(20) Section 16 - Dec 2004

  • Upload
    voonyvr

  • View
    16

  • Download
    0

Embed Size (px)

Citation preview

  • 5/27/2018 (20) Section 16 - Dec 2004

    1/42

    CUMULATIVE ENVIRONMENTA

    EFFECTS ASSESSMEN

    SECTION

  • 5/27/2018 (20) Section 16 - Dec 2004

    2/42

    Environmental Assessment Certificate Application

    for the RichmondAirportVancouver Rapid Transit Project

    16-1 December 2004

    16 Cumulative Environmental Effects Assessment

    16.1 Introduction

    Cumulative environmental effects assessment, required under CEAA, considers

    the interaction between residual effects of the project under consideration, (i.e.,

    those impacts expected to occur during construction and/or operation despite

    implementation of mitigation measures) and those associated with other

    identified projects or activities. The analysis is undertaken with reference to

    defined temporal and spatial boundaries and typically focuses on key

    environmental components. Cumulative effects assessment methodology is

    described in the Cumulative Effects Assessment Practitioners Guide (Hegmann

    et al. 1999) and the CEAA Reference Guide: Addressing Cumulative

    Environmental Effects (CEA Agency 2003).

    The Approved Terms of Reference for the RAV EAC Application (see

    Appendix 1-A) direct that the scope of the cumulative environmental effects

    assessment for the RAV Project consider other projects that:

    are located within or that intersect with the RAV corridor;

    are known to have received or are in the process of acquiring permits and

    authorizations that would allow them to proceed to implementation;

    have secured funding, and

    have schedules and timelines that are known to be imminent in their

    commencement, up to the submission of the Application.

    In addition to the ATOR and the guidance documents noted above, the

    cumulative effects assessment presented in this section was guided by

    discussions with the CEA Agency. The determination of residual effects was

    based on the scientific information presented in the project-specific

    environmental assessments (see SECTIONS 6TO 15).

    As described in the Socio-economic/Socio-community Assessment (see SECTION9.6.5.6), the RAV line may act as a catalyst for future residential, commercial

    and/or industrial development along the RAV corridor, particularly in proximity to

    RAV stations. The extent to which this demand can be accommodated will vary

    along the corridor, depending on existing land use, property availability, zoned

    development capacity, and the receptiveness of neighbourhoods and city

  • 5/27/2018 (20) Section 16 - Dec 2004

    3/42

    Environmental Assessment Certificate Application

    for the RichmondAirportVancouver Rapid Transit Project

    December 2004 16-2

    planners to zoning or land use changes. Since the nature, scope and extent of

    development, the timeframe over which it may occur, and the impacts that may

    be associated with it are unknown, it is not possible to determine whether or how

    future development may interact with the RAV Project to produce cumulativeeffects. Consequently, no attempt was made to assess the cumulative effects of

    potential RAV line-induced development in the following analysis.

    16.2 Analytical Approach

    16.2.1 General

    The cumulative effects assessment builds upon the findings of the 10

    biophysical and socio-economic environmental assessments conducted forthe RAV Project (see SECTIONS 6 TO 15). Each of these assessments

    describes potential project-related impacts, including residual effects that may

    occur along the RAV corridor during construction and/or operation. Residual

    effects are defined as those impacts that cannot be completely addressed

    through the application of mitigation measures. Because they cannot be

    resolved through mitigation and are likely to persist following project

    completion, residual effects may interact with impacts associated with present

    and imminent future developments and activities in the project area,

    potentially resulting in cumulative impacts.

    As previously described, the RAV Project is located along a defined corridor

    through a densely populated, highly developed urban area. The natural

    environment along this corridor has been completely altered due to many

    decades of industrial, commercial and residential use, as well as the

    presence of a complex network of utilities and transportation infrastructure.

    The intent of this cumulative impact assessment is to characterize,

    qualitatively and quantitatively, where possible, the potential consequence of

    residual impacts associated with the RAV Project in the context of urbandevelopment in the project area, as follows:

    Spatially (i.e., locally and/or regionally, depending on the nature of the

    impact and the ecosystem component that is being assessed);

    Temporally (i.e., on a timeline that extends from the present to the future);

  • 5/27/2018 (20) Section 16 - Dec 2004

    4/42

    Environmental Assessment Certificate Application

    for the RichmondAirportVancouver Rapid Transit Project

    16-3 December 2004

    In the context of environmental setting (e.g., effects on suitability of

    existing habitat to support species habituated to an urban setting vs. the

    fundamental habitat capability of the biogeoclimatic zone); and

    In terms of critical thresholds

    1

    , as defined by existing policies andstandards, or with respect to the ecological sustainability of environmental

    components; these thresholds may have been approached as a result of

    previous projects and may be surpassed by development of the RAV

    Project and/or other imminent projects.

