11

Click here to load reader

300710_Proposed Commercial of ICD Project_Draft_irg

Embed Size (px)

Citation preview

Page 1: 300710_Proposed Commercial of ICD Project_Draft_irg

Client : PT. Indonesia Coal Development (ICD)

Project : Geotechnical Investigation - Bridge, Stockyard and Port Offshore Development

Proposal No. :

Date :

Subject : Costs Estimate

1.1 Site Visit by Surveyor and Senior Engineer

1.2 Mobilisation/Demobilisation of Drilling Equipments

1.3 Mobilisation/Demobilisation of Cone Penetration Testing (CPT) Equipments

1.4 Mobilisation/Demobilisation of Personnel

Engineer

CPT Crew (1 personnel)

Master Drillers and Crews

1.5 - Set up Drilling Rigs

- Onshore (Bridge and Stockyard)

- Offshore (Port)

1.6 Field Work Supervision by Senior Engineer

1.7 CPT Testing (including supervision by Field Engineer and Helper)

1.8 Geotechnical Drilling (Coring, including supervision by Field Engineer)

- Onshore (Coring, including supervision by Field Engineer)

- Offshore (Coring, including supervision by Field Engineer)

1.9 Standard Penetration Test (SPT)

1.10 UDS Sampling

1.11 Sample Handling and Shipment

1.12 Core Box

1.13 Platform

1.14 Pontoon

1.15 Transportation (Vehicle Rent and Fuel)

- Onshore (Vehicle Rent and Fuel)

- Offshore (Boat Rent and Fuel)

1.16 Safety Supplies

1.17 Consumables

2.1 Moisture Content (ASTM D2216)

2.2 Atterberg Limit (ASTM D4318)

2.3 Particle size distribution (ASTM D422)

2.4 Unit Weight (ASTM D2937)

2.5 Triaxial Unconsolidated Undrained (UU) (ASTM D2850)

2.6 Triaxial Consolidated Undrained (CU) (ASTM D4767)

2.7 Oedometer Consolidation (ASTM D2435)

2.8 Uniaxial Compressive Strength Test (ASTM D2166)

2.9 Direct Shear Test (ASTM D3080)

DESCRIPTIONNO

I. FIELD INVESTIGATION

II. LABORATORY TESTING

SUB TOTAL :

Page 2: 300710_Proposed Commercial of ICD Project_Draft_irg

2.10 California Bearing Ratio (CBR) (ASTM D1883)

2.11 Standard Compaction (ASTM D698)

3.1 Principal & Associate Engineer

3.2 Senior Geotechnical Engineer

3.3 Civil Engineer

3.4 GIS Engineer

3.5 Draftsman & Technicians

3.6 Project Management

3.7 Administration Support

Notes :

1. Costs are based on Estimated Quantities

2. Estimate of the costs for fieldwork component is based on estimated rate of progress of CPT and Drilling per day which is considered realistic for the site condition

3. Given that the actual quantities will depend on ground and weather condition encountered, our unit rates would apply whether estimated quantity and period is exceeded

4. Costs may vary depending on the actual work condition and consequent time involved, however our costs estimate would not be exceeded without PT. ICD approval

SUB TOTAL :

TOTAL ESTIMATED (EXCLUDING VAT) :

III. ANALYSIS AND REPORTING

SUB TOTAL :

(Bearing Capacity Analysis, Foundation Calculation, Stability Analysis, Soil/Rock Improvement, etc,

Review and Recommendation)

