Basics of OEE Loss Tree
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 2/30
Why Effective Maintenance?
Equipment Breakdown80%
90%Do you think this
5.57%
60%
70%
40%
50% AAMET Loss Structure
5.21%
20%
30%
Changeovers
2.02%
0%
10%
Equipment Breakdown 5.57
Minor Stoppages 5.21Changeovers 2.02
s a o a
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 3/30
16 Big LossesLost Tree
120%
41%
62%
40%
60%
80%
20% 21%38%
2% 4% 9%
14%22%
0%
20%
S T A R
T U P
N T &
A D J
S E R V
I C E
G E O V E
R
E W O R
K S
O G I S
T I C S
T O P P
A G E
A K D O
W N
M E A S
U R E
R E L I G
I O U
C H A
D E F E
C T &
M I N O
R
E Q . B R
Minor Stoppages 100%
60%
80%
100%
120%
Breakdown100%
80%
100%
120%
34% 44%7%
14%22%
0%
20%
40%
h e r s
c t i o n n t
r o l
s t e m t u
r e
19%
52%
3% 6% 10%16%
22%29%
48%
0%
20%
40%
m m r s i l l o l o n r e m
A C M A
S
P a p e
r C
W r a p
p i n g S
D i e s T e
m p e
C o n t
r o l S
y s t
A C M A
H e a t i n g S
y s t
O t h
P a p
e r C o n
A C M
A S u c
t
D i e s T e
m p e
r a t
W r a p p i n
g S y s
t
Dies Temperature Wrapping
Priori ty to be solved
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 4/30
16 Big Losses in Manufacturing
e
Awaiting
Instruction
7 Major Losses which obstruct Overall Equipment Efficiency (OEE)5 Major Manpower Losses
(accompany the 7 major losses in equipment)
Working hour
Loading Time
u own os ses
(1) Equipment Failure
Loss
S c h e d u l e d d o w n t i
Operating man hour
Loading man hour(9) Management
Awaiting
materials
loss
Operating Time
Net
Operating TimeValued
Cleaning
checking
et-up an
Adjustment Loss
(3) Cutting blade and
jig change Loss
Downtime Loss
Performance Loss
Net Operating
man hour
Effective
man hourValued
oss
(10) Operating Motion
Loss
Equipment Downtime loss
Operating TimeAwaiting
Instruction
Awaiting
materials
Awaiting
(4) Start-up Loss
Other downtime Loss
Defects
Quality
Loss
man hourEquipment Performance loss
Method/Procedures loss
Skill & moral loss
3 Major Losses which obstruct Efficiency of
material,die,jig,tool and energy
personne
distribution
Quality
confirmation
(adjustment of
measurement)
(5) Minor Stoppages
& idling Loss
(6) Speed Loss
(11) Line OrganisationLoss
Line Organisation loss
Automatization failure loss
(15) Energy Loss
Start-up loss
Overload loss
(14) Yield Loss
Defects quality loss
Start-up loss
Cutting loss
(7) Defects
& Rework Loss
(12) Logistics
(13) Measurement &Adjustment loss
Temperatureosses n we
Losses in overages
(16) Die, tool & jig Loss
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 5/30
Semua Losses - > Biaya
1 Equipment Breakdown
2 Set U / Chan e Over
T
3 Aktivitas Rutin
4 Start Up / Ramp Down
5 Minor Stoppage
7 Major Equipment Losses ta
l6 Speed
7 Defects and Rework
8 ShutdownShutdown Loss
i
m
o
s
L
oanagemen
10 Operational Motion
11 Line Organisation5 Major Manpower Losses
e s
s
e
og s cs13 Measurement & Adjustment
14 Energy3 Ma or Material & Ener
C C
o15 Maintenance Spare Parts
16 YieldLosses
s
t
s
t
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 6/30
7 losses Penghambat OEE
100% Aktivitas Rutin Aktivitas Rutin
i t y
C a p a b i l
Time
Start-Up Minor Stoppages Defects Failures/
Breakdown
Setup &
Adjustment
(C/O)
Ramp-Down
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 7/30
1. Failure Loss (Breakdown)
Ini adalah loss karena mesin berhenti (tidak diharapkan) yangsama atau lebih dari 10 menit, dan terjadi secara sporadik
.
