Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
?TNSTRLY 6P[L]_XPY_ =Q F]LY^[Z]_L_TZY
.*))4 "%#&($#
D7CG<E<F<A@ @G?47D 6G7 63F7 F<?7 6G7
?6AF BDA=75F ?3@397D =A4 @G?47D "=@# 5A@FDA> E75F<A@ "5E#
67E5D<BF<A@
=3?D @B?942D =0>064B. 5SPNV LWW T_PX^ _Z MP TYNW`OPO
TY&I;<F7 1 D7CG<D76
$$ 1 ABF<A@3>
5SPNV _SP L[[]Z[]TL_P FTP] TY _SP MZc MPWZb
2?>CE<D0>D. B]ZaTOP ZYWd NSPNVPO T_PX^ MPWZb TY
[]Z[Z^LW >63; /==871/083# (3?@ -/8A3 ?1<>7;5 1>7@3>7/ 7? 87?@32
?3=/>/@38C 7; @63 +)*$
!!'8<276*4 2<.5; *9. -.<.9526.- +? <1. &$') (973.,< &*6*0.9#
D84B * #"$#)%))) & "%,)%)))$
D84B 88 #"%,)%)))&"*%&))%)))$
D84B 888 #/"*%&))%)))$
GYOP]^_LYOTYR ZQ EP]aTNP $$
9RRSZFXNSRW
A]RLYTeL_TZYLW 5SL]_
C`LWTQTNL_TZY^ ZQ FPLX
C`LWT_d 3^^`]LYNP(C`LWT_d 5ZY_]ZW $$
<TIGYOTS. FSP [P]NPY_LRP ZQ bZ]V [P]QZ]XPO TY ?TNSTRLY bTWW MP `^PO QZ] LWW ^PWPN_TZY^ `YWP^^ _SP []ZUPN_ T^ QZ] ZY&^T_P TY^[PN_TZY Z] ^`]aPd LN_TaT_TP^% _SPY WZNL_TZY ^SZ`WO MP ^NZ]PO `^TYR _SP OT^_LYNP Q]ZX _SP NZY^`W_LY_ ZQQTNP _Z _SP ZY&^T_P TY^[PN_TZY Z] ^`]aPd LN_TaT_d'
@(3 @(3 B]P^PY_L_TZY $$
@(3 @(3 FPNSYTNLW B]Z[Z^LW "TQ B]P^PY_L_TZY T^ ]P\`T]PO#
/ [LRP^ "?6AF 8Z]X^ YZ_ NZ`Y_PO#
FZ_LW XLcTX`X [LRP^ QZ] D8B STY OSIQZJOSM PK^ UKWXTSSKQ WKXZRKX' DP^`XP^ WTXT_PO _Z + [LRP^ [P] VPd ^_LQQ [P]^ZYYPW'
@B?@?C0< 0>3 183 C744D 4"=08< 033B4CC _ XOZ_&]Q[&]P^[ZY^P2XTNSTRLY'RZa
64>4B0< 8>5?B=0D8?>
3Yd \`P^_TZY^ ]PWL_TaP _Z _SP ^NZ[P ZQ ^P]aTNP^ X`^_ MP ^`MXT__PO Md P&XLTW _Z _SP ?6AF B]ZUPN_ ?LYLRP]' C`P^_TZY^ X`^_ MP ]PNPTaPO Md _SP B]ZUPN_ ?LYLRP] L_ WPL^_ QTaP ".# bZ]VTYR OLd^ []TZ] _Z _SP O`P OL_P LYO _TXP ^[PNTQTPO LMZaP' 3WW \`P^_TZY^ LYO LY^bP]^ bTWW MP [WLNPO ZY _SP ?6AF bPM^T_P L^ ^ZZY L^ [Z^^TMWP LQ_P] ]PNPT[_ ZQ _SP \`P^_TZY^% LYO L_ WPL^_ _S]PP ",# OLd^ []TZ] _Z _SP D8B O`P OL_P OPLOWTYP' FSP YLXP^ ZQ aPYOZ]^ ^`MXT__TYR \`P^_TZY^ bTWW YZ_ MP OT^NWZ^PO'
?6AF T^ LY P\`LW Z[[Z]_`YT_d PX[WZdP] LYO ?6AF 647 QT]X^ L]P PYNZ`]LRPO _Z L[[Wd' FSP [L]_TNT[L_TYR 647 QT]X% L^ N`]]PY_Wd NP]_TQTPO Md ?6AFi^ AQQTNP ZQ 7\`LW A[[Z]_`YT_d% ^SLWW MP WT^_PO TY _SP B]Z[Z^LW'
=3?D 5?B=C B4AE8B43 0C @0BD ?5 @B?@?C0< CE1=8CC8?>
,*))3 f DP\`P^_ QZ] B]Z[Z^LW 5ZaP] ESPP_ ,*))9 f 5ZY^`W_LY_ 6L_L LYO ETRYL_`]P ESPP_ "DP\`T]PO >FI 8CC >AIDJ G=I>FIDAE? EFE$GI=HL8CA>A=< J=IMA;=J FE K@AJ GIFB=;K%#
#DNKXK LTWRX GWK STY OSIQZJKJ OS YNK UWTUTXGQ RG]ORZR UGMK ITZSY'$
@(3
@(3 @(3
+ TFLJW ";5<@ 7SVQW RSX HSYRXJI# >JWYQJW [NPP SRP]
GJ FHHJTXJI KSV 3JWX BFPYJ ?JPJHXNSRW'
@MJ 4SRWYPXFRXW [NPP VJHJNZJ FR J%QFNP VJTP]'RSXNKNHFXNSR KVSQ ;5<@ [MJR XMJ TVSTSWFP NW VJHJNZJI& =PJFWJ VJXFNR F HST] SK XMNW J%QFNP FW TVSSK XMFX XMJ TVSTSWFP [FW VJHJNZJI SR XNQJ& 4SRWYPXFRXW FVJ VJWTSRWNGPJ KSV JRWYVNRL XMFX ;5<@ VJHJNZJW XMJTVSTSWFP SR XNQJ&
$ 4SRXFHX 4SRXVFHX ?JVZNHJW 5NZNWNSR NQQJINFXJP] FX -)/%+/+%,.0( NK ]SY IS RSX LJX FR FYXS VJWTSRWJ&
BLRP * ZQ +
")!$(!'#&% 5?B @B?@?C0<
*- [LRP^ "?6AF %Z]X^ YZ_ NZ`Y_PO#
2742;<8CD D? 34C86>0D4 0B40C ?5
2765 05/06/19 noon est
Kyle Rudlaff 204883EPE 80024(80072,80111)
I-94 and M-40 Interchange Reconstruction Study (PEL)
?6AF .*))4 "%#&($# */53 + ZQ +
FSP ?TNSTRLY 6P[L]_XPY_ ZQ F]LY^[Z]_L_TZY "?6AF# T^ ^PPVTYR []ZQP^^TZYLW ^P]aTNP^ QZ] _SP []ZUPN_ NZY_LTYPO TY _SP L__LNSPO ^NZ[P ZQ ^P]aTNP^'
<Q dZ`] QT]X T^ TY_P]P^_PO TY []ZaTOTYR ^P]aTNP^% [WPL^P TYOTNL_P dZ`] TY_P]P^_ Md ^`MXT__TYR L B]Z[Z^LW% B]Z[Z^LW(4TO ESPP_ Z] 4TO ESPP_ L^ TYOTNL_PO MPWZb' FSP OZN`XPY_^ X`^_ MP -.=.478.- *6- ^`MXT__PO TY LNNZ]OLYNP bT_S _SP WL_P^_ -FY^`W_LY_(
HPYOZ] EPWPN_TZY 9`TOPWTYP^ QZ] EP]aTNP^ 5ZY_]LN_^$h
B5@ C@428582 8>5?B=0D8?>
7@9<@77D<@9 E7DH<57E 4GD73G A8 FD3@EBADF3F<A@ B>3@@<@9 AF;7D
F;7 E7DH<57 I3E BAEF76 A@ F;7 3@F<5<B3F76 CG3DF7D>J D7CG7EFE 8AD BDABAE3>E
@A J7E 63F76 KKKKKKKKKKKKKKKKKKKK F;DAG9; KKKKKEEKKKKKKKKKKK
@WKVZGQOLOKJ CKW[OIKX f EPP _SP L__LNSPO ENZ[P ZQ
EP]aTNP^ QZ] ]P\`T]PO B]P\`LWTQTNL_TZY 5WL^^TQTNL_TZY^'
>TS&@WKVZGQOLOKJ CKW[OIKX f <Q ^PWPN_PO% _SP aPYOZ] X`^_ XLVP ^`]P _SL_ N`]]PY_ QTYLYNTLW TYQZ]XL_TZY% TYNW`OTYR WLMZ] ]L_P^% ZaP]SPLO NZX[`_L_TZY^% LYO QTYLYNTLW ^_L_PXPY_^% T^ ZY QTWP bT_S ?6AFi^ AQQTNP ZQ 5FDDAJJAFE ,L<AKJ#FST^ TYQZ]XL_TZY X`^_ MP ZY QTWP QZ] _SP GIAD= M=E<FI 8E<LWW ^`M aPYOZ]^ ^Z _SL_ _SP NZY_]LN_ bTWW YZ_ 9= <=C8O=<% '583 &%$$( 09 8,7<08,+ >0;/ 685659)2 -58 )22 -0839 6,8-58304. 454"68,7<)20-0,+ 9,8=0*,9 54 ;/09 6851,*;#
5TW GQQ AZGQOLOIGYOTSX 1GXKJ CKQKIYOTSX% _SP ^PWPN_TZY _PLX bTWW ]PaTPb _SP TYQZ]XL_TZY ^`MXT__PO LYO bTWW ^PWPN_ _SP QT]X NZY^TOP]PO XZ^_ \`LWTQTPO _Z [P]QZ]X _SP ^P]aTNP^ ML^PO ZY _SP []Z[Z^LW^' FSP ^PWPN_PO QT]X bTWW MP L^VPO _Z []P[L]P L []TNPO []Z[Z^LW' @PRZ_TL_TZY^ bTWW MP NZYO`N_PO bT_S _SP QT]X ^PWPN_PO'
5TW G ITXY UQZX LO]KJ LKK ITSYWGIY% _SP ^PWPN_PO aPYOZ] X`^_ SLaP L NZ^_ LNNZ`Y_TYR ^d^_PX _Z ^`[[Z]_ L NZ^_ [W`^ QTcPO QPP NZY_]LN_' FST^ _d[P ZQ ^d^_PX SL^ L UZM&Z]OP] NZ^_ LNNZ`Y_TYR ^d^_PX QZ] _SP ]PNZ]OTYR LYO LNN`X`WL_TZY ZQ NZ^_^ TYN`]]PO `YOP] T_^ NZY_]LN_^' 7LNS []ZUPN_ T^ L^^TRYPO L UZM Y`XMP] ^Z _SL_ NZ^_^ XLd MP ^PR]PRL_PO LYO LNN`X`WL_PO TY _SP aPYOZ]i^ UZM&Z]OP] LNNZ`Y_TYR ^d^_PX'
AZGQOLOIGYOTS 1GXKJ CKQKIYOTS ( <T\ 1OJ f G^P 5ZY^`W_LY_(HPYOZ] EPWPN_TZY 9`TOPWTYP^' EPP 4TO ESPP_ TY^_]`N_TZY^ QZ]
LOOT_TZYLW TYQZ]XL_TZY'
8Z] C`LWTQTNL_TZY DPaTPb(>Zb 4TO ^PWPN_TZY^% _SP ^PWPN_TZY _PLX bTWW ]PaTPb _SP []Z[Z^LW^ ^`MXT__PO' FSP aPYOZ] _SL_ SL^ XP_ P^_LMWT^SPO \`LWTQTNL_TZY _S]P^SZWO LYO bT_S _SP WZbP^_ MTO bTWW MP ^PWPN_PO'
1KXY FGQZK f G^P 5ZY^`W_LY_(HPYOZ] EPWPN_TZY 9`TOPWTYP^% EPP 4TO ESPP_ <Y^_]`N_TZY^ MPWZb QZ] LOOT_TZYLW TYQZ]XL_TZY'
FSP MTO LXZ`Y_ T^ L NZX[ZYPY_ ZQ _SP _Z_LW []Z[Z^LW ^NZ]P% YZ_ _SP OP_P]XTYTYR QLN_Z] ZQ _SP ^PWPN_TZY'
<T\ 1OJ "YZ \`LWTQTNL_TZY^ ]PaTPb ]P\`T]PO f YZ []Z[Z^LW ]P\`T]PO'#
183 C744D 8>CDBE2D8?>C
Q]ZX NZY^TOP]L_TZY# &$') 9.;.9=.; <1. 9201< <7 9.3.,< *6? *6- *44 +2-;'
?6AF LYO 3575 N]PL_PO L BL]_YP]^ST[ 5SL]_P] 3R]PPXPY_ bSTNS P^_LMWT^SP^ R`TOPWTYP^ _Z L^^T^_ ?6AF LYO 5ZY^`W_LY_^ TY
^`NNP^^Q`W [L]_YP]TYR' 4Z_S _SP 5ZY^`W_LY_ LYO ?6AF B]ZUPN_ ?LYLRP] L]P ]PXTYOPO _Z ]PaTPb _SP ()+)#
,*-/.0?A<3?@67> )60?A3? (5?33;3<A 0<2 0?3 0@832 A= 4=99=C 099 1=;;B<710A7=<@" 7@@B3@ ?3@=9BA7=< 0<2 =A63? >?=132B?3@
0<2 5`TOLYNPi^ 1=<A07<32 A63?37<$
,<0654510;587 #0932 .3631;587 $ 6J= -FEJLCK8EK&7=E<FI 4=C=;KAFE 0LA<=CAE=J%
+"-/*%-.'(+ $'"-/%- "&-%%)%*/
4TO ESPP_"^# L]P WZNL_PO L_ _SP PYO ZQ _SP ENZ[P ZQ EP]aTNP^' E`MXT_ MTO ^SPP_"^# bT_S _SP []Z[Z^LW% _Z _SP P"XLTW LOO]P^^0
;5<@%>7"&>P^[ZY^P2XTNSTRLY'RZa' 8LTW`]P _Z NZX[Wd bT_S _ST^ []ZNPO`]P XLd ]P^`W_ TY dZ`] MTO MPTYR ]PUPN_PO /975
01/01/19 03/31/19
PROPOSAL REQUIREMENTS
Proposals must be submitted for this project electronically. Proposal submittal requirements are
listed in PART IV – INSTRUCTION FOR SUBMITTING PROPOSALS
at the following link Selection Guidelines for Service Contracts
FINANCIAL REQUIREMENTS FOR NON-PREQUALIFIED VENDORS
Financial Requirements for Non‐Prequalified Consultants/Vendors
