3 Drill String

Embed Size (px)

Citation preview

  • 7/23/2019 3 Drill String

    1/43

    CHAPTER THREE: DRILLSTRING

  • 7/23/2019 3 Drill String

    2/43

    C O N T E N T S 1. Introduction ............................................................................................................ 1

    2. Drill Pipe ............................................................................................................... 2

    2.1. Drillpipe Stress and Failure............................................................................. 4

    2.2. Drillpipe Inspection......................................................................................... 5

    2.3. Drillpipe Classification ................................................................................... 8

    2. ToolJoints .............................................................................................................. 8

    3. Heavy Wall Drillpipe (HWDP) ........................................................................... 10

    5. Drill Collars ......................................................................................................... 11

    5.1. Special Types of Collar ................................................................................. 12

    6. Other Drillstring Components ............................................................................. 13

    7. Drill-String Design .............................................................................................. 16

    7.1. Design of a Stabilised String ......................................................................... 16

    7.2. Bending Moments in String Design .............................................................. 19

    7.3. Drillstring Selection ...................................................................................... 19

    7.3.1. Drillpipe Selection ................................................................................. 19

    7.3.2. Drillcollar Weight and Length ............................................................... 21

    7.4. Drillstring Design Criteria ............................................................................ 23

    7.4.1. Collapse Load ........................................................................................ 24

    7.4.2. Tension Load ......................................................................................... 25

    7.4.3. Design Factor ......................................................................................... 27

    7.4.4. Slip Crushing ......................................................................................... 27

    7.4.5. Additional Design Variables .................................................................. 28

    8. Appendix .............................................................................................................. 30

    9. Calculations ......................................................................................................... 33

  • 7/23/2019 3 Drill String

    3/43

    Soran University Drilling Engineering I

    LEARNING OBJECTIVES:

    Having worked through this chapter the student will be able to:

    General

    Describe the basic components and the function of each component in the

    drillstring

    Drill-pipe

    Describe the components parts of a joint of drillpipe.

    Describe the way in which drillpipe is classified in terms of size, weight and

    grade

    Describe the stresses and wear mechanisms to which the drillstring is exposed.

    Describe the techniques used to inspect drillpipe and the worn pipe

    classification system

    Tool-joints

    Describe a tooljoint and identify the major characteristics of a tooljoint.

    HWDP

    Describe the HWDP and the reasons for running HWDP

    Drill-collars

    Describe the reasons for using Drillcollars.

    Describe the loads to which Drillcollars are subjected.

    Describe the function of: conventional; Spiral; Square and Monel Drillcollars.

    BHA Components:

    Describe the function of: Stabilisers, Roller Reamers; Shock Subs; Subs andDrilling Jars

    Describe the ways in which the above are configured in the BHA

    Drill-string Design:

    Calculate the dry weight and buoyant weight of the drillstring

    Calculate the length of drillcollar required for a drilling operation

    Calculate maximum drillable depth for a given grade and weight of drillpipe

    Understand the effect of slip crushing on drillpipe design.

  • 7/23/2019 3 Drill String

    4/43

  • 7/23/2019 3 Drill String

    5/43

    1

    Soran University Drilling Engineering I

    1. Introduction

    The term drillstring is used to describe the tubular and accessories on which the drillbit is

    run to the bottom of the borehole. The drillstring consists of drillpipe, drillcollars, the Kellyand various other pieces of equipment such as stabilisers and reamers, which are included

    in the drillstring just above the drillbit (Figure 1). All of these components will be

    described in detail below. The drillcollars and the other equipment which is made up just

    above the bit are collectively called the Bottom Hole Assembly (BHA). The dimensions of

    a typical 10,000 ft drillstring would be:

    (Component)(Outside Diameter, in) (Length, ft)

    Drillbit 12 1/4 Drillcollars 9 1/2 600

    Drillpipe 5 9400

    The functions of the drillstring are:

    To suspend the bit

    To transmit rotary torque from the kelly to the bit

    To provide a conduit for circulating drilling fluid to the bit

    It must be remembered that in deep wells the drillstring may be 5-6 miles long.

    Figure 1: Components of the drillstring

  • 7/23/2019 3 Drill String

    6/43

    The Drillstring T H R E E

    2

    2. Drill Pipe

    Drillpipe is the major component of the drillstring. It generally constitutes 90-95% of the

    entire length of the drillstring. Drillpipe is a seamless pipe with threaded connections,

    known as tooljoints (Figure 2). At one end of the pipe there is the box, which has thefemale end of the connection. At the other end of each length of drillpipe is the male end of

    the connection known as the pin. The wall thickness and therefore the outer diameter of the

    tooljoint must be larger than the wall thickness of the main body of the drillpipe in order to

    accommodate the threads of the connection. Hence the tooljoints are clearly visible in the

    drillstring. Tooljoints will be discussed in greater depth below.

    Figure 2: TooljointsEach length of drillpipe is known as a joint or a single . The standard dimensions for

    drillpipe are specified by the American Petroleum Institute. Singles are available in three

    API length ranges (see Table 1) with range 2 being the most common. The exact lengthof each single must be measured on the rig-site since the process used to manufacture the

    drillpipe means that singles are not of uniform length. Since the only way in which the

    driller knows the depth of the drillbit is by knowing the length of the drillstring, the length

    of each length of drillpipe (and all other drillstring components) made up into the drillstring

    must be measured and recorded on a drillpipe tally . The drillpipe is also manufactured in a

    variety of outside iameters, and weights (Table 2) which assuming a specific gravity for

    steel of 490 lb/cuft, is a reflection of the wall thickness of the drillpipe. The specification

    for a particular string of drillpipe could therefore appear as:

    5 19.5 lb/ft Grade S Range 2

  • 7/23/2019 3 Drill String

    7/43

    3

    Soran University Drilling Engineering I

    API Range Length, ft

    1 18-22

    2 27-30

    3 38-45

    Table 1: Drillpipe Lengths

    Size OD, in ID, in Weight (Ib/ft)

    2 3/8 1.815 6.65

    2 7/8 2.151 10.40

    3 2.992 9.50

    3 1/2 2.764 13.30

    5 4.602 15.52

    5 4.408 16.25

    5 4.276 19.505 4.00 25.60

    5 4.776 21.90

    5 1/2 4.670 24.70

    Table 2: Dimensions of Drillpipe

    The drillpipe is also manufactured in a variety of material grades (Table 3). The grade of

    drill pipe describes the minimum yield strength of the pipe. APIdefines five grades: D, E,

    X, G and S. However, in oilwell drilling, only grades E,G and S areactually used. In most

    drillstring designs, the pipe grade is increased if extra strength isrequired.

