Annex 1.2 Typical Delegation of Duties & Authority to a Resident Engineer In accordance with Sub-Clause 3.2 of the General Conditions of Contract (GCC), I hereby further delegate authority to Mr ____ as detailed below. All references to Sub-Clause numbers shall expressly include reference to any associated Particular Conditions of Contract (PCC). Therefore, separate reference is not made to the PCC, except where for any reason including clarity it is necessary to refer to a specific Sub-Clause in the PCC. Multiple delegations against a particular Sub-Clause generally follow the same sequence in which the circumstance occurs in the text of the Sub-Clause. GCC Sub Clause No Heading Delegation 1.3 Communication s To receive communications. To issue communications within the limitations confirmed elsewhere in this notification of delegation. 1.8 Care and Supply of Documents To receive copies of the Contractor’s Documents. 1.9 Error’s in the Employer’s Requirements To receive notices. 1.12 Confidential Details To require disclosure of confidential and other information. 2.1 Right of Access to the Site To receive notices. 2.3 Employer’s Personnel Mr ......... is included in Employer’s Personnel. 3.1 Engineer’s Duties and Authority Mr ......... is authorised to exercise the authority attributable to Mr…………, subject to the delegations stated herein. Delegation of authority to Mr ......... does not preclude the requirement for Mr ......... to seek the approval of the Employer where expressly required in the Contract. In sub clause (a), Mr ......... is Annex 1-2 Delegation to RE Page 1 of 7

4. A1-2 Delegation to RE Final Draft

Embed Size (px)

