70
Manildra Solar Farm Environmental Assessment 4 November 2010 36 2.5 PROPOSAL PHASES 2.5.1 Construction and commissioning Before project approval has been received, it is not possible to define the timeline for the construction of the project. It would be expected that from the time project approval is received, it would take a number of months to finalise the additional agreements required before construction could commence. This includes finalising the grid connection agreement and ordering long leadtime items such as transformers. An indicative proposed timeline is outlined in Table 27. Table 27: Indicative project timeline Stage Approximate timeframe Duration Construction April 2012 8 months approx Commissioning May 2012 Operation May 2012 30 to 50 years Decommissioning 2042 TBD The construction phase of the solar farm would then occur over an 8 month period and would include such activities as: Transportation of people, materials and equipment to each precinct Civil works for access track construction and trenching for cables Installation of PV array Construction of onsite power reticulation lines and cables Augmentation of substation Construction of temporary offices and facilities Temporary storage Restoration and revegetation of disturbed onsite areas on completion of construction works This proposal may be constructed in a phased or staged approach, with separate groups of infrastructure considered discrete work packages and commenced at different times. In general, construction would commence with the upgrading of roads and all other site civil works, including fencing of the site, preparation of hardstand areas and laying of cables. This would be followed by construction of the site facilities compound, installation of the PV array mounting structures and panels, inverters and kiosk transformers. The PV array would be constructed using vibrated piling to drive the pylons into the ground or installed on precast concrete footings. The module mounting structure would be attached to the upright pylons, and the panels fixed to the mounting structure using the predrilled mounting holes in the panel frame. The proposed concrete footings are shown in Figure 212.

2.5.1 Construction and commissioning

  • Upload
    others

  • View
    18

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     36 

2.5 PROPOSAL PHASES 

2.5.1 Construction and commissioning 

Before project approval has been received, it is not possible to define the timeline for the construction of the project.   It would be expected that from the time project approval  is received,  it would take a number  of  months  to  finalise  the  additional  agreements  required  before  construction  could commence.  This includes finalising the grid connection agreement and ordering long lead‐time items such as transformers. An indicative proposed timeline is outlined in Table 2‐7. 

Table 2‐7: Indicative project timeline 

Stage  Approximate timeframe  Duration 

Construction  April 2012  8 months approx 

Commissioning  May 2012  ‐ 

Operation  May 2012  30 to 50 years 

Decommissioning  2042  TBD 

 

The construction phase of the solar farm would then occur over an 8 month period and would include such activities as: 

• Transportation of people, materials and equipment to each precinct 

• Civil works for access track construction and trenching for cables 

• Installation of PV array 

• Construction of onsite power reticulation lines and cables 

• Augmentation of substation 

• Construction of temporary offices and facilities 

• Temporary storage 

• Restoration and revegetation of disturbed onsite areas on completion of construction works 

This  proposal  may  be  constructed  in  a  phased  or  staged  approach,  with  separate  groups  of infrastructure considered discrete work packages and commenced at different times. 

In general, construction would commence with the upgrading of roads and all other site civil works, including  fencing  of  the  site,  preparation  of  hardstand  areas  and  laying  of  cables.    This would  be followed  by  construction  of  the  site  facilities  compound,  installation  of  the  PV  array  mounting structures and panels, inverters and kiosk transformers.  

The PV array would be constructed using vibrated piling to drive the pylons into the ground or installed on  precast  concrete  footings.  The module mounting  structure  would  be  attached  to  the  upright pylons,  and  the panels  fixed  to  the mounting  structure using  the pre‐drilled mounting holes  in  the panel frame.  The proposed concrete footings are shown in Figure 2‐12. 

Page 2: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     37 

 

Figure 2‐12: Module mounting structure with concrete footing 

Concrete  trucks  would  be  used  to  supply  concrete  required  for  inverter,  kiosk  transformer  and substation transformer bases and to construct the slab for the operations and maintenance building. Concrete batching plants would not be used during  the project. The concrete  footings  for PV arrays would be pre‐cast. 

The necessary substation augmentation and grid connection works would be carried out in parallel. 

The  commissioning  phase  would  include  pre‐commissioning  checks  on  all  high‐voltage  equipment prior to connection to the TransGrid transmission system.  Once the solar farm electrical connections have been commissioned and energised, each array block  is then separately connected and put  into service. 

On completion of construction, disturbed areas would be revegetated and all waste materials removed and disposed of appropriately.  

2.5.2 Construction hours 

Construction  activities  associated  with  the  project  that  would  generate  noise  audible  at  nearby residences would be undertaken during the hours of: 

Monday – Friday  7am – 6pm 

Saturday  8am – 1pm 

Sunday and public holidays  Not proposed 

These  working  hours  have  been  proposed  to  allow  reasonable  efficiencies  of  effort  to  achieve maximum  productivity  to  minimise  the  overall  construction  duration.  However,  some  work  (e.g. delivery of substation transformer) may occur overnight due to logistical reasons.   

Page 3: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     38 

2.5.3 Operation 

The solar farm would operate for a period of 30 to 50 years. A site manager would be employed and security staff would be present at night, and possibly 24 hours a day. Other security provisions would include security  lighting and potentially cameras and motion sensors as well as  fencing and warning signs to prevent unauthorised access. 

While  the  solar  farm operates with minimum personnel,  the PV  array  and other  equipment would require  regular maintenance.  It  is possible  that some equipment may  require unscheduled  repair or replacement. 

After the expected 25 to 30 year lifetime of the PV panels, the solar panels and other components of the solar  farm may be refurbished or replaced to  improve the performance or decommissioned and removed from the site. 

Routine maintenance 

To ensure the solar  farm operates  in a safe and reliable manner,  it would require regular  inspection and maintenance  on  an  ‘as  needs’  basis.    This would  generally  be  carried  out  using  standard  light vehicles and maintenance crews would attend the site as required. 

A supervisory control and data acquisition (SCADA) system would monitor the solar farm and identify any electrical faults, which could then be addressed by isolating and shutting down the relevant array block.  

Weed  control  would  be  undertaken  as  required  using  a  spray  unit  mounted  on  a  quad  bike. Groundcover  vegetation  around  the  panel  rows  would  be  either  slashed  or  grazed  by  sheep  to maintain a safe height below the panels. 

While  it  is not envisaged that panels would need to be regularly washed, event‐based panel washing may be undertaken after  incidents  such as dust  storms. Washing would be undertaken using water only without detergent. Water would be sourced from Cabonne Council and most likely applied using a portable pressure washer or water  truck. Up  to 100,000  litres of water may be  required per month during operation for panel washing. 

Major repairs 

It  is possible  that major unexpected equipment  failures could  take place during  the  life of  the solar farm.  While the PV array and electricity connections are designed for a 20 ‐ 30 year life, failures can occur  due  to  a  number  of  factors  including  lightning  strike  (offsite  on  the  transmission  line)  and damage  to  key  components  (such  as  PV panels  and  transformers).  Failure  can  also occur on  other equipment including that located in substations. 

Most  repairs  can be  carried out  in a  similar manner  to  routine maintenance, although  transport of large or heavy infrastructure such as replacement inverters or kiosk transformers would require heavy vehicles. 

 

Page 4: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     39 

Site monitoring program 

A post‐construction monitoring program would be established  to determine any additional  impacts resulting  from  the  operation  of  the wind  farm.    The Operational  Environmental Management  Plan would contain specific monitoring programs required and would assess key issues such as biodiversity and visitation numbers.  

The  operation  of  the  solar  farm would  require minimal  personnel  onsite  (approximately  one  staff member).  Security  is  likely  to  show  a  presence  onsite  and  security  lighting  may  be  required. Maintenance crews would attend the site as required. Water may be required to periodically wash the solar panels. A SCADA system would be used to monitors the solar farm, enabling the rapid shutdown of the affected part of the system if a problem is detected. 

2.5.4 Decommissioning  

The proposal includes a commitment to decommissioning at the end of the project life. The lifetime of the project is expected to be between 30 and 50 years. 

All above ground infrastructure would be removed from the site and recycled or otherwise disposed of at approved facilities. Footings and pylons and underground cabling may be  left  in place. All areas of soil disturbed during decommissioning,  including  tracks, would be  rehabilitated  in consultation with the land owner, using appropriate species. Access tracks that the land owner wishes to retain may be left in place. 

Decommissioning would involve similar road access arrangements to construction, and would require access for transport vehicles to dismantle and remove infrastructure.  The decommissioning period is likely  to  be  significantly  shorter  and with  significantly  less  truck movements  than  the  construction phase. 

   

Page 5: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     40 

2.6 JUSTIFICATION 

This section provides a strategic overview of the need for the project in regards to the requirement for additional electricity supply in NSW and the need for more renewable energy projects. It also outlines Government policy objectives and targets for renewable energy and greenhouse gas reductions. 

The Manildra Solar Farm would: 

• Help secure reliable energy in a market where demand will soon exceed supply  

• Assist in the reduction of Green House Gas (GHG) emissions contributing to climate change 

• Help meet Federal and State policy objectives. 

2.6.1 Energy context 

The National Electricity Market 

The  National  Electricity  Market  (NEM)  is  an  all‐inclusive  market  which  facilitates  the  supply  of electricity  to  retailers  and  consumers  in  Queensland,  New  South  Wales,  the  Australian  Capital Territory,  Victoria,  South  Australia  and  Tasmania  (AEMO  2010a).  The  NEM  is  a  public‐private partnership  (PPP) where  energy  generated  by  various  enterprises  is  aggregated  into  a  pool made available  to  consumers.  The  NEM  currently  supplies  over  eight million  end‐use  consumers  which commands more than $10 billion of electricity to be traded annually (AEMO 2010a).  

Electricity demand in NSW 

In NSW, energy demand is growing. TransGrid’s 2010 Annual Planning Report indicates that growth in electricity demand will soon exceed supply during peak times. AEMO (2010b) indicates that New South Wales  has  a  2010/2011  summer  aggregate  scheduled  and  semi‐scheduled  generation  capacity  of 15,950  MW,  however  forecasts  show  demand  will  surpass  this  amount  in  the  next  5  years. Consequently,  the State will need  to build additional electricity generators  to meet  this demand, as well as to evade power outages and blackouts. 

The  AEMO  Electricity  Statement  of Opportunities  2010  report  analyses  the  supply  and  demand  of electricity for each region of the National Electricity Market. The NSW average annual growth rate of energy consumption and maximum demand (based on a medium economic growth forecast) over the next 10 years is 2.6%. The summer supply‐demand outlook graph (Figure 2‐13) shows that additional capacity will be required to meet this forecast demand. 

As depicted in the graph there is currently enough installed or planned energy infrastructure to meet the reliable capacity up until the summer of 2016/2017, from which a minimum additional capacity of 27 MW  will  be  required  (again  based  on  a  medium  economic  growth  forecast).  The  amount  of additional capacity  required  increases  in subsequent years. Under  low and high growth scenarios  in NSW,  AEMO  (2010c)  identifies  the  points  at which  installed  capacity  falls  below  that  required  for reliable supply, or “Low Reserve Capacity” (LRC point), and their applicable reserve deficits as follows: 

• Low Growth – LRC point is reached in 2017/2018 with a reserve deficit of 91 MW. 

• High Growth – LRC point in reached in 2016/2017 with a reserve deficit of 285 MW. 

Page 6: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     41 

 

Figure 2‐13: NSW Summer Outlook under medium economic growth forecast (Source: AEMO 2010c) 

Role of renewable energy 

Climate change 

There  is  scientific  evidence  that  the  Earth’s  climate  is  changing.  Observations  have  shown  global increases in air and ocean temperatures, the widespread melting of snow and ice and rising sea levels (IPCC 2008). It has further been observed that many of the world’s natural systems are already being affected by  the  change of  regional  climates,  in particular  temperature  increases  (IPCC 2008). Other indicators  include  altered  rainfall patterns  and more  frequent or  intense weather patterns  such  as heatwaves, drought, and storms (DCCEE 2010a). In Australia, this change in the climate is anticipated to have an impact on water supply and quality, ecosystems and conservation, agriculture and forestry, fisheries, settlements and industry and human health. Australian trade and commodity prices may also be impacted on by the global impacts of climate change (DCCEE 2010a). 

The drivers  for  climate  change have been  identified  as being  from both natural and anthropogenic forces, however  a main  contributor  is  the  release of  green house  gases  into  the  atmosphere  (IPCC 2008). 

GHG emissions world‐wide 

The  International Panel  for climate change  (IPCC) has acknowledged that  it  is very  likely that human GHG  emissions  have  directly  influenced  global  temperatures  to  increase,  as well  as  lead  to  other climate impacts. As GHG emissions stay in the atmosphere for decades, a predicted warming of around 0.2°C per decade is already expected regardless of future emission levels (IPCC 2008). However, if GHG emissions continue to be emitted at their current rate then further and more extreme changes to the global climate system will be experienced (IPCC 2008). Therefore, a reduction in GHG emissions is able 

Page 7: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     42 

to reduce the rate and magnitude of climate change. The IPCC recognises that GHG mitigation efforts over the next 20‐30 years will be crucial to stabilising the amount of change (IPCC 2008).  

The GHG contributing most significantly to climate change is Carbon dioxide (CO2). Between 1970 and 2004 the amount of CO2 being emitted from human‐based activities increased by 80% and the current level of CO2  in the atmosphere  is now higher than ever measured (IPCC, 2008). This  large  increase  is predominantly due  to  the burning of  fossil  fuels, such as coal,  for energy generation. Therefore  the IPCC  (2008)  recommends  a  vital  step  to  reducing CO2  emissions  is by employing  renewable energy technologies. 

GHG emissions in Australia and NSW 

Department of Climate Change and Energy Efficiency  reports  (2010b) show  that emissions  from  the stationary  energy  sector,  which  include  those  from  electricity  generation  and  the manufacturing, construction and commercial sectors,  is the  largest and fastest growing area  in terms of greenhouse gas emissions in Australia. Between 1990 and 2008, emissions from electricity generation increased by 74.8 Mt CO2‐e, an average of 3.2% per year  (DCCEE 2010b).  In  the December 2009 quarter, 202 Mt CO2‐e,  or  almost  38%  of  total  greenhouse  gas  emissions, were  produced  during  the  generation  of electricity (DCCEE 2010b). 

In 2008, 38% of  the  total GHG emissions  in NSW were  from  the generation of electricity and heat. Between 1990 and 2006 emissions from electricity and heat generation grew by 43% to a total amount of 63.2 MtCO2‐e (DCCEE 2010c). This made up 11% of the total GHG emissions in Australia. 

The total number of GHG emissions avoided as a result of the proposal would be 0.075MtCO2‐e per annum. This  represents 0.12% of  the 2006 emissions. Cumulative  reductions  in GHG emissions  from the construction of other solar farms  in NSW  including Nyngan, Moree and Bungendore would result in avoiding a total of 0.62% of the 2006 emissions. 

