April 15, 2019 40’ PARCEL REQUIRED TO CONSTRUCT OHME SUBSTATION Existing Olds Station Substation Future Ohme Substation Location of Proposed 40’ Purchase

40’ PARCEL REQUIRED TO CONSTRUCT OHME SUBSTATION · April 15, 2019. 40’ PARCEL REQUIRED TO CONSTRUCT OHME SUBSTATION . Existing . Olds Station. Substation. Future. Ohme. Substation

  • Upload
    others

  • View
    11

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 40’ PARCEL REQUIRED TO CONSTRUCT OHME SUBSTATION · April 15, 2019. 40’ PARCEL REQUIRED TO CONSTRUCT OHME SUBSTATION . Existing . Olds Station. Substation. Future. Ohme. Substation

April 15, 201940’ PARCEL REQUIRED TO CONSTRUCT OHME SUBSTATION

Existing Olds StationSubstation

FutureOhme

Substation

Location of Proposed

40’ Purchase

Page 2: 40’ PARCEL REQUIRED TO CONSTRUCT OHME SUBSTATION · April 15, 2019. 40’ PARCEL REQUIRED TO CONSTRUCT OHME SUBSTATION . Existing . Olds Station. Substation. Future. Ohme. Substation

Proposed PropertyLine

April 15, 2019

TOPOGRAPHY OF PROPOSED 40’ AQUISITION

Page 3: 40’ PARCEL REQUIRED TO CONSTRUCT OHME SUBSTATION · April 15, 2019. 40’ PARCEL REQUIRED TO CONSTRUCT OHME SUBSTATION . Existing . Olds Station. Substation. Future. Ohme. Substation

Neighboring Property

ExistingSubstation Property

Current Status• Additional property needed

Site Work Required• Build 4’ X 300’ retaining wall• Relocate existing waterline• 1200 cubic feet soils removal• Grading• Sum of work ~ $326K

• 2019- Targeted construction

OhmeSubstation Layout

Olds Station