Upload
nathan-raja
View
2
Download
0
Embed Size (px)
DESCRIPTION
fyki
Citation preview
MANDATORY SPARE PARTSROTATING EQUIPMENT
BALANCE OF PLANT PACKAGE PHASE-III REFINERY PROJECT, MRPL
SECTION: E-3 6782-334-16-45-E3-01-A Page 1 of 2
Format No. EIL-1641-1924 Rev.1 Copyright EIL – All rights reserved
E STANDARD SPECIFICATION
E-3 ROTATING EQUIPMENT
BALANCE OF PLANT PACKAGE FOR
DELAYED COKER UNIT
PROJECT : PHASE-III REFINERY PROJECT OWNER : MANGALORE REFINERY AND PETROCHEMICALS LTD PMC : ENGINEERS INDIA LTD. JOB NO. : 6782
A 29/01/09 Issued with the Bid Package AG SM SM
Rev. No Date Purpose Prepared
by Checked
by Approved
by
MANDATORY SPARE PARTSROTATING EQUIPMENT
BALANCE OF PLANT PACKAGE PHASE-III REFINERY PROJECT, MRPL
SECTION: E-3 6782-334-16-45-E3-01-A Page 2 of 2
Format No. EIL-1641-1924 Rev.1 Copyright EIL – All rights reserved
There is no attachment in this section.