E-VERIFY REQUIREMENTS
E-Verify is an Internet based system that allows an employer, using information reported on an
employee’s Form I-9, Employment Eligibility Verification, to determine the eligibility of that
employee to work in the United States. There is no charge to employers to use E-Verify. The E-
Verify system is operated by the Department of Homeland Security (DHS) in partnership with the
Social Security Administration. E-Verify is available in Spanish.
The State of Michigan is requiring, under Public Act 200 of 2012, Section 381, that as a condition
of each contract or subcontract for construction, maintenance, or engineering services that the pre-
qualified contractor or subcontractor agree to use the E-Verify system to verify that all persons
hired during the contract term by the contractor or subcontractor are legally present and authorized
to work in the United States.
Information on registration for and use of the E-Verify program can be obtained via the Internet at
the DHS Web site: http://www.dhs.gov/E-Verify.
The documentation supporting the usage of the E-Verify system must be maintained by each
consultant and be made available to MDOT upon request.
It is the responsibility of the prime consultant to include the E-Verify requirement documented in
this NOTIFICATION in all tiers of subcontracts.
DIGITAL SIGNATURE OF CONTRACTS
On January 4, 2018, Contract Services Division implemented the use of CoSign as the exclusive
software for digitally signing all consultant contracts and consultant contract related documents.
All other digital signing methods are no longer accepted.
Prior to using CoSign, all external partners must apply for a free digital signature user account by
submitting a MDOT Digital Signature Certificate Request Form.
MDOT INSURANCE UPDATED 3.9.17
At a minimum, the insurance types and limits identified below, may be required from the selected
consultant, prior to contract award.
Required Limits Additional Requirements
Commercial General Liability Insurance
Minimal Limits:
$1,000,000 Each Occurrence Limit
$1,000,000 Personal & Advertising Injury Limit
$2,000,000 General Aggregate Limit
$2,000,000 Products/Completed Operations
Consultants must have their policy endorsed
to add “the State of Michigan, its
departments, divisions, agencies, offices,
commissions, officers, employees, and
agents” as additional insureds
Automobile Liability Insurance
Minimal Limits:
$1,000,000 Per Occurrence
Workers' Compensation Insurance
Minimal Limits:
Coverage according to applicable laws
governing work activities.
Waiver of subrogation, except where waiver is
prohibited by law.
Employers Liability Insurance
Minimal Limits:
$500,000 Each Accident
$500,000 Each Employee by Disease
$500,000 Aggregate Disease
Professional Liability (Errors and Omissions) Insurance
Minimal Limits:
$1,000,000 Per Claim
The Insurer shall provide at least thirty (30) days written notice of cancellation. The Prime Consultant
will be responsible to verify subconsultant(s) compliance with MDOT’s insurance requirements.
1 Final Posted Scope: 4/22/2019
Michigan Department of Transportation
SCOPE OF SERVICE
FOR
DESIGN SERVICES
Road and Bridge Scoping
CONTROL SECTION(S): 80024 (80072, 80111)
JOB NUMBER(S): 204883EPE
PROJECT LOCATION:
The project is located on I-94 from 40th Street easterly to 1.2 miles east of M-40 and on M-40
from 1.1 miles south of I-94 northerly to Michigan Ave. (Red Arrow Hwy) in Antwerp
Township and the village of Paw Paw, Van Buren County.
The project length is 3.5 miles on I-94 and 1.9 miles on M-40.
PROJECT DESCRIPTION:
Provide road and bridge scoping service for reconstruction of the M-40 at I-94 bridge (S03 of
80024) and interchange, pavement improvement on I-94 EB and M-40, bridge scoping for
rehabilitation of I-94 EB & WB over South Branch of Paw Paw River (B01-3&4 of 80024), M-
40 over East Branch of Paw Paw River (B01 of 80072), M-40 over Maple Lake Inlet, (C01 of
80072), I-94 over Three Mile Lake Drain (C02 of 80024), and M-40 over Martin Drain (C01 of
80111).
Develop improvement alternatives, bridge in-depth inspections, bridge scoping, drainage video
inspection, interchange traffic operational analysis, safety analysis, Data Driven Safety Analysis
(DDSA) of alternatives, stakeholder engagement, and reporting in the Planning and
Environmental Linkage (PEL) format are to be completed in this service.
ProjectWise Documents
ANTICIPATED SERVICE START DATE:
June 20, 2019
ANTICIPATED SERVICE COMPLETION DATE:
September 30, 2020
DBE PARTICIPATION REQUIREMENT: N.A
PRIMARY PREQUALIFICATION CLASSIFICATION(S):
Design: Project Development Studies
SECONDARY PREQUALIFICATION CLASSIFICATION(S):
2 Final Posted Scope: 4/22/2019
Design – Bridges
Design – Bridges: Scoping
Design – Bridges: Safety Inspection
Design – Hydraulics I
Design – Roadway: Intermediate
Design – Traffic: Capacity & Geometric Analysis
Design – Traffic: Safety Studies
Design – Traffic: Signal Operations
Design – Traffic: Work Zone Mobility and Safety
Design – Utilities: Municipal
PREFERRED QUALIFICATIONS AND CRITERIA (FOR NON-CLASSIFIED
SERVICES):
1) UTILITY COORDINATION: MDOT shall be responsible for project Utility
Coordination.
2) Bridge Scoping Work: Refer to ATTACHMENT A, BRIDGE SCOPING for
qualifications related to bridge and culvert inspection and scoping.
MDOT PROJECT ENGINEER MANAGER:
Kyle Rudlaff, Pavement Management Engineer
Southwest Region Office
1501 E. Kilgore Road
Phone: 269-337-3928
E-mail: [email protected]
CONSTRUCTION COST:
A. The approximate amount for year 2024 construction cost:
1. Road work – I-94 EB HMA overlay $ 10,000,000
2. Road work – I-94 at M-40 interchange $ 10,000,000
3. Road work - M-40 rehabilitation $ 7,000,000
4. Work on seven structures $ 13,000,000
Year 2025 approximate construction amount: $ 40,000,000
B. The estimated cost of real estate is: $ 25,000
3 Final Posted Scope: 4/22/2019
REQUIRED MDOT GUIDELINES AND STANDARDS:
Work shall conform to current MDOT, FHWA, and AASHTO practices, guidelines, policies,
and standards (i.e., Road Design Manual, Standard Plans, Published MDOT Design Advisories,
Drainage Manual, Roadside Design Guide, A Policy on Geometric Design of Highways and
Streets, Michigan Manual of Uniform Traffic Control Devices, etc.).
The Consultant is required to use the MDOT Current Version of Bentley Microstation/GEOPAK
or PowerGEOPAK (published at Section 2.2.2 of the Design Submittal Requirements) with the
current MDOT workspace (published at Section 2.2.1 of the Design Submittal Requirements).
3D Models are required for all applicable projects. See Chapter 2 of the Design Submittal
Requirements for a complete listing of applicable projects. The consultant shall comply with all
MDOT CADD standards and file naming conventions.