The need for renewable energy technology 

As  discussed  above,  the  Intergovernmental  Panel  on  Climate  Change  (IPCC  2008)  recommends employing renewable energy as a vital step to reducing CO2 emissions. Renewable energy technologies produce zero (e.g. solar PV) or  low GHG emissions during generation, and can displace the emissions that would otherwise be produced by fossil fuel based electricity generation. Even taking into account the  ‘lifecycle  emissions’  of  renewable  energy  technologies  (that  is,  the  emissions  produced  during construction,  production,  generation  and  decommissioning),  coal  produces  at  least  10  times  the lifecycle emissions of renewables (Wright and Hearps 2010). For example, it is estimated that Solar PV produces  in  the  order  of  19‐59 gCO2e/kWh  compared  to  rates  for  Coal, with  carbon  capture  and storage, of 255‐441 gCO2e/kWh (Wright and Hearps 2010).  

An  indicator  used  to  determine  the  amount  of  greenhouse  gases  emitted  per  kWh  of  electricity supplied  to  the NSW grid  in a particular year  is  the NSW Annual Pool Value  (GGAS 2008). Table 2‐8 shows that the Annual Pool Value is calculated by dividing the total energy supplied to the NSW grid by the total NSW emissions in that year.  

To account for one‐off highs or lows that may be experienced in a particular year the Pool Coefficient is determined. This value  is calculated by averaging the five Annual Pool Values from previous years, with a lag of two years (GGAS 2010). So the NSW Pool Coefficient for 2010 is the average of the Annual Pool Values from 2004 to 2008.  

 

Page 8: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     43 

Table 2‐8: NSW Annual Pool Values and Pool Coefficients (2003‐2010) (Source: GGAS 2010) 

Year  Total NSW emissions  (tco2‐e) 

Total NSW sent out generation (MWH) 

Annual pool value tco2‐ e/MWH 

Pool coefficient  tco2‐ e/MWH 

2003  63,431,793  66,800,866  0.950  0.897 

2004  65,979,036  67,276,401  0.981  0.906 

2005  65,896,606  69,341,455  0.950  0.913 

2006  70,010,515  72,222,646  0.969  0.929 

2007  69,810,669  71,015,242  0.983  0.941 

2008  71,394,801  72,646,917  0.983  0.954 

2009  TBA  TBA  TBA  0.967 

2010  TBA  TBA  TBA  0.973 

 

 

 

Figure 2‐14: Historical NSW Pool Value and Pool Coefficient (1999‐2009) (Source: GGAS 2010) 

The  2010  Pool  Coefficient  value  indicates  that  presently  for  every  megawatt‐hour  of  electricity supplied  to  the NSW electricity pool, 973 kg of greenhouse gases are emitted. At  this point  in time, approximately 90% of electricity in NSW is generated by fossil fuel power stations, primarily coal fired. Therefore  it can be assumed  that  for every megawatt‐hour of electricity generated at a coal power station 973kg of green house gases are emitted. 

The Annual Pool Value is calculated using the total sent out electricity from all technologies, including that  from  renewable  energy.  It  is  expected  that  the  more  electricity  supplied  to  the  pool  from renewable sources, reducing the amount required from coal power stations, the lower the Annual Pool Value and the lower the Pool Coefficient. 

Page 9: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     44 

Employing  low emission,  renewable energy  technologies  to produce electricity  instead of  fossil  fuel based  technology will  reduce GHG emissions and  lead  to a  reduction  in  the  rate and magnitude of climate change. 

Renewable energy targets 

The Australian Government’s Mandatory Renewable Energy Target (MRET) scheme was established in 2001  to expand  the  renewable energy market and  increase  the amount being utilised  in Australia's electricity supply. The MRET targeted the generation of an additional 9,500 GWh of extra renewable electricity per year by 2010 (PoA, 2010).  

In 2007, the NSW State Government introduced legislation called the Renewable Energy (NSW) Bill as part of  their Greenhouse Policy  to encourage additional generation of  renewable energy. The NSW Renewable Energy Target (NRET) requires 10% of electricity to be sourced from renewable energy by 2010 and 15% by 2020 (DEUS 2006). The NRET is consistent with the Commonwealth MRET.  

The Renewable Energy Target (RET) scheme is an expansion of the MRET and has been established to encourage  additional  generation  of  electricity  from  renewable  energy  sources  to  meet  the Government’s commitment to achieving a 20% share of renewables in Australia’s electricity supply in 2020 (ORER 2010). The RET legislation: 

• places a legal liability on wholesale purchasers of electricity to proportionally contribute to an additional 45,000 gigawatt hours (GWh) of renewable energy per year by 2020. 

• sets the framework for both the supply and demand of renewable energy certificates (RECs) via a REC market. 

This means a total of 45,000 GWh of electricity will need to be sourced from renewables, requiring an additional 8,000 ‐ 10,000 MW of new renewable energy generators to be built across Australia in the next  decade.  The  RET  also  assures  that  national  greenhouse  gas  emissions  are  reduced  to meet Federal Government targets.  

Energy reliability 

In the State Plan, the Government has identified energy reliability as a priority for supporting business and  jobs while  recognising providing  a  secure  and efficient energy  supply will be done  in  a  carbon constrained  future  (NSW  Government  2010).  One  of  the  Government’s  priorities  is  therefore  to develop a clean energy future. To ensure this, along with the  issue of controlling GHG emissions, the Government  aims  to  increase  the  State’s  energy  efficiency while  at  the  same  time  increasing  the proportion  of  the  State’s  consumed  electricity  is  generated  from  renewable  sources  (NSW Government 2010). Stable and reliable renewable energy projects  in NSW are required to help meet these aims and a new Clean Energy Strategy will  include working to secure a  large solar power plant for NSW under the Commonwealth’s Solar Flagships program (NSW Government 2010). 

Photovoltaic solar farms are able to provide a regular and secure source of renewable energy. While solar radiation is intermittent because of daily and seasonal variations, the correlation between solar radiation and daytime peak electricity demand means that solar energy has the potential to provide electricity during peak demand times (GA and ABARE 2010). Solar PV farms are therefore able to form an important contribution to meeting future electricity demand. 

Page 10: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     45 

2.6.2 Proposal benefits 

The Manildra Solar Farm would be clean, renewable and sustainable and would emit zero greenhouse gases during operation (Infigen Energy 2010b). Based on a proposed operating capacity of 50MW, the Manildra PV Solar Farm would generate enough renewable energy to power up to 10,000 homes and would  be  the  equivalent  of  removing  approximately  15,000  cars  from  Australian  roads  each  year (Infigen Energy 2010b). The project would avoid carbon emissions of 75,000 t/CO2 p/a. 

Building a solar farm of this scale near Manildra would be a major boost to the Australian solar energy industry.  It would provide  local employment opportunities both  throughout  the  construction phase and once the site becomes operational, and would also help to develop local and regional capabilities in solar photovoltaic plant construction.  

The  solar  farm would  contribute  to  Australia’s  Renewable  Energy  Target  (RET)  of  sourcing  20%  of electricity from renewable sources by 2020. 

The Manildra Solar Farm would: 

1. Provide reliable energy in a market where demand would soon exceed supply. 

2. Reduce greenhouse gas emissions that contribute to climate change. 

3. Assist  in meeting  Federal and  State policy objectives  to enhance  the  contribution made by renewable energy sources to meeting demand. 

4. Contribute to the development of the utility scale renewable energy industry in NSW. 

5. Assist in the experience and learning required in local industry to further develop utility scale solar in Australia. 

6. Provide a local and regional economic stimulus through jobs and training. 

Page 11: 2.5.1 Construction and commissioning

    Manild

 

4 November 2010     46 

3 LEGISLATIVE CONTEXT 

3.1 NEW SOUTH WALES 

3.1.1 Legislation 

Environmental Planning and Assessment Act 1979 

The  Environmental  Planning  and  Assessment  Act  1979  (EP&A  Act)  and  its  supporting  Regulation,  the Environmental  Planning  and  Assessment  Regulation  2000  (EP&A  Regulation),  provide  the  framework  for development assessment and approval within NSW. Assessment provisions are provided  in Part 3A, Part 4 and Part 5 the EP&A Act. 

Major and critical infrastructure 

In accordance with Part 3A of the EP&A Act the proposed solar farm development is considered to be Major Infrastructure.  Clause  75B  (1)  of  the  EP&A  Act,  states  that:  [Part  3A]  applies  to  the  carrying  out  of development that is declared under this section to be a project to which this Part applies: 

(a) by a State environmental planning policy, or 

(b) by order of the Minister published in the Gazette (including by an order that amends such a policy). 

Part  3A  projects  declared  in  the  State  Environmental  Planning  Policy  (Major  Development)  2005  (Major Development SEPP) include development for the purposes of solar electricity with a capital investment value greater than $30 million. The proposed Manildra solar farm would have a capital investment in excess of $30 million and is therefore considered to be Major Infrastructure under Part 3A of the EP&A Act. 

The proposal would also be considered  ‘critical  infrastructure’  in accordance with Clause 75C of  the EP&A Act.  In  2009  the  Minister  declared  renewable  energy  projects  with  a  peak  generating  capacity  of  30 megawatts  (MW) or more  to be  ‘critical  infrastructure’, providing  increased  certainty  for  industry and  the community. The declaration was published  in  the NSW Government gazette on 27 November 2009, which identified  such  development  as  essential  to  the  State  for  economic  reasons,  social  and  environmental reasons. 

Part 3A approval process 

The proposal is a Major Infrastructure which would be assessed under Part 3A of the EP&A Act. The project has a capital investment of more than $30 million and was confirmed to be a project to which Part 3A of the EP&A Act applies by the Director‐General of the Department of Planning on 5 July 2010, refer to Appendix A. 

Part 3A integrates the assessment and approval regime for all Major Infrastructure that require the approval of the Minister for Planning, previously dealt with by Parts 4 and 5 of the Act. Projects approved under Part 3A of the EP&A Act do not require authorisations under the: 

• Coastal Protection Act 1979 (Part 3 concurrence)  

• Fisheries Management Act 1994 (Sections 201, 205 or 219, stop work orders) 

• Heritage Act 1977 (Part 4 or Section 139, orders under Division 8 of Part 6) 

• National Parks and Wildlife Act 1974 (Section 87, consent under Section 90,  interim protection and stop work orders) 

Page 12: 2.5.1 Construction and commissioning

    Manild

 

4 November 2010     47 

• Native Vegetation Act 2003 (Section 12) 

• Rivers and Foreshores Improvement Act 1948 (Part 3A) 

• Rural Fires Act 1997 (Section 100B) 

• Water Management Act 2000 (Sections 89, 90, 91) 

• Threatened Species Conservation Act 1995 (interim protection and stop work orders) 

• Protection of the Environment Operations Act 1997 (environment protection notices) 

• Local Government Act 1993 (orders under Section 124) 

Director ‐General’s Requirements 

Under Clause 111 (1) of the EP&A Act, Determining Authorities are to consider ‘to the fullest extent possible all matters affecting or  likely  to affect  the environment by  reason of  that activity’. The Director‐General’s Requirements  (DGRs)  that outline  the  form and content of  the Environmental Assessment are attached  to this document (Appendix B). Table 3‐1 summarises the requirements and where they are addressed  in this report. The DGRs were issued by the DoP on 1st September 2010. 

Table  3‐1:  Director  General’s  Requirements  and  where  each  item  is  addressed  in  this  Environmental Assessment.  

Director‐General Requirements  Chapter addressed 

General Requirements   

• Executive summary  Executive Summary 

• Detailed project description  including  site plan, construction, operation and  decommissioning  details,  project  component  details,  timelines, supporting maps and resourcing requirements 

• Relevant  statutory provisions  including  consistency of  the project with the objectives of the EP&A Act  

• Assessment  of  key  issues  (as  outlined  below)  during  construction, operation and decommissioning 

6  

• Draft Statement of Commitments   8.1 

• Conclusion justifying the project  9 

• Certification by the authors of the EA  11 

Key Assessment Requirements   

• Strategic justification  2.6 

• Visual impacts  6.2 

Page 13: 2.5.1 Construction and commissioning

    Manild

 

4 November 2010     48 

Director‐General Requirements  Chapter addressed 

• Noise impacts  6.4 

• Flora and fauna  6.1 

• Indigenous heritage  6.3 

• Traffic and transport  7.1 

• Hazards/risks  7.9 and 7.10 

• Water supply, water quality, waterways and flooding  7.4 

• General environmental risk analysis  5 

Consultation requirements   

• Consultation  program  must  be  undertaken  to  include  stakeholder involvement, outline details of consultation undertaken and issues raised during consultation and how these have been addressed. 

 

Protection of the Environment Operations Act 1997 

The Protection of  the Environment Operations Act 1997  (POEO Act)  is administered by  the Department of Environment, Climate Change and Water (DECCW). There  is a broad allocation of responsibilities under the POEO Act between the EPA,  local councils and other public authorities. Projects approved under Part 3A of the EP&A Act do not generally require authorisations under this Act. Matters relevant to this Act have been taken into consideration in the preparation of this EA. 

Until  recently, general electricity works with  the  capacity  to generate more  than 30 megawatts of power required a licence under this Act. Recent amendments to this Act describe “general electricity works” as: 

 the generation of electricity by means of electricity plant  that, wherever  situated,  is based on, or uses, any energy source other than wind power or solar power.  

Therefore, the proposed development of the Manildra Solar Farm does not require a licence under the POEO Act. 

Crown Lands Act 1989 

The proposal site passes through a crown road as defined by the Crown Lands Act 1989. The road is located in the north eastern corner of the proposal site as indicated in Figure 3‐1. There is also adjacent Crown Land to the  southwest of  the  site. This  land would not be used as an access point  for  the  site during any project phase. The proponent would need to apply for a licence to access the crown road reserve for the purpose of laying cables and/or intersecting tracks. Alternatively, the proponent may sponsor a landowner’s application to close and purchase the crown road in accordance with Division 6 of the Crown Lands Act 1989 or, redesign the layout to avoid the road, as advised by the Land and Property Management Authority (LPMA).  

Page 14: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     49 

 

Figure 3‐1: Crown Land within and adjacent to the proposal site which includes a crown road in the north‐eastern corner. 

Page 15: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     50 

State Environmental Planning Policy No. 44 – Koala Habitat Protection 

NSW  State  Environmental  Planning  Policy  44  –  Koala  Habitat  Protection  aims  to  identify  areas  of potential and core Koala habitat. These are described as follows: 

• Potential Koala Habitat: areas of native vegetation where the trees listed in Schedule 2 of SEPP 44 constitute  at  least  15%  of  the  total  number  of  trees  in  the  upper  or  lower  strata  of  the  tree component; and 

• Core Koala Habitat: an area of land with a resident population of Koalas, evidenced by attributes such as breeding females, and recent and historical records of a population. 

Using these definitions the site would be considered potential Koala habitat as no resident population is present and White Box is the dominant tree species (listed in Schedule 2 of SEPP 44) and constitutes >15% of the total number of trees on site.  