    API Grade Minimum YieldStress (psi)

    Minimum TensileStress (psi)

    D or D-55 55,000 95,000 0.58

    E or E-75 75,000 100,000 0.75

    X or X-95 95,000 105,000 0.7

    G or G-105 105,000 115,000 0.91

    S or S-135 135,000 145,000 0.93

    Table 3: Drillpipe Material Grades

    All of these specifications will influence the burst, collapse, tensile and torsional strength of

    the drillpipe and this allows the drilling engineer to select the pipe which will meet the

    specific requirements of the particular drilling operation.

    Care must be taken when using the specifications given in Table 2 since although these are

    the normally quoted specifications for drillpipe, the weights and dimensions are nominal

    values and do not reflect the true weight of the drillpipe or the minimum internal diameter

    of the pipe.

  • 7/23/2019 3 Drill String

    8/43

    The Drillstring T H R E E

    4

    2.1. Drillpipe Stress and Failure

    It is not uncommon for the drillpipe to undergo tensile failure (twistoff) whilst drilling.

    When this happens, drilling has to stop and the drillstring must be pulled from the borehole.

    The part of the string below the point of failure will of course be left in the borehole whenthe upper part of the string is retrieved. The retrieval of the lower part of the string is a very

    difficult and time consuming operation.

    The failure of a drillstring can be due to excessively high stresses and/or corrosion.

    Drillpipe is exposed to the following stresses:

    Tension the weight of the suspended drillstring exposes each joint of drillpipe to

    several thousand pounds of tensile load. Extra tension may be exerted due tooverpull (drag caused by difficult hole conditions e.g. dog legs) when pulling out of

    hole.

    Torque during drilling, rotation is transmitted down the string. Again, poor hole

    conditions can increase the amount of torque or twisting force on each joint.

    Cyclic Stress Fatigue in deviated holes, the wall of the pipe is exposed to

    compressive and tensile forces at points of bending in the hole. As the string is

    rotated each joint sustains a cycle of compressive and tensile forces (Figure 3). Thiscan result in fatigue in the wall of the pipe.

    Stresses are also induced by vibration, abrasive friction and bouncing the bit off bottom.

    F igure 3: Cyclic loading

  • 7/23/2019 3 Drill String

    9/43

    5

    Soran University Drilling Engineering I

    Corrosion of a drillstring in a water based mud is primarily due to dissolved gases,

    dissolved salts and acids in the wellbore, such as:

    Oxygen present in all drilling fluids. It causes rusting and pitting. This may lead

    to washouts (small eroded hole in the pipe) and twist offs (parting of the drillstring).

    Oxygen can be removed from drilling fluids using a scavenger, such as sodium

    sulphate. Even small concentrations of oxygen (< 1 ppm) can be very damaging.

    Carbon dioxide can be introduced into the wellbore with the drilling fluid

    (makeup water, organic drilling fluid additives or bacterial action on additives in the

    drilling fluid) or from the formation. It forms carbonic acid which corrodes steel.

    Dissolved Salts increase the rates of corrosion due to the increased conductivity

    due to the presence of dissolved salts. Dissolved salts in drilling fluids may come

    from the makeup water, formation fluid inflow, drilled formations, or drilling fluid

    additives.

    Hydrogen sulphide may be present in the formations being drilled. It causes

    hydrogen embrittlement or sulphide stress cracking. Hydrogen is absorbed on

    to the surface of steel in the presence of sulphide. If the local concentration of

    hydrogen is sufficient, cracks can be formed, leading rapidly to a brittle failure.

    Hydrogen embrittlement in itself does not cause a failure, but will accelerate failure

    of the pipe if it is already under stress or notched. Only small amounts of H2S need

    be present to induce fatigue (< 13 ppm). Special scavengers can be circulated in the

    mud to remove the H2S (e.g. filming amines).

    Organic acids These produce corrosion by lowering the pH, remove protective

    films and provide hydrogen to increase hydrogen embrittlement.

    Although added chemicals can build up a layer of protection against corrosion, the fatigue

    stresses easily break this layer down, allowing corrosion to re-occur. It is this interaction of

    fatigue and corrosion which is difficult to combat.

    2.2. Drillpipe Inspection

    When new pipe manufactured, they will be subjected to a series of mechanical tests by the

    manufacturer such as; tensile and hydrostatic pressure tests in accordance with API

    Specification 5A and 5AX. This will ensure that the pipe can withstand specified loads. A

    joint of drillpipe will however be used in a number of wells. When it has been used it will

    undergo some degree of wear and will not be able to withstand the same loads as when it isnew.

  • 7/23/2019 3 Drill String

    10/43

    The Drillstring T H R E E

    6

    It is extremely difficult to predict the service life of a drillstring since no two boreholes

    experience. However, as a rough guide, the length of hole drilled by a piece of drillpipe,

    when part of a drillstring will be:

    Soft drilling areas: 220000 - 250000 ft

    Hard or deviated drilling areas: 180000 - 210000 ft

    This means that a piece of drillpipe may be used on up to 25 wells which are 10,000ft deep.

    During the working life of the drillpipe it will therefore be necessary to determine the

    degree of damage or wear that the pipe has already been subjected to and therefore its

    capacity to withstand the loads to which it will be exposed in the future. Various non-

    destructive tests are periodically applied to use drillpipe, to assess the wear and therefore

    strength of the pipe, and to inspect for any defects, e.g. cracks. The strength of the pipe is

    gauged on the basis of the remaining wall thickness, or if worn eccentrically, the average

    minimum wall thickness of the pipe. The methods used to inspect drillpipe are summarized

    in Table 4.