MISCELLANEOUS INFORMATION:
A. The project schedule contains an interim cost estimate. This cost estimate for
improvement alternatives must be advanced to completion with the best information
available prior to the completion of other related scoping progress or report steps. This
cost information is vital to the Southwest Region’s annual selection and documentation of
year 2025 proposed projects. The interim cost estimates are considered separate tasks
detached from progress towards the finished scoping report. Subsequent changes and
refinements to the assumptions made at these estimate events are expected and not
considered additional service.
B. The reference to Bentley Microstation under “Required MDOT Guidelines and
Standards” applies to the Soil Boring/Core Sheets to be provided in the requested service.
No other Microstation products are specifically required, but standard conventions apply
to any other Microstation files that are created with this service.
MDOT RESPONSIBILITIES:
A. Collect traffic counts.
B. Provide crash information.
C. Issue any environmental resource content and/or permit information to be included in
the report documentation.
D. Provide existing utility information. Coordinate any necessary utility communication or
meetings.
E. Provide preliminary pavement designs.
4 Final Posted Scope: 4/22/2019
F. Subsequent to scoping progress, select bridge work to be estimated.
G. Schedule project related meetings:
1. Base Scoping Report & Kick-Off Meeting
2. Interim Estimate Meeting
3. Stakeholder Engagement Meetings
4. Bridge Scoping Results Meeting
5. Road & Bridge Scoping Progress Meetings
6. Public Information and Input Events
7. Preliminary Scoping Report
H. Furnish pertinent reference materials.
I. Furnish prints of old plans of the area. The collection of old plans is posted to the
MDOT ProjectWise RFP folder:
pw:\\HCV591PWISPAA01.ngds.state.mi.us:MDOTProjectWise\Documents\External
J. Provide existing bridge and culvert inspection reports.
K. Provide access to MiBRIDGE inspection program and assign bridges as necessary.
CONSULTANT RESPONSIBILITIES:
The Consultant must adhere to all applicable OSHA and MIOSHA safety standards, including
the appropriate traffic signs for the activities and conditions for this job and perform field
operations in accordance with the Department’s Personal Protective Equipment (PPE) policy as
stated in the MDOT Guidance Document #10118.
Meet with the MDOT Project Manager to review project, location of data sources and contact
persons, and review relevant MDOT operations. The Consultant shall review and clarify project
issues, data needs and availability, and the sequence of events and team meetings that are
essential to complete the design by the project plan completion date. Attention shall be given to
critical target dates that may require a large lead time, such as Railroad coordination
requirements, utility conflict resolution, local agency meetings, etc.
5 Final Posted Scope: 4/22/2019
A. Perform the following duties summarized by service prequalification:
Prequalification Service Performance
Design: Project
Development Studies
Perform selection of interchange alternative,
selection of road and bridge treatments, and
reporting according to the Planning and
Environmental Linkage (PEL) process.
Design – Bridges Develop bridge replacement concept.
Design – Bridges
Scoping
Develop concepts for bridge treatments.
Design – Bridges:
Safety Inspections
Provide bridge safety inspection service on all
structures listed in the project description.
Design – Hydraulics
Evaluate drainage system condition, repair
options, and improvements.
Design – Roadway:
Intermediate
Developing and Cost estimating alternatives,
and Reporting .
Design – Traffic:
Capacity & Geometric
Analysis
Provide traffic models and analysis for M-40
interchange alternatives.
Design – Traffic:
Safety Studies
Perform crash analysis as described in
Attachment F and DDSA of interchange
alternatives.
Design – Traffic:
Signal Operations
Evaluate signal components of interchange
alternatives and other M-40 signal work.
Design – Utilities:
Municipal
Compile information and report on
watermain, sanitary, and other utility
considerations impacted by improvement
alternatives.
Design – Traffic: Work
Zone Mobility and
Safety
Diagram, describe, and cost estimate
construction staging of work. Increase
concept detail with refinement of alternatives.
B. Provide Data Driven Safety Analysis (DDSA) for all refined alternatives brought
forward to the public for consideration. The DDSA should utilize at least one of
the following for alternatives analysis tools: The Enhanced Interchange Safety
Analyst Tool (iSATe), Interactive Highway Safety Design Model (IHSDM) or the
Michigan Highway Safety Manual (HSM) Spreadsheet. Develop benefit / cost
ratios for alternatives from State of Michigan data. Perform iterations of analysis
as necessary to optimize safety performance of alternatives.
6 Final Posted Scope: 4/22/2019
C. Post existing utility locations to plan diagrams as provided by MDOT and track
conflicts with improvement alternatives using a utility conflict matrix form.
Complete Watermain Study documentation for Watermain locations within the
right-of-way. The Utility Conflict Matrix (UCM) is located on the
http://www.trb.org/Main/Blurbs/166731.aspx website under Training materials >
Prototype 1 – Stand-alone UCM.
D. Maintain with updates and comments the drainage table provided by MDOT that
identifies each sewer and culvert by size, location, material and concept treatment.
Perform storm pipe and culvert video inspection as indicated on the marked
inventory table. There is no cleaning request. Inspect obstructed pipes until
blockage and advance to next pipe location. Perform panoramic image scans of
indicated 25 drainage structures. See ATTACHMENT H for details.
E. Create plan diagrams that highlight proposed work features and Right-of-Way
impacts for the length of the project. Overlay aerial images with graphics if
desirable. Prepare typical cross sections and details to illustrate unique project
features. Provide construction staging typical sections and plan diagrams to
illustrate concepts as described in ATTACHMENT E.
F. Use MDOT provided counts to create traffic operation modeling from the M-40
Walmart entrance northerly through the Ampey Road intersection for interchange
traffic operational alternatives requested by MDOT. Differing lane configurations
of M-40 are to be analyzed and operational levels of service forecasted.
G. Perform high level cost estimating for comparing different road and bridge
treatments and each interchange alternative. Increase the cost estimating detail
for the leading improvement alternatives at the preliminary scoping step.
H. Perform bridge scoping as described in ATTACHMENT A. Provide a new
structure concepts for each M-40 over I-94 interchange alternative.
I. Calculate work zone user delays as determined necessary for making comparisons
between construction of different alternatives or between the use of different
staging concepts.
J. Maintain traffic during Consultant field services on I-94 and M-40 as described in
ATTACHMENT G. Consultant traffic control is required for lane closures to
inspect the top and bottom of each lane on each bridge deck except the top side of
interior lanes on the M-40 over I-94 bridge. Consultant traffic control is required
for storm sewer video inspection and bridge scoping. Additionally Provide one
portable changeable message sign (PCMS) along M-40 near the interchange for
three days prior to each of the two public open houses for publicizing the event.
7 Final Posted Scope: 4/22/2019
K. Complete MDOT Form 0595 – Road Scoping Checklist.
L. Produce illustrations of alternatives and simplified illustrations and summaries of
work for stakeholder and public input meetings.
M. Solicit from stakeholders and the public crash experiences and suggestion for
improvement. Produce crash maps and illustrate crash reduction ideas of similar
type that would be produced for an Road Safety Audit. Depict described
problems and potential solutions in a dedicated area of the study report.
Additionally perform crash analysis as described in ATTACHMENT F.
N. Compute and verify all estimate quantities.
O. Provide solution concepts to unique problems that may arise during the design of
this project.
P. Maintain a Design Project Record in ProjectWise, which includes a history of
significant events (changes, comments, etc.) which influenced the development of
the products, dates of submittals and receipt of information.
Q. The Consultant shall prepare a simplified CPM network for the construction of
this project.
R. The Consultant representative shall record the minutes and submit in ProjectWise
(in PDF format), for all project related meetings to the MDOT Project Manager
within two weeks of the meeting. The Consultant shall also distribute the minutes
to all meeting attendees.
S. The Consultant will provide to MDOT, by entering into MDOT ProjectWise at
the scheduled submittal dates, electronic documents (in PDF format) of the
required set materials for distribution by MDOT in advance of all meetings.
T. Attend any project-related meetings as directed by the MDOT Project Manager.
U. The MDOT Project Manager shall be the official MDOT contact person for the
Consultant and shall be made aware of all communications regarding this
project. The Consultant must either address or send a copy of all correspondence
to the MDOT Project Manager. This includes all Subcontractor correspondence
and verbal contact records.
V. The Consultant shall contact the MDOT Project Manager whenever discoveries or
design alternatives have the potential to require changes in the scope, limits,
quantities, costs, or right-of-way of the project.
8 Final Posted Scope: 4/22/2019
W. The Consultant shall be responsible for obtaining up to date access permits and
pertinent information for tasks in MDOT Right of Way (ROW).
This information can be obtained through the, Utilities/Permits Section,
Development Services Division.
X. On the first of each month, the Consultant Project Manager shall submit in
ProjectWise a monthly project progress report to the Project Manager.
ATTACHMENT D contains a sample format.
DELIVERABLES:
The Consultant shall enter in MDOT ProjectWise, in the appropriate folders all electronic files
associated with the project in their native format (spreadsheets, CADD files, GEOPAK files,
Roadway Designer Templates etc.) as directed by the MDOT Project Manager.
Stand Alone Proposal Estimator’s Worksheet (SAPW) shall be used to generate the txt and xml
files necessary for import into the Trns*port bid letting software. The SAPW files shall be
entered into MDOT ProjectWise in the appropriate folder. Spreadsheet files that show the
derivation of work item quantities in the cost estimate must be provided with all cost estimate
submissions.
BASE SCOPING MATERIALS
This report includes evaluation of existing geometric elements, key roadway features, and ideas
on the best improvements to consider making in the next improvement project. Briefly describe
the approach that will be taken to accomplish the requested service. Forecast progress on
interchange analysis. Assemble base scoping materials and distribute prior to the Kick-Off
meeting. The CONSULTANT makes a 20 minute presentation at the Kick-Off meeting that
features project highlights. The Kick-Off meeting is listed in the Scoping Schedule. Prior to this
meeting a first version of geometric design criteria table will be provided as illustrated in
ATTACHMENT C.
PRELIMINARY SCOPING REPORT
Address all the items listed in ATTACHMENT B as being required in the Preliminary Scoping
Report. A Preliminary Scope Review Meeting is listed in the Scoping Schedule. In the
Preliminary Scoping Report, if there are any items, in the CONSULTANT’S opinion, warrant
further review, discussion and/or additional information on which to base a sound design concept,
those items shall be clearly listed at the end of report.
FINAL SCOPING REPORT
This report shall address and document all the items listed in this scope and ATTACHMENT B.
Incorporate the comments and/or changes received from the Preliminary Scoping Report and the
Preliminary Scope Review meeting. A Final Scope Review Meeting will not be held.
9 Final Posted Scope: 4/22/2019
FINAL DELIVERABLE PACKAGE
The Final Deliverable Report shall be submitted according to the Scoping Schedule. This report
shall list all items provided under this Consultant scope of services and provide those items not
previously provided.
PROJECT SCHEDULE:
The Consultant shall use the following events to prepare the proposed implementation schedule
as required in the Guidelines for the Preparation of Responses on Assigned Design Services
Contracts. These dates shall be used in preparing the Consultant’s Monthly Progress Reports.
Distribution of event material must be completed one week prior to the event. Some of these
events will be conference calls.