Contohnya :. o or er a ar
2. Shaft patah
3. Bearing Macet
Note : Jika kerusakan berlangsung ke shift berikutnya (misalnya karena
tidak ada spare part, maka shift berikutnya akan dihitung sebagai PM)
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 8/30
Failure Loss (Breakdown)
100% Capabil ity
Failures
Time
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 9/30
2. Set-up / Change Over Loss
dari produk 1 ( pada speed dan kualitas normal ) ke produklainnya ( pada kecepatan dan kualitas normal ).
Loss ini termasuk Change Over Packaging,Size, & Variant.
Elemen yang paling lama ketika melakukan Change Over
adalah test-running dan adjusment ( penyetelan ).
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 10/30
Set-up / Change Over Loss
100% Capabil ity
Failures Setup / Change
Over
Time
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 11/30
3. Routine Activity (Aktivitas Rutin) Loss
Loss yang terjadi akibat pemberhentian mesin rutin untuk
mengganti mata gerinda, mata gergaji, cutter ketika sudah
tum ul atau rusak chan e blade .
Loss ini juga termasuk penggantian wrapper, cleaning rutin di
pertengahan minggu (misalnya tiap shift), dll.
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 12/30
Routine Activity Loss
100% Capabil ity
Aktivitas Rutin Aktivitas Rutin
Failures Setup & C/O
Time
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 13/30
4. Start Up/Ramp Down Loss
.
mulai dari mesin dijalankan sampai mencapai kondisi stabilpada kecepatan normal dan kualitas produk yang bagus.
Start Up Losses dapat terjadi setelah :
- Perbaikan rutin (PM)
- Mesin berhenti dalam waktu an lama
- Liburan- Istirahat makan
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 14/30
Start Up/Ramp Down Loss
100% Capabil ity
Aktivitas Rutin Aktivitas Rutin
Start-Up
LossFailures Setup & C/O
TimeRamp-down
Loss
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 15/30
5. Minor Stoppages & Idling Loss
,
mengakibatkan mesin berhenti sesaat dan jalan lagi dalamwaktu yang relatif singkat ( kurang dari 10 menit ).
Hal ini biasanya terjadi karena produk tersangkut pada suatu
bagian mesin atau ketika produk defect mengaktifkan sensor
an men hentikan mesin.Pada kasus-kasus ini, produk hanya perlu dipindahkan dan
mesin di-reset untuk dijalankan kembali.
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 16/30
Minor Stoppages & Idling Loss
100% Capabil ity
Aktivitas Rutin Aktivitas Rutin
Start-Up
LossMinor Stoppages
and IdlingFailures Setup & C/O
TimeRamp-down
Loss
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 17/30
6. Speed Loss
Loss ini ter adi karena erbedaan s eed antara desi n s eed
mesin terhadap speed aktual mesin ketika jalan.Ketika mesin dijalankan pada design speed, kadang-kadang
,
operator menurunkan speed mesin.
Ada 2 tipe Speed Loss :
- Loss karena perbedaan antara actual speed dengan standard speed.- Loss yang diakibatkan karena design speed lebih rendah dari teknologi
saat ini ataupun kondisi yang diinginkan.
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 18/30
Speed Loss
100% Capabil ity
pee oss Aktivitas Rutin Aktivitas Rutin
Start-Up
LossMinor Stoppages
and IdlingFailures Setup & C/O
TimeRamp-down
Loss
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 19/30
7. Defect and Rework Loss
Waktu yang digunakan untuk menghasilkan produk yang reject
dan juga waktu yang digunakan untuk menghasilkan
waste/rework.
Material/energi yang berkaitan dengan rework ini akan dihitung
pada Energy & Yield Loss.
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 20/30
Defect and Rework Loss
100% Capabil ity
pee oss Aktivitas Rutin Aktivitas Rutin
Start-Up
LossMinor Stoppages
and IdlingDefects Failures Setup &C/O
TimeRamp-down
Loss
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 21/30
Loss mempengaruhi Utilisasi
8. SHUTDOWN LOSS adalah loss akibat scheduled downtime
(planned stoppages). Ini adalah waktu yang yang dijatah tidak
.
tanggung jawab management atau engineering, bukandepartemen produksi.
Loss ini termasuk :
- Holidays (hari libur)- o ro uct on r ers t a a a rencana pro u s m sa nya arena :
planner tidak membuat planning, training, teambuilding, dan 3 masalah yang
diketahui 1 shift sebelumnya yaitu tidak ada operator, tidak ada utility, & tidak ada
material.