As the proposal site is considered potential Koala habitat and that Koala records exist in the forested areas within the district, an Assessment of Significance was carried out  for Koalas and  is  included  in Appendix E. No significant impact is anticipated. 

3.1.2 Polices 

Ecologically Sustainable Development (ESD) 

Ecologically sustainable development (ESD)  involves the effective  integration of social, economic and environmental considerations in decision‐making processes. In 1992, the Commonwealth and all state and territory governments endorsed the National Strategy  for Ecologically Sustainable Development. In NSW, the concept has been incorporated in legislation such as the EP&A Act and Regulation. 

For the purposes of the EP&A Act and other NSW legislation, the Intergovernmental Agreement on the Environment  (1992)  and  the  Protection  of  the  Environment  Administration  Act  1991  outline  the following principles which can be used to achieve ESD. 

(a)  The precautionary principle: that if there are threats of serious or irreversible environmental damage,  lack  of  full  scientific  certainty  should  not  be  used  as  a  reason  for  postponing measures to prevent environmental degradation.  

In  the  application  of  the  precautionary  principle,  public  and  private  decisions  should  be guided by:  

(i)  Careful evaluation to avoid, wherever practicable, serious or irreversible damage to the environment. 

(ii)  An assessment of the risk‐weighted consequences of various options. 

(b) Inter‐generational  equity:  that  the  present  generation  should  ensure  that  the  health, diversity and productivity of the environment are maintained or enhanced for the benefit of future generations. 

(c) Conservation of biological diversity and ecological  integrity:  that  conservation of biological diversity and ecological integrity should be a fundamental consideration. 

Page 16: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     51 

(d)  Improved valuation, pricing and incentive mechanisms: that environmental factors should be included in the valuation of assets and services, such as:  

(i)  Polluter pays: that  is, those who generate pollution and waste should bear the cost of containment, avoidance or abatement. 

(ii)  The users of goods and services should pay prices based on the full life cycle of costs of providing goods and services, including the use of natural resources and assets and the ultimate disposal of any waste. 

(iii)  Environmental  goals,  having  been  established,  should  be  pursued  in  the most  cost effective way, by establishing incentive structures, including market mechanisms, which enable those best placed to maximise benefits or minimise costs to develop their own solutions and responses to environmental problems. 

The precautionary principle has been adopted in the assessment of impact; all potential impacts have been considered and mitigated where a risk is present. Where uncertainty exists, measures have been suggested to address the uncertainty.  

The majority of potential impacts of the proposal are likely to be localised and would not diminish the options  regarding  land  and  resource  uses  and  nature  conservation  available  to  future  generations. Parameters such as the site’s soil, hydrology and native vegetation have been valued in terms of their broader contribution to the catchment and catchment processes.  

The impacts of the proposal on biodiversity, including EPBC listed species, have been assessed in detail in the attached Biodiversity Assessments (summarised in Section 6.1).  

The  aims,  structure  and  content  of  this  EA  have  incorporated  these  ESD  principles.  The  Draft Statement  of  Commitments  in  Section  8.1  provides  an  auditable  environmental  management commitment to these parameters. Based on the social and environmental benefits accruing from the proposal at a local and broader level, and the assessed impacts on the environment and their ability to be managed,  it  is  considered  that  the  development  would  be  ecologically  sustainable  within  the context of the above ESD definitions. 

Lachlan Catchment Action Plan 2006 

This plan was produced by the Lachlan Catchment Management Authority (2006) to provide strategic direction for natural resource management activities in the catchment over 10 years. The action plan includes  Mandagery  and  Manildra  Creeks  which  form  part  of  the  Lachlan  Catchment.  The  plan identifies  four  key  themes:  biodiversity  and  native  vegetation, water  and  aquatic  ecosystems,  land management and people and  community.  It  sets out management  targets and measures ecological improvements,  the effectiveness of  funding disbursements and partnerships and  identifies areas  for further work and improvement. 

The proposal would not exacerbate any of the resource management  issues  identified  in the plan, or conflict  with  the  objectives  and  strategies  contained  in  the  Lachlan  Catchment  Action  Plan.  The impacts  of  the  proposal  on  biodiversity, water,  community  and  land  assets  have  been  assessed  in chapters 6 and 7 of the EA. 

Page 17: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     52 

3.1.3 Guidelines 

A range of State Government guidelines have been used in undertaking the environmental assessment for this project. Specific guidelines are referenced in relevant sections of the EA, covering threatened species assessment (DEC 2004a, DEC 2004b, DEC/DPI 2005, DECC 2007, DECC 2008a and DPI 2008) and erosion and sedimentation control (Landcom 2004, DWE 2008a, b, c, DLWC 1994 and DECC 2008b).  

The proposal was also assessed  for compliance with water  resources policies,  including  the ANZECC National Water Quality Management Strategy, the NSW State Groundwater Policy Framework and its component Groundwater Quality Protection Policy and Groundwater Dependent Ecosystems Policy.  

The  Community  Consultation  Plan  complies with  the  State  Government  guidelines  for  community consultation (DoP 2007b, DEC 2004b). 

3.2 COMMONWEALTH 

3.2.1 Acts and regulations 

Environment Protection and Biodiversity Conservation Act 1999 

This Act provides for a Commonwealth assessment and approvals system for: 

i) Actions that have a significant impact on ‘matters of national environmental significance’ 

ii) Actions  that  (indirectly  or  directly)  have  a  significant  environmental  impact  on Commonwealth land 

iii) Actions carried out by the Commonwealth Government 

A proposal requires the approval of the Environment Minister if an action is likely to have a significant impact  on  a  matter  of  national  environmental  significance  or  is  listed  as  a  matter  of  national significance, which includes:  

i) world heritage properties 

ii) wetlands of international importance (Ramsar wetlands) 

iii) Commonwealth listed threatened species and ecological communities 

iv) Commonwealth listed migratory species 

v) nuclear action 

vi) commonwealth marine areas 

vii) commonwealth land 

The Act aims to ensure the conservation and recovery of flora and fauna species and communities at a state and national level. The requirements of EPBC Act under Part 13 ‐ Species and communities, are that  the  Minister  must  establish  a  list  of  threatened  species,  threatened  communities  and  key threatening  processes.  The  list must  contain  threatened  species  and  communities  as  contained  in Schedules 1 and 2 of the Endangered Species Protection Act 1992. Listed species are divided  into the following  categories:  Extinct,  extinct  in  the wild,  critically  endangered,  vulnerable  and  conservation dependent. Threatened communities are divided  into the  following categories: Critically endangered 

Page 18: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     53 

and endangered. Key  threatening processes are  contained  in Schedule 3 of  the Endangered Species Protection Act 1992.  

A  search  for matters  of  national  environmental  significance  based  on  the  proposal  site  and  a  25 kilometre buffer was undertaken using  the Commonwealth Government’s  Environmental Reporting Tool (ERT). This tool covers World Heritage properties, National Heritage places, significant wetlands, migratory species, nationally listed threatened species and communities and other matters protected by  the  EPBC  Act.  The  report  generated  by  the  ERT  is  provided  in  full  and  discussed  within  the Biodiversity  Assessment,  provided  in  Appendix  E.  A  summary  of  the  results  of  the  Environmental Reporting Tool is provided in Table 3‐2 below.   

Table 3‐2: Summary of the results of the Environmental Reporting Tool for the Manildra solar farm site – records within 2 km 

Protected Matter  Number of matters identified 

Threatened Species  8 

Migratory Species  11 

Listed Marine Species  9 

Whales and other cetaceans  0 

Invasive Species  13 

Threatened Ecological Communities  2 

World Heritage Properties  0 

Australian Heritage Sites  0 

Ramsar Wetlands  0 

Nationally Important Wetlands  0 

NPI Reporting Facilities  0 

NPI Airsheds  0 

NPI Catchments  1 

Protected Areas  0 

 

   

Page 19: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     54 

Environment Protection and Biodiversity Conservation Regulation 2000 No. 181 

Bilateral agreements 

In accordance with subsection 45(4) of the EPBC Act and Division 16.1 of the EPBC Regulations 2000, the Commonwealth of Australia entered into a bilateral agreement with New South Wales. One of the aims  of  the  agreement  is  to minimise  duplication  of  environmental  impact  assessment  processes, ensuring a co‐ordinated approach  for actions  requiring approval  from both  the Commonwealth and the  state.  Should  the proposal be  considered  a  ‘controlled  action’ under  the  EPBC Act  the  referral would be assessed by the NSW Department of Planning, funded by the federal agency. 

Renewable Energy (Electricity) Act 2000 

The objects of the Renewable Energy (Electricity) Act 2000 (RE Act) are: 

a. To encourage the additional generation of electricity from renewable sources; and  b. To reduce emissions of greenhouse gases in the electricity sector; and  c. To ensure that renewable energy sources are ecologically sustainable.  

This is done through the issuing of certificates for the generation of electricity using eligible renewable energy sources and requiring certain purchasers (called liable entities) to surrender a specified number of certificates for the electricity that they acquire during a year.  

The Australian Government’s Renewable Energy Target (RET) scheme sets the framework for both the supply and demand of  renewable energy certificates  (RECs) via a REC market. Section 17 of  the Act defines renewable energy sources eligible under the RET. The list of eligible renewable energy sources includes solar energy. 

3.3 LOCAL 

3.3.1 Local Government instruments and policies  

Cabonne Local Environment Plan 1991 

The  proposed Manildra  Solar  Farm  is  located  in  the Cabonne  Local Government Area  (LGA)  and  is located on land zoned 1(a) (General Rural) under the Cabonne Local Environmental Plan 1991 (LEP).  

The  LEP  adopts  the definition of  ‘generating works’  in  the Environmental Planning and Assessment Model Provisions 1980 (Model Provisions), which would encompass the proposal; ‘a building or place used for the purpose of making or generating gas, electricity or other forms of energy’. 

The objectives and permissibility of the solar  farm proposal  in the above mentioned zone under the LEP is outlined below.  

Generating works are permitted with development consent in Zone 1(a) General Rural. The solar farm proposal  is  not,  therefore,  prohibited  in  Zone  1(a)  under  the  LEP,  but would  require  development consent.  

 

Page 20: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     55 

Development Control Plans 

Development Control Plan No. 5 – General Rural Zones (DCP5)  

DCP5  sets out  controls  that  apply  to development  in  zone 1(a) General Rural  in  the Manildra  LGA. Development controls relate to subdivisions and building requirements, however they are not relevant to the solar farm development. 

Draft Blayney, Cabonne and Orange City Sub Regional and Industrial Land Use Strategy 

The  draft  Blayney,  Cabonne  and  Orange  City  Sub  Regional  and  Industrial  Land  Use  Strategy  (the Strategy) has been prepared by the Blayney, Cabonne and Orange City councils to guide  future  land use  planning  over  30  years.  The  Strategy  contains  objectives  and  actions  related  to  agriculture, industry,  residential  and  rural  subdivision,  the  natural  and  scenic  environment  and  heritage  and culture within the three LGAs. These have been taken into consideration when writing this EA. 

Cabonne Villages Strategy 

The Cabonne Villages Strategy aims to guide decision making  in the villages within Cabonne Shire.  It relates  to  land  zones  2(v)  (Village  Zone)  and  1(c)  (Rural  Small  Holdings).  The  proposal  site  is  not situated within either of these zones. 

Page 21: 2.5.1 Construction and commissioning

    Manildra Solar Farm Environmental Assessment 

 

4 November 2010     56 

4 CONSULTATION 

4.1 COMMUNITY CONSULTATION PLAN 

An overarching Consultation Plan has been prepared by Kathy Jones and Associates (KJA) covering all of the solar  farm projects currently being progressed by  Infigen Energy and more detailed sub‐plans have been developed  for  specific project  sites,  including  the Manildra  solar  farm. The Consultation Plan  is attached  in Appendix D and  includes stakeholder  (community and government) consultation. The consultation process complies with the State Government guidelines for major project community consultation (Department of Planning 2007a). 

Stakeholders  including community members and government agencies,  their  interests  in  the project and the relevant consultation strategy are indicated in Table 4‐1. 

 

Page 22: 2.5.1 Construction and commissioning

        Manildra Solar Farm Environmental Assessment 

 

4 November 2010      57 

Table 4‐1 Stakeholders consulted under the Community Consultation Plan 

Stakeholder  Concern or Interest  Management Strategy 

Federal, State and Local Government     

Federal and State Member   Access to information  

Community concerns 

Initial project briefing as required 

Project and construction updates 

Project website 

Local Shire Council  Access to information 

Community concerns and interest 

Impacts to council assets 

Consultation during EA process 

Initial project briefing as required 

Project and construction updates 

Project website 

Government Agencies     

NSW  Department  of  the  Environment,  Climate Change and Water (DECCW) 

Access to information 

Pollution control  including noise, water, air,  land and waste 

Community impacts and disruption 

Consultation during the EA process 

Construction Management Plan 

Environmental Management Plan 

Heritage Management Plan 

Project and Construction updates 

Enquiries and Complaints Management  

Community information hotline (infoline) contact 

Project website 

NSW Department of Planning  Access to information 

Construction impacts 

Operational impacts 

Consultation during the EA process 

Community access to information 

Project briefing/ meeting 

Construction Management Plan 

Environmental Management Plan 

Infoline contact 

Project email 

Project website 

Page 23: 2.5.1 Construction and commissioning

        Manildra Solar Farm Environmental Assessment 

 

4 November 2010      58 

Stakeholder  Concern or Interest  Management Strategy 

NSW Department of Aboriginal Affairs  Access to information 

Heritage 

Employment opportunities 

Consultation during the EA process 

Construction Management Plan 

Environmental Management Plan 

Infoline contact 

Project email 

Project website 

NSW  Department  of  Industry  and  Investment (Primary Industries and Agriculture) 

Access to information 

Pasture protection 

Construction impacts 

Operational impacts 

Weed/noxious plant control 

Pest control 

Construction Management Plan 

Environmental Management Plan  

Infoline contact 

Project email 

Project website 

Aviation and transport 

Civil Aviation Authority  (Private pilots and crop dusting companies) 

Regional Airlines 

Royal Flying Doctor 

Country Rail Network  

Major road freight companies  

Access to information 

Project awareness 

Construction site awareness 

Increased  traffic  on  local  roads  and  over  local level crossings 

Consultation during the EA process 

Infoline contact 

Project email 

Project website 

 

Emergency Services 

Police 

Ambulance 

Rural Fire Services 

State Emergency Services 

Access to information 

Road and traffic impacts 

Changes to property access 

Project briefings and ongoing consultation 

Traffic management plans 

Delivery and/or construction hours/activities 

Project and Construction updates 

Page 24: 2.5.1 Construction and commissioning

        Manildra Solar Farm Environmental Assessment 

 

4 November 2010      59 

Stakeholder  Concern or Interest  Management Strategy 

Infoline contact 

Project website 

Local, Community  and Interest Groups 

Landowners/tenants adjacent to construction site 

Landowners/tenants adjacent  to construction  staff facilities/office  

Access to information 

Impacts on property values 

Damage to boundary fencing, stock grids, gates 

Damage to trees/shrubbery 

Noise/pollution during construction 

Personal consultation 

Project and Construction updates (notifications) 

Information sessions and feedback forms 

Enquiry and complaints management 

Infoline contact  

Project email 

Project website 

Local Community  Access to information 

Employment opportunities 

Economic benefits 

Local business support 

Local resource provision 

Project and Construction updates (notifications) 

Advertising and media releases 

Information sessions and feedback forms 

Enquiry and complaints management 

Infoline contact  

Project email 

Project website 

Interest Groups  

Agricultural Associations 

Agricultural Show Societies 

Progress/Business Associations 

Tourism Associations 

Aboriginal Land Councils 

Innovation 

Community/Regional benefits 

Impacts/risk to historical icons 

Asset protection 

Access to information 

Environmental impacts 

Briefings /meetings (as required) 

Project and Construction updates (notifications) 

Advertising and media releases 

Infoline contact Enquiry and complaints management 

Project email 

Project website 

Page 25: 2.5.1 Construction and commissioning

        Manildra Solar Farm Environmental Assessment 

 

4 November 2010      60 

Stakeholder  Concern or Interest  Management Strategy 

Local Heritage Groups 

Agricultural  Field  Days  (e.g.  Australian  National Field Days Assoc.) 