Completion Date Description
07/15/2019 Anticipated Consultant Authorization
08/01/2019 Kick-Off Meeting
08/14/2019 2025 Interim Cost Estimate Progress Meeting
08/14/2019 2025 Interim Cost Estimate and Scoping Form 0595 Due
09/30/2019 Interchange Traffic Analysis and Alternatives, Pavement
Treatment, Underground Utilities, Drainage Video
Deliverables, and Bridge Scoping Progress Review Meeting
10/21/2019 Stakeholder Meeting #1
11/13/2019 Public Open House #1
12/02/2019 Public involvement follow-up and Preliminary Bridge
Scoping meeting.
01/07/2020 Stakeholder #2 Meeting
01/14/2019 Interal Refinement of Alternatives for Detail Analysis
03/16/2020 Interchange DDSA and Traffic Operation Model Results
Final Bridge Scoping Meeting
05/05/2020 Stakeholder Meeting #3
05/19/2020 Public Open House #2
05/28/2020 Public Involvement Follow Up Meeting
07/14/2020 Preliminary Scope Report Review Meeting
07/30/2020 Submittal of Final Road and Bridge Scoping Report
10 Final Posted Scope: 4/22/2019
CONSULTANT PAYMENT – Actual Cost Plus Fixed Fee
Compensation for this project shall be on an actual cost plus fixed fee basis. This basis of
payment typically includes an estimate of labor hours by classification or employee, hourly labor
rates, applied overhead, other direct costs, subconsultant costs, and applied fixed fee. The fixed
fee for profit allowed for this project is 11.0% of the cost of direct labor and overhead.
All billings for services must be directed to the Department and follow the current guidelines. The
latest copy of the "Professional Engineering Service Reimbursement Guidelines for Bureau of
Highways" is available on MDOT's website. This document contains instructions and forms that
must be followed and used for billing. Payment may be delayed or decreased if the instructions
are not followed.
Payment to the Consultant for services rendered shall not exceed the maximum amount unless an
increase is approved in accordance with the contract with the Consultant. Typically, billings must
be submitted within 60 days after the completion of services for the current billing. The final
billing must be received within 60 days of the completion of services. Refer to your contract for
your specific contract terms.
Direct expenses, if applicable, will not be paid in excess of that allowed by the Department for its
own employees in accordance with the State of Michigan’s Standardized Travel Regulations.
Supporting documentation must be submitted with the billing for all eligible expenses on the
project in accordance with the Reimbursement Guidelines. The only hours that will be considered
allowable charges for this contract are those that are directly attributable to the activities of this
project.
MDOT will reimburse the consultant for vehicle expenses and the costs of travel to and from
project sites in accordance with MDOT’s Travel and Vehicle Expense Reimbursement
Guidelines, dated May 1, 2013. The guidelines can be found at
http://www.michigan.gov/documents/mdot/Final_Travel_Guidelines_05-01-
13_420289_7.pdf?20130509082418. MDOT’s travel and vehicle expense reimbursement
policies are intended primarily for construction engineering work. Reimbursement for travel to
and from project sites and for vehicle expenses for all other types of work will be approved on a
case by case basis.
MDOT will pay overtime in accordance with MDOT’s Overtime Reimbursement Guidelines,
dated May 1, 2013. The guidelines can be found at
http://www.michigan.gov/documents/mdot/Final_Overtime_Guidelines_05-01-
13_420286_7.pdf?20130509081848. MDOT’s overtime reimbursement policies are intended
primarily for construction engineering work. Overtime reimbursement for all other types of
work will be approved on a case by case basis.
MDOT reserves the right to request services on other projects located in the Region/TSC area
that are not listed above, under the conditions of this “as needed” scope of services.
11 Final Posted Scope: 4/22/2019
Full time services may not be required on all projects at all times. This scope is for “as needed”
services, based on the intermittent needs of MDOT. It must be noted that this is not a guarantee
that MDOT will use the Consultant’s services.
ATTACHMENT A
BRIDGE SCOPING
CONTROL SECTION(S): 80024 (80072, 80111)
JOB NUMBER: 204883EPE
PROJECT LOCATION:
The four bridges and three culverts are located in the City of Paw Paw and Paw Paw Township,
Van Buren County, Michigan.
Structure Number
Bridge ID Facility Carried Features
Intersected Locations
Deck Area
(sq ft)
Year Built
Year Recon
10718 80024-S03 M-40 I-94 At M-40 17,506 1960 1981
10709 80024-B01-3 I-94 EB South Branch of the
Paw Paw River 0.6 Miles West of M-
40 6,848 1960 2006
10710 80024-B01-4 I-94 WB South Branch of the
Paw Paw River 0.6 Miles West of M-
40 6,848 1960 2006
10731 80072-B01 M-40 East Branch of the
Paw Paw River In Paw Paw 3,412 1960 N/A
10733 80072-C01 M-40 Maple Lake Inlet In Paw Paw CMP 1960 N/A
10713 80024-C02 I-94 Three Mile Lake
Drain 0.1 Miles East of M-
40 1,152 1960 N/A
10735 80111-C01 M-40 Martin Drain 0.4 Miles Southeast
of I-94 652 1900 N/A
TEAM REQUIREMENTS:
The CONSULTANT will provide a team of bridge inspectors and scoping engineers that are
technically qualified and cost effective. All site visits will be done with at least a two-person team
for safety reasons. The CONSULTANT must staff the project with the number of teams necessary
to complete the field inspections and report documents in the allotted time. The requirements
listed below are in addition to the prequalification requirements.
12 Final Posted Scope: 4/22/2019
Qualified Team Leader, QTL(S)
If requested, the CONSULTANT will provide current copies of certificates to the MDOT PM for all
QUALIFIED TEAM LEADERS (QTL(S)) that will be performing bridge in-depth inspections and
scoping on this project.
The following are the minimum qualifications for this position(s):
1. Registered as an engineer or structural engineer; licensed to practice in the State of
Michigan.
2. Three (3) years of documented experience performing routine, element, and detailed
inspections.
Changes made to the CONSULTANT QTL that occurs after the authorization must be submitted in
writing for MDOT’S PROJECT MANAGER’S approval. Failure to comply with this requirement may
result in termination of the contract.
PROJECT DESCRIPTION:
This scope of services includes in-depth bridge and culvert inspections, collection of stream bed
cross sections and bridge scoping services.
Routine and in-depth bridge and culvert safety inspections are performed to ensure the safe use of
the structures by the motoring public. To accomplish this, the National Bridge Inspection
Standards (NBIS), AASHTO Manual for Bridge Evaluation, FHWA Bridge Inspection Reference
Manual (BIRM), MDOT NBI Rating Guidelines, Michigan Structure Inspection Manual (MiSIM),
Michigan Bridge Element Inspection Manual (MiBEIM), and MDOT Bridge Advisories are to be
used as guidance to complete the inspection and provide necessary information.
For the purposes of this project, the work is separated into three phases: A) Site Evaluation, B)
Engineering Analysis, and C) Report Preparation. The CONSULTANT must be capable to
perform and complete all phases for successful completion of the project.
A. SITE EVALUATION
Each bridge and culvert must be visited by the CONSULTANT PROJECT MANAGER. The
purpose of this visit is to locate all areas of deterioration, determine feasible repair options,
associated approach work, maintenance of traffic options, and ascertain quantities. Where
necessary, high-reach equipment must be used to get close enough to evaluate the structural
components (See Section EQUIPMENT AND SAFETY, below).
The CONSULTANT team will visit each bridge and culvert and perform an inspection
according to the NBIS and AASHTO manual description for an “In-Depth” inspection.
This will be done by hands-on inspection and non-destructive testing (NDT).
The CONSULTANT QTL(S) must gain access to the MiBRIDGE web based application.
Instruction are provided at the following link to register with the application:
13 Final Posted Scope: 4/22/2019
https://www.michigan.gov/documents/mdot/ACCESS_To_MiBRIDGE_using_the_MiLo
gin_User_Authentication_557244_7.pdf
The information collected in the field must be sufficient to determine quantities and
locations of repairs and improvements. This information must be detailed in the field notes
and/or sketches. These notes are to be included in the report.
1. Concrete Deck (Surface/Underside)
a. The deck surface/underside will be inspected for wet areas, map cracking,
delamination, exposed reinforcing steel or any other evidence of deterioration.
b. The concrete deck surface and underside will be sounded with a hammer or
chain drag. It may be necessary to remove and replace false decking in order
to access the deck bottom and beams. The underside of the deck must be
sounded whether there is any evidence of deterioration or not.
Delaminated, spalled, and cracked areas will be marked with spray chalk,
crayon, kiel or white permanent surveyor’s paint that will be evident in the
photographs. The use of permanent surveyor’s paint is required to mark out
delaminated and spalled areas of the deck underside. Photos of the area must
be recorded, and a written description of the deterioration must be documented
for inclusion in the report. Sketches will be prepared of areas spalled,
delaminated, or with substantial cracking showing the location of the
deteriorated areas. Existing patches will also be shown on the sketches with
differentiation between various patch materials (i.e. concrete, asphalt). These
sketches are to be CAD drawings, not to scale, but in relative proportion and
dimension on 8.5” x 11” sheets. This information shall be presented in the
Appendix of the report.
c. The percentage of deck surface and soffit deficiencies will be noted in the
report. A table shall be provided for each span noting the quantity and
percentage of cracking, delamination, patches and spalling in the structural deck
and wearing surface (if applicable). The condition of existing patches should
be reflected in the report.
d. Note as to whether the deck has previously been overlaid.
2. Substructure
a. Sound all substructure concrete elements (pier columns, caps, abutments,
backwalls, etc.) for delamination and unsound areas. All delaminated areas are
to be marked with spray chalk, crayon, kiel, or white permanent surveyor’s
paint that will be evident in the photographs. All delamination surveys are part
of the site review work (not part of testing). Sketches of the substructure units
mapping the areas of distress (cracks, delaminations, spalls, etc.) and existing
patches are to be included in the appendix of the scoping report in CAD format.
14 Final Posted Scope: 4/22/2019
The quantity and percentage of the total surface area distressed and patched
areas shall be calculated and shown on each sketch.
b. Visually inspect all substructure units for signs of settlement, lateral movement,
cracking, spalling, existing patches, exposed reinforcement and material
defects. Visually examine fractured concrete to determine if it contains slag
aggregate or suspected Alkali Aggregate Reaction (ASR). Note the condition
of the backwalls and check the bridge seat for undermining at bearing locations.
Check for flexural cracks and shear cracks in pier caps. Note areas of previous
repairs. Pictures of the area must be recorded and a written description of the
deterioration and location must be documented for inclusion in the report.
c. Inspection of underwater portions of the substructure is limited to observations
during low-flow periods and probing for signs of scour and undermining.
Follow the plan of action for scour critical bridges. Stream and river bed scour
must be evaluated to ensure the foundation for the bridge has adequate support.
The CONSULTANT QTL will perform a scour inspection around all structural
elements that are in water up to ten feet deep utilizing the wade and probe or
the boat and probe methods. Substructure elements in water over ten feet will
be inspected by a diver under a separate contract.