    16.2.2 Biophysical and Socio-community Environmental

    Components

    In an urban setting, such as that of the RAV corridor, biophysical

    environmental components typically considered during impact assessmentinclude features such as remnant natural habitat areas (e.g., wooded

    ravines); fisheries habitat (e.g., instream habitat and associated riparian

    zones); and vegetation stands that are valued for aesthetic, historic, or

    biological qualities. Since the RAV corridor crosses the lower Fraser River in

    two locations, biophysical environmental components of particular interest in

    this cumulative effects assessment include estuarine intertidal marsh and

    mudflat habitats, as well as the river bottom and water column in the vicinity

    of proposed bridge piers. Although the focus of the analysis with respect to

    biophysical components is on habitat rather than individual species, the

    assessment also considers potential impacts to species at risk, as defined in

    the Federal Species at Risk Act (SARA) and/or identified in the provincial

    Red-and Blue-lists2maintained by the BC Conservation Data Centre, that are

    known to occur in the project area.

    Socio-community components of interest during impact assessment include

    social and cultural attributes, such as sites and resources of importance for

    First Nations traditional use, and any structure, site or object that is of

    historical, archaeological, palaeontological or architectural significance.

    Potential changes in ambient noise levels, air quality and electric and

    1A threshold is defined as the limit of tolerance of an ecosystem component to an effect

    that, if exceeded, results in an adverse response by that ecosystem component (afterHegmann et al. 1999).2See SECTION 7.3.1.1for an explanation of provincial red- and blue-list designations.

  • 5/27/2018 (20) Section 16 - Dec 2004

    5/42

    Environmental Assessment Certificate Application

    for the RichmondAirportVancouver Rapid Transit Project

    December 2004 16-4

    magnetic fields are of interest from both a biophysical and socio-community

    perspective.

    Biophysical and socio-community components identified and addressedduring planning and environmental assessment of the RAV Project (see

    SECTIONS 6to15) are as follows:

    Aquatic Environment

    North Arm and Middle Arm, Fraser River:

    Intertidal marsh habitat

    Intertidal mudflat habitat

    River bottom sediments

    Water column

    Water quality

    Terrestrial Environment

    Estuarine, riparian and upland plant communities, including those

    supporting plant species listed on Schedule 1 under SARA and/or

    provincially red- or blue-listed plant species that occur in the project area

    Wildlife habitat and wildlife, including wildlife species listed on Schedule 1

    under SARAor provincially red- or blue-listed wildlife species that occur in

    the project area

    Air Quality

    Local air quality

    Regional air quality

    Greenhouse gas emissions

    Noise Environment

    Ambient noise levels

    Electric and Magnetic Fields

    Ambient levels of EMF

    Archaeological Resources

    Existing and potential archaeological sites

  • 5/27/2018 (20) Section 16 - Dec 2004

    6/42

    Environmental Assessment Certificate Application

    for the RichmondAirportVancouver Rapid Transit Project

    16-5 December 2004

    Historical and Heritage Resources

    Cambie Heritage Boulevard

    First Nations Traditional Use Existing and historic traditional use sites and activities

    In this analysis, potential cumulative effects are assessed only for those

    environmental components that are likely to sustain residual impacts as a

    result of construction or operation of the RAV Project, and that also may

    sustain impacts due to other existing or imminent developments or activities

    in the project area.

    16.2.3 Potential Residual Effects

    Table 16.1 describes residual impacts that may occur during construction

    and/or operation of the RAV Project and that will be discussed further in the

    cumulative environmental effects analysis. These impacts, which relate to

    aquatic and terrestrial environment, air quality and noise levels, are predicted

    in association with the conceptual reference alignment and station locations

    which, in effect, constitute a worst case scenario. Such a scenario refers to

    a situation in which all potential environmental impacts actually occur. In

    reality, it is anticipated that changes and refinements made by the

    Concessionaire during the RAV Projects detailed planning and design-build

    phases will reduce the type and magnitude of the environmental impacts

    considered in this analysis. Therefore, in some cases, potential residual

    impacts described in Table 16.1may be eliminated.

    Note that, based on the results of the environmental assessments of the RAV

    Project, residual effects are not anticipated with respect to electric and

    magnetic field levels, archaeological resources, historical and heritage

    resources, or First Nations traditional use sites and activities. To ensure that

    the reasons for this determination are well understood, a brief explanation is

    presented with respect to each of these environmental components inSECTION 16.4.

    Health-related issues are discussed in previous sections of the EAC

    Application (i.e., contaminated sites (SECTION 10), air quality (SECTION 11),

    noise (SECTION 12) and EMF (SECTION 15)). Based on the assessments

  • 5/27/2018 (20) Section 16 - Dec 2004

    7/42

    Environmental Assessment Certificate Application

    for the RichmondAirportVancouver Rapid Transit Project

    December 2004 16-6

    presented in these sections, no long-term residual impacts to human health

    are anticipated as a result of the RAV Project, following implementation of

    appropriate mitigation measures. By providing an efficient and effective

    alternative to the use of private vehicles, the RAV Project is expected tocontribute to improved air quality and reduced noise levels in the RAV

    corridor. Despite the fact that residual impacts related to air quality and

    ambient noise levels are expected to be localized and short-term during

    construction, the discussion in SECTION 16.4 also addresses these

    biophysical and socio-community components.