Shires Association 

Heritage Groups 

Historical Societies 

Local area promotion 

Schools and kindergartens   Education opportunities about renewable energy 

Project participation activities 

Briefing/information sessions (at schools – post construction) 

Enquiry and complaints management 

Infoline number 

Project email 

Project website 

design and painting activity for SPVFP project promotion (optional) 

Media     

WIN TV Corporation 

Prime Television 

Capital Television 

Local and regional newspapers 

The Land newspaper 

Regional Radio Stations 

ABC TV and radio 

Community benefits 

Road and traffic impacts 

Environmental  impacts 

Construction impacts 

Employment opportunities 

Tourism promotion 

Access to information 

Media releases 

Project and Construction updates (notifications) 

Infoline contact  

Enquiry and complaints management 

Project website 

Project email 

Page 26: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       61 

4.2 STAKEHOLDER CONSULTATION  

The Consultation Plan provides for specific activities at different stages of the project as well as specific strategies targeting different stakeholder groups, as detailed below. 

4.2.1 Environmental assessment stage 

During  the  public  exhibition  of  the  Environmental  Assessment  (EA),  public  community  information sessions will be advertised, so attendees can meet members of the project team and obtain a greater level of detail about the project, its benefits and potential impacts.   

Stakeholders would  be  advised  of  the  EA  exhibition  and  offered  project  briefings  at  their  offices.  Stakeholders  would  also  be  provided  with  all  project  contact  information  and  invited  to  make submissions or provide feedback. 

Project Community Consultation Manager 

A dedicated Project Community Consultation Manager  (PCCM) would be  responsible  for organising, advertising and managing all community consultation activities at the EA and construction phases of the project. PCCM duties would  include planning and managing  stakeholder briefings/meetings and community  consultation  activities,  liaising  with  project  personnel,  developing  media  releases  and media  kit  and  responding  to  enquiries  and  complaints. An  Environmental Assessment  Team would work closely with the PCCM during the EA stage to provide all necessary information for the delivery of clear,  concise  and  easy  to  understand  information  about  the  project  to  stakeholders  and  the community. 

Communication and consultation tools 

The following communications and consultation tools would be used during the EA stage. 

• information sessions 

• stakeholder briefings/meetings 

• advertising 

• website and other web based tools 

• fact sheets 

• display boards 

• EA exhibition venues 

4.2.2 Construction phase 

Community consultation and stakeholder engagement would continue during the construction phase of the project, with activities and events scheduled to align with project milestones. The PCCM may continue in this role as a follow on from the EA stage of the project. 

Communication and consultation tools 

During the construction phase of the project, community consultation would focus more on engaging the  community,  providing  information  about  key  construction  activities,  handling  enquiries  and 

Page 27: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       62 

complaints, encouraging project championing and celebrating project milestones. The following tools would be used: 

• information sessions 

• stakeholder meetings 

• emails 

• advertising 

• project branding 

• construction site fencing 

• photography 

• community notifications 

• website 

• fact sheets 

• site inspections/visitors 

4.2.3 Complaints handling and reporting 

A complaints management procedure is detailed in the Community Consultation Plan. 

4.2.4 Community and stakeholder consultation action calendar 

An  indicative  and  example  calendar  to  implement  the  Community  Consultation  Plan  is  indicated below.  Implementation of the plan commences with project  introduction  information sessions to be scheduled on determination of preferred sites.  

July 2010   ‐ undertake initial site assessments 

  ‐ stakeholder analysis 

  ‐ broad base project introduction to gauge community reaction (information session, fact sheets, contact number, project email) 

  ‐ develop communications materials 

Sept 2010   ‐ prepare Environment Assessment for each site 

  ‐ coordinate key stakeholder meetings, where relevant 

Oct 2010   ‐ Environmental Assessment exhibition period 

  ‐ announce and promote exhibition period  

Nov 2010   ‐ Environment Assessment community feedback 

  ‐ response to submissions 

Media release upon Project Determination by the Minister. 

Page 28: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       63 

4.3 CONSULTATION UNDERTAKEN TO DATE 

4.3.1 Open house 

The  open  house  session  was  held  on  3rd  August  2010  at  the Manildra  Town  Hall,  Kiewa  Street, Manildra. It was advertised in the Central Western Daily on the 15th July 2010. 

The  event  ran  from  12:00‐8:00pm.  Representatives  from  Infigen  including  Stephen Donnelly,  Chris McGrath and Luke Thrum and representatives from Suntech, the project technology partner and Tenix Alliance,  the  project  construction  partner  were  present  to  discuss  the  proposal  specifics,  general questions  about  solar  farms  and  solar  farm  developments  and  any  specific  concerns  or  questions raised by the community. A brochure about the proposal was distributed as well as feedback forms.  

Twenty people entered  their details on  the Community Open Day Register. All  comments provided were  positive  and  supportive  of  the  project. One  comment  referred  to  concerns  about  glare  and consideration of fire hazards. 

Feedback forms and open house follow‐up 

The community feedback forms allowed the community an opportunity to comment on the proposed solar farm through answering a number of questions. Four feedback forms were received following the open  house.  The  feedback  forms mainly  focussed  around  the  positives  of  increasing  tourism  and people  traffic  in  the  township,  including  offers  of  services  from  accommodation,  food  and  service providers.   The  issues of most  concern were  limited  to  that of glare  for nearby properties and  fire protection and suppression.  It is considered that the low level of feedback forms was reflective of the low level of concern expressed by the community at the open day. 

Face‐to‐face consultation 

To  help  the  community  better  understand  the  potential  issues  associated  with  the  proposal,  the proponent  directly  contacted  landowners  neighbouring  the  proposal  site.  Where  requested,  the proponent  provided  the most  up‐to‐date  information  possible  on  various  different  aspects  of  the project and provided supplementary material to answer general solar farming questions.  

Brochure 

The proponent prepared a  fact sheet brochure  to  introduce  the solar  farm proposal and  inform  the community and  interested parties about proposed details. The brochure was distributed at the open house information session and was placed on Infigen Energy’s website. 

Media articles 

An advertisement in relation to the open house information session was placed in the Central Western Daily  (refer Appendix D). Articles outlining  the Manildra  solar  farm proposal have appeared  in  local newspapers, including the Central Western Daily (15 July 2010). 

Website and email contacts 

Infigen  Energy  maintains  a  Solar  Flagships  Program  page  on  its  website (http://www.infigenenergy.com/solar‐flagships‐program.aspx), which includes: 

Page 29: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       64 

• A brief summary of each solar farm proposal, with downloadable pdf fact sheets. 

• Community consultation arrangements for each site (Community Information Days). 

• Contact  details  for  Infigen  Energy with  an  invitation  to  comment  on  the  proposals  via  the website, email, fax, telephone or mail. 

Infigen has received one email and two letters from members of the local community: 

• Two  letters were  received  from  local  businesses  (9  and  10  August  2010)  offering  services including earthmoving services and accommodation. 

• One email was received (14 August 2010) asking when the project would start and how many solar panels there would be and included support for the project. 

Another page on the website outlines the support provided by Infigen to local community groups and events (http://www.infigenenergy.com/about‐us/community.aspx). 

4.3.2 Government consultation 

Initial meetings 

The proponent met with the consent authority, the NSW Department of Planning, formally on 15 June 2010, introducing the proposal and seeking advice on the assessment process. The proponent sought a determination  from  the  Director General  that  the  proposal would  be  assessed  as  a Major  Project under Part 3A of the Environmental Planning and Assessment Act. On 5 July 2010, the proponent was issued with a letter from the Department of Planning confirming that the proposal would be assessed as a Major Project under Part 3A of the EP&A Act.  

Preparation of Director‐General’s Requirements 

During  preparation  of  the  Director  General’s  Requirements,  various  government  agencies  were consulted by the Department of Planning. Those listed below provided written responses in relation to the proposal: 

• Central West Catchment Management Authority 

• Department of Environment, Climate Change and Water 

• Department of Industry and Investment 

• Land and Property Management Authority 

• NSW Rural Fire Service 

• NSW Office of Water 

These  responses were provided  to  Infigen  and have been  addressed within  the preparation of  this Environmental Assessment. 

 

 

Page 30: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       65 

5 RISK ASSESSMENT: SCOPING OF KEY ISSUES 

5.1 POTENTIAL IMPACTS 

The potential environmental  impacts of PV solar farms depend on the size and nature of the project and  are  frequently  site  specific  (Gekas  et  al.  2002). Gekas  et  al.  (2002)  summarised  the  potential environmental impacts of PV solar farms in general terms, including: 

• Environmental benefits  ‐ significant noise or chemical pollutants emission reductions and an increase in soil humidity and plant growing conditions in dry areas 

• Social impacts – direct local benefits (access to electricity, employment) 

• Land  use  ‐  depend  on  specific  factors  such  as  the  area,  land  characteristics,  visual  or environmental sensitivity of surroundings. Solar farms can ‘reserve’ soils for future uses 

• Visual impact ‐ visual intrusion is highly dependent on frame design and the surroundings 

• Pollution  and  occupational  health  ‐  soil  and  groundwater  pollution  due  to  poorly  stored materials, abnormal plant operations, damaged panels or fire, posing small human health risks 

• Air pollution ‐ minor emissions associated with infrastructure transport 

• Depletion of natural sources and energy consumption ‐ panel production is energy intensive.  

Mitigation  of  environmental  impacts  can  be  achieved  by  avoiding  ecologically  sensitive  areas  or archaeological sites, site restoration to alleviate visual impacts and good work practices and protective clothing  to  avoid  occupational  accidents  (Gekas  et  al.  2002).The  impact  assessment  in  this  report covers all of these issues, guided by a comprehensive scoping and risk assessment process to identify key issues and risks. 

5.2 SCOPING OF KEY ISSUES 

Identification  of  key  environmental  issues  was  undertaken  for  the  Preliminary  Environmental Assessment (PEA) provided to the Department of Planning on 28 July 2010. The key  issues  identified were; Community, Visual, Archaeology and Biodiversity issues. 

Since  undertaking  the  PEA  and  the  field  surveys,  the  key  issues  have  been  revised  through  an environmental  risk  assessment  (Table  5‐3),  taking  into  account  the  specific  characteristics  of  the proposal site and the impacts associated with the proposed development.  

The  risk  assessment  aims  to  quantify  the  environmental  risks  associated  with  the  construction, decommissioning and operation of the proposed solar farm. Environmental risks can be considered in terms of the degree of potential impact, the sensitivity of the environment and the likelihood that an impact would occur. 

A risk rating between one and five has been applied to identified issues, where one is a lower risk and five is the highest. The range of risk ratings are shown in Table 5‐1. 

   

Page 31: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       66 

Table 5‐1: Risk rating of environmental aspects. 

Nature of impact Sensitivity of receiving 

environment Likelihood 

1 ‐ Negligible  1 ‐ Low  1 – Rare/never 

2 ‐ Minor  2 – Low to moderate  2 – Unlikely 

3 ‐ Moderate  3 ‐ Moderate  3 – Possible 

4 ‐ Major  4 ‐ High  4 – Likely  

5 ‐ Catastrophic  5 – Very high  5 – Highly likely/definitely 

 

The overall risk rating is determined by multiplying the individual risk ratings of:  

Impact x Sensitivity x Likelihood 

 

The level of risk is considered to be high moderate or low in accordance with Table 5‐2. 

Table 5‐2: Overall risk rating classes 

Overall risk rating   Level of risk 

41 +  High 

21‐40  Moderate 

1 ‐ 20  Low 

 

   

Page 32: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       67 

Table 5‐3: Risk analysis of environmental issues 

RELEVANT CHAPTER 

ENVIRONMENTAL ISSUE 

NATURE  OF IMPACT 

SENSITIVITY  OF RECEIVING ENVIRONMENT 

LIKELIHOOD  OF OCCURRENCE 

RISK RATING 

6.1  Biodiversity  3  3  4  36 

6.2  Visual amenity  2  3  5  30 

6.3  Aboriginal heritage  3  2  5  30 

6.4  Noise  2  4  5  40 

7.7  Socioeconomic  and Community 

2  4  3  18 

7.6  Waste  Management and reuse 

2  2  5  20 

7.1  Traffic and access  2  2  3  12 

7.3  Soils and landforms  2  4  2  16 

7.2  Historic heritage  2  3  1  6 

7.4  Hydrology  and  water quality 

1  1  4  4 

7.5  Air quality and climate  1  4  4  16 

7.8  Land  use  and  mineral resource impacts 

2  1  2  4 

7.9  Health and safety  1  2  1  2 

7.10  Fire and bushfire issues and risks 

3  2  1  6 

7.11  Cumulative impacts  2  2  3  12 

Environmental  issues  with  moderate  to  high  risk  levels  (yellow  to  red)  have  been  given  greater attention in terms of investigation and mitigation of impacts, most of which have had specialist studies undertaken. These are considered key issues and are discussed in Section 6. Environmental issues with a low risk rating (green) are considered to be readily identifiable and manageable and therefore less of a priority. Desktop investigations have generally been undertaken for these issues, which are assessed in  Section  6.  A  site  visit was  undertaken  on  8  July  2010  to  get  a  general  overview  of  the  existing environment and  identify potential environmental  impacts. Additional site visits were undertaken for specialist studies including biodiversity, heritage and visual amenity. 