Stream bed cross sections shall be performed at all structures over water. The
cross sections will record the elevation of the stream with reference to an
established datum on the form and show the existing substructure units in
relation to the stream bed. The completed cross sections shall be uploaded to
MiBRIDGE for reference during subsequent inspections.
Questions regarding scour are to be directed to Erik Carlson in the MDOT-
Hydraulics Unit at (517) 335-1919, [email protected]
3. Reinforced Concrete and Prestressed Concrete Superstructures
Visually inspect for map, shear or flexure cracking, exposed or broken prestressing
strands, crushing of beam ends in bearing areas, discoloration of concrete caused by
corroding mild reinforcement or prestressing strands, high load hit damage and signs
of previous repairs. Observe live loads crossing structure and note excessive
deflections or working cracks. Inspect the diaphragms for spalling or diagonal cracking
from structure movement or excessive deflection, and any other defects. Note the use
of temporary supports.
4. Bearing Devices
Note the condition of all bearing devices. Inspect for pack rust, rocker alignment,
section loss and paint condition of steel bearings such as rocker bearings or pedestal
bearings. Check for excessive bulging of the sides (greater than 15% of bearing
thickness), shear deformation due to thermal movement, splitting and tearing, and
discoloration from exposure to light of elastomeric bearings.
15 Final Posted Scope: 4/22/2019
5. Vertical Clearance
The vertical clearance of the bridge must be field verified and noted in the executive
summary and stated in the report. A picture of any vertical clearance sign attached to
the bridge must be taken and any evidence of high load hits documented. See the
MDOT Bridge Design Manual, Volume 5, Section 7.01.08 for minimum vertical
clearance requirements. These measurements will be recorded on MDOT’s 1190 form.
Raising the structure to meet the current standards must be considered in selecting the
repair option for structures not meeting minimum vertical under clearance criteria. Any
option including a deck replacement, superstructure replacement or bridge replacement
must meet the minimum vertical under clearance requirement. The cost of raising the
grade of the bridge to obtain acceptable under clearance must consider approach work.
6. Structure Geometry
The width of the structure must be evaluated to determine whether it meets current
standards. It must be stated in the report if widening is necessary to upgrade the
structure to current standards, or for maintaining traffic during construction. Please
refer to the MDOT Bridge Design Guides, Section 6.05 for acceptable bridge deck
cross sections. The CONSULTANT will describe how and where the widening is to take
place and provide a plan view sketch showing the proposed widening. Specify if
widening can be done within the deck overhang, or if additional beam lines and
substructure width will be needed to accommodate the required deck cross section.
Widening may require additional approach work to transition between the roadway
width and the new bridge width.
7. Bridge Approaches
Any work required for the approaches must be included in the report and these items
accounted for on the Estimate Sheet.
8. Bridge Railing
Note the type and condition of the bridge railing. Is there evidence indicative of AAR
and is testing recommended? Does the railing meet current standards? Is a railing
replacement required? Note the condition of the pedestrian fencing. Guardrail on the
approaches should also be evaluated. Note the condition of brush blocks, raised
shoulders and sidewalks, and how these elements transition from the approaches.
9. Culverts
The CONSULTANT will visually inspect all culvert components, including wingwalls,
headwalls, culvert side walls, and culvert pier walls for signs of settlement, loss of
backfill, cracking, spalling, exposed reinforcement, and any other deterioration. The
culvert shall also be checked for signs of scour inside the culvert and at the culvert
entrances, including probing at the culvert apron and/or footings to determine if there
is exposure or undermining. The condition of the channel and the channel banks
upstream and downstream of the culvert shall be recorded, including any aggradation,
degradation, erosion, and undermining. Also, note any debris that may be blocking the
16 Final Posted Scope: 4/22/2019
flow of the channel outside or inside the culvert. The condition of the roadway and
slopes at the culvert shall also be noted. Record any deterioration in the pavement
and/or any issues on the slopes. All findings shall be documented with a written
description and pictures of the current conditions along with recommendations for
repairs or replacement.
10. Requests for Action (RFA)
The CONSULTANT will use the Request for Action (RFA) report in MiBRIDGE to
document communication to MDOT of circumstances that need more urgent attention
than otherwise noted in the Work Recommendations, including documenting critical
findings. The need for an RFA shall be discussed with the Region Bridge Engineer
prior to submittal.
11. Critical Findings
Notify the Region Bridge Engineer immediately if a critical finding is discovered. A
critical finding includes any instance where an entire bridge, lane, or shoulder must be
closed due to public safety concerns. Specific examples include:
1. Shoulder closure on bridge due to high load impact to fascia beam
2. Lane closure on redundant bridge due to deep spall under bearing
3. Bridge closure due to pressure flow or undermining of footing
Each critical finding requires an RFA report to be completed in MiBRIDGE.
12. Non-Destructive Testing
The CONSULTANT may determine that other non-destructive testing beyond what is
mentioned in the Scope of Work is needed to make a better judgement. Testing
(magnetic particle testing, acoustic emission, ground penetrating radar, etc.) must be
approved by the MDOT PM. If the project manager approves the test, the CONSULTANT
must submit a testing proposal. The testing proposal will show what tests are to be
performed, what specific information is to be gained from testing, how the information
is to be used, and the cost of testing and necessary traffic control. Proposals submitted
with insufficient information will be denied.
13. The area immediately around the bridge must be closely evaluated to determine if there
are any site issues or constraints that may have an impact during construction. These
include items such as:
• Businesses or driveways close to the approaches
• Utilities attached to or near the bridge
• Signs or sign brackets attached to the bridge (welded or bolted?)
• Poor alignment or geometrics
• Approach and departure guardrail terminals or presence of impact attenuators
17 Final Posted Scope: 4/22/2019
• Bank erosion or scour
• Unusual channel features
• Railroad tracks that have been removed from over or under the bridge
• Proximity of other bridge structures
• Is drainage sufficient? Any evidence of ponding on structure?
• Is Right-of-Way limited and might additional ROW or easements be required?
14. The following, if applicable, must be evaluated and costs considered:
• Is the bridge historical?
• Is vertical clearance substandard?
• Is widening needed?
• If over a watercourse, what hydraulic opening is needed?
• Does this bridge have special structural design features which may affect the
repair options (e.g., non-redundant or fracture critical)?
• Are there environmental issues that may impact the project?
• If the structure carries pedestrians, does it's geometrics meet current ADA
Guidelines? If not, consider what repair options would be necessary to meet
the guidelines set by the ADA.
Determine impacts of the proposed bridge treatment on the existing horizontal and
vertical alignments, pavements, curb and gutter, drainage, right of way (ROW), etc.
Every effort shall be made to minimize ROW impacts within the limits of the projects.
In areas of potential ROW impacts, the CONSULTANT shall identify the potential need
for additional ROW, by station or address, type of ROW required (grading permit,
easement or fee), and roadside improvements proposed (i.e. fencing, turf establishment,
landscaping, non-motorized, etc.).
Review and document the final scope for conformance to 3R/4R Guidelines for non-
freeway jobs and 4R, AASHTO and Interstate Standards for freeway jobs.
Documentation shall include existing condition, treatment as per design standards, and
recommendations. Identify areas where bridge design standards cannot be met on the
final proposed recommended treatment, give justification and documentation as to the
reason.
Review and document the roadside safety related items (i.e. guardrail, barriers,
attenuators, etc.) which need to be modified or included in the project. Documentation
will include location, existing type and condition, and the recommended treatment.
Document and identify any possible utility conflicts and estimate the cost of relocation
and/or adjustment.
Document and identify locations of possible environmental issues which may impact
the project and estimate the cost of treatment.
18 Final Posted Scope: 4/22/2019
Develop Construction Zone Traffic Control Concepts in accordance with the Michigan
Department of Transportation Mobility Policy.
All estimates and other project related items shall meet all MDOT requirement and
detailing practices (i.e., format, materials, symbols, patterns and layout) or as otherwise
directed by MDOT.
The CONSULTANT must determine if part-width construction is possible or if the entire
crossing must be closed and a detour used. The CONSULTANT must contact the TSC
Traffic and Safety Engineer for assistance estimating the costs for maintaining traffic.
Final detailed traffic control costs for construction will be reviewed by the TSC and
MDOT PM.
If, during the site review, the CONSULTANT finds any structural condition that may
cause the bridge to be load restricted (such as holes in beams or broken pre-stressing
strands), or which may require other immediate action (such as lane closures or
emergency repairs to holes in the deck, etc.), the CONSULTANT will notify the MDOT
PROJECT REVIEW ENGINEER as soon as possible. The CONSULTANT will also provide
documentation of the condition (such as beam measurements) to the MDOT PROJECT
REVIEW ENGINEER as quickly as possible and submit a Request for Action (RFA) in
MiBRIDGE.
15. Scoping Checklist and Determining Repair Options
Each bridge will be evaluated to determine the most appropriate repair option based on
the physical condition of the bridge, economic considerations, operations, safety and
engineering judgment. An initial determination is to be made in the field and the Bridge
Rehabilitation Scoping Checklist is completed accordingly. An MDOT Bridge
Rehabilitation Scoping Checklist and must be completed before leaving the field.
The following are the types of repair options that are to be considered (See
ENGINEERING ANALYSIS for more discussion about the option choices):
• "Hold", or defer work three to five years
• Selective repairs
• Overlay
• Concrete overlay (Deep or Shallow)
• Asphalt overlay with waterproofing membrane
• Thin epoxy overlay
• Healer/Sealer
• Deck replacement
• Superstructure replacement
• Bridge or culvert removal or replacement
19 Final Posted Scope: 4/22/2019
Recommended repair options should conform to the latest MDOT Bridge Deck
Preservation Matrix. Written justification will be required for the following work
recommendations:
• Proposed deck work does not follow the Bridge Deck Preservation Matrix
• Proposed work is deck replacement where item 58>4
• Proposed work is superstructure replacement where item 59>4
• Proposed work is substructure replacement where item 60>4
• Proposed work is bridge replacement
The justification form will be provided by the MDOT PROJECT REVIEW ENGINEER
16. Photographs
A photo log of each bridge and culvert and the surrounding areas must be included in
the report. All pictures must be captioned to describe the picture’s general view (such
as north elevation, etc.) and to describe the pertinent items or deterioration. In addition,
pictures must be taken which will support the CONSULTANT’s recommendations. The
deck surface photos will be an "aerial view" taken from a height of at least 12 feet
above the surface of the deck. These photos will be taken after the deck delamination
survey and the areas of delamination are expected to show clearly in the photo. Each
bridge report must show the following items:
• Elevation views of both sides of the bridge or culvert
• Deck surface (entire deck surface to be photographed, including a typical of the
bridge railing and joints)
• Railing, sidewalks, brush blocks, raised shoulders, or any other feature of the
deck surface
• Approaches
• Underside of deck or culvert (to sufficiently show condition of soffit)
• Typical superstructure elements (beams, bearings, pin and hanger, etc.)