  • 5/27/2018 (20) Section 16 - Dec 2004

    8/42

    Environmental Assessment Certificate Applica

    for the RichmondAirportVancouver Rapid Transit Proj

    16-7 December 2

    Table 16.1 Potential Residual Environmental Effects of the RAV Project

    EAC

    Application

    Section

    Environmental

    Component

    Description of Potential Residual Impacts

    During Design/Construction

    Extent/Duration of

    Residual Impact

    Description of Potential Residual Impacts

    During Operation

    Extent/Duration of Residual Impa

    Fraser River:

    Intertidal mudflat

    North Arm Crossing: Depending on its location

    relative to the shore, untreated wood support piles

    for a temporary work pad may disturb a small area

    of green coded mudflat along the eastern margin of

    the RAV alignment, riverward of the Kidd No. 1

    Substation on the north shore of the river. Similarly,

    a small area of the red coded intertidal mudflat on

    the south shore, which is approximately 5 to 15 mwide and comprises the lower level of a two-tier

    intertidal bench, may be disturbed due to placement

    of a temporary work pad during construction.

    Middle Arm Crossing: Densification treatment and

    rip rap installation associated with bank revetment

    may affect a small area of red coded intertidal

    mudflat on the western shoreline. Densification

    treatment and installation of footing and foundation

    for a pier on the eastern shoreline may temporarily

    or permanently alienate red coded intertidal mudflat

    area. Support piles for temporary work pads may

    disturb small areas of intertidal mudflat on either

    shore.

    North Arm Crossing: Small

    areas of disturbed mudflat

    would readily recover

    following removal of

    temporary work pad.

    Middle Arm Crossing: Small

    areas of disturbed mudflat

    would readily recover

    following removal of

    temporary work pad.

    As condition of Section 35(2)

    Authorization under the

    Fisheries Act, Concessionaire

    will be required to compensate

    for any loss of mudflat habitat

    that may occur during

    construction.

    None anticipated Not ApplicableFisher ies &

    Aquat ic

    Habitat

    (SECTION 6)

    Intertidal marsh

    North Arm Crossing: Depending on its locationrelative to the shore, untreated wood support piles

    for a temporary work pad may disturb a small area

    of green coded intertidal marsh along the eastern

    margin of the RAV alignment, riverward of the Kidd

    North Arm Crossing: Smallareas of disturbed marsh

    would readily recover

    following removal of

    temporary work pad.

    Dredging and filling activities, as well as presence ofbridge piers, may alter sedimentation regime and

    hydrology downstream of crossings resulting in gain

    or loss in extent (i.e., width, length) of Fraser River

    foreshore marshes.

    As condition of Section 35(2) Authorizaunder the Fisheries Act, Concession

    will be required to compensate for

    habitat loss.

  • 5/27/2018 (20) Section 16 - Dec 2004

    9/42

    Environmental Assessment Certificate Application

    for the RichmondAirportVancouver Rapid Transit Project

    December 2004 16-8

    EAC

    Application

    Section

    Environmental

    Component

    Description of Potential Residual Impacts

    During Design/Construction

    Extent/Duration of

    Residual Impact

    Description of Potential Residual Impacts

    During Operation

    Extent/Duration of Residual Impa

    No. 1 Substation on the north shore of the river.

    Similarly, a small area of the red coded marsh on

    the south shore, which is approximately 6 to 8 m

    wide and comprises the upper level of a two-tier

    intertidal bench, may be disturbed due to placement

    of a temporary work pad during construction.

    Middle Arm Crossing: Densification treatment and

    installation of rip rap with anticipated bank

    revetment may affect pockets of red coded intertidal

    marsh on western shoreline. Densificationtreatment and installation of footing and foundation

    for pier on eastern shoreline may temporarily or

    permanently alienate red coded intertidal marsh

    area. Support piles for temporary work pads may

    disturb a small area of intertidal marsh.

    Middle Arm Crossing: Small

    areas of disturbed marsh

    will readily cover followingremoval of temporary work

    pads.

    As condition of Section 35(2)

    Authorization under the

    Fisheries Act, Concessionaire

    will be required to compensate

    for any loss of mudflat habitat

    that may occur during

    construction.

    River bottom

    sediments

    North Arm Crossing: Installation of footings, fenders

    and associated rip rap armaments for 2 piers would

    permanently alienate portions of the sand/silt river

    bottom.

    Middle Arm Crossing: Densification treatment and

    installation of footings, fenders and associated rip

    rap armaments for 2 piers would permanently

    alienate a portion of the sand/silt river bottom.

    As condition of Section 35(2)

    Authorization under the

    Fisheries Act, Concessionaire

    will be required to compensate

    for any loss of mudflat habitat

    that may occur during

    construction.

    None anticipated.

    Water column North Arm Crossing: Subject to final design, 2

    bridge piers may occupy a portion of the water

    column in the North Arm.

    As condition of Section 35(2)

    Authorization under the

    Fisheries Act, Concessionaire

    North Arm Crossing: Presence of bridge piers may

    alter hydraulic conditions of river channels (i.e.,