt (the typical average life is less than 20 years).

We do not have variable rate debt, derivatives or swap agreements. This conservative structure allows for predictable

financial planning and mitigates risk. NYU conservatively projects a cost of future borrowing at 6%, but NYU’s

current cost of capital is estimated in the range of 4% to 4.5%%.

• It remains our conclusion that the proposed 181 Mercer project financing plan is unlikely to impair the financial status of

NYU.