• Abutments, including slope protection
• Piers showing all faces
• Waterways
• Areas of major deterioration
• Vertical clearance signs
• Utilities
• Quadrant photos, showing businesses or other items that could affect the cost
of the construction
• Guardrail attachments
• Traffic signals / pedestrian signals within construction influence area
• Indications of pedestrian use / “goat paths”
• Approach sidewalks
• Culvert inlet and outlet
20 Final Posted Scope: 4/22/2019
• Culvert joints
• Roadway over the culvert
• Sink holes or settlement in the vicinity of the structure
In addition, pictures must be taken which will support the CONSULTANT’s
recommendations.
B. ENGINEERING ANALYSIS
The engineering analysis phase will include an evaluation of the site review findings and
determination of the work type category of the appropriate repair. The degree of required
analysis and required deliverables vary based on the work category.
Rehabilitation & Replacement (R&R)
Proceed with the preparation of and evaluation of three repair strategies, including
the estimate of cost of the repair strategies and the selection of the best repair option.
This will also include determining the scope of road work and maintaining traffic
concepts as outlined in the scope.
An initial repair option will be determined during the site review in the field. The
CONSULTANT is required to perform an engineering analysis of this option and one
the options above and below it from the list in the section Scoping Checklist and
Determining Repair Options. For example, if deck replacement is determined in
the field to be the most appropriate repair option, the engineering analysis will also
be performed on the overlay and superstructure replacement options.
The CONSULTANT will analyze eliminating or correcting undesirable or deficient
design characteristics (e.g., structural capacity, widening, etc.) for the deck,
superstructure, and bridge replacement options. Analysis of the load carrying
capacity of some components of the bridge may be required.
Estimating Various Repair Options
Cost estimates for each repair option will be prepared for each structure. A standard
form Estimate Sheet with unit prices will be used (Bridge Cost Estimate Sheet,
provided by the MDOT PROJECT REVIEW ENGINEER The Estimate Sheet provides
space to show all the repairs to be performed. A life cycle cost estimate (LCCA)
may be required for certain repair options.
Capital Scheduled Maintenance (CSM) & Capital Preventive Maintenance (CPM)
21 Final Posted Scope: 4/22/2019
Proceed with the preparation of a cost estimate using the Cost Estimate Sheet. This
phase shall also include determining the scope of road and maintaining traffic
concepts as outlined in the scope.
It is recommended that bridge aesthetics be considered as part of the scoping and cost
considerations be included in the estimates. Treatments may include concrete surface
coatings, aesthetic barrier treatments, ornamental pedestrian fencing and concrete
formliner patterns.
If the final recommended repair option is different from the one determined in the field, a
second Rehabilitation Scoping Checklist for the final recommendation will be completed
and included in the report.
The estimates required are "early preliminary estimates" and not the more detailed
"engineering estimates." The object is to determine the most economical method of
treatment and to establish the budget. The unit prices on the attachment are averages of
various types of repairs, and a description of what is included in the unit price can be found
in the "key". The more detailed estimates will be determined in the design phase (not a
part of this scope of work).
If additional information is necessary for estimating/unit price not on the list, contact
MDOT – Bridge Management and Scoping, Brandon Boatman, 517-242-5597,
C. REPORT
The deliverables for this scope of work will be the reports, photographs, printed
worksheets, checklists, sketches, and notes. The electronic files will be submitted for the
entire estimate sheets included in the report on USB Flash Drives.
All of the documents created by the inspection will be assembled in a PDF binder and
presented under cover of a letter stating that the inspections have been performed in
accordance with this scope of services, and that all appropriate procedures and guidelines
have been followed. This letter will also have the professional registration seal of the
CONSULTANT QTL or CONSULTANT PM. Two sets of each binder will be submitted, first
in draft form, then revised as necessary and submitted in final form. An individual report
for each bridge and culvert will also be provided such that it can be placed in the MDOT
bridge file.
The Report will be submitted in two phases: draft version and final version. The draft
report will be a complete report, with 3 copies (without binder) submitted to the MDOT
PM. These will be reviewed by the Region MDOT PM, Region Bridge Engineer and TSC
Manager. Comments and questions arising from those reviews will be given to the
CONSULTANT to be incorporated into the final report if appropriate or addressed separately
and submitted with the final report.
22 Final Posted Scope: 4/22/2019
The CONSULTANT will not be required to enter the inspection reports into MiBRIDGE, but
will provide recommendations in the final report to the MDOT PROJECT REVIEW ENGINEER
for suggested changes to the existing inspection ratings.
Incomplete final reports or reports with errors will be returned to the CONSULTANT for
revision. Failure to make the required changes will be considered a failure to meet the
terms of the scope of work.
1. Table of Contents
For complete document.
2. General Site Review Procedures
This section will summarize the general procedures used during the site
reviews. This information will include a table showing the site review dates for
each bridge, who was on site, typical equipment used, typical traffic control
procedures, typical site review procedures, etc. Any significant variations from
this typical information can be stated under the section for a specific bridge.
3. Executive Summary
This is to include a statement of the recommended treatment for the bridge and
the cost of the repair options. The executive summary will be a "stand alone"
section and will not refer to other sections of the report, nor will the main text
refer to information in the executive summary.
4. Bridge Properties
• Length
• Width (clear and out-out)
• Number of Lanes
• Shoulder Widths
• Number of Spans
• Skew
• Underclearance
• Beam Type
• Foundation Type
• Deck Thickness
• Deck Surface Type
• Design Loading
• Overload Class
• Year Built
• ADT
23 Final Posted Scope: 4/22/2019
• Posted Speed
• NHS
• NFC
Also include a typical cross section drawing of the existing bridge or
culvert.
5. Field Site Review Findings
This section will include, at a minimum, discussion of the following areas:
a. Site observations and issues, i.e., geometrics, maintenance of traffic,
utilities, scour, signs, vertical clearance, etc. In case of the situation
where no site issues that would impact the rehabilitation of the structure
were identified, a statement will be made that all areas were investigated
and no issues were found. Also include the roadway and/or interchange
type, watercourse characteristics, traffic observations, etc.
b. Overall assessment of the condition of the bridge or culvert including
an evaluation of the beam condition taken during the site review.
c. Testing results and implications to the repair options. If no testing was
performed, this will be stated in the report.
6. Condition
a. Deck (surface, soffit, joints, sidewalk, and railing)
b. Superstructure (beams, diaphragms/cross frames, paint, bearings, pin
and hangar)
c. Substructure (abutments, wingwalls, piers, slope protection, scour)
d. Culvert
e. Approaches
7. NBI Ratings
This section will display the ratings of the major NBI elements and minor
elements rated in poor condition and would also provide recommended updates
to the Bridge Safety Inspection Report, SI&A and Work Recommendations
with justification for the change.
8. Work Description
24 Final Posted Scope: 4/22/2019
This section describes the proposed work and explains why it was selected over
the other options analyzed. A proposed bridge or culvert cross section will also
be provided if different from existing.
9. Non-Motorized Needs
This section will address any observed or known non-motorized needs at the
site and discuss options for addressing the needs.
10. Aesthetics
This section will include a discussion on proposed aesthetics for the bridge or
culvert.
11. Utilities
This section will discuss the observed and known utilities that are in the area
and explain the impacts to those utilities due to construction
12. Real Estate
This section will discuss any real estate concerns or needs based on the
recommended fix.
13. Preliminary Maintaining Traffic Concept
This section will include any known traffic restrictions and a proposed
maintaining traffic concept.
14. Federal Aviation Administration (FAA)
This section will address any FAA permit needs based on the FAA Notice
Criteria Tool.
15. Innovative Bridge Construction/Accelerated Bridge Construction (ABC)
This section will provide recommendations for innovative contracting methods,
bridge construction activities or emerging technologies, or accelerated bridge
construction with a justification and discussion of cost implications.
16. Bridge Repair Options
This section will include a discussion of the rehabilitation options, as described
in Sections Scoping Checklist and Determining Repair Options. For each
option evaluated, a discussion of the necessary improvements and the
25 Final Posted Scope: 4/22/2019
associated costs (initial construction costs) will be included. The report must
discuss and state the reasoning and judgment for selection of the recommended
option. This discussion will also include the reasoning for the elimination of
all other options, as appropriate.
A table summarizing the initial construction cost for each of the options
considered will be included in this section for ease of comparison.
17. Summary with Repair Recommendation
This section will state the recommended course of action for the bridge and the
factors used in determining this recommendation. This section will also briefly
discuss the effects of postponing the recommended improvements.
18. Maintenance Strategies
This section will state the recommended actions to further extend the life of the
bridge and ensure the safety of the structure before a major repair project
scheduled.
19. Appendix
a. Title sheet with photo
b. Aerial Image
c. General Plan of Site
d. General Plan of Structure
e. Right-of-Way Sheet
f. Rehabilitation Scoping Checklist
g. Field notes and sketches, including sketches of deck deficiencies, beam
end repair areas, substructure repair areas, and widening options
h. Paint calculations
i. Estimate Sheets
j. Photos with captions
k. RFA Report
l. Stream bed cross sections
m. FAA Notice Criteria Tool
n. Underclearance form (MDOT Form 1190)
EQUIPMENT AND SAFETY:
The CONSULTANT will be responsible for providing and operating all necessary inspection
equipment. Some of the items that CONSULTANT will want to include in their proposal are:
26 Final Posted Scope: 4/22/2019
• All safety equipment to comply with MIOSHA requirements. Hard hats, safety glasses,
safety shoes, and safety vests must be worn in the field. Life vests are required while
working in or above water.
• Vehicle equipped with high visibility lighting to transport personnel and inspection
equipment to the site.
• Tools required for inspection such as a ladder, waders, rock pick hammer, tape measure,
lighting, marking paint, etc.
• Global Positioning Device (GPS) to locate bridges.
• Cell phone so the team leader may be contacted during normal working hours.
• Harnesses, tripods, air monitor, air supply, etc. for the proper entry of MIOSHA defined
permit-required confined spaces.
• Chain drag, sounding hammer.
• Bucket truck or aerial lift for access to beam ends, bearings, deck soffit and other elements
during in-depth inspections.
Under Bridge Inspection trucks may be supplied by MDOT. The CONSULTANT will be responsible
for scheduling the equipment and performing their inspections based on availability. The
CONSULTANT will review the bridge(s) in advance of scheduling the equipment to ensure enough
freeboard is available to permit access (minimum 6.5’ required). The Under Bridge Inspection
truck is to be used for structures greater than 45’ in height or bridges crossing water. The Under
Bridge Inspection trucks will not be utilized where a bucket truck or aerial lift can safely provide
access to bridge elements. Upon Notice to Proceed (NTP) contact Chris Zube, MDOT – Reachall
(517) 896-9726, [email protected] to schedule an Under Bridge Inspection truck.
MAINTENANCE OF TRAFFIC:
Traffic control will be the responsibility of the CONSULTANT.. Traffic control will follow standard
MDOT procedures. Permits for traffic control and for working in the MDOT Right of Way must
be obtained from the appropriate MDOT Transportation Service Center or Region office prior to
the start of work. Allow ample time for permit issuance. The CONSULTANT will be responsible
for obtaining all permits and notifying the MDOT PM of the time and location of the work.