Page 33: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       68 

6 KEY ISSUES 

6.1 BIODIVERSITY 

6.1.1 Existing environment 

Approach 

The Biodiversity Assessment was undertaken by nghenvironmental. It involved: 

• A  desktop  review  of  research  literature,  online  databases  and  other  sources  to  determine regional and local biodiversity values and assist field survey planning and design  

• Flora and fauna surveys and habitat assessments  

• Analysis and assessment of data to establish conservation values and significance of  impacts in relation to environmental legislation 

• Development of measures to reduce the risks and identified impacts, focussing on avoidance and mitigation and offsets where impacts were unavoidable 

Online database searches  included the DECCW threatened species database and the Commonwealth EPBC Act Protected Matters search tool. The field flora survey was based on stratified sampling sites, general  site  inspection  and  targeted  searches  for  threatened  species  in  likely  habitats.  The  fauna survey  focused  on  habitat  assessment  with  bird  surveys  and  opportunistic  records  of  sign  and observations. Field surveys were  limited by the winter timing of the fieldwork. Supplementary spring surveys have been included in the safeguards in Section 6.1.3, below. 

Regional 

The Proposal  is located in the NSW South Western Slopes Bioregion, an extensive area of foothills and isolated ranges comprising the  lower  inland slopes of the Great Dividing Range extending from north of Cowra through southern NSW into western Victoria. The South Western Slopes Bioregion has been intensively  cleared  and  cultivated;  remaining  native  vegetation  is  fragmented.  The  proposal  site  is located close to the boundary of four catchment subregions:  

• Central West CMA o Upper Slopes subregion o Orange subregion 

• Lachlan CMA o Upper Slopes subregion o Orange subregion 

These catchment subregions contain a large variety of landforms and vegetation types. Around 76% of the  Lachlan  CMA  supports  native  vegetation  cover  although much  of  this  is  modified,  while  the majority of the Central West CMA has been cleared for agriculture. 

Local 

The  proposal  site  is  located  in  an  area  of  largely  cleared  agricultural  land  which  forms  a matrix between several areas of remnant native vegetation. Nearby forest areas include: 

Page 34: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       69 

• Five  kilometers  to  the west  lies  forest/woodland  that  is  connected with Goobang National Park to the north and Mandagery and Black Yamma State Forests to the south and south west.  

• Five  kilometers  to  the  north  lie  low  rocky  ranges  supporting  uncleared  native  vegetation connected to Killonbutta State Forest further to the north.  

• Located seven kilometers to the east, three thin, parallel, wooded ridges extend over twenty kilometers from north to south.  

Connectivity between the remnant forests is generally limited to farmland carrying low density cleared woodland  and  isolated  paddock  trees,  with  no  clearly  delineated  corridors  for  fauna.  Several waterways  in  the  district  provide more  definitive  fauna movement  corridors  through  this matrix. Manildra Creek provides a movement corridor to the west and Mandagery Creek provides somewhat less continuous riparian tree coverage to the north and south of the proposal site.  

Land at  the proposal site  is gently undulating with  rocky patches  throughout. Elevation  ranges  from 450 m to 490 m. The site is at a higher elevation than the majority of the Manildra township which lies roughly 1km to the south west. A small drainage line runs through a short section of the most western paddock. Mandagery Creek lies 1.5 km west of the site. 

The  proposal  site  is  largely  cleared  of  tree  and  shrub  cover.  The  understorey  is  entirely  exotic  in cropped areas, and in grazed areas, is dominated by exotic grasses or native grasses with exotic forbs. Native species diversity is generally low. Native vegetation at the site is likely to be derived from Box‐Gum Woodland. Overstorey  species  are  predominantly White  Box  and  Yellow  Box  eucalypts. Most trees are mature although very few have formed hollows. 

Results 

Vegetation communities 

The majority of the proposal site (excluding the far western paddock) was under cropping at the time of the survey, or was dominated by exotic grass species. These areas where no overstorey  is present cannot be said to constitute a native vegetation community. However, scattered paddock trees were present  in cropped and exotic pasture areas and,  in comparison with more  intact native vegetation within  and  adjoining  the proposal  site,  it was possible  to  ascertain  the  vegetation  community  that these trees were derived from.  

Remnant  native  vegetation  within  and  adjoining  the  proposal  site  is  representative  of  Box‐Gum Woodland  communities  including  species  such  as  White  Box  (Eucalyptus  albens),  Yellow  Box  (E. melliodora) and Blakely’s Red Gum (E. blakelyi). Native grassland occurs in the far west of the site and is likely to be derived from these communities. 

Other vegetation present within the proposal site was restricted to isolated paddock trees comprising Kurrajong (Brachychiton populneus) and the introduced Pepper Tree (*Schinus areira). 

In summary, three vegetation communities were identified: 

• Derived native grassland 

• Box‐Gum Woodland (native) 

• Exotic (crop or pasture) 

Page 35: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       70 

 

Figure  6‐1  Cultivated  paddocks  make  up approximately  two  thirds  of  the  area  to  be occupied by the Proposed Manildra Solar Farm  

 

Figure 6‐2   Exotic dominated pasture makes up  the remainder  of  the  land  to  be  occupied  by  the Proposed Manildra Solar Farm  

Habitat at the proposal site 

Six major habitat types were identified on the proposal site:  

• Cultivated paddocks 

• Pasture 

• White Box, Yellow Box, Blakely’s Red Gum Woodland stands (Box‐Gum Woodland) 

• Rocky outcrops 

• Isolated remnant trees 

• Modified aquatic habitat 

These habitats are described in Table 6‐1and habitat features are mapped on Figure 6‐8.  

 

 

Figure  6‐3  Remnant  White  Box  stand  in cultivated paddock 

 

Figure 6‐4 Rocky outcrop  in  the  far west of  the  site (infrastructure layout has been designed to avoid the higher diversity native pasture in this area) 

Page 36: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       71 

 

Figure 6‐5 Shallow dam  in the central south of the proposal site 

 

Figure 6‐6 Isolated White Box tree on thin outcrop of rock within a cultivated paddock 

 

Page 37: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       72 

 

Figure 6‐7 Approximate distribution of vegetation communities at the Proposed Manildra Solar Farm site 

Site boundary

Vegetation (type, condition)Box Gum Woodland (EEC TSC), PoorBox Gum Woodland Derived Grassland (EEC TSC), Poor to moderateCrop or exotic pasture

°

0 200 400100 Metres

    @ A4 Reference: 1338 ‐ 6

1:15000

Coordinate System:      GDA94 Zone 55

www.nghenvironmental.com.au

Page 38: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       73 

Table 6‐1: Description of fauna habitat features at the proposal site 

Habitat type  Habitat quality 

Location  Habitat features  Potential threatened species2 

White Box, Yellow Box, Blakely’s Red  Gum  Woodland  stands (degraded) 

Low ‐moderate 

Seven stands of three or more trees are found across the proposal site 

Few  hollows,  foraging  and shelter  habitat,  little  fallen timber 

Diamond  Firetail,  Superb  Parrot, Turquoise  Parrot,  Flame  Robin, Scarlet Robin 

Isolated  remnant  trees, Kurrajong,  Yellow  Box,  White Box 

Low ‐Moderate 

Scattered at a low density across the site   Few  hollows,  limited  foraging and shelter habitat 

Superb Parrot 

 

Rocky outcrops 

Granitic and metamorphic 

Low ‐Moderate 

Two  linear  outcrops  of  presumably  the  same  rock strata occur on the site running south east to north west  in  the  western  paddock  and  through  the woodland stand adjacent to the substation in B1 and B3.  In addition surface scatters of rock occur within the central/northern paddocks B4 and B5.  

Surface rocks  Pink‐tailed Worm Lizard 

Little Whip Snake 

Pasture (native or exotic)  Low ‐ Moderate 

Predominantly  native  pasture  in  the  western paddock, exotic dominated paddocks  in  the  central north (B5)and central east (B2)of the proposal site  

Seed  resources  and invertebrate foraging area 

Cover  for  reptiles  (this  feature is  likely to change with drought or increased grazing) 

Diamond  Firetail,  Superb  Parrot, Turquoise  Parrot,  Flame  Robin, Scarlet Robin, Little Whip Snake 

Modified  aquatic  habitats (dams  and ephemeral drainage lines) 

Low  Few  aquatic  habitats  were  found  within  proposal site.  Shallow  ephemeral  dams were  located  in  the western paddock and the central paddock B3, with a dry drainage  line  running  south  east  to north west through  the  south  eastern  corner  of  the  western paddock. 

Limited  breeding  opportunities for  amphibians,  ephemeral water source for fauna 

 

                                                              

2 These are species that have been recorded in high quality examples of the habitat type, many have a very low probability of actually occurring on site 

Page 39: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       74 

Habitat type  Habitat quality 

Location  Habitat features  Potential threatened species2 

Cultivated paddocks  Low  Paddocks B4, B6, B7 and B1.  Source  of  grain  for  parrots, cultivation  provides  arthropod foraging  for  insectivores  and generalists 

Superb Parrot, Flame Robin, Scarlet Robin 

Page 40: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       75 

 

Figure 6‐8: Fauna habitat features at the proposal site

Þ!

Þ!

Ð

Þ!

Þ!

Þ!

Þ!Þ!

Þ!

!R

Þ!

Þ!

#

Þ!

Þ!

Þ! Þ!

Þ!

9

8

7

6

5

4

3

2

1

15

1413

12

11

10

Site boundary

Development envelope

Habitat feature

Dam

Þ! Hollow bearing stag

Þ! Hollow bearing tree

Þ! Hollow bearing trees

Ð Nest (Brown Falcon)

# Kangaroo grass

!R Rabbit warren

Rock outcrop

°

0 200 400100 Meters

    @ A4 Reference: 1338‐4

1:15000

Coordinate System:      GDA94 Zone 55

www.nghenvironmental.com.au

Page 41: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       76 

Threatened species and communities 

Preliminary evaluation results 

One threatened community, three threatened flora species and 12 threatened fauna species have at least moderate potential  to be present  at  the proposal  site,  and  at  least moderate potential  to be impacted by the proposal. These threatened entities are listed in Table 6‐2. 

Table 6‐2: Threatened ecological communities flora and fauna potentially impacted by the proposal 

Common name  Scientific name  Status 

FLORA 

Austral Toadflax  Thesium australe  V TSC, V EPBC 

Small Purple‐pea  Swainsona recta  E TSC, E EPBC 

Silky Swainson‐pea  Swainsona sericea  V TSC 

ECOLOGICAL COMMUNITIES 

Box‐Gum Woodland  EEC TSC 

FAUNA 

Brown Treecreeper  Climacteris picumnus  V TSC 

Diamond Firetail  Stagonopleura guttata  V TSC 

Flame Robin  Petroica phoenicea  V TSC 

Scarlet Robin  Petroica boodang  V TSC 

Superb Parrot  Polytelis swainsonii  V TSC, V EPBC 

Turquoise Parrot   Neophema pulchella  V TSC 

Greater Long‐eared Bat  Nyctophilus timoriensis  V TSC 

Little Pied Bat  Chalinlobus picatus   V TSC 

Yellow‐bellied Sheathtail‐bat  Saccolaimus flaviventris  V TSC 

Koala  Phascolarctos cinereus  V TSC 

Little Whip Snake  Suta flagellum  V TSC 

Pink‐tailed Worm‐lizard  Aprasia parapulchella  V TSC 

V TSC = listed as Vulnerable under Schedule 2 of the TSC Act 1995. 

V EPBC = listed as Vulnerable under the Commonwealth EPBC Act 1999 

E TSC = listed as Endangered under Schedule 1 of the TSC Act 1995 

E EPBC = listed as Endangered under the Commonwealth EPBC Act 1999 

EEC TSC = listed as an Endangered Ecological Community under Schedule 1 of the TSC Act 1995 

Assessments of significance, pursuant to NSW and Commonwealth legislation, have been undertaken to characterise  the significance of potential  impacts. While not  required under Part 3A of  the EP&A Act, they provide a transparent and systematic characterisation of impact. 

Page 42: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       77 

The Assessments concluded  that the proposal would not be  likely  to significantly  impact threatened species and communities, subject to a supplementary survey in spring which is required to confirm the assumptions of this assessment and subject to the  implementation of the safeguards  included  in the Biodiversity Assessment (included in full in this EA as Statements of Commitment). 

Endangered Ecological Communities (EEC) 

Box‐Gum Woodland – NSW  Endangered Ecological Community (EEC) 

The Box‐Gum Woodland,  listed under  the NSW Threatened Species Conservation Act 1995,  includes intact and disturbed areas such as: 

• Woodlands  which  include  Yellow  Box  or  Blakely’s  Red  Gum  (with  or  without  native understorey); and  

• Grasslands and pastures dominated by native grasses that are derived from this community. 

The woodland and native grassland at the site meets the above description. This community has the potential to be  impacted by the Proposal. An Assessment of Significance pursuant to the TSC Act has been undertaken (refer to the Biodiversity Assessment). This assessment concluded that a significant impact to the local occurrence of the EEC is unlikely as the result of the Proposal. 

Box‐Gum Woodland – Commonwealth Critically Endangered Ecological Community (CEEC) 

The Commonwealth Environment Protection and Biodiversity Conservation Act 1999  (EPBC Act)  sets more stringent criteria for the recognition of the Box‐Gum Woodland Critically Endangered Ecological Community (CEEC) listed under that Act. Vegetation at the proposal site would not meet these criteria and the Commonwealth Box‐Gum Woodland CEEC is therefore not present at the site. 

Threatened flora 

No threatened species were recorded during the field survey. 

Threatened fauna 

Two  threatened  fauna  species  listed under  the Threatened Species Conservation Act 1995  (TSC Act) were recorded during the survey (see Figure 6‐9):  

• Flame Robins were  recorded along  the southern boundary of  the western paddock  in  the vicinity of the regeneration seeding trial plots. Seven birds were seen foraging within the site and adjacent sown field.   

• Two pairs of Superb Parrots were seen on site; one in the remnant Box‐Gum Woodland near the substation (between B1 and B3) and another (possibly the same pair) flying over the site from south to north.  

Biodiversity constraints 

A preliminary biodiversity constraints assessment based on the findings of the biodiversity survey was produced  and  provided  to  the  Proponent  early  in  the  planning  phase.  Based  on  the  biodiversity constraints  identified  in this report the development envelope was created with the aim of avoiding areas  of  high  biodiversity  values  and  therefore minimising  impacts  to  biodiversity. High  constraint features  include derived grassland and  rocky out crops  in  the western paddock and areas of hollow bearing Box‐Gum Woodland EEC remnants. Areas requiring additional survey work are also  indicated on the constraints map Figure 6‐10.

Page 43: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     78 

 

Figure 6‐9: Threatened fauna records at the Manildra Solar Farm site 

!

!

!

Site boundary

Threatened fauna

! Flame Robin

! Superb Parrot

°

0 200 400100 Metres

    @ A4 Reference: 1338 ‐ 3

1:15000

Coordinate System:      GDA94 Zone 55

www.nghenvironmental.com.au

Page 44: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     79 

 

Figure 6‐10: Key biodiversity constraints overlayed with the development envelope at the Manildra Solar Farm site 

Site boundary

Development envelope

ConstraintLowFurther survey predicted lowFurther survey requiredModerateHigh

°

0 200 400100 Metres

    @ A4 Reference: 1338 ‐ 5

1:15000

Coordinate System:      GDA94 Zone 55

www.nghenvironmental.com.au

Page 45: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       80 

6.1.2 Impact assessment 

Construction and decommissioning 

Loss of vegetation and habitats during construction 

Estimates of the areas affected by each component of the proposal are  indicated  in Table 2‐5 of this EA and have been used to assess the impact of the proposal on biodiversity values. 