    Table 4: Summary of inspection techniques

    Following inspection, the drillpipe is classified in terms of the degree of wear or damage

    which is measured on the pipe. The criteria used for classifying the drillpipe on the basis of

    the degree of wear or damage are shown in Table 5. The Grade 1 or Premium drillpipe

    classification applies to new pipe, or used pipe with at least 80% of the original wall

  • 7/23/2019 3 Drill String

    11/43

    7

    Soran University Drilling Engineering I

    thickness still remaining. A classification of Grade 2 and above indicates that the pipe has

    sustained significant wear or damage and that its strength has been significantly reduced.

    The strength of some typical drillpipe sizes when new and when worn is shown in tables 11

    and 12.

    Drillpipe will generally be inspected and classified before a new drilling contract is started.

    The operating company would require that the drilling contractor provide proof of

    inspection and classification of the drillstring as part of the drilling contract.

    CLASSIFICATION OF USED DRILL PIPE AND USED TUBING WORK STRINGS

    (All Sizes, Weights and Grades. Nominal dimension is basis for all calculations)

    C o n d

    i t i o n 1 2 3 4

    Pipe condition Premium class Class 2 Class 3

    E x

    t e r

    i o r

    A) OD Wear Wall Remaining wall not lessthan 80%

    Remaining wall notless than 65%

    Remaining wallnot

    less than 55%B) Dents & Marshes Not over 3% of OD Not over 4% of OD

    C) Slip area dia.variations;

    1- Crushing2- Necking Not over 3% of OD Not over 3% of OD

    Not over 4% of OD Not over 4% of OD

    D) Stress induced dia.variations;

    1- Stretched

    2- String Shot

    Not over 3% of ODreduction

    Not over 3% of ODincrease

    Not over 4% of ODreduction

    Not over 4% of OD

    increase

    E) Cuts, Gouges &Corrosion

    1- Round Bottom

    2- Sharp Bottom:Longitudinal

    Transverse

    Remaining wall not lessthan 80%

    Remaining wall not lessthan 80%

    Remaining wall not lessthan 80% and length not

    over 10%

    Remaining wall knotlessthan 65%

    Remaining wall not lessthan 65%

    Remaining wall not lessthan 65% and length

    not over 10%F) Fatigue cracks None None None

    I n t e r

    i o r

    A) Corrosive Piping Wall Remaining wall notless than 80%

    Remaining wall notless than 80%

    A) Erosion & Wear Wall Remaining wall notless than 80%

    Remaining wall notless than 80%

    B) Fatigue cracks None None None

    Table 5: Classification of used drillpipe and used tubing work strings

  • 7/23/2019 3 Drill String

    12/43

    The Drillstring T H R E E

    8

    2.3. Drillpipe Classification

    Drill pipe, unlike other oilfield tubulars such as casing and tubing, is re-used and therefore

    often worn when run. As a result the drill pipe is classified to account for the degree of

    wear.

    The API has established guidelines for pipe classification in API RP7G. A summary of the

    classes follows:

    New : No wear, has never been used.

    Premium : Uniform wear and a minimum wall thickness of 80% of new pipe.

    Class 2 : Drill pipe with a minimum wall thickness of 65% with all the wear on one

    side so long as the cross sectional area is the same as the premium class.

    Class 3: Drill pipe with a minimum wall thickness of 55% with all the wear on one

    side

    Drill pipe classification is an important factor in the design and use of drill pipe since the

    degree of wear will affect the pipe properties and strengths. API RP7G provides a series of

    tables which detail the strengths and properties of the various grades and classes of pipe as

    shown in table 5.

    2. ToolJoints

    Tooljoints are located at each end of a length of drillpipe and provide the screw thread for

    connecting the joints of pipe together (Figure 4). Notice that the only seal in the connection

    is the shoulder/shoulder connection between the box and pin. Initially tool joints were

    screwed on to the end of drillpipe, and then reinforced by welding. A later development

    was to have shrunk-on tooljoints. This process involved heating the tool joint, then

    screwing it on to the pipe. As the joint cooled it contracted and formed a very tight, close

    seal. One advantage of this method was that a worn joint could be heated, removed and

    replaced by a new joint. The modern method is to flash-weld the tooljoints onto the pipe. A

    hard material is often welded onto the surface of the tooljoint to protect it from abrasive

    wear as the drillstring is rotated in the borehole. This material can then be replaced at some

    stage if it becomes depleted due to excessive wear. When two joints of pipe are being

    connected the rig tongs must be engaged around the tooljoints (and not around the main

    body of the drillpipe), whose greater wall thickness can sustain the torque required to

  • 7/23/2019 3 Drill String

    13/43

    9

    Soran University Drilling Engineering I

    make-up the connection. The strength of a tool joint depends on the cross sectional area of

    the box and pin. With continual use the threads of the pin and box become worn, and there

    is a decrease in the tensile strength. The size of the tooljoint depends on the size of the

    drillpipe but various sizes of tool joint are available. The tooljoints that are commonly used

    for 4 1/2 drillpipe are listed in Table 6. It should be noted that the I.D. of the tooljoint is

    less than the I.D. of the main body of the pipe.

    F igure 4: Tool joint

    Table 6: API tool joints

  • 7/23/2019 3 Drill String

    14/43

    The Drillstring T H R E E

    10

    Tooljoint boxes usually have an 18 degree tapered shoulder, and pins have 35 degree

    tapered shoulders. Tool joints are subjected to the same stresses as drillpipe, but also have

    to face additional problems:

    When pipe is being tripped out the hole the elevator supports the string weight

    underneath the shoulder of the tool joint.

    Frequent engagement of pins and boxes, if done harshly, can damage threads.

    The threaded pin end of the pipe is often left exposed and is therefore exposed to

    possible damage.

    Tool joint life can be substantially extended if connections are greased properly when the

    connection is made-up and a steady torque applied.

    3. Heavy Wall Drillpipe (HWDP)

    Heavy wall drillpipe (or heavy weight drillpipe) has a greater wall thickness than ordinary

    drillpipe and is often used at the base of the drillpipe where stress concentration is greatest.