Required traffic control typicals and lane restrictions are detailed in ATTACHMENT G.
MDOT PROJECT REVIEW ENGINEER- BRIDGE:
27 Final Posted Scope: 4/22/2019
Any questions regarding the Scope of Services for Bridge Scoping may be directed to the MDOT
Project Review Engineer.
James Covey, PE
Southwest Region – Bridge Inspection Engineer
6345 American Ave
Portage, MI 49002
Office: 269-327-4499 ext. 233
Cell: 269-217-2737
E-mail: [email protected]
28 Final Posted Scope: 4/22/2019
ATTACHMENT B
Scoping Report
CS 80024 (80072,80111) – JN 204883EPE
The Preliminary and Final Scoping Reports
The Base, Preliminary, and Final Scoping Reports shall contain the following, and shall be
assembled in the order as listed. Please note report sections.
The scoping report is the complete written description and explanation of the entire project scope,
as well as a comparison as needed between multiple courses of action where relevant.
A unique scope report is to be written and shall follow the format as described below.
The scope report is to be written using complete sentences and sentence structure. In addition,
simple, clear, and concise language is required to ensure that the report is both readable and
understandable.
Also the listed format contains many sections, which may or may not apply to the project.
Sections, which do not apply, may be omitted from the report as directed by the Project Manager.
Information, which has no apparent section, may be placed within a related section, or within a
newly created section. Keep the addition of new sections to a minimum.
Project Description
Provide a general statement regarding the project type, length, and nature of work being proposed
in the scoping of the project. Average length should be no more than one to three sentences.
Project Limits
Establish the projects limits (roadway name, roadway number, project beginning, project ending,
mile points (both Control Section and PR), project length, major cross streets, local municipalities
affected, etc.). List also if this roadway is an NHS route, a non-NHS route, or if it registered as a
National Historic Highway.
Design Speed
List the following information for each of the major roadways within the project limits:
Posted Speed (mph) = _________ Design Speed (mph) = __________
If speeds change within the project limits, list all segments and associated mile points.
Pavement Treatments
Address each pavement treatment for each course of action.
29 Final Posted Scope: 4/22/2019
Cross Section
A brief description of the existing and proposed cross section (pavement type, lane width, curb
and gutter, catch basins, storm sewer location, side slopes, ditch location, setback to existing right
of way line, etc.) for each course of action being proposed as potential scope alternatives. Include
a statement regarding the impact the proposed pavement treatment will have upon existing, or
proposed, curb and gutter. Include a brief statement to establish the presence and location of
existing pedestrian sidewalk, and existing sidewalk ramp terminals at sidewalk street intersections.
Note: At locations of sidewalk street intersections, if not already present, ramp terminals will be
installed.
Discussion of the existing and proposed cross sections through the project length will also address
the existing pavement crown and super elevation, and the impact that the proposed project will
have upon it (to include any potential corrections or recommended adjustments).
Include a statement addressing the existing slopes and ditches, and the impact that the proposed
project will have upon them (include any potential corrections or recommended adjustments).
Vertical Alignment
Address the existing vertical alignment of the roadway and the impact that the proposed project
will have upon it (include any potential corrections or recommended adjustments). The basis of
any correction should be reflective of existing conditions being substandard (i.e. K value too low,
not enough sight distance, etc.).
Horizontal Alignment
Address the existing horizontal alignment of the roadway, and the impact that the proposed project
will have upon it (include any potential corrections or recommended adjustments).
Intersections
Include a brief description of the existing intersections and the impact that the proposed project
will have upon them (include any potential corrections or recommended adjustments). Discuss
alterations based on analysis of the existing geometric conditions and the existing and future
traffic volumes through the intersection. Include any potential economic growth impacts that are
expected by local governmental agencies. Include in the intersection analysis and discussion,
additional recommended geometric improvements, in particular the recommended
countermeasures as identified through the crash analysis, and the impact that these improvements
will have on the proposed project.
Driveways
List the number and type of driveways present within the limits of this project. Include a brief
description of the type of driveways and the impact that the proposed project will have upon them.
Where access management concerns exist, note concerns, and make recommendations (to include
any potential corrections or recommended adjustments or closures).
30 Final Posted Scope: 4/22/2019
Guardrail, Barriers and Attenuators
Discuss the existing guardrail, barriers and attenuators and the impact that the proposed project
will have upon them (include any potential corrections or recommended adjustments). Make note
of locations where culvert extensions and/or slope flattening would be recommended to eliminate
the need for guardrail.
Other Safety Improvements
Address additional recommended geometric improvements, in particular the recommended
countermeasures as identified through the crash analysis, and the impact that these improvements
will have on the proposed project. DO NOT reiterate recommendations from crash analysis
reflected in other portions of the report (i.e. typical section changes, intersection improvements,
etc.).
Bridges
List all existing bridges within the limits of this project in which the roadway crosses over a bridge.
Explain for each bridge how the pavement transition into the bridge deck will be addressed.
Provide lane and shoulder widths on bridges.
List all existing bridges within the limits of this project in which the roadway passes under a bridge.
List the existing under clearance for each bridge; explain how the pavement will be treated below
the bridge; and how the issue of bridge under clearance will be addressed. Provide lane and
shoulder widths under bridges.
Drainage
Address the existing drainage throughout the project length. Include any potential corrections or
recommended adjustments that are required in order to alleviate any existing drainage issues within
the project limits. Note drainage issues that need to be addressed and are not specific to any course
of action being presented to deal with pavement life span.
Environmental Issues
Document existing environmental issues and the impact that the proposed project will have upon
them. Include any potential corrections or recommended adjustments to mitigate environmental
impacts. Make note of potential permit needs.
Maintenance of Traffic
Provide the maintenance of traffic recommendations developed through the process as outlined in
Attachment E.
Right-of-Way Needs
For the roadway in general for each recommended geometric/safety improvement (include the
crash analysis recommended countermeasures, slope flattening recommendations and culvert
extensions), each intersection, each commercial and/or residential driveway, each signal and each
sign; write a brief statement addressing the existing right-of-way, and the impact that the proposed
31 Final Posted Scope: 4/22/2019
project will have upon it (include any potential corrections or recommended adjustments). If
additional right- of- way is required note the type that will be needed (fee take, grading permit,
permit to grade drive, etc.).
Signage Recommendations
Address the existing traffic signs and the impact that the proposed project will have upon them
(include any potential corrections or recommended adjustments). Any modifications or
replacements of overhead sign structures will be included in this discussion.
Utilities
Address the existing utilities present within the roadway right of way and the impact that the
proposed project will have upon them.
Detail Cost Summary
Provide a summary of the estimated construction cost after scoping for each course of action, list
the number of lane miles within the project limits, and a price per lane mile.
Appendix A: Level One Design Criteria Checklists
Provide the Level One Design Criteria Checklists as shown in Attachment
C. Note that there is a checklist for existing and proposed conditions.
Design exceptions will not be allowed and all courses of action being
presented in the scoping reports must have provisions to eliminate any
design exception conditions as determined by the Engineer.
Appendix B: Final Design Criteria
Provide a summary of the design criteria utilized to evaluate and constrain
the scope for each course of action. Use the format provided in Attachment
C.
Appendix C: Stakehold Input Phase
Include comments made at the meeting that solicited stakeholder input.
Provide response to each public comment that states how that comment was
integrated into the project scope, or how the comment was used to affect the
scope in some fashion.
Appendix D: Detail Cost Estimate
Estimates are to be as detailed as possible. They shall be developed using
the most recent MDOT pay items and are to be provided in spreadsheet
format. Individual pay item costs shall be rolled up into a construction cost
estimate.
Appendix E: Detailed Design Hours Estimate
Estimates are to be as detailed as possible, attempt to breakdown hours per
PPMS tasks.
32 Final Posted Scope: 4/22/2019
Appendix F: Crash Analysis Data
Summary of countermeasure recommendation(s) that shall include each
location’s crash pattern and countermeasure individually listed along with
the associated ROW impacts (area and type) and construction cost estimate.
Appendix G: Field Notes & Photographs
Provide digital files of the existing roadway and roadside conditions to
document the needs as identified in the project scope.
Appendix H: Plan Diagrams
Location Map: A location map shall show a map of the project area
showing the roadway name, roadway number, project beginning, project
ending, project length, major cross streets, interchanges and local
municipalities affected. The Location Map shall be presented on a regular
letter size paper (8 ½" x 11")
Typical Cross Sections: Prepare existing typical cross sections and
proposed typical cross sections - generally one per standard cross section
area (i.e. if the road changes from a three lane to a five lane section, a cross
section for the three lane and for the five lane sections will be needed) for
each course of action being presented as potential scope alternates.
The MDOT reviewer, by viewing the typical cross sections, should be able
to understand the existing pavement section, the proposed pavement
section, and all of the work that is expected to implement the project. For
example, if additional right of way will be required, the typical sections
should provide a visual explanation as to why so that the MDOT reviewers
can evaluate options.
Plan Diagrams: Generate plan diagrams that depict and appropriate labels
for the location of existing and proposed roadways, bridges, railroads, cross
roads, edge of pavements, edge of shoulders, curb lines, and drainage
features. A graphics overlay of an aerial image is an example of a desirable
format for a plan diagram.
Maintenance of Traffic Typical Sections and Plan Diagrams:
All maintenance of traffic courses of action are to be detailed with sets of
typical sections and plan diagrams providing information on the concept(s).
Include narrative bullets on each sheet that describe the work occurring
during the construction/traffic stage.
33
ATTACHMENT C
Geometric Design Criteria CS 80024 (80072,80111) – JN 204883EPE
LEVEL ONE DESIGN CRITERIA CHECKLIST
Report conformance for existing and proposed conditions for the FHWA’S level one design
criteria. Calculations supporting these checklists are be provided.
DESIGN CRITERIA
The following example format or another similar format will be utilized to display the design
criteria used to constrain the project scoping process. If additional design criteria are needed to
fully convey the constraints of the design, they may be added to the table.
Project Information Header: Route, Location Control Section, Job Number, AADT, Design Year.
Level One Design Criteria Checklist
Design Criteria (Provide
numerical value for project,
where indicated) Reference
Do the existing conditions meet MDOT
criteria?
Existing Y/N Proposed
1. Design
Speed:
Mainline:
Ramps:
mph
mph
RDM 3.06
Posted
70 mph Posted Y 75 mph Design
2. Lane Width
Mainline:
Ramps:
Auxiliary lanes:
ft
ft
ft
Design Stand.
InterState S.
AASHTO
12 feet
Y 12 Feet
3a. Uncurbed Sections –
Shoulder Width adjacent to:
Design Stand.
InterState S.