Groundlayer vegetation 

Groundlayer vegetation over an estimated area of around 12.45 hectares would be removed  for the operating  life  of  the  solar  farm. Most  of  this  clearing would  result  from  the  establishment  of  the perimeter and  internal access  tracks. This  figure  is based on all  tracks and  roading  requiring an 8m wide clearing zone and this is likely to be an over estimation of the actual clearing required. 

These  works  would  affect  exotic  dominated  pasture  and  cultivated  paddocks,  all  with  generally minimal conservation value. Similar vegetation  is  locally abundant. The  loss of  this vegetation  is not considered to be significant. 

Canopy vegetation and hollow bearing trees 

A total of approximately 55 mature trees would be removed to reduce shading of the PV arrays. This would  include six hollow bearing  trees  (see section 5.3.2 of  the Biodiversity Assessment  for a  list of hollow bearing trees found onsite, including those to be removed). The loss of these habitat resources is considered manageable with the implementation of safeguards. 

Disturbance to fauna during construction 

Habitat alienation may occur during the construction of infrastructure. Noise and vibration, increased human and vehicle activity and night work (if required) may not directly harm individual animals but it could affect  feeding and breeding behaviours  resulting  in negative  impacts on  long  term population viability. Adhering to timing restrictions, where possible, this impact is considered manageable. 

Trenching works  have  the  potential  to  injure  or  trap  native  fauna. Mitigation measures would  be adopted to minimise the risk of biodiversity impacts. 

Alteration to microclimate and erosion potential under the solar array 

An  estimated  100  hectares  of  cultivated  land  would  be  affected  by  the  proposed  solar  farm. Vegetation and ground habitats would be affected by altered microclimate beneath the array, through reduced insolation and temperature and increased humidity. Wind speeds may also be reduced. Solar module washing,  in addition to microclimatic changes, would contribute to an  infrequent  increase  in soil moisture under the array during dry times. 

Changes in rainfall distribution 

The vertically projected area under  the solar panels  is estimated  to be 30.6 hectares, or 30% of  the total array site. There would be a concentration of rainfall runoff in a strip below the lower edge of the solar panel rows. This would increase rain splash intensity and soil erosion potential in this area during heavy  rainfall events. The erosion  risks  should be manageable using adequate  site preparation, and responsive pasture and stock management. A rain shadow below the solar panel rows would also be created.  Soil  in  this  area may  be  drier  than  surrounding  soil,  but  this would  be  offset  by  reduced 

Page 46: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       81 

evapotranspiration losses due to shading and reduced air movement, variation in the angle of rainfall and lateral movement of soil water from adjacent rain‐exposed areas. 

Shading and groundcover management under the array 

The total area of permanent shading is estimated to be 30% of the area under the array (36 hectares). 70% (84 hectares) would be partially shaded depending on the season and time of day.  

Shading  by  the  PV  arrays  will  have  an  impact  on  the  microclimate  of  at  least  120  ha  of  the development  envelope.  Reduced  insolation may mean  lower  rates  of  plant  growth  and  biological productivity.  However,  this  may  be  offset  by  increased  soil  moisture  and  reduced  evaporative demands due to increased humidity and/or reduced temperature resulting in enhanced plant growth (Prinder and Facelli 2004).  

The grass species that dominate the modified pastures to be impacted by the proposal are C4 species with the potential to be significantly  impacted by shading. In areas dominated by exotic species such as Stinking Lovegrass  it  is  recommended  that a new pasture of  shade  tolerant perennial  species be sown and established prior to any infrastructure construction. In areas under cropping by Wheat this practice is also recommended as wheat is an annual species which will perish, leave bare ground and unlikely  recolonise which may  lead  to erosion and weed  invasion. This action will assist with weed control by  locking up  soil nitrogen  and providing  competition  for  soil moisture  and will  reduce  the potential for erosion by providing a more stable ground cover.  

Maintaining  the groundcover under  the array would be an  important element of  site management. Approaches could  include the use of cell grazing by sheep or  irrigation  (pers comm. C. Waters, NSW Department of Primary Industry Research Scientist, A. Southwell, Charles Sturt University Lecturer). It is recommended that consultation be undertaken with a qualified agronomist to  inform appropriate groundcover establishment and management under the PV arrays.  

Fauna impacts 

It  is unclear what  the  impact  to soil moisture, soil nitrogen and subsequent vegetation composition from factors such as reduced light and near ground wind levels would be following the installation of the PV arrays. The response of  local  fauna to these changes  is equally hard to predict and would be largely influenced by the vegetation changes that occur. An altered microclimate under the PV arrays due to shading and associated vegetation changes has the potential to affect sensitive fauna eg ants and  poikilothermic  species  such  as  reptiles.  Basking  opportunities  may  be  reduced  however  the structure of the PV arrays may provide fauna with a degree of protection from predation, particularly from  raptors.  Increased  soil  moisture  may  create  favourable  shelter  and  foraging  habitat  for amphibians. As the PV arrays will be located in exotic dominated grazing and cropping paddocks there is  little  probability  of  threatened  species  being  impacted  by  any  microclimate  and  associated vegetation changes that may occur.  

Granite  outcrops  are  predominant  geological  features  in  agricultural  landscapes  in  south‐eastern Australia, and some fauna species, particularly reptiles, are restricted to these habitats (Michael et al. 2010). Outcrop habitats can be negatively impacted by physical damage or shading. It is recommended that where possible  the small  rock outcrops at  the site be excluded  from  the array,  together with a minimum 2.5 metre buffer to avoid shading. 

Page 47: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       82 

Fauna habitat loss and collision hazards 

Increased  vehicle movements during  construction may  lead  to  collisions with native  fauna. Vehicle movements  should  be  restricted  during  dawn  and  dusk  and  speed  limits  should  be  enforced.  It  is unlikely that any threatened species would be put at risk by this potential impact. 

The construction of a perimeter fence has the potential to impact native fauna by creating a barrier to movement and by providing a collision risk. Where security concerns permit, barbed wire should not be used in the fence construction as it is capable of entangling and killing a range of native fauna (van der Ree 1999). High  chainlink  fences are a hazard  to  fast  flying parrot  species  (Pfennigwerth 2008) Superb Parrots were  recorded on  site  and  there  is  some potential  for  this  species  to be  impacted. Installing  coloured  streamers,  using  shade  cloth  or  using  coloured  wire  are  recommended  as mitigation measures  to  increase  the  visibility  of  this  type  of  fence  to  parrots  (Pfennigwerth  2008). Fencing along Molong Manildra Road should be maintained so as macropods and other  large native fauna are not  funnelled along  the perimeter  fence and onto  the  road  creating a  traffic hazard and collision risk to the animal. 

A perimeter fence would provide a barrier to the movement of many  large terrestrial fauna species. Species  likely  to  use  the  proposal  site  for  foraging  and  dispersal  would  be  capable  of  covering significant distances of open ground and are unlikely to be greatly effected by the reduction habitat brought about by a perimeter fence. Similar modified grazing habitat is abundant and wide spread in the district. There is a low possibility that Koalas dispersing from forested areas to the west and north may occasionally  cross  the proposal  site. A perimeter  fence would  limit  their movement  at  a  local scale, however the proposal site  is not considered a fauna movement corridor and the adjacent  land carries similar structural characteristics and would provide alternative movement opportunities. 

For species that would still have access to the habitat within the perimeter fence habitat modification due  to microclimate  changes  and  associated  invertebrate  and  vegetation  changes may  reduce  the quality  of  the  foraging  habitat.  As  the  land  is  highly modified  and  representative  of much  of  the farmland in the district loss of 100 ha of this habitat type would not be likely to be significant.  

Species with the ability to disperse through open country are likely to utilise the remnant trees on the proposal site however if clearing of any of the site was required it would not be likely to be significant in terms of restricting fauna movement considering the surrounding matrix. 

Potential introduction and spread of weeds (general) 

The site carries noxious weeds which would require control before and after the proposed works. With the application of weed controls during and following construction, weed  impacts within and off the proposal  site  are not expected  to be  significant. The  spacing between  the PV array  rows would be adequate  to  allow  an  all  terrain  vehicle  to  access  the  site  for  ongoing weed  control  and  pasture renovation, as required. 

Indirect impacts 

Indirect  impacts  occur  when  project  related  actions  affect  species,  populations  or  ecological communities in a manner other than direct loss, usually beyond the footprint of the Proposal. Indirect impacts can include loss of individuals through predation by domestic and/or feral animal, deleterious hydrological  changes  (including  increased  runoff  and  raising  or  lowering  the water  table),  erosion, 

Page 48: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       83 

weed  invasion,  pollution,  trampling,  altered  fire  regimes,  habitat  fragmentation  and  disruption  of wildlife movement corridors.  

Indirect and off‐site impacts relevant to the proposal include:  

• Fauna habitat avoidance and corridor impacts 

• Downstream sedimentation and pollution 

• Effects on fire frequency and impact. 

Fauna habitat avoidance and corridor impacts 

The structure provided by the PV arrays and perimeter fence my deter species from foraging between the PV arrays however they may also increase the habitat value for perching species such as the Flame and Scarlet Robin. Flame Robins were recorded foraging from the south western boundary fence and would be  likely  to use  the PV arrays  (particularly  those on  the edges) as a  surrogate  for  the  fallen timber that they use in a more natural setting. Post construction site usage studies would be valuable to determine the level of site usage by native fauna. 

As the proposal site is largely cleared and representative of the adjacent land, connectivity is unlikely to be compromised by the construction of the PV arrays and perimeter fence.  

The  infrastructure of the solar farm  including the perimeter fence and PV arrays may provide shelter from predators such as foxes and raptors. 

Downstream sedimentation and pollution 

The  proposed  works  have  potential  to  release  sediment  and  pollutants  into  riparian  and  aquatic habitats of Mandagery Creek,  located 200m  to  the west of  the site. These  risks would apply mainly during  the  construction  phase.  This  can  be  effectively managed  onsite  by  installation  of  sediment erosion controls if required. 

A  continuous  grassy  groundcover will  need  to  be  established  and maintained  under  the  array  to maximise  infiltration of module washing water,  reduce  sediment  runoff and  reduce dust during  the operational phase of the project. 

Module washing 

The panels would be periodically washed as required, using a pressure hose and water truck. Washing is expected  to be  infrequent, and  in  response  to particular events  such as a dust  storm. Water  for washing would be obtained  from existing Council supplies. No detergent would be used  for washing the  panels.  The  panel washwater  is  not  expected  to  result  in  pollution  of  local waterways  or  the groundwater resource. 

Effects on fire frequency and impact 

Although there have been  isolated cases of sparks from the back of panels, the risk of this causing a grass fire is considered to be low. Vegetation under the array would be kept low by slashing or sheep grazing. Access tracks would be constructed to each  inverter and around the perimeter of the  farm. This network would serve to contain any fire starting at the array, to protect the array during a wildfire and  to provide  access  for  fire  suppression during  an event. The Proposal  is unlikely  to  significantly affect wildfire frequency in the proposal site. 

Page 49: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       84 

The Suntech modules to be used do not have passed the Underwriters Laboratories standard UL1703 (which includes flammability tests) and are inflammable and do not pose a pollution risk in the event of fire. 

Threatened species and ecological communities 

Assessments of Significance for impacts to the EEC and threatened flora and fauna (listed in Table 6‐2) conclude that, with the adoption of specific mitigation measures and pending follow up spring surveys to confirm the assumptions of the assessment, the proposal is unlikely to have a significant impact on any of the threatened entities.  

The  focus of  the  follow up  surveys would be  to  confirm  the presence or  absence of  the  following threatened species at the site: 

Silky Swainson‐pea (Swainsona sericea) 

Small Purple‐pea (Swainsona recta) 

Austral Toadflax (Thesium australe) 

Should  presence  be  confirmed, management  actions  would  be  incorporated  into  the  proposal  to ensure significant impacts are avoided.  

Offsetting 

An offset plan would be developed prior to any construction impacts and would be based on the final infrastructure  layout.  It would  reflect  the  value of habitat areas  to be  removed or modified by  the proposal. The permanent removal of quality flora and fauna habitat is expected to be minimal, as the infrastructure  footprint  is  comparatively  small  and  areas  of  conservation  significance  have  been mapped  to  allow  infrastructure  placement  to  avoid  them.  This  assessment  considers  that  there  is ample  ability  to  offset  native  vegetation  removal  onsite.  Native  pasture  is  in  varying  condition. Offsetting impacts to native pasture would only be undertaken where it is in moderate‐good condition as defined by the biometric guidelines and considered to provide quality habitat. Offsite offset areas may  be  required  to  achieve  this.  Surveys  and  assessments  conducted  in  spring would  be  used  to determine  the  area  and  locations  of  native  pasture  in moderate  to  good  condition  and  providing quality habitat. 

The  biodiversity  offset  principles  developed  by DECCW would  guide  the  development  of  an Offset Plan. The  final  infrastructure  layout will determine  the precise amount of clearing  required. At  that time, formal agreements would be sought with the affected involved land owners to secure offsetting for areas of habitat permanently removed by the proposal. It appears that, by locating infrastructure in areas of  lesser habitat value, managing offset areas to  improve their biodiversity value for the  life of the project and, viewed in terms of the wider environmental benefits of establishing renewable energy generation  in rural areas, that the proposal can achieve an overall  ‘maintain or  improve biodiversity outcome’. 

6.1.3 Environmental safeguards 

By  identifying  areas  of  high  biodiversity  values  early  in  the  planning  process  and  then  using  this information  to  develop  a  sensitive  layout  design,  the  Proposal  achieves  the  aim  of minimising  any impacts to biodiversity.  In conjunction with a targeted offset plan, that aims to  improve connectivity 

Page 50: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       85 

and habitat values both on  site and  for  the wider  locality,  the Proposal would maintain or  improve biodiversity values. With the effective implementation of the safeguards below, it is considered that in terms  of  the  significance  thresholds  identified  in  the  Draft  Guidelines  for  Threatened  Species Assessment for Part 3A Applications (DEC/DPI 2005) the project would: 

• Be likely to maintain or improve biodiversity values 

• Be  unlikely  to  reduce  the  long‐term  viability  of  a  local  threatened  species  population  or ecological community 

• Be unlikely  to accelerate  the extinction of a species, population or ecological community or place it at risk of extinction 

• Not adversely affect critical habitat. 

 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

1  Flora protection  Avoid  and minimise impact 

A  supplementary  flora  survey during  spring  (November) would be undertaken to confirm the assumptions of the Biodiversity Assessment  (Appendix E),  in areas  including the  western  paddock,  western  access  and  areas identified on  the Biodiversity Constraints map  (Figure 6‐1) that would be impacted by infrastructure. 