- Planned Modifikasi- Planned Maintenance ( PM), termasuk kerusakan mesin/perbaikan (yang
diketahui 1 shift sebelumnya), tidak ada spare part (yang diketahui 1 shift
se e umnya .
- Planned Trial (trial dev (produk, packaging), trial engineering)
- Sholat Jumat
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 22/30
5 Loss impeding Labor Effectiveness
9. MANAGEMENT LOSS
problems, such as failure to provide materials, spare parts,utilities, waiting instructions, etc
10. OPERATIONAL MOTION LOSS
This include losses created as a result of difference in skilllevels and losses attributable to inefficient layout, e.g.
walking loss
.Loss resulting from the shortage of Operators on the line,
-. .
than was originally planned while he don’t have necessary
skills to operate multi lines
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 23/30
5 Loss impeding Labor Effectiveness
12. LOGISTIC LOSS
Time wasted in inefficient delivery of raw, packing,products, etc to the line and removal of finished products
from the line.
13. MEASUREMENT & ADJUSTMENT LOSS
These are worker-hour losses that result from frequent
implementation of measuring and adjustment to prevent
occurrence o qua y e ec s an ow ou .
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 24/30
3 Loss impeding Resource Cons.
14. ENERGY LOSS
processing, e.g. start up loss, idling loss.15. DIE, JIG AND TOOL LOSS
These are monetary losses resulting from the
manufacturing and repair of dies, jigs and tools necessary
,
supplementary supplies such as cutting & grinding fluid
16. YIELD LOSSIs the difference between the weight of material fed into
.
material losses in the form of defective product, give away,
over pack, leaks, spills, evaporation, etc
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 25/30
OEE Concept
Mengukur performa lines berdasar tiga
kategori dan 16 loss yang didefinisikan olehTPM
OEE = Availability x Performance x Quality
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 26/30
OEE Concept ( cont’d )
Secara sederhana
OEE = Actual output/ Standard Output
Machine dengan sign off speed 100 ppm
berproduksi 1 shi t ( 8 jam ), machine lancar
dengan out put 25000 product.
Perhitungan :
EE = 25000/(100*480)x100 = 52
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 27/30
OEE & CU
=CU
Total Time
OEE
Notes:
• Standard Cycle Time is based on Line Design speed
• Defects include waste and reworked units
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 28/30
Link between Losses & Reasons
4Holidays / Weekends / Factory Shutdown4No production orders
4Planned Maintenance4Planned Modification
48- Shutdown
4Losses Level 4Reasons Level (Some Examples)
4Loading Time u t d o w n
s e s 41- Equipment Breakdown
42- Chan eover
4Breakdown (>10´)
4Changeover - format4Changeover - product
4Shutdown of the Packing Line
4Operating Time 4 D
o w n t i m e
4
L o s s e s
S h
L o
43- Cutting Blade Change
44- Start-up / Ramp down
49- Management
410- Operational Motion
app ca e4Start up of the Packing Line4Failure to provide material4Utilities Stops due the sites reasons4
Power Cuts from Government4
4Net
4Operating
4Time 4
P e r f o r m a n c e
4
L o s s e s
45- Minor Stoppages
46- Speed
411- Line Organisation
4Minor Stoppages (<10´)
4Should be calculated automatically
4Meals break & Prayer Breaks4Unexpected lack of operators
4
Lack of product from the process area4
Value4Operating
4Time 4
D e f e
c t s
4
L o s s e s -
47- Defects and rework 413 – Measurement &Ad ustment
4Quality problem with product4Quality problem with Packaging
4Cleaning routine4 4 -
415 - Maintenance spare parts
416 - Yield
4Machine Adjustment
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 29/30
Contoh 2
Packaging Machine standard speed 100 ppm
berproduksi selama 1 shift atau 8 hr
selama 1 jam
Terjadi beberapa minor stop
.
Hitunglah OEE-nya
7/17/2019 5 OEE Loss Tree
http://slidepdf.com/reader/full/5-oee-loss-tree 30/30
Jawaban contoh 2
Availability = ( 8-1)/8*100%=87,5%
Performance = 36000/(100*60*7)=85,7%
OEE = 74,98%