AASHTO
9 ft Outside
5 ft Inside
7 ft Outside
TBD
N
N
Y
13 ft Outside
10 ft Inside
7 ft Outside
4 ft Inside
Mainline: 10’
Out
Mainline: 10’ In
Ramps: 7 ft Out
Ramps: 4 ft In
Auxiliary lanes:
ft
ft
ft
3b. Curbed Sections – Curb
Offset:
NA Y
Mainline: ft
34
4. Bridge Clear Roadway
Widths: 10 ft Outside
5 ft Inside
Design Stand.
InterState S.
AASHTO
S13 Lake Street:
12’ Out 10’ In
R04 Lost Dunes:
10’ Out 5.25’ In
S16 Puetz Rd
10’ Out, 5.25’ In
Y
Y
Y
S13 Lake St:
12’ O 10’ In
R04 L. Dunes:
10’ O 5.25’ In
S16 Puetz Rd
10’ O 5.25’ In
5. Structural Capacity HS 20 Design Stand.
InterState S.
AASHTO
S13 Lake Street:
HS25
R04 Lost Dunes:
HS20
S16 Puetz Rd:
HS 20 + Mod
Y
Y
Y
No Change
6. Horizontal Curvature
(minimum Radius)
Rmin=2344 ft
Item 7 below
For listing.
Sta 915+70
R=2292’
N
Check Radii for
WB. File DE
for
70mph R=2292’
7. Super Elevation Rate RDM 3.09.02
1.
Straight L.
5.3%
Straight L .
2.0%
Straight L .
2.1%
R-107
7%
Sta 576+20.65R
R=2865’ e=5.5%
Sta 757+21L
R=11459’ e=2%
Sta 875+70L
R=7689’ e=2%
Sta 915+70
R=2292’ e=5%
Y
Y
N
N
R=2865’e=5%
R=11459’e=2%
R=7689’e=2.1%
R=2292’E=6%
File DE 70mph
8a. Stopping Sight Distance –
Horizontal Curves
R=2000’
MDOT SSD
Rmin=2292’ Y All OK, Clear
to 40’ min.
8b. Stopping Sight Distance –
Vertical Curves
75 mph
K=206 Sag
K=312 Crest
MDOT SSD
GUIDE
561+79C K=313
576+00S K=364
592+00C K=750
630+00C K=2222
649+00S K=722
688+00C K=632
718+00S K=1411
776+00S K=6250
824+00S K=5555
863+00C K=7692
887+00S K=3225
914+80S K=400
936+26C K=379
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Retain Ex.
Retain Ex.
Retain Ex.
Retain Ex.
Retain Ex.
Retain Ex.
Retain Ex.
Retain Ex.
Retain Ex.
Retain Ex.
Retain Ex.
Retain Ex.
Retain Ex
9. Maximum Long. Grades RDM 3.09.02
Retain Ex.
Sta 576+00,
+1.81%
Y
Retain Ex
35
Sta 936+00,
-2.74
Y Retain Ex
10. Through Travel Lane Cross
Slope
RDM 3.09.02
1.5%-2%
1.5% Crown in
Center
No 2% Crown on
Outside Lane
line
11. Vertical Clearances 16’ 0” S14 Livingston
16’ 10”
R06 I&M
24’ 10”
S15 John Beers
16’ 4”
Y
Y
Y
16’ 7”
24’ 7”
16’ 1”
12. Accessibility Criteria for
Handicapped Individuals
NA No Sidewalk
Ramps
13. Ramp Accel/Decl G. D. Guides
Exit 16 WB Off:
Must be extended
Exit 22 WB Off:
Must be extended
N
N
GEO-131
Compliant
GEO-131
Compliant
14. Rollover NA NA NA NA
36
ATTACHMENT D
Monthly Progress Reports
CS 80024 (80072,80111) – JN 204883EPE
MONTHLY PROGRESS REPORTS
The first two pages of this attachment are the necessary layout of the Monthly progress reports
and the last three pages are a completed example.
Control Section 00000
Job Number 00000C
Structure Number S00
Date 00/00/00
MONTHLY PROGRESS REPORT
A. Work accomplished during the previous month.
B. Anticipated work items for the upcoming month.
C. Real or anticipated problems on the project.
D. Update of previously approved detailed project schedule (attached), including
explanations for any delays or changes.
E. Items needed from MDOT.
F. Contact Records for the period.
37
ATTACHMENT E
DEVELOP MAINTAINING TRAFFIC CONCEPT CS 80024 (80072,80111) – JN 204883EPE
1. Scope
This procedure covers the development of a concept to maintain and control traffic during
construction.
2. Work Steps
A. Review the type of construction task(s) included in the project.
B. Review the traffic data and the project site to determine project specific
construction zone traffic requirements. Requirements shall be consistent with the
constraints identified at the Base Report Meeting with the TSC Traffic & Safety
Engineer. Any necessary or recommended exceptions shall be clearly identified
and justification provided.
C. Prepare preliminary written recommendations for maintaining traffic. Included the
following pertinent items:
1) Constraints as identified by the TSC Traffic and Safety Engineer.
2) Method for maintaining traffic. Typical and non-typical areas shall be
addressed. All areas where the pavement widths are narrower than typical
shall be clearly noted and the recommendations for maintaining traffic shall
address these areas.
3) Exceptions to constraints as identified by the TSC Traffic and Safety
Engineer. Justification shall be required for any exceptions.
4) Need for detour, staging and/or flagging operation.
5) Need for temporary widening and/or shoulder upgrading.
6) Time constraints and lane requirements (number and width).
7) Method for maintaining traffic at cross streets.
8) Local considerations (school buses, emergency vehicles, large traffic
generators, etc.).
9) Need for temporary traffic signals (a minimum of two signal heads in view
at all times).
10) Construction zone speed limits.
11) Special events (parades, festivals, etc.).
12) Recommendations for expedited construction for both the entire project and
specific work stages.
D. Prepare maintaining traffic typical sections using the existing and proposed typical
cross sections developed for project work that show traffic lane use and work being
constructed.
E. Submit the written description of traffic stages including a description of the work
to be completed and traffic lane use.
38
F. Receive any items returned by the TSC Traffic and Safety Engineer and/or from
meetings at which maintaining traffic has been discussed, as incomplete or deficient
and make the necessary revisions.
G. Submit the revised recommendations and maintaining traffic typical section with
the Final Scoping Report.
39
ATTACHMENT F
CRASH ANALYSIS REPORTS
CS 80024 (80072, 80111) – JN 204883EPE
Draft and Final Crash Analysis Reports
The Consultants shall provide MDOT with a Crash Analysis Report which shall detail the safety
performance of the project location (includes not only the mainline but all ramps, major and minor
intersections and crossovers within the project limits) and provide detailed graphic depiction of
countermeasures and cost/benefit analysis for crash concentration locations. The Crash Analysis
Report shall at a minimum compare the project location features (mainline, ramps, major
intersections, minor intersections and crossovers) to regional averages, identify crash
concentration locations, examine crash concentration locations for crash patterns and provide
countermeasures for correctable crash patterns. The Consultants shall combine a thorough review
of computer-based crash records with field reviews of the roadways characteristics (geometric and
operational features shall be specifically noted) to identify crash concentration locations. Crash
diagrams shall be provided for the crash concentration locations. The Consultants shall provide a
Draft Crash Analysis Report and upon review and comment by MDOT, the Consultants shall make
any changes identified and submit a Final Crash Analysis Report.
The Consultants shall review and analyze the most recent five years of MDOT crash data. For the
analysis, the Consultants shall stratify the data by location and the crash data shall also be
aggregated by similar roadway segment characteristics. The Consultants shall quarry SEMCOG
to determine regional crash averages which will provide a normative measure of comparison to
aid in the identification of crash concentration locations.
The Consultants shall identify crash concentration locations and determine crash patterns. Based
on the crash patterns identified for each crash concentration location the Consultants shall develop
proposed crash countermeasures. The countermeasures shall be graphically depicted, to scale, with
sufficient detail to determine the countermeasures impact to the existing roadway and the proposed
roadway improvement.
The countermeasures may range from simple sign / marking / signal modifications up through
substantial reconstruction. The Consultants shall present countermeasures stratified into short and
long-term solutions. The Consultants shall provide a construction cost estimate for each
countermeasure using MDOT Pay Items and shall clearly identify any right-of-way impacts a
countermeasure may have. The Consultants shall provide a full cost/benefit analysis for each
countermeasure. The Consultants shall also evaluate the crash impacts on design exceptions
sought.
Develop a Time of Return (TOR) analysis for each countermeasure using the MDOT TOR format
as provided by the MDOT Region Traffic Safety Engineer.
This information shall be included in the appropriate area of the Attachment B.
40
ATTACHMENT G
CONSULTANT TRAFFIC CONTROL
CS 80024 (80072,80111) – JN 204883EPE
The following traffic control must be implemented by the Consultant for bridge scoping and
drainage video inspection.
Closure type Traffic Typical
Workzone Tapers Table M0020a I-94 Shoulder Closure, No speed Red. M-40 Flag Control M-40 Center Lane closure and shift M-40 Outside Lane Closure
M0110a M0140a M0231a M0250a
M-40 Interior Lane Closure M-40 3 Lane Closure I-94 Shoulder Closure, Speed Red.
M0350a M0500a M0880a
I-94 Lane Closure M0980a
Traffic Restrictions
1. Lane closures can occur Monday - Thursday 9am to 3pm 2. No devices will be left in place overnight at any location. 3. Inspection of deck bottom of M-40 will require intermittent night
closure of I-94 EB On ramp. The maintenance of traffic array will require a flagging station, two PCMS’s, site lighting, channelizing devices, and other statics signs. The layout details will be issued by Coloma Business Office Traffic and Safety Engineer.
4. One PCMS will be required to be positioned for three days in advance of two public events at the location designated by Coloma Business Office Traffic and Safety Engineer.
Prior to scheduling traffic control to be installed contact Gary Loyola, Coloma Business
Office, Traffic, Safety & Operations Engineer at 269-849-2346 or [email protected] to
discuss the traffic control work.
Standard MDOT Traffic Control Typicals are available on the MDOT web site at:
http://mdotcf.state.mi.us/public/tands/plans.cfm
41
ATTACHMENT H
Drainage Video Inspection
CS 80024 (80072,80111) – JN 204883EPE
Storm Sewer Video Inspection
Reference files for this task have been posted to the MDOT RFP site under the following folder:
pw:\\HCV591PWISPAA01.ngds.state.mi.us:MDOTProjectWise\Documents\External
Partnerships\RFP\ or this link: RFP
Labeled drainage pipes and drainage structures are shown on a table and annotated old plans
found in this requisition’s folder.
Provide storm sewer pipe video inspection and panoramic images of drainage structures as
indicated in the inventory file. The indicated pipes comprise an approximate sample size of
100% of the storm sewer and small culverts on the project. Panoramic images are required for
25 selected drainage structures. Video inspection of all I-94 and M-40 drainage pipes 48” size
and smaller is required. Physical inspection of culverts over 48” is required. Coordinate with
the project manager excluding video inspection of pipes in the expected interchange
reconstruction zone.
The inspection product pipes and drainage structures must retain the same annotation as the table
and corresponding plan mark up provided.