Pre‐determination 

CEMP

2  Loss  or modification  of habitat 

Minimise  and offset impact 

An  Offset  Plan  would  be  prepared  by  an  ecologist consistent  with  ‘maintain  or  improve’  principles  for biodiversity  outcomes,  as  set  out  in  the  Biodiversity Assessment.  The  plan  would  be  developed  in consultation with  the  landowner and would operate  for the life of the project. 

Pre‐construction  CEMP

 

3  Infrastructure related biodiversity impacts 

Minimise biodiversity impacts  

The PV array, site access tracks and other  infrastructure should be sited to avoid constraints identified within the Biodiversity  Assessment  constraints  mapping.  These include: 

• The  larger stands of Box‐Gum Woodland across the site 

• Hollow bearing trees 

• Isolated shade trees where possible 

• Native  grassland  and  associated  rock  outcrops in the Western Paddock 

• As  far  as  possible  rock  outcrops  across  the proposal  site  together  with  a  minimum  2.5 metre buffer to avoid shading. 

Design phase  CEMP

4  Infrastructure related biodiversity impacts 

Minimise biodiversity impacts  

Areas  of  high  biodiversity  value  would  be  clearly identified  throughout  construction  and  protected  from the  direct  and  indirect  impacts  of  the  Proposal. Contractors  and  staff  would  be  made  aware  of  the significance and sensitivity of these areas. 

Design phase  CEMP

5  Infrastructure related biodiversity impacts 

Minimise biodiversity impacts  

The  western  paddock  of  the  proposed  solar  farm  site should  be  avoided  if  possible  to  minimise  impacts  to grassy  groundcover  flora  comprising  the  Box‐Gum Woodland EEC.  

Design phase  CEMP

6  Construction impacts 

Minimise biodiversity impacts  

Where security concerns permit perimeter fences should not contain barbed wire, particularly the top strands. If a cycisolated mesh  fence  is  to  be  used  efforts  should  be made to increase the visibility to fast flying parrots. 

Design 

Construction 

CEMP

Page 51: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       86 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

7  Construction impacts 

Minimise biodiversity impacts  

If  used,  and  where  practicable,  power  poles  and overhead  powerlines  will  be  bird‐safe  using  flags  or marker  balls,  large  wire  size  and  wire  and  conductor spacing. 

Design 

Construction 

CEMP

8  Infrastructure related biodiversity impacts 

Minimise biodiversity impacts  

If the removal of any hollow bearing trees was required this activity would be proceeded by a pre clearance check by a qualified ecologist  including anabat survey and stag watching. 

Pre‐construction  CEMP

9  Infrastructure related biodiversity impacts 

Minimise biodiversity impacts  

Works will avoid  impacts  to mature eucalypts wherever possible.  Tree protection  standards  should  comply with Australian  standard AS4970‐2009 Protection of  trees on development sites (Standards Australia, 2009). Wherever practicable,  excavations  and  vehicle/machinery movements  will  occur  outside  the  canopy  dripline  of large eucalypts. 

Design phase 

Construction 

CEMP

10  Construction impacts 

Minimise biodiversity impacts  

Existing farm tracks should be used wherever possible to minimise the number of new roads. 

Construction  CEMP

11  Construction impacts 

Minimise biodiversity impacts  

Where cement is included in cable trench backfill, at least 20 centimetres of cement‐free topsoil will be replaced as the top layer in the backfill. 

Construction  CEMP

12  Construction impacts 

Minimise biodiversity impacts  

Where practicable, whole sods will be  removed with an excavator  where  these  areas  are  well‐vegetated  with dense root systems. Sods will be stored in moist, shaded conditions and replaced following the works. Sod storage time will  be minimised  and  sods  will  be  replaced  in  a manner that maximises the chances of re‐establishment. 

Construction  CEMP

13  Construction impacts 

Minimise biodiversity impacts  

Where  possible,  as  a  precaution,  works  should  be planned  to  avoid  sensitive  times  for  Superb  Parrots  ‐ September to January.  

Construction  CEMP

14  Construction impacts 

Minimise biodiversity impacts  

Excavated  topsoil,  subsoil will be  stored  separately  and replaced  in a manner  that  replicates  the original profile as closely as possible.  

Construction  CEMP

15  Construction impacts 

Minimise biodiversity impacts  

Where  practicable,  grass  surfaces  and  shrubs  will  be retained or restored on infrequently used vehicle routes. 

Construction  CEMP

16  Construction impacts 

Minimise biodiversity impacts  

Site  stabilisation,  rehabilitation  and  revegetation  of  all disturbed areas would be undertaken without delay. 

Construction  CEMP

17  Construction impacts 

Minimise biodiversity impacts  

As  a  general  rule,  disturbed  areas  will  be  used preferentially for vehicle and machinery access, materials laydown,  stockpiling  of  cleared  vegetation  and  the deposition and retrieval of spoil whenever practicable.  

Construction  CEMP

18  Construction impacts 

Minimise biodiversity impacts  

Works will be avoided during, and immediately following heavy  rainfall  events  to  protect  soils  and  vegetation  at the site. 

Construction  CEMP

19  Construction impacts 

Minimise biodiversity impacts  

Weed  /  pathogen  controls  will  be  implemented, including: 

o Machinery  and  vehicles  used  in  construction works will be washed before and after site access to  reduce  the  introduction  and  spread  of weeds and pathogens. 

Construction  CEMP

Page 52: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       87 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

o Laydown sites for excavated spoil, equipment and construction  materials  will  be  weed‐free  or treated for weeds wherever practicable.  

o Weed monitoring will  be  carried  out  at  all  sites after  the  completion  of  construction  works  and ongoing weed control will occur where noxious or invasive  species  are  recorded.  In  particular, monitoring  will  be  undertaken  during  the following  late spring/early summer, and  remedial action taken as required. 

o Sediment  control materials  should  be weed  free (straw bales, geotextiles).  

o Imported materials such as sand and gravel will be sourced from sites which do not show evidence of noxious weeds or Phytophthora infection. 

20  Construction impacts 

Minimise biodiversity impacts  

If  dams  are  removed  during  site  development  works, alternative  watering  points  should  be  established  to compensate  for  their  loss  and maintain  similar  habitat resources for native fauna. 

Construction  CEMP

21  Construction impacts 

Minimise biodiversity impacts  

Any  trench  sections  left  open  for  greater  than  a  day would be  inspected daily, early  in  the morning and any trapped  fauna  removed. The use of  ramps or  ladders  to facilitate trapped fauna escape is recommended. 

Construction  CEMP

22  Construction impacts 

Minimise biodiversity impacts  

Rock  and  log  habitat  removed  during  the  construction phase will be reinstated following the works. 

Construction  CEMP

23  Construction impacts 

Minimise biodiversity impacts  

Where  tree hollows are  required  to be  removed,  these should  be  replaced  by  nest  boxes  of  similar  size  in nearby trees. 

Construction  CEMP

24  Construction impacts 

Minimise biodiversity impacts  

Wherever possible small rock outcrops at the site should be  excluded  from  the  array,  together with  a minimum 2.5 metre buffer to avoid shading. 

Construction  CEMP

25  Operational impacts 

Minimise biodiversity impacts  

A  groundcover management  plan would  be  developed that  would  include  regular  monitoring  of  vegetation cover  and  composition  and  allow  for  adaptive management. This would include: 

o Establishment  of  a  shade  tolerant  perennial groundcover   across  the  cropping and exotic dominated  grazing  paddocks  prior  to  the installation of the PV arrays 

o Advice  from  an  agronomist  in  relation  to preferred  species/varieties,  establishment methods  of  alternative  pastures  and  best practice management.  

o Where  information  is  lacking,  trials  may  be required onsite 

Pre‐construction Construction 

operation 

CEMP 

OEMP 

Page 53: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       88 

SoC  Impact  Objective  Mitigation tasks  Project phase  Auditing 

26  Operational impacts 

Minimise biodiversity impacts  

If  localised  erosion  is  detected,  effective  treatments would be applied without delay, such as hardening with mulch, reseeding and covering with an open weave  jute matting,  gypsum  application  to  improve  structure  and infiltration, protection with geotextile  fabric or  localised flow dispersal and diversion structures. 

Operation  OEMP

27  Operational impacts 

Minimise biodiversity impacts  

The  space  between  the  PV  array  rows  should  be maintained  and  kept  clear  to  enable  access  by  vehicles for  ongoing  weed  control,  and  pasture  renovation  if required. 

Operation  OEMP

28  Operational impacts 

Minimise biodiversity impacts  

Efforts  should  be made  to minimise  disturbance  to  the existing  groundcover  during  construction.  Construction and  maintenance  vehicles  should  not  access  the  site when soils are very wet to minimise soil compaction and disturbance.  

Construction 

Operation 

CEMP

OEMP 

29  Operational impacts 

Minimise biodiversity impacts  

Fencing  along  Molong  Manildra  Road  should  be maintained so as macropods and other large native fauna are not funnelled along the perimeter fence and onto the road  creating  a  traffic  hazard  and  collision  risk  to  the animal. 

Operation  OEMP

30  Operational impacts 

Minimise biodiversity impacts  

Monitoring  of  fauna  site  habitat  usage  pre  and  post construction  is  recommended  but  not  considered essential. 

Operation  OEMP

6.2 VISUAL AMENITY 

6.2.1 Introduction 

The  proposed Manildra  Solar  Farm would  be  a  contrasting  visual  element within  the  existing  rural landscape. The solar farm would potentially attract attention from a range of viewpoints  in the area. As  a  result,  the  visual  assessment  is  recognised  as  being  an  important  component  of  the environmental assessment (EA) process. 

Moir  Landscape  Architecture  were  commissioned  by  the  Proponent  to  prepare  a  Visual  Impact Assessment (VIA) for the proposed Manildra Solar Farm. A comprehensive Visual  Impact Assessment has  been  undertaken  and  is  included  as  Appendix  F  of  this  EA  as  per  the  Director  General’s Requirements (DGR). The key aspects of the visual assessment have been summarised in this chapter of the EA. 

The objectives adopted for the visual assessment are as follows: 

1. To identify and describe the existing visual/landscape environment and to evaluate its current qualities; 

2. An assessment of the site in relation to any landscapes of local or regional significance; 

3. Visibility from the general surrounds including major roads and surrounding residential areas; 

4. Visual impacts associated with any potential development; and 

Page 54: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       89 

5. Proposed mitigation measures  to  reduce  visual  impacts  associated with  any  development within the proposal site. 

Survey work for the study was undertaken during August 2010 using key viewpoints and locations with potential views towards the proposal site. The comprehensive report (Appendix F) details the results of the field work, documents the assessment of the landscape character and visual setting, and makes recommendations concerning measures to mitigate any impacts arising from potential development. 

The method applied to this study involved systematically evaluating the visual environment pertaining to the site and using value judgements based on community responses to scenery. 

The assessment was undertaken in five stages as noted below: 

1. Description of  the  existing  visual  environment,  including  the  identification  and  appraisal of visual catchments/landscape units; 

2. Undertaking  of  a  viewpoint  analysis  to  identify  sites  likely  to  be  affected  by  development within the investigation zone; 

3. Photographic  survey using  a Canon  40D Digitals  SLR with  a  50mm  Fixed  Focal  lens  (80mm 35mm Film SLR equivalent) and a handheld GPS unit to record position and altitude; 

4. Assessment of visual impacts (including reflectivity); and, 

5. Preparation  of  recommendations  for  impact  mitigation  and  suggestions  for  suitable development to maintain the area’s visual quality.  

The purpose of the above methodology  is to reduce the amount of subjectivity entering  into  impact assessment and to provide sufficient data to allow for third party verification of results. A summary of the key aspects of  the Visual  Impact Assessment are summarised  in  the subsequent sections of  this chapter.  

6.2.2 Existing visual environment 

The proposed Manildra Solar Farm  is  located  to  the north east of  the Manildra  township  in central western  New  South Wales.  The  topography  of  the  proposed  solar  farm  site  is  defined  by  slightly undulating, grazing land, generally devoid of native vegetation. The majority of the Site is cleared with tree coverage occurring in sparse patches. 

The  broader  landscape  is  characterised  by  a mosaic  of  agricultural  land with  a  sparse  coverage  of remnant native woodland and riparian vegetation. Creek and natural drainage  lines branch from the Mandagery Creek through the low points of the slightly undulating landscape.  

Landscape character units

The surrounding  landscape was divided  into Landscape Character Units  (LCU), each defined by  their own distinct and recognisable pattern of elements. Representative views of these LCUs are presented in the following figures. 

 

Page 55: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       90 

 

LCU1  Manildra  Town:  The  LCU encompasses  the  land  and  associated infrastructure to the west of Mandagery Creek.  The  land  area  is  predominately residential  with  an  industrial  main street,  associated  with  the  Manildra Grain  Silos.  The  town  is  flat  and vegetation  associated  with  the Mandagery  Creek  creates  a  visual barrier to the north east. 

Figure 6‐11: Manildra Town 

 

LCU2  Manildra  Rural  Residential:  The LCU  encompasses  the  rural/residential development associated with Manildra, located  on  the  eastern  side  of  the Mandagery  Creek.  The  LCU  is characterised  by  a  country  town character.  The  LCU  includes  the  rural residential properties  located along Old Orange  Road,  Orange  Road  and Mandagery Lane.  

Figure 6‐12: Manildra Rural Residential 

 

Page 56: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       91 

LCU3  Open  Pastoral  Land:  The  LCU encompasses  the  typically  open,  rural grazing  land  surrounding  Manildra. Vegetation  consists  of  sparse  coverage of  remnant  woodland  vegetation  and open pastoral land. The land is used for a  number  of  agricultural  pursuits including  grazing,  cropping  and improved pasture. 

Figure 6‐13: Open Pastoral Land 

LCU4 Molong Manildra  Road:  The  LCU includes  the  road  and  associated homesteads  which  run  along  the western perimeter of the proposal site. The  landform  is  slightly undulating and remnant  native  vegetation  follows  the roadside.  

Figure 6‐14: Molong Manildra Road 

Page 57: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       92 

Figure 6‐15: Landscape Character Units 

Page 58: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     93 

6.2.3 Viewpoint analysis 

The  visual  assessment  considers  the  likely  impact  that  development  would  have  on  the  existing landscape  character  and  visual  amenity  by  selecting  prominent  sites,  otherwise  referred  to  as viewpoints.  For  the  purpose  of  the  VIA,  nine  viewpoints  were  selected  on  the  basis  of  where development of the proposal site would be most prominent. This was either based on the degree of exposure or the number of people who are likely to be affected by the development.  

