12
Conversion Status 72 Total Scope

3g Upgrades Iub

Embed Size (px)

DESCRIPTION

3G Upgrades

Citation preview

Page 1: 3g Upgrades Iub

Balance

Conversion Status 72 6 66

Total Scope

Completed

Page 2: 3g Upgrades Iub

8.33%

% Completion

Page 3: 3g Upgrades Iub

Site_Name Tx Type

3705_MUMBWA E1 Sites 1984 1717313304_CHISAMBA E1 Sites 1984 03153_MALCOM_WATSON E1 Sites 1984 491953123_KASUMBALESA E1 Sites 1984 04088_Lubengele_Coverage E1 Sites 1984 03178_HELEN_KAUNDA E1 Sites 1984 03409_SINDA E1 Sites 1984 03508_NCHELENGE E1 Sites 1984 31503500_MANSA E1 Sites 1984 11363511_KAWAMBWA E1 Sites 1984 93505_SAMFYA E1 Sites 1984 03397_KAFUE_3_RIF E1 Sites 1984 279873518_CHINSALI E1 Sites 1984 66645885_KASAMA_TOWN_3_RLF E1 Sites 1984 2083503_MPULUNGU E1 Sites 1984 1203502_MBALA E1 Sites 1984 173519_MPOROKOSO E1 Sites 1984 03520_MUNGWI E1 Sites 1984 03880_T1069_KANSANSHI_MINE_VILLAGE E1 Sites 1984 1948713720_ZAMBEZI E1 Sites 1984 03785_MUKINGEMISION E1 Sites 1984 03226_MAAMBA E1 Sites 1984 125805162_MAZABUKA_TOWN E1 Sites 1984 05121_SOS_VILLAGE E1 Sites 1984 03234_CHIKANKATA E1 Sites 1984 03814_KAFUE_RIVERSIDE E1 Sites 1984 03371_ZIMBA_TOWN E1 Sites 1984 03703_MWANDI E1 Sites 1984 03309_MKUSHI_TOWN E1 Sites 1984 03937_CHISAMBA_FARMS E1 Sites 1984 04084_T3159_CHILILABOMBWE_KAMEZA E1 Sites 1984 03171_KABUSHI E1 Sites 1984 03186_KITWE_INDUSTRIAL E1 Sites 3968 03436_KATOPOLA-HILL E1 Sites 1984 4850733444_KATETE_JUNCTION E1 Sites 1984 113663440_MUTILASEMBE E1 Sites 1984 78813402_KATETE E1 Sites 1984 8843428_CHIPATA-SHOPRITE E1 Sites 1984 203441_MCHENGA E1 Sites 1984 83460_PETAUKE_JUNCTION E1 Sites 1984 13468_LUNDAZIEAST3 E1 Sites 1984 13406_NYIMBA E1 Sites 1984 0

IUB Configuration

IUB Congestion Failure

Page 4: 3g Upgrades Iub

3412_CHAMA E1 Sites 1984 03414_CHADIZA E1 Sites 1984 03429_CHIEF_MWANSE E1 Sites 1984 03548_MUTENDE E1 Sites 1984 17684145_T3409_MANSA_EXT E1 Sites 1984 383784_T3376_ZNBC_TRANSMITTER_KABESHA E1 Sites 1984 23615_CHAKOPA E1 Sites 1984 03856_KAFUE_SUGAR E1 Sites 1984 03507_MPIKA E1 Sites 1984 3885973542_KASAMA-TOWN E1 Sites 3968 2560683654_MPIKA2 E1 Sites 1984 10703547_LAURA_SCHOOL E1 Sites 1984 1484140_NP_KASAMA_ZAMTEL_COMPLEX E1 Sites 1984 473605_TAZARA E1 Sites 1984 25963_NAKONDE_3_Rlf E1 Sites 1984 03517_ISOKA E1 Sites 1984 03512_LUWINGU E1 Sites 1984 03514_KAPUTA E1 Sites 1984 03723_MUFUMBWE E1 Sites 1984 03724_MANYINGA E1 Sites 1984 03205_CHIRUNDU E1 Sites 1984 3331523206_SIAVONGA E1 Sites 1984 175102_MONZE_BARCLAYS E1 Sites 1984 03212_MONZE E1 Sites 3968 03228_ITEZHI_TEZHI E1 Sites 1984 03214_KAZUNGULA E1 Sites 1984 03704_SESHEKE E1 Sites 1984 24815192_MONGU1RLF E1 Sites 1984 7373701_SENANGA E1 Sites 1984 03713_LUKULU E1 Sites 1984 0