    The stress concentration is due to:

    The difference in cross section and therefore stiffness between the drillpipe anddrillcollars.

    The rotation and cutting action of the bit can frequently result in a vertical bouncing

    effect.

    HWDP is used to absorb the stresses being transferred from the stiff drill collars to the

    relatively flexible drillpipe. The major benefits of HWDP are:

    1. Increased wall thickness

    2. Longer tool joints

    3. Uses more hard facing

    4. May have a long central upset section (Figure 5)

    HWDP should always be operated in compression. More lengths of HWDP are required to

    maintain compression in highly deviated holes.

  • 7/23/2019 3 Drill String

    15/43

    11

    Soran University Drilling Engineering I

    F igure 5 : Heavyweight drillpipe

    5. Drill Collars

    Drillcollars are tubulars which have a much larger outer diameter and generally smaller

    inner diameter than drillpipe. A typical drillstring would consist of 9 O.D. x 2

    13/16I.D.drillcollars and 5 O.D. x 4.276 I.D. drillpipe. The drillcol lars therefore have a

    significantly thicker wall than drillpipe. The function of drill collars are:

    To provide enough weight on bit for efficient drilling.

    To keep the drillstring in tension, thereby reducing bending stresses and failures due

    to fatigue.

    To provide stiffness in the BHA for directional control.

    Since the drillcollars have such a large wall thickness tooljoints are not necessary and the

    connection threads can be machined directly onto the body of the collar. The weakest point

    in the drillcollars is the connection and therefore the correct make up torque must be

  • 7/23/2019 3 Drill String

    16/43

    The Drillstring T H R E E

    12

    applied to prevent failure. The external surface of a regular collar is round (slick), although

    other profiles are available.

    Drillcollars are normally supplied in Range 2 lengths (30 - 32 ft). The collars are

    manufactured from chrome-molybdenum alloy, which is fully heat treated over the entire

    length. The bore of the collar is accurately machined to ensure a smooth, balanced rotation.

    Drill collars are produced in a large range of sizes with various types of joint connection.

    It is very important that proper care is taken when handling drillcollars. The shoulders and

    threads must be lubricated with the correct lubricant (containing 40-60% powdered

    metallic-zinc or lead).

    Like drillpipe, collars are subjected to stresses due to:

    Buckling and bending forces

    Tension

    Vibrations

    Alternate compression and tension.

    5.1. Special Types of Collar

    Square collars

    These collars are usually 1/16 less than bit size, and are run to provide maximum

    stabilization of the bottom hole assembly.Monel collars

    These collars are made of a special non-magnetic steel alloy. Their purpose is to isolate

    directional survey instruments from magnetic distortion due to the steel drillstring.

    Anti-wall stickWhen drilling through certain formations the large diameter drillcollars can become stuck

    against the borehole (differential sticking). This is likely to happen when the formation is

    highly porous, a large overbalance of mud pressure is being used and the well is highly

    deviated. One method of preventing this problem is to reduce the contact area of the collar

    against the wellbore. Spiral grooves can be cut into the surface of the collar to reduce its

    surface area (Figure 6).

  • 7/23/2019 3 Drill String

    17/43

    13

    Soran University Drilling Engineering I

    Fi gure 6: Spiral drillcollar

    6. Other Drillstring Components

    6.1. Roller Reamer

    A roller reamer consists of stabiliser blades with rollers embedded into surface of the blade.

    The rollers may be made from high grade carburised steel or have tungsten carbide inserts

    (Figure 7). The roller reamer acts as a stabiliser and is especially useful in maintaining

    gauge hole. It will also ream out any potential hole problems (e.g. dog legs, key seats,

    ledges).

    F igur e 7: Roller reamers

  • 7/23/2019 3 Drill String

    18/43

    The Drillstring T H R E E

    14

    6.2. Stabilisers

    Stabilisers consist of a length of pipe with blades on the external surface. These blades may

    be either straight or spiral and there are numerous designs of stabilisers (Figure 8). The

    blades can either be fixed on to the body of the pipe, or mounted on a rubber sleeve (sleevestabilizer), which allows the drillstring to rotate within it.

    The function of the stabilizer depends on the type of hole being drilled. In this section we

    are concerned only with drilling vertical holes. Drilling deviated holes will be dealt with

    later. In vertical holes the functions of stabilisers may be summarized as follows:

    - Reduce buckling and bending stresses on drill collars

    - Allow higher WOB since the string remains concentric even in compression.

    - Increase bit life by reducing wobble (i.e. all three cones loaded equally)

    - Help to prevent wall sticking.

    - Act as a key seat wiper when placed at top of collars.

    F igur e 8: Stabilisers

    Generally, for a straight hole, the stabilisers are positioned as shown in Figure 9.Normally

    the stabilisers used will have 3 blades, each having a contact angle of 140 degrees (open

    design). When stabilisers begin to wear they become under gauge and are less efficient.

    Stabilisers are usually replaced if they become 1/2 under gauge ( 3/16 under gauge may

    be enough in some instances).

  • 7/23/2019 3 Drill String

    19/43

    15

    Soran University Drilling Engineering I

    F igur e 9: Stabiliser positions for straight hole drilling

    6.3. Subs (substitutes)

    Subs are short joints of pipe which act as crossovers (i.e. connect components which cannot

    otherwise be screwed together because of differences in thread type or size).

    6.4. Drilling Jars

    The purpose of these tools is to deliver a sharp blow to free the pipe if it becomes stuck in

    the hole. Hydraulic jars are activated by a straight pull and give an upward blow.

    Mechanical jars are preset at surface to operate when a given compression load is appliedand give a downward blow. Jars are usually positioned at the top of the drill collars.

    6.5. Shock Sub (vibration dampener)

    A shock sub is normally located above the bit to reduce the stress due to bouncing when the

    bit is drilling through hard rock. The shock sub absorbs the vertical vibration either by

    using a strong steel spring, or a resilient rubber element (Figure 10).

