2015 PlantPAx System Estimator UpdateNew Virtualization sizing calculationsEnhanced assignment of I/O to Intelligent Motor ControlsNew ability to add network switch to controller and I/O locationsFactoryTalk Historian and FactoryTalk AssetCentre now default on new systemsUpdated controller sizing footprints

Target Release: End of MayCopyright 2015 Rockwell Automation, Inc. All Rights Reserved.PUBLIC12015 PSE UpdateNew Virtualization sizing calculations

PSE calculates minimum virtual requirements for virtualization of the PlantPAx System servers and workstationsSizing shown in System Properties and reportsUser selects whether workstations are to be virtualized (or just servers)Virtual sizing requirements tunable from System PreferencesOVERVIEWBENEFITS123Simplifies sizing of virtualized systems aligning with the latest recommendations in the PlantPAx Selection Guide and Reference Manual. Copyright 2015 Rockwell Automation, Inc. All Rights Reserved.PUBLIC

2015 PSE UpdateEnhanced assignment of I/O to Intelligent Motor ControlsSimplified workflow to map I/O configuration to Intelligent Motor Control Devices:Enter in the number of IMC devices by type and see the I/O count that is decremented from totalChange specific IMC devices by locationHW Defaults allow you to exclude IMC from BOM. System Preferences allows you to tune I/O mapping by device.OVERVIEWBENEFITS12Easily generate a single BOM inclusive of PlantPAx System and IMC devicesCopyright 2015 Rockwell Automation, Inc. All Rights Reserved.PUBLIC

2015 PSE UpdateNew ability to add network switches to controller and I/O locationsMore flexibility to layout network switches:Added checkbox to include Stratix 5700 on Supervisory network aligned with controllerAdded checkbox to include Stratix 5700 on I/O network for an I/O locationOVERVIEWBENEFITS1Easily attach network switches to your control and I/O panels and layout your networks in IAB

2Copyright 2015 Rockwell Automation, Inc. All Rights Reserved.PUBLIC

2015 PSE UpdateHistorian and AssetCentre now added by default for new systemsNew systems include AppServ-Info element for Historian by defaultNew systems include AppServ-AssetMgt with Disaster Recovery by defaultAdded information messages when the licensed tag count of FT Historian or licensed assets of FactoryTalk AssetCentre dont match up with PSE calculated valuesOVERVIEWBENEFITS1Default system is closer to typical system configuration so that there is less steps to configure. 332Copyright 2015 Rockwell Automation, Inc. All Rights Reserved.PUBLIC

2015 PSE UpdateUpdated controller sizing footprintsUpdated location preferences with adjusted control strategy footprintsAdded ability to account for I/O that will not be assigned to a Process Object for sizingAdded details of what control strategies were used to develop each footprint in the Help fileOVERVIEWBENEFITS1More accuracy and clarity in the controller sizing calculations. 2

3Copyright 2015 Rockwell Automation, Inc. All Rights Reserved.PUBLIC2015 PSE UpdateAdditional InfoCopyright 2015 Rockwell Automation, Inc. All Rights Reserved.PUBLIC

PUBLIC - 5058-CO900H Copyright 2015 Rockwell Automation, Inc. All Rights Reserved.PUBLIC

2015 PSE UpdateAdditional InfoVirtualization sizing footprints can be adjusted in system preferences workbookMCC Sizing I/O assignments can be adjusted in system preferences workbookOVERVIEW12Copyright 2015 Rockwell Automation, Inc. All Rights Reserved.PUBLIC

2015 PSE UpdateAdditional InfoWhen using 1769-L24ER-QBFC1B, new option in assign I/O to hardware to use embedded I/O on controllerOVERVIEW1Copyright 2015 Rockwell Automation, Inc. All Rights Reserved.PUBLIC

2015 PSE UpdateAdditional InfoNew option in hardware defaults to exclude intelligent motor control devices from BOM if IMC devices are existing or part of MCCOVERVIEW1Copyright 2015 Rockwell Automation, Inc. All Rights Reserved.PUBLIC