DESCRIPTION

model

Citation preview

Annex 1.2Typical Delegation of Duties & Authority to a Resident EngineerIn accordance with Sub-Clause 3.2 of the General Conditions of Contract (GCC), I hereby further delegate authority to Mras detailed below. !ll references to Sub-Clause nu"bers shall e#$ressly include reference to any associated %articular Conditions of Contract (%CC). &herefore, se$arate reference is not "ade to the %CC, e#ce$t where for any reason including clarity it is necessary to refer to a s$ecific Sub-Clause in the %CC. Multi$le delegations against a $articular Sub-Clause generally follow the sa"e se'uence in which the circu"stance occurs in the te#t of the Sub-Clause.GCC Su Clause !o Heading Delegation(.3 Communications &o recei)e co""unications. &o issue co""unications within the li"itations confir"ed elsewhere in this notification of delegation.(.*Care and Supply of Documents &o recei)e co$ies of the Contractor+s ,ocu"ents.(.- Errors in the Employers Requirements &o recei)e notices. (.(2 Confidential Details &o re'uire disclosure of confidential and other infor"ation.2.( Right of Access to the Site &o recei)e notices. 2.3 Employers Personnel Mr ......... is included in ."$loyer+s %ersonnel.3.(Engineers Duties and Authority Mr ......... is authorised to e#ercise the authority attributable to Mr////, sub0ect to the delegations stated herein. ,elegation of authority to Mr ......... does not $reclude the re'uire"ent for Mr ......... to see1 the a$$ro)al of the ."$loyer where e#$ressly re'uired in the Contract. In sub clause (a), Mr ......... is authorised to act for the ."$loyer. In sub clause (c), reference to the .ngineer shall include any $erson with delegated authority $ro$erly issued under the Contract."CC Su#Clause !o $.1Engineers Duties and Authority In res$ect of e"ergencies, Mr ......... is authorised to act on Mr. ////.+s behalf, sub0ect to the $ro)ision of reference to Mr. Cross"an for $rior a$$ro)al for "atters sub0ect to Clause (3.3.2 Delegation by the Engineer Mr ......... has no authority to issue further delegations.3.3 Instructions of the Engineer &o issue instructions in writing only relating to re"edying of any defects or to safety.3.2 Management Meetings &o re'uire "eetings. &o record decisions, $re$are and issue records of the "eetings.3.( Contractors &o re'uire details to be sub"itted by the Contractor.!nne# (-2 ,elegation to 4. %age ( of 5GCC Su Clause !o Heading Delegationeneral !bligations &o recei)e notifications of alterations.3.2 Performance Security &o recei)e a co$y of the Security.3.3 Contractors Representati"e &o recei)e the Contractor+s $ro$osals and6or all notifications forall consents re'uired by this clause.3.3 Subcontractors Sub-Clause (c)7 &o recei)e notices.3.8 Co#operation &o recei)e docu"ents.3.2 Setting !ut &o issue notifications of setting out. &o recei)e notices.3.- $uality Assurance &o recei)e $rocedures and co"$liance docu"ents.3.(2 %nforeseeable Physical Conditions &o recei)e notices. &o ins$ect $hysical conditions. &o re)iew other $hysical conditions. &o ta1e due account of e)idence foreseen by the Contractor.3.(8 &ransport of oods &o recei)e notices.3.(2 Contractors Equipment &o issue consents to the Contractor.3.29 Employers Equipment and 'ree#Issue Material &o recei)e notices.3.2( Progress Reports &o recei)e "onthly re$orts.3.22 Security of the Site &o notify the Contractor of rele)ant %ersonnel.3.23 Contractors !perations on Site &o agree additional areas for Contractor+s o$erations. &o recei)e a$$lications for, and to issue of consents, in res$ect of o$erations.3.23 'ossils &o recei)e notices of disco)ery. &o recei)e notices in res$ect of delay6Cost.5.( eneral Design !bligations &orecei)e$ro$osalsinres$ect of designersanddesignsub-contractors. &o recei)e notices of error, fault or defect.5.2Contractors Documents &o recei)e Contractor+s ,ocu"ents. &o recei)e notice of $ro$osed "odification.&o re'uire further Contractor+s ,ocu"ents.5.3 &echnical Standards and &o recei)e notices, and if a$$ro$riate, $ro$osals. &o deter"ine co"$liance.!nne# (-2 ,elegation to 4. %age 2 of 5GCC Su Clause !o Heading DelegationRegulations5.8As#(uilt Documents &o recei)e co$ies of records. &o recei)e co$ies of drawings, and to issue consent as to details. &o re)iew drawings.5.2 !peration and Maintenance Manuals &o recei)e co$ies of $ro)isional and final "anuals.8.5 )or*ing +ours &o recei)e ad)ice.8.2+ealth and Safety &o recei)e accident re$orts. &o re'uire re$orts. &o recei)e Contractor+s Safety Methodology. 8.(9 Records of Contractors Personnel and Equipment &o recei)e details.2.2 Samples &o recei)e sa"$les. &o re)iew sa"$les2.3 Inspection &o recei)e notices. &o carry out e#a"inations etc2.3 &esting &o agree ti"e and $lace of testing. &o issue notices to attend tests. &o issue instructions. &o recei)e notices. &o recei)e re$orts of tests. &o endorse re$orts of tests, sub0ect to $rior consultation with M. %ettersson. &o endorse re$orts and6or issue certificates.2.5 Re,ection &o re0ect %lant, Materials, design or wor1"anshi$. &o re'uire %lant, Materials, design or wor1"anshi$ to be retested.*.3 Programme &o recei)e $rogra""es &o issue notices of non co"$liance. &o recei)e notices of future e)ents. &o re'uire sub"ittal of esti"ates and6or $ro$osals.*.- Consequences of Suspension &o recei)e notices.*.(( Prolonged Suspension &o recei)e re'uests. &o recei)e notices.*.(2 Resumption of )or* &o e#a"ine the :or1s.-.( Contractors !bligations &o recei)e notices.!nne# (-2 ,elegation to 4. %age 3 of 5GCC Su Clause !o Heading Delegation-.2 Delayed &ests &o recei)e notices.-.3 Retesting &o re'uire re$etition of tests, after consultation with 4esident .ngineer-.3 'ailure to Pass &ests on Completion &o order re$etitions, after consultation with 4esident .ngineer(9.( &a*ing !"er of the )or*s and Sections &o recei)e notices of readiness for &a1e ;)er.(9.2 &a*ing !"er of Parts of the )or*s &o recei)e Contractor+s re'uests. &o recei)e notices of Costs.(9.3 Interference -ith &ests on Completion &o recei)e notices of ti"e and6or Costs.((.8 'urther &ests &o re'uire re$etition of tests.((.* Contractor to Search &o re'uire searches.(2.2 Delayed &ests &o recei)e notices.(2.3 'ailure to Pass &ests after Completion &o recei)e notices.(3.( Right to .ary &o recei)e notices.(3.2 .alue Engineering &o recei)e sub"ittals.(3.3 .ariation Procedure !ll "atters relating to