Page 3: 300710_Proposed Commercial of ICD Project_Draft_irg

BRIDGE STOCKYARD PORT OFFSHORE

1 1 1

1 1 -

3 3 2

1 1 -

5 5 7

6 6 -

- - 6

30 40 -

180 180 -

- - 180

90 90 90

36 36 36

36 36 36

36 36 36

- - 6

- - 1

1 1 -

- - 2

10 10 10

40 40 40

54,600,000IDR

91,000,000IDR

91,000,000IDR

20,475,000IDR

163,800,000IDR

245,700,000IDR

49,140,000IDR

19,656,000IDR

4,914,000IDR

14,742,000IDR

327,600,000IDR

10,920,000IDR

13,650,000IDR

109,200,000IDR

382,200,000IDR

196,560,000IDR

AMMOUNT

IDR

13,650,000IDR

136,500,000IDR

36,400,000IDR

5,460,000IDR

46,410,000IDR

45,500IDR

136,500IDR

54,600,000IDR

54,600,000IDR

1,365,000IDR

IDR 1,820,000

IDR

13,650,000IDR

45,500,000IDR

10,920,000IDR

2,730,000IDR

2,730,000IDR

910,000IDR

45,500,000IDR

682,500IDR

each

sum

sum 45,500,000IDR

ESTIMATED QUANTITY

1

set

each

days

sum

UNIT

m

sum

2,275,000IDR

TOTAL

IDR

UNIT RATE

sum

sum

sum

sum

4,550,000IDR

21,840,000IDR

days

days 2,730,000IDR

5,460,000IDR

40

182,000IDR

182,000IDR

each

each

each

each

set 30 30 30

546,000IDR

1,365,000IDR

SUB TOTAL :

each

each

m

2,055,417,000IDR

IDR 163,800,000

Page 4: 300710_Proposed Commercial of ICD Project_Draft_irg

20 20 20

40 40 40

40 40 40

40 40 40

20 20 20

20 20 20

1 1 1

1 1 1

2. Estimate of the costs for fieldwork component is based on estimated rate of progress of CPT and Drilling per day which is considered realistic for the site condition

3. Given that the actual quantities will depend on ground and weather condition encountered, our unit rates would apply whether estimated quantity and period is exceeded

4. Costs may vary depending on the actual work condition and consequent time involved, however our costs estimate would not be exceeded without PT. ICD approval

SUB TOTAL :

TOTAL ESTIMATED (EXCLUDING VAT) :

16,380,000IDR

10,920,000IDR

54,600,000IDR

27,300,000IDR

IDR 273,000

1,365,000IDR

IDR 1,820,000

273,000IDR

182,000IDR

18,200,000IDR

9,100,000IDR

SUB TOTAL :

455,000IDR

273,000IDR

manhour

manhour

sum

sum

set 30 30 30

163,800,000IDR

54,600,000IDR

180,180,000IDR

IDR 163,800,000

IDR 16,380,000

32,760,000IDR

360,360,000IDR

2,595,957,000IDR

set

manhour

manhour

manhour

Page 5: 300710_Proposed Commercial of ICD Project_Draft_irg

on-site based arrival (YBM Machine Rate)

on-site based arrival (5 ton Cpacity CPT Rigs)

on-site based arrival

on-site based arrival

on-site based arrival

1.00USD 9,100.00IDR

TOTALRemarks

IDR

2,055,417,000IDR

Page 6: 300710_Proposed Commercial of ICD Project_Draft_irg

180,180,000IDR

360,360,000IDR

2,595,957,000IDR

Page 7: 300710_Proposed Commercial of ICD Project_Draft_irg

Client : PT. Indonesia Coal Development (ICD)

Project : Geotechnical Investigation - Bridge, Stockyard and Port Offshore Development

Proposal No. :

Date :

Subject : Tentative Work Schedule

Duration

(Days) 1 2 3 4 5

1 Preliminary Site Visit 4

2 Mobilization and Demobilization 3(Drilling & SPT Equipment, Personnels, etc)

3 Moving of Equipment And Set Up of Rigs 9

4 Full Core Drilling 36HQ diameter - based on ASTM D-2112

5 Undisturbed Sampling "Shelby Tube" 36at 2 m intervals base on ASTM D-1586

6 Standard Penetration Test (SPT) 36at 5 m intervals based on ASTM D 1586-1587

7 Cone Penetration Test (CPT) 4030

8 Sample Handling, Packing & Shipping 12

9 Laboratory Test 40

10 Geotechnical Analysis 21

11 Reporting 14

GeneralField Work - StockyardField Work - BridgeField Work - Port OffshoreLaboratory WorkOffice Work

No Description 1st Week

Page 8: 300710_Proposed Commercial of ICD Project_Draft_irg

6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 75th Week 6th Week1st Week 2nd Week 3rd Week 4th Week

Page 9: 300710_Proposed Commercial of ICD Project_Draft_irg

1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 212th Week7th Week 8th Week 9th Week 11th Week10th Week

Page 10: 300710_Proposed Commercial of ICD Project_Draft_irg

3 4 5 6 712th Week

Page 11: 300710_Proposed Commercial of ICD Project_Draft_irg

Desription Amount (IDR)

Field Investigation IDR 2,055,417,000

Laboratory Testing IDR 180,180,000

Analysis and Reporting IDR 360,360,000

Total Estimate (Excluding VAT) IDR 2,595,957,000