  • 7/23/2019 3 Drill String

    20/43

    The Drillstring T H R E E

    16

    F igur e 10: Shock sub

    7. Drill-String Design

    There are four basic requirements which must be met when designing a drillstring:

    1. The burst, collapse and tensile strength of the drillstring components must not be

    exceeded

    2. The bending stresses within the drill string must be minimized.3. The drillcollars must be able to provide all of the weight required for drilling.

    4. The BHA must be stabilised to control the direction of the well.

    7.1. Design of a Stabilised String

    A drilling bit does not normally drill a vertical hole. This is partly due to the forces acting

    on the string by sloping laminar formations. When the slope (or dip) of the beds is less than

    45 degrees the bit tends to drill up-dip (perpendicular to the layers).If the dip is greater than

    45 degrees it tends to drill parallel to the layers (see Figure11). In hard rock, where greater

  • 7/23/2019 3 Drill String

    21/43

    17

    Soran University Drilling Engineering I

    WOB is applied, the resulting compression and bending of the drillstring may cause further

    deviation. There are two techniques for controlling deviation.

    F igur e 11: Drilling through dipping strata

    Packed hole assembly (Figure 12) This is basically a stiff assembly, consisting of

    reamers, drill collars and stabilisers. The purpose of this design is to align the bit

    with the hole already drilled and minimize the rate of change in deviation.Pendulum assembly The first stabiliser of a pendulum assembly is placed some

    distance behind the bit. The unsupported section of drill collar (Figure 12) swing to

    the low side of the hole. A pendulum assembly will therefore tend to decrease the

    angle of deviation of the hole and tend to produce a vertical hole. This will tend to

    reduce deviation. The distance L from the bit up to the point of wal l contact is

    important, since this determines the pendulum force. To increase this distance, a

    stabiliser can be positioned some distance above the bit. If placed too high thecollars will sag against the hole and reduce the pendulum force.

  • 7/23/2019 3 Drill String

    22/43

    The Drillstring T H R E E

    18

    F igur e 12: Pendulum effect The optimum position for the stabiliser is usually based on experience, although theoretical

    calculations can be done. When changing the hole angle it must be done smoothly to avoid

    dog legs (abrupt changes in hole angle). Some typical Bottom hole assemblies (BHA), for

    different drilling conditions, are given in figure 13.

    F igur e 13: Typical BHAs

  • 7/23/2019 3 Drill String

    23/43

    19

    Soran University Drilling Engineering I

    7.2. Bending Moments in String Design

    A useful parameter when considering bending of the drillstring is the:

    Field results have shown that if the ratio of section modulus between various string

    components is kept below 5.5 the failure rate is reduced. The section modulus ratio for a

    variety of drillpipe sizes is given in Table 8. In larger holes, or more severe drilling

    conditions, the ratio should be kept below 3.5 (Table 13). Essentially these guidelines will

    eliminate abrupt changes in cross sectional area throughout the drillstring.

    Table 8: I/C Data for drillstring components

    7.3. Drillstring Selection

    7.3.1. Drillpipe Selection

    The drillpipe is to provide a fluid conduit for pumping drilling mud, imparting rotary

    motion to the bit and for drill stem testing and squeeze cementing. Basic factors for

    consideration in drill string design includes: collapse, tension, dogleg severity and slip

    crushing. Collapse together with tension primarily applies to weight selection, grades and

    couplings. High-strength pipe is required in the lower sections of the drillstring for collapse

    resistance. Tension is considered to dictate the higher strength at the top of the well.

    Classes are given to drill pipe to account for its weight, grade and class.

  • 7/23/2019 3 Drill String

    24/43

    The Drillstring T H R E E

    20

    The weight per foot of the pipe is a function of the connection type and grade of the

    drillpipe.

    The weight per foot that should be used when calculating the true weight of a string of pipe

    is given in table 9.The weight of the pipe calculated in the manner described above will

    reflect the weight of the drillpipe when suspended in air ( Weight in air ). When the pipe

    is suspended in the borehole it will be immersed in drilling fluid of a particular density and

    will therefore be subjected to a buoyant force. This buoyant force will be directly

    proportional to the density of the drilling fluid. The weight of drillpipe when suspended in a

    fluid ( Wet Weight ) can be calculated from the following:

    Buoyant Weight (Wet Weight) of Drillpipe = Weight of pipe in Air x Buoyancy Factor

    Table 9: Specifications of Various Sizes of Drillpipe

    Example 1// Dimensions and Weight of Drillpipe

    a) What is the weight in air of a joint (30 ft) of 5 19.5 lb/ft Grade G drillpipe with 41/2?

    b) What is the wet weight of this joint of drillpipe when immersed in a drilling fluidwith a density of 12 ppg?

  • 7/23/2019 3 Drill String

    25/43

    21

    Soran University Drilling Engineering I

    7.3.2. Drillcollar Weight and Length

    The sizes and weight per foot of a range of drillcollar sizes are shown in table 10. The

    weights that are quoted in table 10 are the weight in air of the drillcollars.

    Table 10: Drillcollar Weights

    Example 2// Drillcollar Dimensions and Weights

    A) What is the weight in air of 200 ft of 9 1/2 x 2 13/16 drillcollar?

    B) What is the weight of this drillcollar when immersed in 13 ppg mud?

  • 7/23/2019 3 Drill String

    26/43

    The Drillstring T H R E E

    22

    The length of drillcollars, L that are required for a particular drilling situation depends on

    the Weight on Bit, WOB that is required to optimize the rate of penetration of the bit and

    the buoyant weight per foot, w of the drillcollars to be used, and can be calculated from the

    following:

    ....1

    For directional well:

    .2 Where = well inclination

    If the drillpipe is to remain in tension throughout the drilling process, drillcollars will have

    to be added to the bottom of the drillstring. The buoyant weight of these additional

    drillcollars must exceed the buoyant force on the drillpipe.

    This will be sufficient to ensure that when the entire weight of the drillcollars is allowed to

    rest on the bit, then the optimum weight on bit will be applied. The WOB will however

    vary as the formation below the bit is drilled away, and therefore the length of the

    drillcollars is generally increased by an additional 15%. Hence the length of drillcollars will

    be 1.15 L.