Sites  were  first  selected  by  using  topographical  maps.  This  was  followed  by  field  inspections  to ascertain the visibility from these sites. Further viewpoints were selected by driving or walking around the  site  area.  It  is  important  to  note  that  viewpoints  for  this  study  have  been  taken  only  from accessible public land. As part of the Viewpoint Analysis the Landscape Character and Visual Sensitivity were also assessed  from each viewpoint. The detailed VIA  included  in Appendix F encompasses  the detailed viewpoint description and analysis.

Page 59: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       94 

 

Figure 6‐16: Assessment Viewpoint Locations 

Page 60: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     95 

6.2.4 Photomontages 

Photomontages of the proposed solar  farm were prepared to assist  in the  impact assessment of the proposal, conveying the final visual impact from typical vantage points.  

Photomontages are a  representation of  the solar  farm  that are superimposed onto a photograph of the  site. The process  for generation of  these  images  involves  computer generation of a wire  frame perspective  view  of  the  solar  farm  and  the  topography  from  each  viewpoint.  The  images  that  the photographic simulations are based on have been captured with a Canon 40D SLR digital camera with 50mm lens which closely represents the central field of vision of the human eye.  

It is important to note the photomontages are based on worst case scenario, without the inclusion of mitigation methods. Therefore measures  to mitigate  the  impact of  the solar  farm would  reduce  the impact conveyed in the photomontage.  

A complete collection of  the photomontages are  included  in  the detailed Visual  Impact Assessment included in Appendix F of this report. Examples of these photomontage images are included in Figure 6‐17 to Figure 6‐25 below. These figures have been copied and as a result they are not to scale. 

Figure 6‐17: Existing view towards the site from Molong Manildra Road. 

Figure 6‐18: Photomontage of the site from Molong Manildra Road. 

Figure 6‐19: Photomontage of the site from Molong Manildra Road with screen planting. 

 

Page 61: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     96 

Figure 6‐20: Existing view towards the site from Molong Manildra Road. 

Figure 6‐21: Photomontage of the site from Molong Manildra Road. 

Figure 6‐22: Photomontage of the site from Molong Manildra Road with boundary planting  

Figure 6‐23: Existing view over the site from the Manildra Substation. 

Figure 6‐24: Photomontage of the site from the Manildra Substation. 

Figure 6‐25: Photomontage of the site from the Manildra Substation with boundary planting. 

Page 62: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     97 

6.2.5 Visual impact assessment 

Overview of visual impact 

The nature and scale of the project would create a new landscape and visual environment. This part of the  report will  assess  the  source  and magnitude of development  effects on  the  existing  landscape elements, character and quality in the context of the site and its environs. 

Overall  the  proposed  Manildra  Solar  Farm  would  result  in  impacts  on  the  existing  surrounding environment in terms of landscape and scenic values. The visual impacts associated with the proposal would  vary  depending  on  the  viewing  location.  The  potential  visual  impacts  associated  with  the proposed development are assessed in this section of the report. 

Character of the proposal 

The Solar Panels are relatively low lying, reaching a height of approximately 2 to 3m above the existing ground level. The solar farm is designed as an array of panels arranged in an east‐west direction, facing approximately north on an angle of 30 degrees. The highest visual effect of the PV panels is likely to be seen from the north and south, where the most surface area is visible. Visibility of the solar farm from the east and west would be significantly  lower. The visual  impact  is mostly  likely to be at  its highest during the construction phase. 

Visual impact assessment 

Existing landscape features of the region which assist in the reduction of the visual impact of the Site have been illustrated in the visual impact analysis (Figure 6‐26). 

Riparian vegetation associated with Mandagery Creek to the east of Manildra provides a strong visual screen  for a  large percentage of developed area. The natural  topography prevents views  to  the site from residential properties to the south of the Site associated with Old Orange Road.  

Areas surrounding the proposed development are largely uninhabited parcels of undulating land with a  sparse  coverage  of woodland  vegetation.  The  Site  upon which  the  development  is  proposed  is characterised by an undulating, cleared pastoral land.  

The highest visual impact would be felt from those areas within the immediate vicinity of the proposed development,  in  particular  a  narrow  section  of  Molong  Manildra  Road  as  represented  in  the photomontages. 

The Molong Manildra Road is located approximately 500m to the east at its closest point. Views from Molong Manildra Road are  towards  the western edge of  the proposed development and would be seen as a grey line within the landscape. Due to topography and existing vegetation, views to the site other  than Manildra Molong Road are  restricted  to areas of private  land. No  residences are  located within these vantage areas. 

Page 63: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       98 

 

Figure 6‐26: Visual Impact Map 

Page 64: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     99 

Review of visibility surrounding the site 

Views to the site from Manildra: 

The Manildra Town and associated  residential development are  located approximately 1.2km  south west of the proposal site. The Town is bounded on its eastern edge by the Mandagery Creek, with its associated  vegetation.  The  Riparian Vegetation  creates  a  visual  barrier  between  the  town  and  the proposal site. The proposed Solar Farm would not be visible from the town or associated residential properties.  

Views to the site from the north: 

To  the  north  of  the  Site,  the  land  is  generally  characterised  by  uninhabited  pastoral  land. A  small number  of  homesteads  are  located  to  the  north  of  the  Site.  The  closest  property  is  “Yarran” farmhouse,  from which  the  Site would  be  obscured  by  a  rise  in  topography  between  the  Site  and farmhouse. Viewpoint MASF02 is taken from the property entry.  

The nearest properties north of the Yarran Farmhouse are sited approximately 2.3km north of the Site. A sparse coverage of remnant woodland vegetation and undulating topography prevent views of the Site from these properties. 

Views to the site from the east: 

East of  the Site,  the  landscape  is characterised by uninhabited, undulating grazing  land. The closest residential property  to  the east of  the  Site  is  located  at  a distance of  approximately 2km. The  Site would not be visible from these properties. 

Views to the site from the south: 

The  closest  residences  to  the  south  of  the  Site  are  located  along  Old  Orange  Road.  These  rural residential properties are located approximately 500m from the sites southern boundary. Views from these properties are impeded by a rise in topography south of the Site.   

The  Broken  Hill  Railway  runs  in  an  east‐west  direction  to  the  south  of  the  Site.  The  proposed development  would  not  be  visible  from  passenger  trains  travelling  along  this  road  due  to  the undulating topography and coverage of vegetation north of the railway line. Orange Road follows the same  route  as  the  railway  and  as  a  result  views  to  the  Site  from  the  road would  be  impeded  by topography and vegetation. 

Views to the site from the west: 

Two homesteads are located approximately 600 metres to the west of the Site on the eastern side of the Molong Manildra Road. A combination of the existing roadside vegetation and foreground planting associated with the homesteads buffer views towards the Site.  

Views to the proposal site from residential properties to the east of Manildra, along Mandagery Lane would be  impeded by dense  remnant woodland  vegetation between  the  Site  and  rural properties. Beyond these properties to the east of the Mandagery Creek riparian vegetation creates a visual buffer towards the Site.   

Molong Manildra Road: 

Travelling  in a southern direction along  the Molong Manildra Road  towards Manildra Road, glimpse views towards the proposal site would be visible along a 500m stretch of road approximately 2.6km 

Page 65: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     100 

from the Manildra town centre. Views to the proposal site  in all other sections are restricted due to topography, roadside planting and the distance to the Site.  

Manildra Toogong Road: 

The Manildra Toogong Road  runs  in a north‐south direction  towards Manildra. Travelling along  this road in a northerly direction views to the Site are obscured by the dense riparian vegetation associated with Mandagery Creek. 

Of  the 9  viewpoints  assessed  as  apart of  this VIA,  the proposed  solar  farm development would be visible  from  6  viewpoints.  These  6  viewpoints  have  all  been  assessed  as  having  a moderate  visual impact. Table 6‐3 summarises the visual impact of all 9 viewpoints. 

Table 6‐3: Viewpoint visual impact summary 

VIEWPOINT  LOCATION  VISUAL SENSITIVITY  VISUAL EFFECT  VISUAL IMPACT 

MASF01  North West  corner  of  Proposal site 

     

MASF02  Yarran  Farmhouse,  Molong Manildra Road 

‐  ‐  ‐ 

MASF03  Molong  Manildra  Road‐ Ridgelite 

Moderate  Moderate  Moderate 

MASF04  Paddock  Low  High  Moderate 

MASF05  Paddock  Low  High  Moderate 

MASF06  Molong Manildra Road  Moderate  Moderate  Moderate 

MASF07  Silo East of Substation  Low  High  Moderate 

MASF08  Manildra Substation  Low  High  Moderate 

MASF09  Property  South  of  Mandagery Lane on Molong Manildra Rd 

‐  ‐  ‐ 

Page 66: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010       101 

Figure 6‐27: Zone of Visual Influence (based on topography)

Page 67: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     102 

6.2.6 Reflectivity 

There  is  a  perceived  issue  of  glint  and  glare  surrounding  the  reflectivity  of  the  proposed  PV  solar panels. As  a  result  of  the  perceived  reflection  levels,  there  is  a  concern  of  possible  distractions  to motorists, aircraft and the hazard of eye damage.  

The Poly‐Crystalline Solar Panels proposed for the installation are designed to absorb the suns energy and directly convert  it  to electricity. The PV modules being used  in  the  installation  for  the Manildra Solar Farm absorb approximately 82‐90% of the light received. The Suntech Solar Panels proposed for the Manildra  Solar  Farm  have  been  designed  using  two  anti‐reflective  coatings which  significantly reduce the reflectivity. An innovative method of developing the required metal contact on the face of the solar panel reduces the metal surface area and further reduces any potential glare.  

A number of rural landing grounds are located within close proximity to the area. PV Solar Panels have been  installed  at  a  number  of  airports  in  the  USA,  including  Denver  and  the  Oakland  FedEx International Airport Hub. These precedents and further studies have found that the reflection created would not cause problems for aircraft, particularly at the critical take off and landing stage.  

The  level of glare and  reflectance  from  the PV solar panels are considerably  lower  than  the  level of glare and reflectance of common land surfaces including those surrounding the proposed Solar Farm.  The  PV  panels  would  reflect  approximately  10‐18%  of  energy  which  is  less  than  typical  rural environments which have a reflectivity of approximately 15‐30%. Figure 6‐28, Figure 6‐29 and Figure 6‐30  compare  the  percentage  of  reflected  energy  from  common  reflective  surfaces  to  that  of  the Suntech PV Solar Panels.  

Figure 6‐28: Analysis of typical material reflectivity (Sunpower) 

Page 68: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     103 

Figure 6‐29: Comparative reflection analysis.

Figure 6‐30: Comparative reflection diagram. 

Page 69: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     104 

6.2.7 Impact mitigation methods 

Overview of impact mitigation 

A range of methods for mitigating the visual impact of the proposed development have been identified and  are  outlined  below.  The  recommendations  seek  to  achieve  a  better  visual  integration  of  the proposed Manildra  Solar  Farm  and  the  retention of existing  landscape  character  at both  local,  and regional  scales.  The  mitigation  measures  attempt  to  lessen  the  visual  impact  of  the  proposed development whilst enhancing the visual character of the surrounding environment.  

When site planning the Solar Farm, the design should consider some or all of the following mitigation strategies to lessen the visual impact of the proposal. This is by no means an exhaustive list, however the  adoption  of  these  recommendations  would  assist  considerably  in  ensuring  the  proposal contributes positively to the visual quality and character of the area.  

In  addition  to  the  impact mitigation  strategies  outlined  in  the  following  sections,  a  visual  impact mitigation plan has been prepared and is included as Figure 6‐31 below.  

Construction mitigation 

It  is  likely  the  greatest  visual  impact  would  occur  through  the  construction  stage.  Though  the construction phase would be temporary practical methods should be employed to reduce the impact of this stage. These include but are not limited to the following: 

• Dust reduction throughout the construction process 

• Restoration of any earthworks required for the construction 

• Clearing of existing vegetation is to be kept to a minimum 

Solar panel and associated infrastructure 

Once construction has been completed, the solar  farm would be a relatively  low  lying development, with panels having  a  vertical height of  approximately 2  to 3m  above  ground  level. Due  to  the  low height,  visibility  of  the  solar  panels  can  potentially  be  significantly  reduced  through  a  variety  of mitigation methods.  

Although the PV Solar Panels are the most visible feature of the landscape, a considerable amount of associated infrastructure is to be included in the proposal. This infrastructure associated with the solar panels is outlines in the project proposal section of this report. Methods of mitigation which would be incorporated into the project include: 

• Colour of above ground infrastructure to be sympathetic to the landscape character 

• Underground cabling to be utilised where possible  

• The design and  location of ancillary works are to  incorporate measures which would reduce the visual impact 

Landscaping and visual screening 

Visual  screen planting  is a beneficial mitigation method used  to assist  in  the  reduction of  the Solar Farm’s  visual  impact.  Visual  screen  planting  can  be  undertaken  in  the  form  of  boundary  planting around the solar farm, foreground planting at affected viewpoints and residential tree planting.  

Page 70: 2.5.1 Construction and commissioning

Manildra Solar Farm Environmental Assessment 

 

4 November 2010     105 

The existing remnant woodland vegetation contributes significantly to the character of the area. The selection  of  endemic  species  for  use  as  screen  planting  would  enhance  the  existing  landscape character,  and be  a  seen  as  a  continuation of  the  existing  vegetation.  This planting would be best implemented  in areas where natural vegetation has been  removed  for access  roads and agricultural activity.  

To assist  in concealing the proposal site from areas with a visual  impact, screen planting  is proposed along  the  boundary  edges  of  the  proposed  development.  Boundary  planting  is  proposed  to  be undertaken along the northern, western and southern perimeters of the proposed solar farm. Screen planting  along  these  boundaries  would  ensure  visibility  is  restricted  from  roads  and  nearby homesteads.  

Roadside planting along the eastern edge of Molong Manildra Road is an additional mitigation method proposed to ensure views from the road are fragmented. Planting along the roadside would be seen as a  continuation  of  the  existing  roadside  vegetation  and  would  reinforce  the  existing  landscape character.  

In  areas  where  additional  screen  planting  is  required,  the  proposed  solar  farm  can  be  screened through the implementation of foreground planting around areas affected. Amelioration of the visual impact from homesteads within close proximity to the proposed development should be undertaken in consultation with the relevant land owners. 

Proposed visual  impact mitigation  in the form of visual screen planting has been suggested  in Figure 6‐31. 

Visual opportunities: 

The proposed Manildra Solar Farm is a flagship development for renewable energy which, due to the relatively  large  scale  and  new  technology,  is  bound  to  be  of  interest  to  viewers.  There  are opportunities for the provision of educational viewing areas at various locations around the site.  The integration  of  a  viewing  area  where  visitors  would  be  able  to  safely  view  the  solar  farm  and surrounding landscape would be a positive attribute to the development. Combined with interpretive signage these viewing areas would provide insight into the function, output and benefits of large scale solar farms. 

An  area  on  the  southern  edge  of  the  Site  has  been  identified  as  a  potential  location  for  a  public viewpoint due  to  the expansive views over  the proposed  solar  farm  site. The public viewing area  is identified in Figure 6‐31on the following page.