2815

Page 5: 3g Upgrades Iub

17-08-15 18-08-15 19-08-15 20-08-15 21-08-15 22-08-15 23-08-15

89 90 90 91 89 91 9085 86 73 85 73 88 8393 77 66 93 69 92 5183 79 83 88 91 90 8789 91 91 86 82 85 6288 67 77 91 48 64 5187 65 79 85 74 74 8089 87 88 89 88 81 9085 89 90 89 88 88 8686 87 92 92 87 67 9078 91 85 86 80 68 7891 93 93 88 90 92 9288 90 88 89 88 88 8985 83 90 74 89 92 9286 89 90 89 87 87 8779 74 79 85 83 92 9087 92 92 93 85 93 9394 93 88 93 49 88 8386 88 90 83 82 85 8590 84 82 84 82 79 7593 84 74 94 60 86 2688 88 89 88 89 88 9092 90 91 92 85 88 9180 86 79 93 87 92 9274 79 79 88 82 92 9372 81 86 92 76 94 7569 51 55 72 71 93 7588 35 67 79 49 90 9287 87 87 89 84 84 8075 47 92 93 41 92 5787 80 89 85 81 92 9386 91 84 77 85 91 6985 82 89 88 84 86 6291 88 90 87 88 91 9293 92 91 92 91 88 9383 83 84 92 83 92 8992 91 90 92 91 91 9277 82 84 79 80 82 7989 89 88 87 80 84 9092 91 89 75 59 83 9469 80 77 86 76 73 7889 87 90 89 90 83 80

Page 6: 3g Upgrades Iub

87 86 83 86 85 88 9064 80 61 83 89 85 9383 54 80 61 52 91 8287 67 71 80 68 66 8290 90 90 67 59 90 8375 57 91 73 72 79 5075 86 93 64 60 85 8071 74 74 80 65 85 5792 92 89 90 89 90 9277 82 91 88 89 85 8389 88 89 89 89 89 8791 88 91 91 89 91 8891 92 84 83 85 92 9287 92 92 92 89 91 9288 88 89 89 85 87 8989 85 76 89 87 90 9076 86 92 85 87 83 9072 91 91 85 81 91 7585 71 92 74 85 91 9049 81 91 89 78 91 8488 90 89 88 88 89 8779 85 86 89 89 89 8689 92 90 91 88 87 8980 83 80 85 88 92 9190 90 90 83 81 88 7274 85 72 83 89 73 6592 92 93 93 91 93 9385 93 90 88 85 88 9092 89 85 87 90 91 9355 68 54 83 55 90 89

Page 7: 3g Upgrades Iub

24-08-15 Site_ID Province Status

90 90 ZM0143 Central Pending 92 83 ZM0015 Central Pending 85 78 ZM0800 Copperbelt Pending 91 87 ZM0037 Copperbelt Pending 74 82 ZM6842 Copperbelt Pending 84 71 ZM3292 Copperbelt Pending 90 79 ZM0138 Eastern Pending 91 88 ZM0202 Luapula Pending 88 88 ZM0056 Luapula Pending 90 86 ZM0186 Luapula Pending 82 81 ZM0148 Luapula Pending 92 91 ZM6489 Lusaka Pending 88 89 ZM0177 Northern Pending 84 86 ZM3981 Northern Pending 91 88 ZM0128 Northern Pending 84 83 ZM0124 Northern Pending 93 91 ZM0196 Northern Pending 93 85 ZM0251 Northern Pending 85 86 ZM6802 North-Western Pending 88 83 ZM0206 North-Western Pending 92 76 ZM3777 North-Western Pending 92 89 ZM0154 Southern Pending 87 90 ZM0057 Southern Pending 89 87 ZM3578 Southern Pending 93 85 ZM0150 Southern Pending 75 81 ZM0879 Southern Pending 86 72 ZM3164 Southern Pending 93 74 ZM0129 Western Pending 80 85 ZM0677 Central Pending 93 74 ZM3453 Central Pending 91 87 ZM6634 Copperbelt Pending 92 85 ZM3278 Copperbelt Pending 84 82 ZM3280 Copperbelt Pending 89 90 ZM3341 Eastern Completed93 92 ZM3709 Eastern Completed84 86 ZM3386 Eastern Completed87 91 ZM0120 Eastern Completed82 81 ZM0836 Eastern Completed92 87 ZM3959 Eastern Pending 68 81 ZM3547 Eastern Pending 72 76 ZM3823 Eastern Completed89 87 ZM0132 Eastern Pending