    Example 3//Length of Drillcollars for a Given WOBYou have been advised that the highest rate of penetration for a particular 12 1/4 bit will

    be achieved when 25,000lbs weight on bit (WOB) is applied to the bit. Assuming that you

    are drilling a vertical well and that the bit will be run in 12 ppg mud, calculate the length of

    drillcollars required providing 25,000 lbs WOB.

    Calculate the weight (in air) of 10000 ft of 5 19.5 lb/ft Grade G drillpipe with4

    1/2 IF connections.

    Calculate the weight of this string in 12 ppg mud.

    Calculate the length of 9 1/2 x 2 13/16 drillcollars that would be required to

    provide 25,000lbs WOB and keep the drillpipe in tension in 12 ppg mud.

  • 7/23/2019 3 Drill String

    27/43

    23

    Soran University Drilling Engineering I

    7.4. Drillstring Design Criteria

    When drilling highly deviated, extended reach or horizontal wells, computer modeling of

    torque and drag should be used for establishing grades, size and weight of drill and

    coupling to be used. On such wells, calculation of the effects of deviation on predictedtorque and drag are too complicated to calculate manually.

    The criteria used in a drill string design are:

    1. Collapse Load

    2. Tension Load

    Burst pressure is not considered in drillstring design due to the fact that burst loads and

    backup loads are provided by the same fluid in the well. Therefore under normal

    circumstances there are no effective burst loads, except during squeeze operations where

    surface pressure is applied. If squeeze pressures are high, a back-up annulus pressure would

    normally be applied to reduce the effective burst pressure.

    Collapse and tension considerations are used to select the pipe weights, grades and

    couplings. Slip crushing affects the tension design and pipe selection. Dogleg analysis is

    performed to study the fatigue damage resulting from rotation in doglegs. Doglegs analysis

    may not affect the selection of the pipe, however it will assist in determining the maximum

    permissible dogleg during any section of the well.

    API R7G gives the following design criteria:

    1. Anticipated total depth with this drillstring

    2. Hole size

    3. Expected mud weight

    4. Desired safety factor in tension and/or margin of overpull

    5. Desired safety factor in collapse

    6. Length of drillcollars, OD, ID and weight per foot

    7. Desired drillpipe sizes and inspection class

  • 7/23/2019 3 Drill String

    28/43

    The Drillstring T H R E E

    24

    F igur e 14 : Axial load on the drillstring

    7.4.1. Collapse Load

    The criteria to be used as a worst case for the collapse design of drill pipe are typically a

    DST. The maximum collapse pressure should be determined for an evacuated string, with

    mud hydrostatic pressure acting on the outside of the DP. Use of this criterion also accounts

    for incidence of a plugged bit or failure to fill the string when a float is used during trips

    into the hole.

    A design factor is used in constructing the collapse design line. The design factor to be used

    for this full evacuation scenario is 1.0.

    Collapse calculation

    1. Drill Stem Testing (DST)

    The collapse pressure can be calculated when the string is partially empty, with different

    uid density inside than outside, using the following equation:

    3 Where:

    Pc = collapse pressure (psi)

    Y = depth to fluid inside drillpipe

    L = total depth of well (ft)

    1= fluid density outside the drillpipe (ppg)

    2= fluid density inside the drillpipe (ppg)

  • 7/23/2019 3 Drill String

    29/43

    25

    Soran University Drilling Engineering I

    The drillpipe is completely empty, Y = 0, 2= 0, then it becomes:

    ........4

    When the fluid density inside drillpipe is the same as that outside drillpipe, i.e. 1 = 2 = ,

    then it becomes:

    5

    2. Design factor

    .6 The valve of 1.125 is normally used for DF in collapse.

    7.4.2. Tension Load

    The tensile resistance of drill pipe is usually de-rated by a design factor. The tension

    loading can be calculated from the known weights of the drill collars and drill pipe below

    the point of interest. The effect of buoyancy on the drill string weight, and therefore the

    tension, must also be considered. Buoyancy forces are exerted on exposed horizontal

    surfaces and may act upwards or downwards. These exposed surfaces occur where there is

    a change in cross-sectional area between different sections.

    The tension design is established by consideration of the following:

    Tensile Forces: These include:- weight carried

    - shock loading

    - bending forces

    Design factor

    Slip Crushing Design

    Tensile Forcesa) Weight Carried

    The greatest tension (P) on the drillstring occurs at the top joint at the maximum drilled

    depth, see Figure 15. This is given by:

    . 7

  • 7/23/2019 3 Drill String

    30/43

    The Drillstring T H R E E

    26

    Where:

    = length of drillpipe per foot

    = weight of drillpipe per unit length

    = weight of drillcollars

    = weight of drillcollars per unit length

    BF = buoyancy factor

    Figure 15: TensionNote: P is the total weight of the submerged drillstring. It is highly dependent on mud

    weight. The higher the mud weight the less weight seen at surface on the Martin Decker

    weight indicator. The influence of mud weight is shown through the term BF: buoyancy

    factor.

    The drillstring should not be designed to its maximum yield strength to prevent the

    drillpipe from yielding and deforming. At yield, the drillpipe will have:

    - deformation made up of elastic and plastic (permanent) deformation

    - permanent elongation

    - permanent bend and it may be difficult to keep it straight

    To prevent this, API recommends that the use of maximum allowable design load (Pa),

    given by:

    .8 Where:

    = Max. Allowable design load in tension, lb

    = theoretical yield strength from API tables 3, lb0.9 = a constant relating proportional limit to yield strength

    From the above equation number 7 & 8 can obtain:

    .9 10

    Where:

    MOP = Margin of overpull, lb

    DF = Design factor, dimensionless

  • 7/23/2019 3 Drill String

    31/43

    27

    Soran University Drilling Engineering I

    The Margin of Overpull is the minimum tension force above expected working load to

    account for any drag or stuck pipe. The MOP used is usually of the order of 100,000 lbs.

    When deciding on the magnitude of the MOP or DF, the following should be considered:

    Overall drilling conditions Hole drag

    Likelihood of getting stuck

    Re-arranging equations 7, 8 & 9 gives the maximum length of pipe (Maximum Hole

    Depth) which can be used from a given grade/weight of drillpipe:

    11 b) Shock Loading

    The additional tensile force generated by shock loading is given by:

    ..12 Where = weight of drillpipe per unit length, lb/ft

    c) Bending

    The additional tensile force generated by bending is given by:

    ..13 Where

    = dog-leg severity in /100 ftD = outside diameter of pipe in inches

    7.4.3. Design Factor

    A design factor of 1.6 should be applied to the tension loads calculated above if shock

    loading is not accounted for. If the shock loading is quantified and included in the load

    calculation, a design factor of 1.3 can be used.

    7.4.4. Slip CrushingThe maximum allowable tension load must also be designed to prevent slip crushing of the

    pipe. Reinhold and Spini 6 proposed an equation to calculate the relationship between the

    hoop stress caused by the action of the slips and the tensile stress in the pipe resulting from

    the load of the pipe hanging in the slips. The equations used are as follows:

    .. .14

    Where:

    TS =Tension load due to slip crushing

    TL =Static load tension

  • 7/23/2019 3 Drill String

    32/43

    The Drillstring T H R E E

    28

    SH/ST = Hoop stress to tension stress ratio as derived from the equation

    below:

    ...15

    Where:

    SH =Hoop stress (psi)

    ST =Tensile stress (psi)

    D =OD of the pipe (in)

    K =Later load factor on slips (1/tan (y + z))

    y =Slip taper (typically 9.4625 degrees)

    z =Arctan

    =Coefficient of friction, typically 0.08 - 0.25

    Ls =Length of slips, usually 12 - 16 in

    When all tension loads are calculated, the pipe grade selected in the collapse calculation

    can be assessed and modified for the tension requirements. It is usually preferable to

    increase the grade rather than the weight, as increasing weight usually has negative effects

    in terms of smaller clearance and high pressure drop.

    Couplings are then selected based on the tension design. For highly deviated well or

    horizontal wells torque and drag modeling is performed to evaluate tension strength

    requirements of the pipe and couplings and the computed torque is used for determining

    coupling requirements.

    7.4.5. Additional Design Variables

    Torsion

    The drillpipe torsional strength, when subjected to pure torsion is given by:

    ..16 Where:

    Q = minimum torsional yield strength (lb-ft)

    Ym= minimum unit yield strength (psi)

    J = polar moment of yield inertia = = 0.098175 * D = outside diameter (in)

    d = inside diameter (in)

  • 7/23/2019 3 Drill String

    33/43

    29

    Soran University Drilling Engineering I

    When drillpipe is subjected to both torsion and tension, as is the case during drilling

    operations, equation 16 becomes:

    17

    Where:

    QT = minimum torsional yield strength under tension (lb-ft)

    A = cross-sectional area (in2)

    P = weight carried, (lb)

    Pipe Stretch of Submerged Drillstring

    e1 = stretch due to weight carried (i.e. weight of drillcollars)

    ..18 e2 = stretch due to suspended weight of drillpipe

    .19 Where:

    P = load carried in lbf

    L = length of drillpipe

    = mud density in ppg

  • 7/23/2019 3 Drill String

    34/43

    The Drillstring T H R E E

    30

    8. Appendix

    Table 11 : Ratings for New and Premium Class Drillpipe

  • 7/23/2019 3 Drill String

    35/43

    31

    Soran University Drilling Engineering I

    F igur e 12: Ratings for Class 2 Used Drillpipe

  • 7/23/2019 3 Drill String

    36/43

    The Drillstring T H R E E

    32

    F igur e 13 : Drillpipe/Drillcollar Combinations

  • 7/23/2019 3 Drill String

    37/43

    33

    Soran University Drilling Engineering I

    9. Calculations

    Example 1// Dimensions and weight of drillpipe

    a) The weight (in air) of 30 ft, of 5 19.5lb/ft Grade G drillpipe with 4 1/2

    connections:

    19.5 lb/ft (Approx. wt.) x 30 ft

    = 585 lbs

    b) The weight of this string in 12 ppg mud:

    585 lbs x 0.817 (buoyancy factor)

    = 578 lbs

    Example 2// Drillcollar dimensions and weights

    a) The weight (in air) of 200 ft of 9 1/2 x 2 13/16 drillcollaris:

    220.4 lb/ft (Approx. wt.) x 200ft

    = 44080 lbs

    b) The weight of this string in 13 ppg mud:

    44080 lbs x 0.801(buoyancy factor)

    = 35308 lbs

    Example 3// Length of Drillcollars for a given WOB

    a) The weight (in air) of 10,000 ft of 5 19.5 lb/ft Grade G drillpipe with 4 1/2 IFconnections:

    21.5 lb/ft (Approx. wt.) x 10,000 ft

    = 215,000 lbs

    b) The weight of this string in 12 ppg mud:

    215,000 lbs x 0.817 (buoyancy factor)

    = 175,655 lbs

    c) The length of 9 1/2 x 2 13/16 drillcollars that would be required to provide 25,000lbs WOB in 12 ppg mud:

    An additional length of drillcollars is required to ensure that the drillpipe is in tension when

    drilling. This additional length of collars will be required to overcome the buoyant force on

    the drillpipe and from the above will be equal to:

  • 7/23/2019 3 Drill String

    38/43

    The Drillstring T H R E E

    34

    With an additional 15% length of drillcollar the total length of collar will be:

    (139 x 1.15) + 219 = 379 ft

    Example 4// Tension design with a single drillpipe

    A drill string consists of 600 ft of 8 in x 2 13/16 in drillcollars and the rest is a 5 in

    drillpipe, 19.5 lbm/ft Grade X 95 drillpipe. If the required MOP is 100,000 lb and mud

    weight is 10 ppg, calculate the maximum depth of hole that can be drilled when (a) using

    new drillpipe (Pt = 501,090 lb) (b) using Class 2 drillpipe having a yield strength (Pt) of

    394,000 lb.