Average for last week

Page 8: 3g Upgrades Iub

90 87 ZM0173 Eastern Pending 82 80 ZM0175 Eastern Pending 93 75 ZM0833 Eastern Pending 66 73 ZM3038 Luapula Pending 89 82 ZM6955 Luapula Pending 85 73 ZM6777 Luapula Pending 90 79 ZM0840 Luapula Pending 70 72 ZM3305 Lusaka Pending 91 90 ZM0195 Northern Pending 90 86 ZM3981 Northern Pending 88 88 #N/A Pending 91 90 ZM3077 Northern Pending 87 88 ZM6951 Northern Pending 81 90 ZM3425 Northern Pending 89 88 ZM6190 Northern Pending 90 87 ZM0180 Northern Pending 89 86 ZM0192 Northern Pending 92 85 ZM0183 Northern Pending 90 85 ZM0255 North-Western Pending 80 81 ZM0497 North-Western Pending 89 89 ZM0014 Southern Pending 90 87 ZM0077 Southern Pending 88 89 ZM3340 Southern Pending 93 86 ZM0060 Southern Pending 84 85 ZM0181 Southern Pending 87 78 ZM0102 Southern Pending 92 92 ZM0137 Western Pending 88 88 ZM6194 Western Pending 93 90 ZM0149 Western Pending 73 71 ZM0190 Western Pending

Page 9: 3g Upgrades Iub

Comments Target Closure tx comment

NEC Upgrade, site access issue 2/10/2015Check last mile configurations 24/09/2015Copperbelt Project 15/11/2015Copperbelt Project 15/11/2015Copperbelt Project 15/11/2015Copperbelt Project 15/11/2015convert to FEconvert to FEconvert to FE connecting to New RNCconvert to FEconvert to FEconvert to FEconvert to FE connecting to New RNCconvert to FEconvert to FEconvert to FEconvert to FEconvert to FEconvert to FENEC Project 15/01/2015NEC Project 15/01/2015convert to FEconvert to FEconvert to FEconvert to FEconvert to FEconvert to FENEC Project 15/01/2016Ericsson upgrades 2/10/2015Check last mile configurations 24/09/2015Copperbelt Project 15/11/2015Copperbelt Project 15/11/2015Copperbelt Project 15/11/2015Last mile upgraded, convert to FE 24/09/2015Last mile upgraded, convert to FE 24/09/2015Last mile upgraded, convert to FE 24/09/2015Last mile upgraded, convert to FE 24/09/2015Last mile upgraded, convert to FE 24/09/2015Last mile upgraded, convert to FE 24/09/2015convert to FELast mile upgraded, convert to FELast mile upgraded, convert to FE

Page 10: 3g Upgrades Iub

Last mile upgraded, convert to FEconvert to FEconvert to FEconvert to FEconvert to FE connecting to New RNCconvert to FE connecting to New RNCconvert to FEconvert to FEconvert to FE site visit requiredconvert to FEconvert to FE site visit requiredconvert to FEconvert to FEconvert to FEconvert to FEconvert to FE can be doneconvert to FEconvert to FENEC Project 15/01/2015NEC Project 15/01/2015convert to FE can be doneconvert to FE can be doneconvert to FEconvert to FEconvert to FENEC Project 15/01/2016NEC Project 15/01/2016NEC Project 15/01/2016 can be doneNEC Project 15/01/2016NEC Project 15/01/2016