    Solution

    a) For new drillpipe (Pt = 501,090 lb), from using equation 11:

    Wight of the 8 in x 2.13/16 in drillcollars can be found from Table 10, which is equal to

    161.3 Ibm/ft.

    Buoyancy factor, BF could be calculated as follow;

    16,287 ftThe maximum hole depth that can be drilled with a new drillpipe of Grade X 95 under the

    given loading condition is

    = length of drillpipe + length of drillcollars

    = 16,287 + 600 = 16,887 ft

    b) For class 2 drillpipe (Pt = 394,000 Ib), from using equation 11:

    10,452 ft

    Maximum hole depth = 10,452 + 600 = 11,052 ft

  • 7/23/2019 3 Drill String

    39/43

    35

    Soran University Drilling Engineering I

    Example 5// Drill Pipe Design Using Pressure-Area Method

    Well Data:

    Hole size =12 "

    Bit Depth =11,000 ft

    Collar length =500 ft

    Drill Pipe (premium) =5" OD 4.276" ID (Available Grade X-95)

    Drill Collars =8" OD 3.0" ID

    Overpull =100,000 lbs

    Mud Weight =11.5 ppg

    DST packer depth =10,700 ft

    Length of Slips =16"

    Maximum anticipated surface pressure = 5000 psi

    Design Factors:

    Tension = 1.3 - 1.6

    Collapse = 1.0

    Burst = 1.1

    Solution

    A graphical method will be used to select drillpipe grade/weight:

    1. Construct the collapse load line by calculating the maximum collapse pressure at the

    bottom of the drill pipe, using equation 5.

    Collapse load at 10,700 ft = 0.052 x 10,700 ft x 11.5 ppg = 6399 psi

    The design factor for collapse is 1.0. The design load is the calculated load

    multiplied by the design factor. In this case the design load is also 6399 psi .

    2. Plot the load and design lines graphically (see Figure 16) and select an appropriate pipe grade using API tables of pipe collapse resistance data.

    3. Check the burst rating of the pipe grade chosen against the maximum anticipated

    applied surface pressure. Plot burst load and burst design (see Figure 16)

    In this instance the maximum applied surface pressure will be 5000 psi. Use of a design

    factor of 1.1 gives a design load of 5500 psi.

  • 7/23/2019 3 Drill String

    40/43

    The Drillstring T H R E E

    36

    F igur e 16: collapse and burst design loads

    4. Calculate the tension load line using the following steps and plot graphically (figure

    17).

    i. Calculate the buoyancy force (BF1) acting on the bottom of the drill collars

    using:

    BF1 = - (P x A)

    = - (0.052 x 11,000 x 11.5) x (( /4) x (82 - 3

    2))

    = - (6,578 psi) x (43.197 in2)

    = - 284,149 lb

    ii. Calculate the buoyancy force (BF2) acting at the top of the drillcollars.

    BF2 = (P x A)

    = (0.052 x 10,500 x 11.5) x [/4 (8 2 - 5 2) + /4 (4.276 2 -32)]

    = (6,279) x (30.631 + 7.292)

    = + 238,119 lb iii. Calculate the drill collar weight

    DC Weight = 150 x 500 ft = + 75,000 lbs

    iv. Calculate the drill pipe weight

    DP Weight =19.5 x 10,500 = + 204,750 lb

    v. Calculate the shock load

    Shock load = 1500 x pipe weight per foot

    = 1500 x19.5 lb/ft

    = 29,250 lb

  • 7/23/2019 3 Drill String

    41/43

    37

    Soran University Drilling Engineering I

    vi. Now calculate the total dynamic load at surface

    Total dynamic load = - 284,149 (BF1) + 238,119 (BF2) + 75,000

    (drillcollar weight) + 204,750 (drill pipe weight) + 29,250 (shock

    load)

    Total dynamic surface load = + 262,970 lbs

    Note: static load at surface = 233,720 lbi.e. Without shock load

    Static load at top of drillcollars = -284,149 + 75,000 (DC weight in air)

    = -209,149 lb

    Static load at bottom of drillpipe = 238,119 (BF2) + (-209,149) = 28,970 lb

    Dynamic load at bottom of drillpipe = 28,970 + 29,250 = + 58,220 lb

    Plot the static and dynamic load as shown in figure 16.

    5. Calculate the design line for the tension load by multiplying the load on the drill

    pipe at surface and at the top of the collars by the 1.3 design factor (since shock

    loads have been included) and plot as in figure 17 .

    F igur e 17: static and dynamic loads

    6. Calculate the design line for the MOP by adding the 100,000 lb overpull factor to

    the static tension load values calculated earlier and plot as in figure 18.

    7. Calculate the design line for slip crushing using equation (14):

  • 7/23/2019 3 Drill String

    42/43

    The Drillstring T H R E E

    38

    K = (1/tan (y + z))

    y = 9.4625 degrees

    z = Arctan

    Arctan 0.08 = 0.0798

    Ls = Length of slips, usually = 16 in

    TL = static tension at surface = 233,720 lb

    Therefore at the top of the well where the static tension load (i.e. excluding drag) is

    233,720 lb. The slip crushing load:

    TS =T L (SH/ST)

    =233,720 X 1.42=331,882 lb

    The slip crushing value is then recalculated at the bottom of drillpipe (28,970 x 1.42) and

    the slip crushing design line plotted through the two points as shown in figure 18.

    F igur e 18: complete tension design

  • 7/23/2019 3 Drill String

    43/43

    Soran University Drilling Engineering I

    8. The tensile rating of the pipe in lb is computed from the cross sectional area of the

    pipe and the yield strength as follows:

    Drillpipe area = ( /4) (5 2 - 4.276 2) =5.281 sq. in

    Tensile strength = area x yield strength =5.281 x 95000 psi=501,695 lb

    9. Calculate the tension design factors (TDF) at surface:

    Example 6// Pipe Stretch

    A 3.5 drillpipe, 13.3 lbm/ft. Grade S135 premium class, is used to run a 4.5 OD liner to21,000 ft. If the length of drillpipe is 17,500 ft, the mud weight is 16 ppg and the totalweight of the liner is 50,000 lb, calculate the total stretch in the drillpipe.

    Solution:

    e1 = stretch due to weight carried:

    e2 = stretch due to suspended weight of drillpipe

    Total Stretch = e1+ e2 = 89.5 +134.9 = 224.4 in